PEKERJAAN DINDING (SNI 6897 : 2008) 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS NO.

A.

B.

C.

URAIAN

SATUAN

KOEFISIEN

TENAGA Pekerja Tukang Batu Kepala Tukang Mandor

OH OH OH OH

0.3000 0.1000 0.0100 0.0150 JUMLAH TENAGA KERJA

BAHAN Bata Merah 5 x 11 x 22 cm Semen Portland Pasir Pasang

bh kg m3

70.0000 14.3700 0.0400 JUMLAH HARGA BAHAN

PERALATAN JUMLAH HARGA ALAT

D. E. F.

Jumlah (A + B + C) Overhead & Profit Harga Satuan Pekerjaan (D+E)

0

%xD

PEKERJAAN KAYU (SNI 3434 : 2008) MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I NO.

A.

B.

C.

URAIAN

SATUAN

KOEFISIEN

TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

7.0000 21.0000 2.1000 0.3500 JUMLAH TENAGA KERJA

BAHAN Balok Kayu Jati Paku 10 Cm Lem Kayu

m3 Kg Kg

1.1000 1.2500 1.0000 JUMLAH HARGA BAHAN

PERALATAN JUMLAH HARGA ALAT

D.

Jumlah (A + B + C)

E. F.

Overhead & Profit Harga Satuan Pekerjaan (D+E)

0

%xD

MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II NO. URAIAN SATUAN KOEFISIEN

A.

B.

C.

TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

0.8000 2.4000 0.2400 0.0400 JUMLAH TENAGA KERJA

BAHAN Papan Kayu Kamper Lem Kayu

m3 Kg

0.0240 0.3000 JUMLAH HARGA BAHAN

PERALATAN JUMLAH HARGA ALAT

D. E. F.

Jumlah (A + B + C) Overhead & Profit Harga Satuan Pekerjaan (D+E)

0

%xD

MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I NO. URAIAN SATUAN KOEFISIEN

A.

B.

C.

TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

0.8000 2.4000 0.2400 0.0400 JUMLAH TENAGA KERJA

BAHAN Papan Kayu Jati Paku 1-2,5 Cm Lem Kayu Teakwood 4 mm uk 90x220 c

m3 Kg Kg Lbr

0.0250 0.0300 0.3000 1.0000 JUMLAH HARGA BAHAN

PERALATAN JUMLAH HARGA ALAT

D. E.

Jumlah (A + B + C) Overhead & Profit

0

%xD

F.

Harga Satuan Pekerjaan (D+E)

HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

80,000.00 100,000.00 115,000.00 130,000.00

24,000.00 10,000.00 1,150.00 1,950.00 37,100.00

1,500.00 1,450.00 400,000.00

105,000.00 20,836.50 16,000.00 141,836.50

178,936.50 178,936.50

KELAS I HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

80,000.00 110,000.00 115,000.00 130,000.00

560,000.00 2,310,000.00 241,500.00 45,500.00 3,157,000.00

32,000,000.00 17,297.78 18,900.00

35,200,000.00 21,622.22 18,900.00 35,240,522.22

38,397,522.22

38,397,522.22

II HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

80,000.00 110,000.00 115,000.00 130,000.00

64,000.00 264,000.00 27,600.00 5,200.00 360,800.00

10,100,000.00 18,900.00

242,400.00 5,670.00 248,070.00

608,870.00 608,870.00

HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

80,000.00 110,000.00 115,000.00 130,000.00

64,000.00 264,000.00 27,600.00 5,200.00 360,800.00

37,500,000.00 17,297.78 18,900.00 84,700.00

937,500.00 518.93 5,670.00 84,700.00 1,028,388.93

1,389,188.93 -

1,389,188.93

NO 1 2 2 3

URAIAN PEKERJAAN 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS MBMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I

TOT

Rencana Anggaran Biaya

OTAL BIAYA

JUMLAH

SAT

220.020

m2

0.47500

m3

19.700

m2

2.580

m2

HARGA SATUAN (Rp) Rp

178,936.50

Rp

38,397,522.22

Rp

608,870.00

Rp

1,389,188.93

JUMLAH HARGA (Rp) Rp

39,369,608.73

Rp

18,238,823.06

Rp

11,994,739.00

Rp

3,584,107.45

Rp

73,187,278.23

Related Documents

Pekerjaan
April 2020 27
Pekerjaan Dinding.xls
June 2020 15
Spesifikasi Pekerjaan
May 2020 30
Analisis Pekerjaan
December 2019 24
Pekerjaan Dinding.xls
June 2020 11
Pekerjaan Pembesian
May 2020 5

More Documents from "Donz Sinatraz"