LAPORAN MINGGUAN – APRIL MINGGU KE 4

LAPORAN MINGGUAN MINGGU KE-5 (Periode 30 April – 6 Mei 2018)

PROYEK

TRANSMART PEKALONGAN J l . U r i p S u m o h a r j o N o 2 0 , K o t a P e k a l o n g a n - J a w a Te n g a h

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

2. DAFTAR ISI 1. COVER LAPORAN 2. DAFTAR ISI 3. DATA UMUM PROYEK 4. MONITORING PROGRESS KEMAJUAN PEKERJAAN 5. DETAIL PROGRESS MINGGUAN 6. LAPORAN HARIAN PELAKSANAAN (7 HARI) 7. LAPORAN MINGGUAN PELAKSANAAN 8. RENCANA MINGGU DEPAN (ACTION PLAN) 9. FOTO DOKUMENTASI 10. MASALAH POTENSIAL dan SOLUSI

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

3. DATA UMUM PROYEK

Project name No contract Location Duration Ground breaking Owner Contractor Planning Consultant Construction Management Quantity Surveyor

PROYEK TRANSMART PEKALONGAN

: TRANSMART PEKALONGAN : No.001/PK/TR-PKL/IV/2018 : Jl. Urip Sumoharjo No 20, Kota Pekalongan – Jawa Tengah : April, 6th 2018 – April, 5th 2019 : April, 6th 2018 : PT SRI RATU : PT WIJAYA KARYA BANGUNAN GEDUNG : PT GRATAMA KONSULTAN : PT CIPTA PRIMA SEJAHTERA : PT CIPTA PRIMA SEJAHTERA

LAPORAN MINGGUAN – APRIL MINGGU KE 4

4. MONITORING PROGRESS KEMAJUAN PEKERJAAN MONITOR PROGRESS

ptPROYEK TRANSMART PEKALONGAN Jl. Urip Sumoharjo No 20, Kota Pekalongan-Jawa Tengah

p.t.

PERIODE MINGGU KETANGGAL

Jl . D r. Wahi di n 62 A Semarang 50254 Ph. ( 62-24 ) 8505278 F ax : ( 62-24 ) 8315435 E_ mai l : cp ssm g@ya hoo .co .i d

Periode Minggu ke-

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53

Rencana Mingguan Kumulatif % %

Tanggal

06-Apr-18 09-Apr-18 16-Apr-18 23-Apr-18 30-Apr-18 07-Mei-18 14-Mei-18 21-Mei-18 28-Mei-18 04-Jun-18 11-Jun-18 18-Jun-18 25-Jun-18 02-Jul-18 09-Jul-18 16-Jul-18 23-Jul-18 30-Jul-18 06-Agust-18 13-Agust-18 20-Agust-18 27-Agust-18 03-Sep-18 10-Sep-18 17-Sep-18 24-Sep-18 01-Okt-18 08-Okt-18 15-Okt-18 22-Okt-18 29-Okt-18 05-Nop-18 12-Nop-18 19-Nop-18 26-Nop-18 03-Des-18 10-Des-18 17-Des-18 24-Des-18 31-Des-18 07-Jan-19 14-Jan-19 21-Jan-19 28-Jan-19 04-Feb-19 11-Feb-19 18-Feb-19 25-Feb-19 04-Mar-19 11-Mar-19 18-Mar-19 25-Mar-19 01-Apr-19

s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d

08-Apr-18 15-Apr-18 22-Apr-18 29-Apr-18 06-Mei-18 13-Mei-18 20-Mei-18 27-Mei-18 03-Jun-18 10-Jun-18 17-Jun-18 24-Jun-18 01-Jul-18 08-Jul-18 15-Jul-18 22-Jul-18 29-Jul-18 05-Agust-18 12-Agust-18 19-Agust-18 26-Agust-18 02-Sep-18 09-Sep-18 16-Sep-18 23-Sep-18 30-Sep-18 07-Okt-18 14-Okt-18 21-Okt-18 28-Okt-18 04-Nop-18 11-Nop-18 18-Nop-18 25-Nop-18 02-Des-18 09-Des-18 16-Des-18 23-Des-18 30-Des-18 06-Jan-19 13-Jan-19 20-Jan-19 27-Jan-19 03-Feb-19 10-Feb-19 17-Feb-19 24-Feb-19 03-Mar-19 10-Mar-19 17-Mar-19 24-Mar-19 31-Mar-19 05-Apr-19

