DAVIES TECHNICAL SOLUTIONS INC. CONSTRUCTION WEEKLY PROJECT UPDATE REPORT April 7 - 13, 2018

1. Executive Summary as of 1.1 Safety TRIR s TRIR Derivation (Total Recordable Incident Rate) = (Number of OSHA Recordable Incidents*200,000) / (Total Number of Hours Work) = (0 * 200,000) / 9670 =0% 1.2 Project Status Update DAVIESTECH PROJECT STATUS As of March 31 – April 6, 2018 Target %

Actual %

Variance

39.54 %

26.65 %

12.89%

1.2.1

S Curve % of Financial Completion Target: 39.54 % (P 7,591,680.00) Actual: 26.65 % (P 5,116,800.00) Variance: 12.89 %

1.2.2 CPM Schedule 1.2.2.1 Project Full Completion with Beneficial Occupancy Date: August 31, 2018 1.2.2.2 Days Ahead / (Delayed): 31.3 = 32 days /DELAYED Days Ahead/Delay: = (Actual – Projected) ÷ (100%/Total Contract Days) = (26.65 %- 39.54 %) ÷ (100% / 243 days) = -12.89 % / (.412) = 31.3 1.2.2.3 Forecast Completion Date: August 31, 2018 1.2.2.4 REASON FOR DELAY OF WORKS 1.2.2.4.1 Availability of Areas (January – February 2018) 1.2.2.4.2 Manpower & Materials 1.2.2.4.3 Areas not yet handover / punchlist but are included on S-Curve 1.2.2.4.4 Proper Scheduling and follow up for Waterproofing works

1.2.3

Critical Milestone Dates Actual/Forecast Completion Date

Days Ahead/Days Delayed

Event/Activity

Target Date

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

Jan 27 – Feb 2, 2018

April 30, 2018

88 Days

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)

Jan 27 – Feb 2, 2018

April 30, 2018

88 Days

Jan 27 – Feb 2, 2018

June 30, 2018

149 Days

Jan 27 – Feb 2, 2018

June 30, 2018

149 Days

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

Feb 3 – Feb 9, 2018

April 30, 2018

81 Days

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)

Feb 3 – Feb 9, 2018

April 30, 2018

81 Days

Feb 3 – Feb 9, 2018

June 30, 2018

142 Days

Feb 3 – Feb 9, 2018

June 30, 2018

142 Days

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

Feb. 10 – Feb. 16, 2018

April 30, 2018

74 Days

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)

Feb. 10 – Feb. 16, 2018

April 30, 2018

74 Days

Feb. 10 – Feb. 16, 2018

June 30, 2018

135 Days

June 30, 2018

135 Days

 Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

 Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

 Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

Feb. 10 – Feb. 16, 2018

Green – Accomplishment on Schedule Orange – Accomplishment but Delayed Red – Delayed 1.1.1

Procurement Status Update (Not Applicable) Quantity

Packages

Total

Awarded

On-going/Bid Nego

For Bid

Long Lead Regular For Detailed Package Procurement Status 1.1.2

Total Man-Days This Period

As of April 7 - 13, 2018 Total Man Days = 24 days 1.3 Unit Turnover Status Update ( Not Applicable ) Total # of Units

Target Turn Over Previous This Total Period

Actual Turn Over Previous This Total Period

Variance %

1.4 Bonds/Insurance Updates (As of November 30, 2017,)

Expiring Within CARI Performance Bond

1 Months

2 Months  

3 Months

6 Months

1.5 Key Updates/ Issue and Action Plan Updated / Issues and Action Plan 1.5.1 Key Updates / Issue and Action Plan     

Hand over area by ARDI at Foundation Grid Line Z’-AA/29-30 Sewage Fit/Grease Tank date 04 April 2018 Daviestech will punchlist the area of handover by ARDI. Hand over area by ARDI at Foundation Grid Line F-H/29-30, Sewage Fit/Grease Tank and Grid Line L-N/29-30 Sewage Fit/Grease Tank dated 13 March 2018 Daviestech will punchlist the remaining area of hand over by ARDI. Finished application of waterproofing on Retaining Walls at Lower Ground Grid Line T-W/28-25a, 1st coat and 2nd coat partial area.

 

Hand over area by ARDI at Lower Ground Grid Line 24-30/X-W, Car Park 1 to Car Park 4 Grid Line 29-30/W. Daviestech will punchlist the remaining area of hand over by ARDI.

1.5.2 Other Updates / Issues  Concerns: Hand over Area by ARDI  Concerns: Additional Area of application.  Concerns: Additional Area of hand over for application of waterproofing.  Concerns: Additional Area of hand over for application of waterproofing.

