METHOD STATEMENT & RISK ASSESMENT
ROBERTSBRIDGE COMMUNITY COLLEGE
PROJECT NUMBER – G14/46395
PROJECT MANAGER – Geoff Field
RISK ASSESSMENT & METHOD STATEMENT Job Number
G14/46395
Contract/ Site name
Robertsbridge Community College, Knelle Road, Robertsbridge, TN32 5EA.
Site Location
As Above
Work/Tasks to be carried out :-
Construction of New Parking Bays & Concrete Hardstanding
Contractors Project Manager
Geoff Field
Revision
Date
07753-850726
[email protected]. uk
Contact Mobile E.mail
Client
Robertsbridge Community College
Address
Knelle Road, Robertsbridge, TN32 5EA.
Contact Details
Tony Hougham
Contact Mobile E.mail
Dates/times the work will be carried out :Start Date
28/7/2014
Duration of works
10 Days
Normal Working Hours
Between 8.00am - 6.00pm
Page 2 of 20
21/7/2014
[email protected]
RISK ASSESSMENT & METHOD STATEMENT RISK ASSESSMENTS a) Generic Risk Assessments
- See Appendix D
b) Site Specific Operations What is the Activity
What is the Hazard
Who is at Risk
Hazard Effect 1–5 (A)
Prob 1–3 (B)
Risk
What Control Measures Need to be put in Place
(A x B)
Residual Hazard 1–5 (A)
Residual Prob. 1–3 (B)
Residu al Risk (A x B)
Delivering machinery
Trips and falls
operatives
2
3
6
Ensure unloading takes place in a controlled manner with a banksman
2
1
2
Entering the works area
Trips and falls
Members of the public
2
2
4
Ensure signs are in place to warn pedestrians
2
1
2
Delivering materials
Trips and falls
operatives
2
2
4
Ensure unloading takes place in a controlled manner with a banksman
2
1
2
Excavating Above Tree Roots
Damaging Roots
Trees
5
3
15
5
1
5
Excavating Above Tree Roots
Damaging Roots
Trees
5
3
15
Ensure that all excavations are watched by banksman to ensure no damage to roots Hand dig areas above tree roots
5
1
5
Circulation of Risk Assessment (to be signed) Name of Assessor
Date of assessment
Site Foreman
Operative
Geoff Field
21/7/2014
Foreman
See attached list
Page 3 of 20
Client
Other
HAZARD EFFECT
5 4 3 2 1
Fatality Major injury / illness More than 3 days off work Minor injury Near miss
PROBABILITY
3 2 1
Very likely to occur Likely to occur Unlikely to occur
RISK RATING SYSTEM +12 Very High Risk 8-12 High Risk
Find alternative method; if necessary involving CDM Coordinator and Design Team. If possible use alternative method. If not, implement further control measures Method Statement sections below must be completed.
4-6 Medium Risk
Control measures needed.
1-3 Low Risk
No further action needed.
RISK ASSESSMENT & METHOD STATEMENT COSHH assessment Summary of details below:Type of materials
Is a COSHH assessment required?
x
Manufacturer
Attached COSHH Sheet
Coated macadam
Tarmac
See Appendix B
Bitumen Tack Coat
Colas
See Appendix B
Permit to work required?:Permit type :Hot Works
Yes /No
Location on site
no
Confined space
no
Access
no
Planning only
no
Work on or near electrical equipment
no
Yes
Additional Details
Page 5 of 20
Details when used
No
RISK ASSESSMENT & METHOD STATEMENT Detail any personal protective equipment required (PPE):PPE item
Yes /No Type
Details when used -
Safety Footwear
Yes
Steel toecap with mid sole protection safety boots
All times on site
Head Protection
Yes
Only helmets to BS 5240 or EN 397 less than 3 years old will be worn.
Safety helmets will be worn by all our operatives at all times, in specified locations
Hi-Vis Clothing
Yes
Class 1
At all times on site
Gloves, include type Weather Protection Eye Protection
Yes
Leather
At all times on site
Yes
Water Resistant
When necessary
Yes
Glasses
At all times on site
Ear Protection
Yes
Full ear defender
When operating machinery
Full body safety harness Respiratory Protection
No No
FFP1
FFP2
Detail any safety equipment that will be required:-
Page 6 of 20
FFP3
RISK ASSESSMENT & METHOD STATEMENT Noise assessment Full details below:Type of Name of machine machine Compressor Tandem vib roller Spin Cutter Vibrating plate Paving Machine
Is a noise assessment required?
No
dB (A) max. at source
Area of use:
Ear protection requirements and type:
Atlas Copco
85
In the open air
Ear Defenders
BOMAG
85
In the open air
Ear defenders
Stihl
85
In the open air
Ear Defenders
WACKER
85
In the open air
Ear Defenders
Marini
85
In the open air
Ear Defenders
Vibration assessment Full details below: Type of machine
Yes
Name of machine
Is a vibration assessment required?