0,16% 0,16% 0,16% 0,25% 0,35% 0,38% 0,65% 1,48% 2,31% 2,67% 0,00% 1,54% 1,58% 1,88% 1,25% 1,25% 1,86% 1,37% 1,37% 1,99% 1,26% 1,26% 3,05% 2,43% 2,43% 2,77% 2,88% 3,15% 3,15% 2,53% 2,77% 3,00% 3,94% 3,77% 3,37% 3,50% 3,45% 3,33% 2,49% 2,49% 2,50% 2,45% 2,45% 2,54% 2,54% 2,27% 1,68% 1,68% 1,50% 0,34% 0,13% 0,13% 0,13%

0,16% 0,31% 0,47% 0,72% 1,07% 1,45% 2,10% 3,58% 5,89% 8,57% 8,57% 10,12% 11,69% 13,58% 14,82% 16,07% 17,94% 19,31% 20,68% 22,67% 23,93% 25,19% 28,24% 30,67% 33,10% 35,87% 38,74% 41,89% 45,04% 47,57% 50,33% 53,33% 57,27% 61,04% 64,40% 67,90% 71,35% 74,68% 77,17% 79,66% 82,16% 84,61% 87,06% 89,60% 92,14% 94,42% 96,10% 97,79% 99,28% 99,62% 99,75% 99,87% 100,00%

Realisasi Mingguan Kumulatif % %

0,18% 0,16% 0,21% 0,21% 0,31%

0,18% 0,35% 0,56% 0,77% 1,08%

: :

Selisih

5 30 April 2018

s/d

06 Mei 2018

RENCANA

REALISASI

SELISIH

1,07%

1,08%

0,01%

%

0,03% 0,04% 0,09% 0,05% 0,01%

Chart Title 120,00%

100,00%

80,00%

Axis Title

C I PTA PRIMA SEJAHTERA ARCHITECTURAL & ENGINEERING CONSULTANS

60,00%

40,00%

20,00%

Ra : 1,07% Ri : 1,08%

0,00%

Mengetahui, Pemberi Tugas PT. Sri Ratu

Mengetahui ; Owner PT. Trans Ritail Indonesia

Di Periksa dan Disetujui; Konsultan MK PT. Indra Karya (Persero)

07 Mei 2018 Jakarta, Diajukan Oleh : Kontraktor PT. WIJAYA KARYA Bangunan Gedung

....................................... Manajer

......................................... Site Manager

Gede Ari Legowo Site Manager

M. Syamsul Hadi Project Manager

Catatan : =

REALISASI

=

RENCANA

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

5. DETAIL PROGRESS MINGGUAN PT. WIJAYA KARYA BANGUNA GEDUNG. Tbk

BREAKDOWN PROGRESS

LAPORAN MINGGUAN PERIODE KE :

5

PROYEK TRANSMART PEKALONGAN

KEMAJUAN PEKERJAAN PERIODE :

30 April 2018

BOBOT NO

PEKERJAAN

SATUAN VOLUME %

1.

2.

3.

3. 4.

5.

6.

7.

8.

