ANALISA KUANTITAS PEKERJAAN NO

1.2 2.1

URAIAN PEKERJAAN/SKETSA GAMBAR Divisi 1. Umum Mobilisasi Divisi 2. Drainase Galian Selokan Drainase Dan Saluran Air

0,8m

0,6 m Lebar Atas = 1,2 m Lebar Bawah = 0,6 m Tinggi = 0,8 m Luas=(L.Ats+L.Bwh) x Tinggi 2 L = (0,6 + 1,2) x 0,8 = 0,72 2 Hasil diatas baru sisi kiri drainase Harus di kali dua (sisi kiri dan kanan dari bagian jln)

V=PxL

Ls

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900

m3

Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

1,2 m

0,72 x 0,72 = 0,5184 m2

SATUAN

25,82

37+900 – 37+950 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

37+950 – 38+000 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+000 – 38+050 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+050 – 38+100 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+100 – 38+150 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+150 – 38+200

HASIL

Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+200 – 38+250 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+250 – 38+300 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+300 – 38+350 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+350 – 38+400 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+400 - 38+450 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+450 – 38+500 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+500 – 38+550

HASIL

Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

Segmen 2 38+550 – 38+600 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+600 – 38+650 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+650 – 38+700 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+700 – 38+750 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+750 – 38+800 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+800 – 38+850

HASIL

Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+850 – 38+900 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+900 – 38+950 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

38+950 – 39+000 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

39+000 – 39+050 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

39+050 – 39+100 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

39+100 – 39+150 Panjang = 50,00 Luas = 0,5164 50,00 x 0,5164 =

25,82

KET.

ANALISA KUANTITAS PEKERJAAN NO 2.2

URAIAN PEKERJAAN/SKETSA GAMBAR Pasangan batu dengan mortar

SATUAN

m3

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00 37+900 – 37+950 50,00

L = 0,36 ( 0,36 didapat dari hitungan vol memalui software Autocad ) Hasil diatas baru sisi kiri dari pasangan batu dan mortar Harus di kali dua (sisi kiri dan kanan dari bagian jln) 0,36 x 0,36 = 0,1296 m2 V=LxJ

37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 V=LxJ 0,1296 x 700 =

90,72

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 V=LxJ 0,1296 x 600 =

77,76

KET.

ANALISA KUANTITAS PEKERJAAN NO

5.1(1)

URAIAN PEKERJAAN/SKETSA GAMBAR Divisi 5. Perkerasan Berbutir Lapis Pondasi Agregat Kelas A

SATUAN

m3

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00 37+900 – 37+950 50,00 37+950 – 38+000 50,00 38+000 – 38+050 50,00

Tebal = 0,12 m Lebar = 6 m ( Tebal x Lebar x Panjang )

38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 Tebal x Lebar x Pjg 0,12 x 6 x 700 =

504

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 Tebal x Lebar x Pjg 0,12 x 6 x 600 =

432

KET.

ANALISA KUANTITAS PEKERJAAN NO 5.1(2)

URAIAN PEKERJAAN/SKETSA GAMBAR Lapis Pondasi Agregat Kelas B

SATUAN

m3

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00 37+900 – 37+950 50,00

Tebal = 0,15 m Lebar = 6 m ( Tebal x Lebar x Panjang )

37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 Tebal x Lebar x Pjg 0,15 x 6 x 700 =

630

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 Tebal x Lebar x Pjg 0,15 x 6 x 600 =

540

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR Divisi 6. Perkerasan Aspal 6.1(1)(a) Lapis Resap Pengikat Aspal Cair

SATUAN

Liter

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00

Koefisien : 0,7 Lebar : 6 m (Keofisien Aspal x Lebar x Panjang)

37+900 – 37+950 50,00 37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 Koef x lebar x pjng 0,7 x 6 x 700 =

2940

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 Koef x Lebar x Pjg 0,7 x 6 x 600 =

2520

KET.

ANALISA KUANTITAS PEKERJAAN NO 6.6

URAIAN PEKERJAAN/SKETSA GAMBAR Lapis Penetrasi Makadam

SATUAN

Ton

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00 37+900 – 37+950 50,00

Tebal = 0,15 m Lebar = 4,5 m (Tebal x Lebar x Panjang)

37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 Tebal x lebar x pjng 0,15 x 4,5 x 700 =

472,5

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 Tebal x lebar x pjng 0,15 x 4,5 x 600 =

405

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR 6.3(5)(b) AC-WC Asbp

SATUAN

Ton

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00

AC-WC Agr Kelas A

Agr Kelas B

37+900 – 37+950 50,00 37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00

Berat Jenis = 2,3 Lebar = 6m Tebal = 0,4 m (BJ x Lebar x Tebal x Panjang)

38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 BJ xTebal xLbr x Pjg

2,3x 6 x 0,4 x 700

3864

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 BJ xTebal xLbr x Pjg

2,3x 6 x 0,4 x 600 =

3312

KET.

