Weekly Report 1LEGENDS OFFICE 1.1

Date

1.1.1September 6, 2007

Servers Backups dxbf dxbf2 dxbf3

Disk Space dxbf dxbf2 dxbf3

Virus Def'n updated dxbf dxbf2 dxbf3

Accomplishments Primavera 6 installed on Virtual Machine Access via web browser is enabled hosted on my computer

Site Issues IP address of the Plotter was taken by another computer. Document handler on dxbcopy2 not working How to add printer Need to educate people on how to add printers. The process should be in a standard and documented. That document should be accessible too.

Permissions on folders Need to make assigning of permissions a much more simple process and then apply it to all shared folders. A form to request permissions might be an option.

Microstation Select server is not issuing licenses to workstations Once this problem is fixed I need to have this server transferred to a virtual machine so that when problem arises it will be easy to revert working VM image.

Tasks for next week Transfer hosting of Primavera 6 on dxbf3 server Reinstall Microstation Select server to a virtual machine 1.1.2September 13, 2007