MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
Safety Mass Meeting Report
By Safety Department
5 May 2009
MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
Safety Mass Meeting I.
Date and Time Safety Mass Meeting was held on 5 May 2009 at 07.30 am to 08.15 am.
II.
Location Safety Mass Meeting was held at PLN Area150 KV Yard.
III.
Attendance Safety Mass Meeting was attended by MES-TSW JO, SCJO, SSP, ACSET, SWI Jetty, KYUEI-SWI JO, GEOTEC, SKS, CEM, INDOMIX, and MURINDA.
IV.
Event Organizer Event Organizer of Safety Mass Meeting was Safety Manager of PT. Satyamitra Surya Perkasa, Mr. Dody Achmad.
V.
Agenda Agenda of Safety Mass Meeting as follows: a. Opening by Mr. Dody Achmad (SSP Safety Manager) b. Safety Talk by Mr. Sulaiman (PM of SSP), Topic: Work Coordination between Personnel on Site. c. Safety Contest (Safety Yell), followed by all subcontractors. The winner of the contest was PT. SWI Jetty Nusantara. The winner received incentive Rp. 1000.000,- (one million rupiah) from Safety Committee. d. The Best Housekeeping Team Period of April 2009 was PT. Satyamitra Surya Perkasa. The certificate was handed over by Mr. Tanimoto (SCJO) to Mr. Sulaiman (PT. SSP). Safety Committee handed over 10 pieces of T shirt to PT SSP. e. The Best Safety Performance – Subcontractor Period of April 2009 was handed over by Mr. Takahasi (MES Construction Manager) to Mr. Darmanto (PT. SWI Jetty Nusantara).
VI.
Closing Mr. Dody Achmad closed Safety Mass Meeting with safety yell-yell and praying.
Reported By,
I Gede Sumantra Safety Manager
1
MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
Safety Mass Meeting Attendances
Mr. Dody Achmad Acted as Ceremony Leader on the Safety Mass Meeting
Mr. Sulaiman was Giving Safety Talk on the Safety Mass Meeting.
2
MES-TSW JOINT OPERATION
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
Site Managers of MESJO and subcontractors were taking pledge committing to Health and Safety Implementation Led by Safety Committee Representative MR. I Gede Sumantra
3
MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
All Site Managers of MESJO and Subcontractors Signed the “Janji Site Manager”
Safety Yell Contestants
4
MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
Juries were on a tough discussion to decide the winner of Safety Yell Contest
Congratulation to PT. SWI Jetty, Winner of the Contest
5
MES-TSW
SAFETY REPORT
JOINT OPERATION
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
Congratulation to PT. SSP (The Best Housekeeping Team Period of April 2009)
Congratulation to PT. SWI Jetty (The Best Safety Performance – Contractor Period of April 2009)
6
MES-TSW
SAFETY REPORT
TANJUNG JATI B EXPANSION PROJECT UNIT 3&4
JOINT OPERATION
Mr. Dody Achmad closed Safety Mass Meeting with Safety Yell and Praying
Photo Session after Safety Mass Meeting
7