ANALISA KUANTITAS PEKERJAAN NO

3.1

URAIAN PEKERJAAN/SKETSA GAMBAR Divisi 3. Pekerjaan Tanah Galian Biasa

SATUAN

m3

ANALISA KUANTITAS 37+850 – 37+900

HASIL

37+850 = 1,92 37+900 = 1,89 P= 50,00 V=(1,92+1,89) x50

77,25

2 37+900 – 37+950 37+900 = 1,89 37+950 = 0,55 P = 50,00 V=(0,55+1,89) x50 2

54,75

37+950 – 38+000 37+950 = 0,55 38+000 = 1,02 P = 50,00 V=(0,55+1,02) x50 2

39,25

38+100 – 38+150 38+100 = 7,84 38+150 = 1,61 P = 50,00 V=(7,84+1,61) x50 2 38+300 – 38+350 38+300 = 3,89 38+350 = 2,43 V=(3,89+2,43) x50 2

236,25

158

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+350 – 38+400 38+350 = 2,43

HASIL

38+400 = 0,76 V=(0,76+2,43) x50

79,75

2 38+400 – 38+450 38+400 = 0,76 38+450 = 0,52 V=(0,76+0,52) x50 2 38+450 – 38+500 38+450 = 0,52 38+500 = 0,33 V=(0,33+0,52) x50 2 38+500 – 38+550 38+500 = 0,33 38+550 = 4,58 V=(0,33+4,58) x50

32

21,25

122,75

2 38+550 – 38+600 38+550 = 4,58 38+600 = 2,22 V=(2,22+4,58) x50 2 38+600 – 38+650 38+600 = 2,22 38+650 = 9,33 V=(2,22+9,33) x50 2

170

288,75

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+650 – 38+700

HASIL

38+650 = 9,33 38+700 = 1,64 V=(9,33+1,64) x50

274,25

2 38+700 – 38+750 38+700 = 1,64 38+750 = 3,56 V=(3,56+1,64) x50 2

130

38+750 – 38+800 38+750 = 3,56 38+800 = 3,89 V=(3,56+3,89) x50 2 38+800 – 38+850 38+800 = 3,89 38+850 = 1,11 V=(1,11+3,89) x50

186,25

125

2 38+850 – 38+900 38+850 = 1,11 38+900 = 2,49 V=(1,11+2,49) x50 2

90

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS 38+900 – 38+950

HASIL

38+900 = 2,49 38+950 = 2,87 V=(2,87+2,49) x50

134

2 38+950 – 39+000 38+950 = 2,87 39+000 = 0,27 V=(2,87+0,27) x50 2

78,5

39+000 – 39+050 39+000 = 0,27 39+050 = 0,64 V=(0,64+0,27) x50 2 39+050 – 39+100 39+050 = 0,64 39+100 = 1,64 V=(0,64+1,64) x50

22,75

57

2 39+100 – 39+150 39+100 = 1,64 39+150 = 1,94 V=(1,94+1,64) x50 2

89,5

KET.

ANALISA KUANTITAS PEKERJAAN NO 3.2

URAIAN PEKERJAAN/SKETSA GAMBAR Timbunan

SATUAN

ANALISA KUANTITAS 38+025 – 38+50

m3

38+025 = 16,30

HASIL

38+050 = 21,63 V=(16,30+21,63) x25

474,125

2 38+050 – 38+075 38+050 = 21,63 38+075 = 18.14 V=(18,14+21,63) x25

497,125

2 38+075 – 38+100 38+075 = 18.14 38+100 = 7,84 V=(18,14+7,84) x25

324,75

2 38+175 – 38+200 38+175 = 7,48 38+200 = 15,19 V=(15,19+7,48) x25

283,375

2 38+200 – 38+225 38+200 = 15,19 38+225 = 12,93 V=(15,19+12,93) x25

2

189,875

KET.

ANALISA KUANTITAS PEKERJAAN NO

URAIAN PEKERJAAN/SKETSA GAMBAR 6.1(2)(a) Lapis Perekat Aspal Cair

SATUAN

Liter

ANALISA KUANTITAS Segmen 1

HASIL

37+850 – 37+900 50,00

Koefisien : 0,35 Lebar : 6 m (Keofisien Aspal x Lebar x Panjang)

37+900 – 37+950 50,00 37+950 – 38+000 50,00 38+000 – 38+050 50,00 38+050 – 38+100 50,00 38+100 – 38+150 50,00 38+150 – 38+200 50,00 38+200 – 38+250 50,00 38+250 – 38+300 50,00 38+300 – 38+350 50,00 38+350 – 38+400 50,00 38+400 – 38+450 50,00 38+450 – 38+500 50,00 38+500 – 38+550 50,00 Panjang = 700 ( Pot tiap 50m x jmlh keseluruhan segmen 1 ) 14 x 50,00 = 700 Koef x lebar x pjng 0,35 x 6 x 700 =

1470

KET.

ANALISA KUANTITAS PEKERJAAN

NO

URAIAN PEKERJAAN/SKETSA GAMBAR

SATUAN

ANALISA KUANTITAS Segmen 2

HASIL

38+550 – 38+600 50,00 38+600 – 38+650 50,00 38+650 – 38+700 50,00 38+700 – 38+750 50,00 38+750 – 38+800 50,00 38+800 – 38+850 50,00 38+850 – 38+900 50,00 38+900 – 38+950 50,00 38+950 – 39+000 50,00 39+000 – 39+050 50,00 39+050 – 39+100 50,00 39+100 – 39+150 50,00 Panjang = 600 ( Pot tiap 50m x jmlh keseluruhan segmen 2 ) 12 x 50,00 = 600 Koef x Lebar x Pjg 0,35 x 6 x 600 =

1260

KET.