BUILT-UP RATE FOR METAL DECK HOARDING PROJECT : LOCATION : SUPPLIER : SUB-CONTRACTOR : QUOTATION DATE :
Metal Decking Hoarding ( 3.60m High @ 2.40m c/c/) Allow for 50% scrap value for structural steel & metal hoarding Footing Vertical Struct Horizontal Struct Metal hoarding
1200mm x 600mm x 600mm deep 100mm x 50mm x 3mm thk ( 2nos.) 100mm x 50mm x 3mm thk ( 3nos.) 2.40m x 3.60m
Profit & Overhead @ Tender Price / m
Inclusived
Tender Cost / m @ say
90.00 26.49 52.99 63.00 232.48 232.48 232.50
Metal Decking Hoarding ( 2.40m High @ 2.40m c/c/) Allow for 50% scrap value for structural steel & metal hoarding Footing Vertical Struct Horizontal Struct Metal hoarding
1200mm x 600mm x 600mm deep 100mm x 50mm x 3mm thk ( 2nos.) 100mm x 50mm x 3mm thk ( 3nos.) 2.40m x 3.60m
Profit & Overhead @ Tender Price / m
Inclusived
Tender Cost / m @ say
Cost / m
Cost / m
90.00 17.66 52.99 42.00 202.65 202.65 202.70