Yes
No
No
no
Vibration level Exposure limit and control measure m/ sec ²
Compressor
Atlas Copco
tba
45minutes per person
Vibrating plate
WACKER
tba
45minutes per person
Manual handling assessment
Is a manual assessment required Full details of all items over 20 kgs as follows:Material/ Weight Amount Dimensions Control measure equipment
Additional Details
No items in excess of 20kg to be lifted by individual operatives
Page 7 of 20
Yes
RISK ASSESSMENT & METHOD STATEMENT Detailed sequence of work operations in a logical order See Appendix A for relevant drawings/sketches and/or technical information if required. Ensure that a site induction is carried out with all site personnel prior to the works commencing To ensure that all works are carried out in accordance with the requirements of the attached risk assessments Ensure that all risk assessments have been discussed and that emergency and fire procedures are in place Ensure that all site personnel are familiar with the safe use of plant to be used Ensure that site plant has been appropriately maintained and is fit for use GENERAL SITE APPRAISEL
Before commencement of works, ensure that the site is ‘walked’ by the operatives to familiarise themselves with its terrain Remove any obvious hazards and the like. Carry out visual check for both overhead and underground services Cable Avoidance Tool is to be used prior to works to establish locations of underground services Check for lose and damaged branches and remove as required Check ground conditions are suitable for safe working
THE WORKS
Parking Bays Away From Tree Roots To excavate area 290mm below required finish levels and dispose of all arisings on site. To supply and lay new 255 x 125mm HB kerbs on concrete bed and haunch. To supply and fit 2 no. new 900 x 450mm diameter plastic road gullies with 425 x 425mm cast iron gratings. To connect to existing drainage with 10mm diameter plastic pipe. To supply and lay 200mm depth of granular sub-base, 60mm depth of AC 20 dense binder 100/150 asphalt and 30mm depth of AC 10 close surface 100/150 asphalt consolidated. Parking Bays Above Tree Roots To carefully excavate BY HAND DIGGING existing turf to an approximate depth of 50mm and dispose of all arisings. To exacavate for new kerbing BY HAND DIGGING and dispose of all arisings. To supply and lay new 2600mmx120mmx200mm railway sleepers and secure with new 600mmx50mmx50mm wooden pegs. To supply and lay 200mm depth of Type 3 granular sub-base, 60mm depth of AC 20 open binder 100/150 asphalt and 30mm depth of AC 10 open surface 100/150 asphalt consolidated. Footpath Above Tree Roots To carefully excavate BY HAND DIGGING existing turf to an approximate depth of 50mm and dispose of all arisings on site. To excavate for new kerbing BY HAND DIGGING and dispose of all arisings on site. To supply and lay new 150x25mm tanalised timber Page 8 of 20
RISK ASSESSMENT & METHOD STATEMENT edging board and secure with 600mmx50mmx50mm wooden pegs. To supply and lay 150mm depth of Type 3 granular sub-base, 45mm depth of AC 20 open binder 100/150 asphalt and 20mm depth of AC 6 open surface 100/150 asphalt consolidated. Bike Shelter Base NO EXCAVATION TO BE CARRIED OUT. To supply and lay 100mm depth of granular sub-base. To supply and fit shuttering. To supply and lay polythene membrane, a single layer of A142 reinforcing mesh and 150mm depth of C30 concrete. 7.2.1 To avoid damage to tree roots, existing ground levels should be retained within the RPA. Intrusion into soil (other than for piling) within the RPA is generally not acceptable, and topsoil within it should be retained in situ. However, limited manual excavation within the RPA might be acceptable, subject to justification. Such excavation should be undertaken carefully, using hand-held tools and preferably by compressed air soil displacement. NOTE Due to the demands that manual excavation places on a development project, and limitations arising from health and safety considerations, it is not realistic to plan for excavation using hand-held tools where there is a need for trench shoring or grading the sides of the excavation to a stable angle of repose.
7.2.2 Roots, whilst exposed, should immediately be wrapped or covered to prevent desiccation and to protect them from rapid temperature changes. Any wrapping should be removed prior to backfilling, which should take place as soon as possible. 7.2.3 Roots smaller than 25 mm diameter may be pruned back, making a clean cut with a suitable sharp tool (e.g. bypass secateurs or handsaw), except where they occur in clumps. Roots occurring in clumps or of 25 mm diameter and over should be severed only following consultation with an arboriculturist, as such roots might be essential to the tree’s health and stability. 7.2.4 Prior to backfilling, retained roots should be surrounded with topsoil or encompassed sharp sand (builders’ sand should not be used because of its high salt content, which is toxic to tree roots), or other loose inert granular fill, before soil or other suitable material is replaced. This material should be free of contaminants and other foreign objects potentially injurious to tree roots.