1.6 Permits Status ( Not Applicable )

2. Detailed Project Report 2.1 Safety Report for Year TRIR Derivation (Total Recordable Incident Rate) 𝑅𝑒𝑐𝑜𝑟𝑑𝑎𝑏𝑙𝑒 𝐼𝑛𝑐𝑖𝑑𝑒𝑛𝑡𝑠)∗200,000 𝑇𝑜𝑡𝑎𝑙 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘 = (0 *200,000)/ 9670 =0%

=

(𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑂𝑆𝐻𝐴

Contractor

Number of OSHA Recordable Incidents

Total Number of Hours Worked to Date

TRIR

1.DAVIESTECH

0

9910

0%

2.2 Financial Accomplishment Percentage of Completion Derivation Target: 39.54 % (P 7,591,680.00) Actual: 26.65 % (P 5,116,800.00) Variance: 12.89 % % Completion per Contract Package Package #

CP-08

Contractor Name

DAVIESTECH Total

Target %

Actual %

Variance

Previous

This Period

To Date

Previous

This Period

To Date

%

50.81 %

5.24 %

56.05 %

17.68 %

3.8%

21.48 %

34.57 %

50.81 %

5.24 %

56.05 %

17.68%

3.8%

21.48 %

34.57 %

2.3 Physical Accomplishment CPM Analysis

2.3.1 CPM Schedule 2.3.1.1 Project Full Completion with Beneficial Occupancy Date: August 31, 2018 2.3.1.2 Days Ahead / (Delayed): 31.3 = 32 days /DELAYED Days Ahead/Delay: = (Actual – Projected) ÷ (100%/Total Contract Days) = (26.65 %- 39.54 %) ÷ (100% / 243 days) = -12.89 % / (.412) = 31.3

2.3.1.3 Forecast Completion Date: August 31, 2018

2.3.2 Critical Activities Analysis: (Not Applicable) Critical Duration Target Actual Target Activity Start Date Start Date Completion Date

Actual Completion Date

Ahead/ (Delayed)

2.3.3 Activities Which Will Turn Critical (Not Applicable) Activities Late Start Date

For 1-Month to +3 months CPM Network, see, Annex 3.3 For 3- Month to Look Ahead Construction Activities, see, Annex 3. 2.4 Mile Stone Dates 2.4.1 Critical Milestone Dates Actual/Forecast Completion Date

Days Ahead/Days Delayed

Jan 27 – Feb 2, 2018

April 30, 2018

88 Days

Jan 27 – Feb 2, 2018

April 30, 2018

88 Days

Jan 27 – Feb 2, 2018

June 30, 2018

149 Days

Event/Activity

Target Date

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)  Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

Jan 27 – Feb 2, 2018

June 30, 2018

149 Days

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

Feb 3 – Feb 9, 2018

April 30, 2018

81 Days

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)

Feb 3 – Feb 9, 2018

April 30, 2018

81 Days

Feb 3 – Feb 9, 2018

June 30, 2018

142 Days

Feb 3 – Feb 9, 2018

June 30, 2018

142 Days

 Application of Krystacem-X (Car Park 1 - 4 Flooring Partial Areas)

Feb. 10 – Feb. 16, 2018

April 30, 2018

74 Days

 Hand over/Punchlist/Rectified ( Level 1 - 3 Area)

Feb. 10 – Feb. 16, 2018

April 30, 2018

74 Days

Feb. 10 – Feb. 16, 2018

June 30, 2018

135 Days

Feb. 10 – Feb. 16, 2018

June 30, 2018

135 Days

 Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

 Application of Waterproofing (Embedseal) at Other Area. ( Level 4 - 7 Area)

 Application of Waterproofing (Swelable and Waterstop)

Green – Accomplishment on Schedule Orange – Accomplishment but Delayed Red – Delayed

For Contractor Qualitative Accomplishment, see Annex 3. 2.4.2

Milestone Dates Per Package

2.4.3

Man- Days Tabulation Per Package Per Worker Trade For Manpower Loading, see Annex 2. 5

2.5 Unit Turnover Status (Not Applicable) 2.5.1 Unit Turnover Status Update Total # of Units

2.5.2

Floor

Target Turn Over Previous This Total Period

Actual Turn Over Previous This Total Period

Variance %

Turnover Status Per Floor (Not Applicable) # of Units

Target Turn Over Previous This Total Period

Actual Turn Over Previous This Total Period

Variance %

For Detailed Unit Status, see Annex 2.6 2.6 Updated / Issues and Action Plan 2.6.1 Key Updates / Issue and Action Plan       

Hand over area by ARDI at Foundation Grid Line Z’-AA/29-30 Sewage Fit/Grease Tank date 04 April 2018 Daviestech will punchlist the area of handover by ARDI. Hand over area by ARDI at Foundation Grid Line F-H/29-30, Sewage Fit/Grease Tank and Grid Line L-N/29-30 Sewage Fit/Grease Tank dated 13 March 2018 Daviestech will punchlist the remaining area of hand over by ARDI. Finished application of waterproofing on Retaining Walls at Lower Ground Grid Line T-W/28-25a, 1st coat and 2nd coat partial area. Hand over area by ARDI at Lower Ground Grid Line 24-30/X-W, Car Park 1 to Car Park 4 Grid Line 29-30/W. Daviestech will punchlist the remaining area of hand over by ARDI.

2.6.2 Other Updates / Issues  Concerns: Hand over Area by ARDI  Concerns: Additional Area of application.  Concerns: Additional Area of hand over for application of waterproofing.  Concerns: Additional Area of hand over for application of waterproofing.

2.7 Minutes of Meetings (Not Applicable) 2.7.1 PTG 2.7.2 Construction 2.7.3 Special Meeting

Related Documents

Weekly Report
October 2019 30
Weekly Report
November 2019 26
Weekly Report
May 2020 13
Weekly Report 090509
June 2020 4

More Documents from "International Business Times"