NO. A.

B.

C.

MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II KOEFISIEN HARGA SATUAN URAIAN SATUAN (Rp.) TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

4.0000 12.0000 1.2000 0.2000 JUMLAH TENAGA KERJA

80,000.00 110,000.00 115,000.00 130,000.00

BAHAN Balok Kayu Kamper Besi Strip Tebal 5 cm Paku 12 Cm

m3 Kg Kg

1.1000 15.0000 5.6000 JUMLAH HARGA BAHAN

9,100,000.00 11,960.00 17,297.78

PERALATAN JUMLAH HARGA ALAT

D. E. F.

NO. A.

B.

C.

Jumlah (A + B + C) Overhead & Profit 0 Harga Satuan Pekerjaan (D+E)

%xD

MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II KOEFISIEN HARGA SATUAN URAIAN SATUAN (Rp.) TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

2.4000 7.2000 0.7200 0.1200 JUMLAH TENAGA KERJA

80,000.00 110,000.00 115,000.00 130,000.00

BAHAN Balok Kayu Jati Besi Strip Tebal 5 cm Paku 12 Cm

m3 Kg Kg

1.1000 15.0000 3.0000 JUMLAH HARGA BAHAN

9,100,000.00 11,960.00 17,297.78

PERALATAN JUMLAH HARGA ALAT

D. E. F.

Jumlah (A + B + C) Overhead & Profit 0 Harga Satuan Pekerjaan (D+E)

%xD

NO. A.

B.

C.

MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II KOEFISIEN HARGA SATUAN URAIAN SATUAN (Rp.) TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

0.1000 0.1000 0.0100 0.0050 JUMLAH TENAGA KERJA

80,000.00 110,000.00 115,000.00 130,000.00

BAHAN Kaso-Kaso ( 5 x 7 ) C Reng ( 2 x 3 ) Cm Paku 5 Cm dan 10 C

m3 Kg Kg

0.0140 0.0036 0.2500 JUMLAH HARGA BAHAN

6,700,000.00 8,100,000.00 17,297.78

PERALATAN JUMLAH HARGA ALAT

D. E. F.

NO. A.

B.

C.

Jumlah (A + B + C) Overhead & Profit 0 Harga Satuan Pekerjaan (D+E)

%xD

MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II KOEFISIEN HARGA SATUAN URAIAN SATUAN (Rp.) TENAGA Pekerja Tukang kayu Kepala Tukang Mandor

OH OH OH OH

0.1000 0.2000 0.0200 0.0050 JUMLAH TENAGA KERJA

80,000.00 110,000.00 115,000.00 130,000.00

BAHAN Papan Kayu Kamper Paku 7 Cm dan 10 C

m3 Kg

0.0108 0.1000 JUMLAH HARGA BAHAN

10,100,000.00 17,297.78

PERALATAN JUMLAH HARGA ALAT

D. E. F.

Jumlah (A + B + C) Overhead & Profit 0 Harga Satuan Pekerjaan (D+E)

%xD

AYU KELAS II JUMLAH HARGA (Rp.)

320,000.00 1,320,000.00 138,000.00 26,000.00 1,804,000.00 10,010,000.00 179,400.00 96,867.56 10,286,267.56

12,090,267.56 12,090,267.56

JUMLAH HARGA (Rp.)

192,000.00 792,000.00 82,800.00 15,600.00 1,082,400.00 10,010,000.00 179,400.00 51,893.33 10,241,293.33

11,323,693.33 11,323,693.33

JUMLAH HARGA (Rp.)

8,000.00 11,000.00 1,150.00 650.00 20,800.00 93,800.00 29,160.00 4,324.44 127,284.44

148,084.44 148,084.44

JUMLAH HARGA (Rp.)

8,000.00 22,000.00 2,300.00 650.00 32,950.00 109,080.00 1,729.78 110,809.78

143,759.78 143,759.78

REN NO 1 2 2 3

TOTAL

RENCANA AN URAIAN PEKERJAAN MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II

TOTAL BIAYA

NA ANGGARAN BIAYA

YA

JUMLAH

SATUAN

HARGA SATUAN (Rp)

1.661

M3

Rp

12,090,267.556

0.204

M3

Rp

11,323,693.333

156.900

M2

Rp

148,084.444

46.604

M

Rp

143,759.78

JUMLAH HARGA (Rp) Rp

20,081,934.41

Rp

2,310,033.44

Rp

23,234,449.33

Rp

6,699,780.68

Rp

52,326,197.87

Related Documents

Kap 07
October 2019 8
Kap 27
October 2019 8
Kap 02
October 2019 9
Kap 11
October 2019 14
Kap 14
October 2019 8
Kap 04
October 2019 8

More Documents from ""