PERSIAPAN Persiapan Lahan Proyek Persiapan Direksi Keet, Gudang, dan Loss Kerja Papan Nama Telepon, Air dan Listrik Kerja Koordinasi Keamanan DESAIN & PERIJINAN Desain IMB dan SLF PEKERJAAN PONDASI Mobilisasi Pancang Spun pile Test Sheet pile PEKERJAAN TANAH Galian Tanah PEKERJAAN STRUKTUR Basement Ground floor Lantai F1 Lantai F2 Lantai F3 Lantai F3 Mezanine Atap PEKERJAAN ARSITEK Basement Ground floor Lantai F1 Lantai F2 Lantai F3 Lantai F3 Mezanine Atap PEKERJAAN M E P Pekerjaan HVAC Pekerjaan Plumbing Gas Installation Pekerjaan Fire Fighting Pekerjaan Electrical Energy Management System Vertical Transportation Generator PEKERJAAN LUAR Earth works and Access Road Deep Well PEKERJAAN PROVISIONAL SUMP Pekerjaan Pondasi Pekerjaan Partisi Pekerjaan Struktur lain PROGRESS TERCAPAI

PROYEK TRANSMART PEKALONGAN

sum sum sum sum sum

1 1 1 1 1

sum sum

1 1

sum sum sum sum

1 1 1 1

sum

1

sum sum sum sum sum sum sum

1 1 1 1 1 1 1

sum sum sum sum sum sum sum

1 1 1 1 1 1 1

sum sum sum sum sum sum sum sum

1 1 1 1 1 1 1 1

sum sum

1 1

sum sum sum

1 1 1

0,70% 0,26% 0,25% 0,02% 0,08% 0,08% 1,71% 0,81% 0,90% 1,82% 0,23% 1,49% 0,07% 0,04% 0,36% 0,36% 13,37% 1,73% 2,57% 2,18% 2,18% 2,18% 0,69% 1,84% 9,47% 0,51% 2,42% 1,70% 1,70% 1,39% 0,45% 1,29% 20,17% 5,32% 1,81% 0,25% 1,55% 5,48% 0,23% 3,16% 2,37% 0,23% 0,07% 0,16% 2,53% 1,77% 0,07% 0,69% 100,00%

Progress Minggu Lalu Volume 0,5 0,50 1,00 0,30 0,30 0,20 0,25 0,15 0,05 -

Weight % 0,32% 0,001 0,001 0,000 0,000 0,000 0,39% 0,002 0,002 0,11% 0,000 0,001 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,82%

s/d

Progress MIngguan : 5 Progress Minggu Ini

Progress %

Volume

50,00% 50,00% 100,00% 30,00% 30,00%

0,20 0,30 0,00 0,20 0,20

20,00% 25,00%

0,00 0,00

15,00% 5,00% -

0,00 0,10 0,00 0,00

-

0,00

-

0,00 0,00 0,00 0,00 0,00 0,00 0,00

-

0,00 0,00 0,00 0,00 0,00 0,00 0,00

-

0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00

-

0,00 0,00

-

0,00 0,00 0,00

Weight 0,16% 0,001 0,001 0,000 0,000 0,00% 0,15% 0,001 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,31%

06 Mei 2018

Komulatif Progress

Progress %

Volume

20,00% 30,00% 20,00% 20,00%

0,7 0,8 1 0,5 0,5

-

0,2 0,25

10,00% -

0,15 0,15

-

Weight 0,48% 0,002 0,002 0,000 0,000 0,000 0,39% 0,002 0,002 0,26% 0,000 0,002 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 1,13%

Progress % 70,00% 80,00% 100,00% 50,00% 50,00% 20,00% 25,00% 15,00% 15,00% -

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 1) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/IV/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

30-Apr-18

5

25

340

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN 3

- Finishing pekerjaan Toilet Carrefour - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Koordinasi WeGe dan MK serta perencana terkait dengan Stacking out siteplan

- Material Plester+Acian - Cat Waterbase - Cubicle Toilet - Sanitair - Keramik 60x60 (r. Rapat) - Semen dll

1 Ls 3 3 4 1 Ls

-

-

Roskam Jidar Lot Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering 2 2 2

- Pembuatan Laporan Harian dan Mingguan - Pembuatan Shop Drawing Stacking Out Siteplan - Pembuatan Shop Drawing Penempatan Tower Crane

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

SORE 19 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 2) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