Page 9 of 20
RISK ASSESSMENT & METHOD STATEMENT Resources Number of operatives anticipated to be on site to carry out the work safely:-
3
Plant, equipment to be used Inspection/certification requirements – See appendix C Van Tandem roller Wacker plate 3T Excavator 3T Dumper 16T Grab Lorry
Materials to be used 255mm x 125mm HB Kerbs 150mm x 50mm BN Kerbs C20 Concrete Type 1 Granular Sub Base Type 3 Granular Sub Base AC 20 dense binder 100/150 AC 20 OPEN binder 100/150 AC 10 close surface 100/150 AC 10 OPEN surface 100/150
Page 10 of 20
RISK ASSESSMENT & METHOD STATEMENT Details of access and egress to work areas:All access to site to be gained from KnelleRoad.
Arrangements for delivery, stacking, storing and movement on site of plant/ materials:Delivery Materials delivered and retained on trucks until required Stacking & Storage Stored on delivery vehicles Movement of plant/Materials On specified Haul routes and Under supervision of a banksman
Page 11 of 20
RISK ASSESSMENT & METHOD STATEMENT Protection needed for any site visitors:Yes Other employees
x
PPE Required
Yes
Hi Vis
No
No
x
Hard Hat
Yes Client Personnel
x
No
x Yes
No
Yes Members of the public Hi Vis
Hi Vis
Hi Vis
Hard Hat
Hard Hat
Ear Defenders
x
Ear Defenders
Ear Defenders
Gloves
x
Gloves
Gloves
Safety Glasses
x
Safety Glasses
Safety Glasses
Safety Boots
x
Safety Boots
Safety Boots
Dust Masks
Dust Masks
Page 12 of 20
Dust Masks
No
x Yes
No
RISK ASSESSMENT & METHOD STATEMENT Is site specific signage required?
Signage:-
Yes
No
x
Full details below:Information –
None X Specific detailed description of safe working at heights/prevention of falls:Hierarchy for managing and selecting equipment for work at height. Selected Equipment Details of use, also give reasons Equipment To be Not why equipment is not used. N/A
Detail of work at height
used
1
Suitable
X
2
MEWPS Scissor lifts, cherry pickers etc. Scaffolding/ Fixed Guardrails
3
Stepladders
X
4
Ladders
X
5
Safety Harness / Safety Lines.
X
X
Detail of work at depths not exceeding 5m
None X Specific detailed description of safe working at depths not exceeding 5m:Hierarchy for managing and selecting equipment for work at depth. a. Selected Equipment Details of use, also give reasons Equipment To be Not why equipment is not used. N/A used
Suitable
1
Safety Harness / Safety Lines.
X
2
Gas Detection
X
3
Ladders
X
4 5
Page 13 of 20
RISK ASSESSMENT & METHOD STATEMENT Environmental controls details Ensure that any fauna and natural wildlife is not unnecessarily disturbed by the works
Description of clearance of waste from site including waste transfer procedures:Excavated materials to be loaded on to tipper and taken to a licenced waste facility
Site Welfare Toilet and hand washing facility are available on site
Description of emergency/rescue and fire procedures. Ensure that any formal Fire Procedures explained at site induction are adhered to-
For out of hours emergency contact:First name Surname Geoff Field
Contact Number 07753-850726
Who will be the on-site First Aider:First name Surname Nick Honeysett
Training course/date July 2013
Page 14 of 20
RISK ASSESSMENT & METHOD STATEMENT Nearest Accident and Emergency Hospital CONQUEST HOSPITAL The Ridge, St Leonards on Sea, Hastings, TN37 7RD.
01424-755255
Competent person/supervision/training/procedures:Duties of supervisor/foreman (name if known at this stage) To act as Company Foreman/representative to carry out works as instructed and specified First name
Surname
Training/ level of competence
Nick
Honeysett
Foreman
Name and contact details of Health and Safety Officer/Manager or Consultant (Must include qualifications/ membership of professional H&S body) Name Contact details Qualifications/membership of professional H&S body Bryan Sheldon
0845-2268393
Page 15 of 20
MIOSH, MIIRSM
RISK ASSESSMENT & METHOD STATEMENT Names of all operatives involved in this operation:NB. To be completed by all operatives involved in the works after Site Supervisor has explained the contents. First Name Surname Job title Signature
Rev No Date
Nick
Honeysett
Foreman
21/7/2014
David
Dann
Skilled Operative
21/7/2014
Dave
Seymour
Skilled Operative
21/7/2014
Name of competent person/s who prepared this method statement:Name Job title Signature Geoff Field Managing Director
Page 16 of 20
Date 15/7/2014
RISK ASSESSMENT & METHOD STATEMENT
APPENDIX A Site Drawings
Technical Information
Page 17 of 20
RISK ASSESSMENT & METHOD STATEMENT
APPENDIX B COSHH Details – (Carried in Foreman Pack)
Page 18 of 20
RISK ASSESSMENT & METHOD STATEMENT
APPENDIX C Plant Inspection / Certification
Page 19 of 20
RISK ASSESSMENT & METHOD STATEMENT
APPENDIX D Generic Risk Assessments – (Carried in Foreman Pack)
Page 20 of 20