A Real Risk Assessment Rick A A. Morris Morris, PMP PMP, ITIL ITIL, MCTS
Agenda
1. Overview of Current Risk Process 2. Two Constraining Laws 3 How to Capture Real Risk 3. 4. A New Risk Assessment Tool 5. Questions and Answers
Current Process ¾…so we are told: Create WBS
Current Process ¾…so we are told: Create WBS
Identify Risks
Current Process ¾…so we are told: Create WBS
Identify Risks
Qualify Risks
Current Process ¾…so we are told: Create WBS
Identify Risks
Qualify Risks
Quantify Risks
Current Process ¾…so we are told: Create WBS
Identify Risks
Qualify Risks
Quantify Risks
Pick Strategy
Current Process ¾…so we are told: Create WBS
Identify Risks
Qualify Risks
Quantify Risks
Residual Risks
Pick Strategy
What Really Happens PM Creates Plan Create WBS
Identify Risks
Qualify Risks
Quantify Risks
Residual Risks
Pick Strategy
What Really Happens PM Creates Plan
PM Identifies Risks
Create WBS
Identify Risks
Qualify Risks
Quantify Risks
Residual Risks
Pick Strategy
What Really Happens PM Creates Plan
PM Identifies Risks
Create WBS
Identify Risks
PM Fills Out Spreadsheet p
Qualify Risks
Quantify Risks
Residual Risks
Pick Strategy
What Really Happens PM Creates Plan
PM Identifies Risks
Create WBS
Identify Risks
PM Fills Out Spreadsheet p
Qualify Risks
Quantify Risks
Residual Risks
Pick Strategy
Start P j t Project
Why Risk Assessments Fail ¾End up with an ambiguous answer: } }
This project has a risk level of “medium” Your risk assessment score is 4.87
¾Thanks….but now what?
Two Constraining Laws ¾Parkinson’s Law }
Work will naturally fill the timeframe allotted.
¾Murphy’s Law }
Anything that can go wrong will.
Our Dilemmas ¾How to capture risk when our team / sponsor / management does not believe in risk or will not attend risk meetings. ¾How do we account for risk without g Parkinson’s Law. allowing ¾How can I use a risk assessment to help drive the contingency that I need? ¾How can I create a risk assessment that means something?
Simple Approach ¾Set up your Microsoft Project Plan using best practices (i.e. no manually typed dates, everything linked, etc.) ¾Save a copy and “break” your plan. ¾Figure out if you can recover the plan plan. If so, what kind of lead time do you need? ¾If not not, deal with the risk now!
More Involved Approach ¾ Correlate risk score to time and cost guidelines ¾ Utilize real incidents and lessons learned to baseline risk ¾ Create a repository of items to avoid repeatable issues ¾ Create C t a system t that th t updates d t reall time ti as new risks are identified or old risks that are nullified ¾ Approach begins with general risks, p risks then over time, moves to specific
Start General
Second Step ¾How to Capture Real Risk }
Create a real project plan: No manually entered dates Everything has a predecessor Baseline, Baseline, Baseline
Second Step ¾Track variances
Third Step ¾Gather real variances and categorize them. } }
}
Use actual risks and actual impacts Using historical information, correlation can be made between risk and cost/time impacts Instead of a “general” feeling when sales or a customer inquires about the amount of risk, th answer could the ld b be, “I “In project j t A with ith product B, an overrun occurred due to …”
Fourth Step ¾Create new risk assessment utilizing actual risks and actual impacts. Utilize actual variances to determine impacts.
The New Report
The Process Categories / Question weights reviewed periodically and updated
PMO works on the highest risk % categories for mitigation strategies t t i
PM Completes Risk Assessment Tool
Periodic reviews conducted by PM staff
I Impacts t off risks i k compared against baseline and adjusted if necessary
Information is updated in the Risk Assessment tool too
PM assesses probability and impact of each risk
At the completion of the project, the PM fills out Risk Identification Form
Tool establishes amount of risk by utilizing formula listed below
PMO Receives Risk Identification Form Current risks are evaluated and updated, new risks added if necessary
Risk is added to the project
Formula: ((Best Case Actual Risk) + (4 * Most Likely Actual Risk) + (Worse Case Actual Risk)/6) * Probability * Impact * Question Weight Percentage * Category Weight Percentage
Remember the 2 Laws? ¾How do you plan for risk, put it in your project plan, but not give it away to your team?
Questions?