01-Mei-18

5

26

339

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN

- Hari buruh Nasional - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing

1 Ls 3 3

-

-

Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering 2

- Pembuatan Laporan Harian dan Mingguan

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 3) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

02-Mei-18

5

27

338

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN 3

- Finishing pekerjaan Toilet Carrefour - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Koordinasi WeGe dan MK serta perencana terkait dengan Stacking out siteplan

- Material Plester+Acian - Cat Waterbase - Cubicle Toilet - Sanitair - Keramik 60x60 (r. Rapat) - Semen dll

1 Ls 3 3 4 1 Ls

-

-

Roskam Jidar Lot Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering 2 2 2

- Pembuatan Laporan Harian dan Mingguan - Pembuatan Shop Drawing Stacking Out Siteplan - Pembuatan Shop Drawing Penempatan Tower Crane

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 4) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

03-Mei-18

5

28

337

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN 3

- Finishing pekerjaan Toilet Carrefour - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Joint Survei WeGe dan MK, (Stacking Out Aktual Lapangan)

- Material Plester+Acian - Cat Waterbase - Cubicle Toilet - Sanitair - Keramik 60x60 (r. Rapat) - Semen dll

1 Ls 3 3 4 1 Ls

-

-

Roskam Jidar Lot Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering -

2 2 2

Pembuatan Laporan Harian dan Mingguan Pembuatan Shop Drawing Stacking Out Siteplan Pembuatan Shop Drawing Penempatan Tower Crane Koordinasi WeGe MK terkait kedalaman pondasi Pancang

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 5) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

04-Mei-18

5

29

336

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

KETERANGAN

1 PEKERJAAN LAPANGAN 3

- Toilet Carrefour sudah selesai dan bisa digunakan - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Joint Survei WeGe dan MK, (Stacking Out Aktual Lapangan) - Material Onsite Pancang Spunpile dia 500x15000

- Material Plester+Acian - Cat Waterbase - Cubicle Toilet - Sanitair - Keramik 60x60 (r. Rapat) - Semen - Spunpile dia 500 dll

1 Ls 3 3 4 1 Ls

-

-

Roskam Jidar Lot Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

PROYEK TRANSMAR Jalan Urip Sumoharjo N PEMBERI TUGAS :

2 Administrasi dan Engineering -

2 2 2

Pembuatan Laporan Harian dan Mingguan Pembuatan Shop Drawing Stacking Out Siteplan Pembuatan Shop Drawing Penempatan Tower Crane Koordinasi WeGe MK terkait kedalaman pondasi Pancang

- Komputer/ Laptop - Prnter A4 dan A3 dll

CUACA (CU) / JAM KERJA (HR) 8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

NO.

IT

1 PEKERJAAN LA

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

JAM

PT. S

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

- Toilet Carrefou - Land Clearing - Galian & P - Pengangku - Perataan A - Pembuatan Ru - Joint Survei W - Material Onsite

2 Administrasi d -

Pembuatan La Pembuatan Sh Pembuatan Sh Koordinasi WeG

KETERANGAN (KEJADIAN KHUSUS Pekerjaan dimulai jam : 08.00 WI Jam kerja sepenuhnya dapat/seba

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 6) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

05-Mei-18

5

30

335

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN 1

- Pendatangan Genset dan Kompresor - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Pendatangan Bar bender, Bar Cutter - Material Onsite Pancang Spunpile dia 500x15000

- Material Plester+Acian - Kompresor - Bar bender - Bar Cutter - Semen - Spunpile dia 500 - Genset dll

1 Ls 3 3 4 1 Ls

-

-

Mobile Crane Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering -

2 2 2

Pembuatan Laporan Harian dan Mingguan Pembuatan Shop Drawing Penempatan Tower Crane Koordinasi WeGe MK terkait kedalaman pondasi Pancang Koordinasi WeGe MK terkait desain forcont Struktur ARS

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

6. LAPORAN HARIAN PELAKSANAAN (HARI KE 7) LAPORAN HARIAN PROYEK

PROYEK TRANSMART PEKALONGAN Jalan Urip Sumoharjo No.20, Pekalongan-Jawa Tengah PEMBERI TUGAS :

Nomor : ……../ WG- PGN.3 /LH/V/ 2018

MANAJEMEN KONSTRUKSI

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PT. SRI RATU

NO.

