Earned Value Project Management Colonel John Keesee
1
Objective
To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program plans and schedules Earned value management systems Cost and schedule variances Estimates at completion 2
Scenario
You have been tasked to be the project manager for an important project You have been directed to use an earned value management system Time to market is critical for this development
3
Work Breakdown Structure Identifies 100 % of the work to be accomplished WBS dictionary breaks the scope into measurable tasks Each with an estimated value Responsibility for each task assigned to individuals or work teams
4
Work Breakdown Structure
Space System
Space Vehicle
Launch Vehicle
Payload
Spacecraft
Ground Command, Control, Communications and Mission Equipment
Reentry vehicle
Integration, Assembly, Test and Checkout
5
Project Master Schedule Detailed plan and schedule Identified dependencies between tasks 18 months Estimated resources for each task 10 units at $150K each
6
Project Master Schedule Task/Event Award Design Buy specifications Vendor quotes Purchase orders Receive materials Factory plans Tool design Tool fabrication Parts fabrication Assembly: sub and final Test & checkout
Jan - Jun ^ ^ ^ ^
Jul - Dec
Jan - Jun
^ ^ ^ ^ ^ ^ ^ ^ 7
Project Performance Display 1600000 1400000 1200000 1000000
BCWS BCWP ACWP
800000 600000 400000 200000
Ju ly
il Ap r
nu ar y
Ja
er ob
O
ct
Ju ly
il Ap r
Ja
n
0
8
Plan Review Before Go-Ahead
CEO: “Time to market is critical. You have 12 months.” “This looks gold-plated at $1.5M. You have $1.0M.” “Go ahead, but come back to me with your progress in three months.” 9
The Three Month Review Three units scheduled for completion Two units actually completed $300,000 budgeted at this point $300,000 actually spent Optimist PM: “A little behind schedule but right on the cost plan.”
10
Earned Value System Requires a detailed, bottoms-up performance plan Performance measured against the plan Provides forecast of final expected results based on data
11
Earned Value Measurements 1. 2. 3. 4. 5. 6. 7.
Work scheduled Budgeted cost of work scheduled (BCWS) Work performed Budgeted cost of work performed (BCWP) Actual cost of work performed (ACWP) Schedule variance (SV) = BCWP - BCWS Cost Variance (CV) = BCWP - ACWP 12
New Project Performance Display 1200000 1000000 800000
BCWS BCWP ACWP
600000 400000 200000
De ce m be r
ct ob er O
Ju ly
Ap ril
Ja nu ar
y
0
13
Estimate at Completion Cost efficiency CPI = BCWP/ACWP Schedule efficiency SPI = BCWP/BCWS Estimate at completion BAC EAC1 = CPI
BAC − BCWP EAC 2 = ACWP + CPI * SPI 14
Management Reserve Budgeted to provide the ability to adjust for uncertainty Always accounted at the total project level Normally retained and controlled at the total project level Must not be eliminated by negotiations
15
Summary Earned value management system provides a key link between the cost, schedule, and technical aspects of a project Provides an early and reliable prediction of future performance
16
References Fleming, Quentin W. and Joel M. Koppelman, Earned Value Project Management, PMI, Newtown Square, PA 2000 Lewis, James P., Fundamentals of Project Management, AMACOM, NY 2002