ECCRUZ CORPORATION ENGINEER’s • CONSULTANTS • PROJECT MANAGERS

Ref. No.: BD-P2017-xxx- ALC-Design & Construction of 3-Storey Residential building

September 7, 2017 MR. ANTONIO L. CRUZ 2184 Revillen St., Sta. Ana, City of Manila Subject

:

Dear Sir

:

PROPOSAL FOR THE CONSTRUCTON & SUPERVISION OF THE 3-STOREY RESIDENTIAL BUILDING AT MAKATI CITY

We are pleased to submit our cost proposal for the Construction of the Proposed 3-Storey Residential Building located at 8950 Aranga St., San Antonio, Makati City. We have outlined herewith the terms and conditions that will best fit your requirements. I.

SCOPE OF WORKS: Construction & Supervision      

III.

Architectural Design; Structural Design; Sanitary & Plumbing Design; Drainage Design (tap to existing Road Drainage); Electrical (Power & Light) System Design; Mechanical Ventilation System (AC);

PERFORMANCE PERIOD We proposed to complete the works within 6-7 calendar months upon issuance of the Building Permit, Advance Payment

IV.

PROJECT COST: ECC shall undertake the required services within the prescribed period. The required Services shall commence from the date of receipt of the Notice to Proceed (NTP) and Advance Payment. Construction & Supervision (Supply of Labor & Materials) for the Proposed 3-Storey Residential Building. Our service fee for the proposed services shall be a lumpsum Amount of Php SIXTEEN MILLION TWO HUNDRED THOUSAND & 00/100 (P 16,200,000.00) exclusive of VAT. Floor Areas: Ground Floor 2nd Floor 3rd Floor

255 255 165

sqm sqm sqm

Conditions: 1.

Inclusions/Exclusions (Construction): 

Earthworks & Reinforced Concrete Structural Works: Construction of Building Foundation, all Structural Elements, construction of Septic Tank;

2/F, Diolar Building, 123 Kalayaan Avenue, Brgy. Central, Diliman, Quezon City Telephone: 02-294-8359 • 02-274-5827 • 02-4751841 • 02-475-3501 | Fax: 02-352-3756 | email: [email protected]

Page 1



Architectural Works: Construction covering the Architectural Works fot all Floors, walls, ceiling finishes, Specialized Steel works (Stairs Railing, Steel Gates, Toilet Fixtures, Cubicles, Painting Works, Exclusions: Air Conditioners, Exhaust Fans).  Water Heaters shall be Panasonic portable Electric Water Heaters x Shower Head combo.;  Shower Cubicle shall be Pozzi Brand, Bath Tub shall be Pozzi Brand; Whirlpool shall be HCG Brand

V.

Electrical & Auxiliary Systems Works: Design and Construction for the Power & Light, main power distribution system, lighting & grounding System, Auxiliary System covers the CATV System;



Mechanical HVA Works: Design; supply of Air Conditioners & Exhaust Fans by Owner;

TERMS OF PAYMENT:   

VI.



30% Downpayment upon Signing of Contract Agreement and issuance of Notice to Proceed (NTP); Balance through Monthly Progress Billing; The Downpayment shall be recouped through Progress Billing Payments;

CHANGE ORDERS/VARIATION ORDERS, ADDITIONAL WORK/S 6.1

The OWNER may, at any time, by a written order, make changes in the schedule and work required under this Agreement. If any such change causes an increase or decrease in the work or the time required for performing the work, an equitable adjustment shall be made of the contract price and completion date upon mutual agreement of the parties reflecting such adjustments by way of a written variation order.

6.2

Should the Owner find it necessary to have any additional work carried out for purposes of the Project in addition to the contracted work, such additional work will be carried out immediately by the CONTRACTOR upon receiving written instructions from the OWNER. Adjustments in terms of additional costs or completion date or both, will be reflected by written extra work order or supplemental contract.

6.3

Change Orders and additional works shall be undertaken only after the Owner and the Contractor shall have agreed in writing on the adjustments in the contract price and completion date.

We sincerely value your trust and confidence in ECC. In return, we strongly commit to deliver the best possible service for this project. Please affix your signature on the space provided below if the above terms and conditions are agreeable to you as we look forward to the commencement of our services. Should these meet your approval, please indicate your acceptance subject to all terms and conditions contained hereof. Very truly yours,

EDGARDO C. CRUZ President & CEO Conforme : _____________________________ (Signature over printed name) Date: ________________________

Proposal for the Construction & Supervision Services Ref. No.: BD-P2017-xxx- ALC- Construction of 3-Storey Residential building

Page 2 of 2

Related Documents

Tony Cruz Residence.pdf
August 2019 20
Tony
December 2019 24
Tony
November 2019 29
Cruz
October 2019 33
Tony Buzan.pdf
May 2020 11
Tony Yayo
November 2019 20

More Documents from ""