PAKET PEKERJAANpt : ( √ ) PERSIAPAN ( √ ) STRUKTUR ( √ ) ARSITEKTUR ( ) MEP

Waktu Pelaksanaan Proyek :

Tanggal :

Minggu ke :

Hari ke :

Sisa hari :

365

06-Mei-18

5

31

334

KONTRAKTOR : PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278

TENAGA /JUMLAH ORANG

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

MATERIAL YANG MASUK HARI INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

JENIS BAHAN

ALAT-ALAT YANG DIGUNAKAN

1 PEKERJAAN LAPANGAN 1

- Pendatangan Genset dan Kompresor - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Material Onsite Pancang Spunpile dia 500x15000 Untuk pondasi Tower Crane

- Material Plester+Acian - Kompresor - Bar bender - Bar Cutter - Semen - Spunpile dia 500 - Genset dll

1 Ls 3 3 4 1 Ls

-

-

Mobile Crane Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level dll

2 Administrasi dan Engineering -

2 2 2

Pembuatan Laporan Harian dan Mingguan Pembuatan Shop Drawing Penempatan Tower Crane Koordinasi WeGe MK terkait kedalaman pondasi Pancang Koordinasi WeGe MK terkait desain forcont Struktur ARS

- Komputer/ Laptop - Prnter A4 dan A3 dll

KETERANGAN (KEJADIAN KHUSUS DI LAPANGAN) : Pekerjaan dimulai jam : 08.00 WIB sampai dengan jam 22.00 WIB. Jam kerja sepenuhnya dapat/sebagian tidak dapat digunakan karena: cuaca cerah

CUACA (CU) / JAM KERJA (HR) JAM

8

PAGI 9

10

11

12

13

SIANG 13

14

15

16

17

18

19

SORE 20

21

22

23

24

1

MALAM 2 3

4

5

6

CU

MALAM JAM KERJA

TOTAL JAM JAM TIDAK KERJA

-

16

HR LEGEND

CERAH

BERAWAN

DILAPORKAN OEH, PT WIJAYA KARYA BANGUNAN GEDUNG Tbk

Nama

:

Jabatan

:

Gani A A Engineering

PROYEK TRANSMART PEKALONGAN

HUJAN

TIDAK KERJA

MENYETUJUI, PT. CIPTA PRIMA SEJAHTERA

Nama Jabatan

: Gede Ari Legowo : Site Manajer

MENGETAHUI, PT.SRI RATU

Nama Jabatan

: :

KETERANGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

7. LAPORAN MINGGUAN PELAKSANAAN LAPORAN MINGGUAN Nomor : …….../WG-PGN.3/LM/V/2018 PEMBERI TUGAS

(√) (√) (√)

PAKET PEKERJAAN

NOMOR KONTRAK MULAI PEKERJAAN

NO

1 2

3 4 5 6 7 8 9

ITEM PEKERJAAN/KEGIATAN/TENAGA KERJA

- Finishing pekerjaan Toilet Carrefour - Land Clearing - Galian & Pembongkaran Bangunan eksisting - Pengangkutan material bongkaran bangunan eksisting - Perataan Area Lapangan dari puing-puing - Pembuatan Ruang Rapat Direksi Keet - Koordinasi WeGe dan MK serta perencana terkait dengan Stacking out siteplan - Pembuatan Laporan Harian dan Mingguan - Pembuatan Shop Drawing Stacking Out Siteplan - Pembuatan Shop Drawing Penempatan Tower Crane - Joint Survei WeGe dan MK, (Stacking Out Aktual Lapangan) - Material Onsite Pancang Spunpile dia 500x15000 Untuk pondasi Tower Crane

TOTAL

Hari

365 TENAGA JUMLAH ORANG

3 1 Ls 3 3 4 1 Ls

30 April 2018

MATERIAL YANG MASUK MINGGU INI JUMLAH YANG JUMLAH YANG DITERIMA DITOLAK

PT WIJAYA KARYA BANGUNAN GEDUNG.TBK PERIODE MINGGU KE HARI KE SISA HARI

Material Plester+Acian Cat Waterbase Cubicle Toilet Sanitair Keramik 60x60 (r. Rapat) Semen Spunpile dia 500

2 2 2 1 Ls 1 Ls

-

06 Mei 2018

5

31

ALAT-ALAT YANG DIGUNAKAN

JENIS BAHAN

-

STRUKTUR ARCHITECTURE MEP

TANGGAL

06 April 2018

WAKTU PELAKSANAAN

KONTRAKTOR

PROYEK TRANSMART PEKALONGAN

CONSTRUCTION MANAGEMENT

-

334

KETERANGAN

Roskam Jidar Lot Cangkul Dumtruck index 8 m3 Excavator Theodolith Waterpass / Level Komputer/ Laptop Prnter A4 dan A3

17,00

Pekerjaan dimulai jam 08:00 WIB pagi s/d jam 21:00 WIB sore Jam kerja sepenuhnya dapat / sebagian tidak dapat digunakan untuk bekerja, karena beberapa pekerjaan masih belum mendapatkan ijin pekerjaan dan cuaca sedang hujan Mengetahui, Pemberi Tugas PT. SRI RATU

PROYEK TRANSMART PEKALONGAN

Menyetujui, Manajemen Konstruksi PT. CIPTA PRIMA SEJAHTERA

Dilaporkan oleh, Kontraktor PT.Wijaya Karya Bangunan Gedung. Tbk

Gede Ari Legowo

Gani A.A

Site Manager

Engineering

LAPORAN MINGGUAN – APRIL MINGGU KE 4

8. RENCANA MINGGU DEPAN (ACTION PLAN) RENCANA KERJA MINGGUAN Nomor : 001 /WG-PGN.3/LM/IV/2018 PEMBERI TUGAS

CONSTRUCTION MANAGEMENT

( √ ) STRUKTUR

CIPT A PRIMA SEJAHTERA p .t. ARCHITECTURAL & ENGINEERING CONSULTANS

PAKET PEKERJAAN

( √ ) ARCHITECTURE

Jl. Dr. Wahidin 62 A Semarang 50254 Ph. ( 62-24 ) 8505278 Fax : ( 62-24 ) 8315435 E_mail : [email protected]

NOMOR KONTRAK MULAI PEKERJAAN

NO

ITEM PEKERJAAN/KEGIATAN

1.

PEKERJAAN LAPANGAN - Pek Penyelesaian banner Pagar Proyek - Pek Pembuatan R. Rapat Direksi keet - Pek Bongkar dan angkut material Gedung Eksisting - Pendatangan Material Spunpile dia 500 - Pendatangan service Crane -Material dan Pabrikasi Besi Pondasi TC - Pendatangan HSPD 320 ton - Assembly dan seeting HSPD 320 ton

2.

PEKERJAAN ADM & GAMBAR - GB Layout dan pondasi TC - GB Pondasi spunpile - Laporan Harian dan Mingguan

TOTAL

( √ ) MEP

06 April 2018

WAKTU PELAKSANAAN

PT WIJAYA KARYA BANGUNAN GEDUNG.TBK PERIODE MINGGU KE HARI KE SISA HARI

TANGGAL Hari

365 TENAGA JUMLAH ORANG

KONTRAKTOR

PROYEK TRANSMART PEKALONGAN

pt

07 Mei 2018

13 Mei 2018

6

MINGGU

BOBOT

38

327

TENAGA HARI

SENIN

SELASA

RABU

KAMIS

JUMAT

SABTU

-

Pekerjaan dimulai jam 08:00 WIB pagi s/d jam 22:00 WIB malam Jam kerja sepenuhnya dapat / sebagian tidak dapat digunakan untuk bekerja, karena beberapa pekerjaan masih belum mendapatkan ijin pekerjaan dan cuaca sedang hujan Mengetahui, Pemberi Tugas PT. SRI RATU

PROYEK TRANSMART PEKALONGAN

Menyetujui, Manajemen Konstruksi PT. CIPTA PRIMA SEJAHTERA

Dilaporkan oleh, Kontraktor PT.Wijaya Karya Bangunan Gedung. Tbk

Gede Ari Legowo

Gani A A

Site Manajer

Engineering

LAPORAN MINGGUAN – APRIL MINGGU KE 4

9. FOTO DOKUMENTASI

MOS, SPUN PILE DIA 500 ex WIKA BETON

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

9. FOTO DOKUMENTASI

- PEMBONGKARAN BANGUNAN EKSISTING, - M U ATA N M AT E R I A L P U I N G B O N G K A R A N

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

9. FOTO DOKUMENTASI

-

P E N D AT A N G A N M AT E R I A L , ANGKUR TOWER CRANE

PROYEK TRANSMART PEKALONGAN

-

P E N D AT A N G A N B A R BENDER, BAR CUTTER, KOMPRESOR DAN GENSET

LAPORAN MINGGUAN – APRIL MINGGU KE 4

9. FOTO DOKUMENTASI

- P E M A S A N G A N B A N N E R T R A N S M A R T PA D A PA G A R P R O Y E K

PROYEK TRANSMART PEKALONGAN

LAPORAN MINGGUAN – APRIL MINGGU KE 4

9. FOTO DOKUMENTASI

-

PERBAIKAN BANGUNAN EKSISTING, UNTUK R. CLINIC DAN KANTOR SHE

PROYEK TRANSMART PEKALONGAN

-

R. TOILET CARREFOUR SUDAH BI

LAPORAN MINGGUAN – APRIL MINGGU KE 4

10. MASALAH POTENSIAL dan SOLUSI

NO 1

MASALAH POTENSIAL

SOLUSI

KOORDINASI DENGAN CAREFOUR TERKAIT PEMBONGKARAN DAN PARTISI

RUTIN DI LAKUKAN, HAL INI DIKARENAKAN PEKERJAAN BONGKARAN YANG FRONTAL SEHINGGA MEMBUTUHKAN SPACE/RUANG YANG LUAS, DAN INSTALASI 2 YANG MASIH DIPAKAI OLEH CAREFOUR. -

2

KONDISI TANAH EKSISTING TERKAIT PEKERJAAN PONDASI

-

-

3

4

PEKERJAAN PONDASI MOBILISASI ALAT HSPD DAN SPUN PILE

DESAIN

PROYEK TRANSMART PEKALONGAN

-

PENYELIDIKAN TANAH SEGERA DI SELESAIKAN SAMPAI REPORT LAPANGAN BORLOG 1 DAN BORLOG 2 KEDALAMAN 60 M, UNTUK DATA PERHITUNGAN STRUKTUR TEST PILE PADA PONDASI TC, SPUN 500 M KEDALAMAN 30 M. HASILNYA BISA DI GUNAKAN UNTUK ACUAN PERENCANAAN MOBILISASI ALAT DARI JAKARTA MEMAKAN WAKTU 3 HARI DARI JAKARTA DIKARENAKAN WEEKEND, SERVICE CRANE SUDAH ON SITE SEJAK HARI JUMAT. SEGERA SETTING UNTUK MEMULAI PEKERJAAN. ALAT HSPD 320 T MASUK SENIN MALAM 5/5/18 SPUN PILE D 500 M MASUK SENIN MALAM 30/4/18 PEKERJAAN PONDASI TC MULAI 5/5/2018

PARSIAL FOR CONSTRUCTION NYA AGAR BISA TERBIT, UNTUK ACUAN