The Cebu CFBC Plant Chronicle
EDITION NO. 13, April 20, 2009
CEBU POWER PLANT PROJECT ACHIEVES 1 MILLION MANHOURS WITH ZERO ACCIDENT
d o
oosan, KEPCO SPC Power Corporation’s main contractor for the 200-
megawatt Cebu Power Plant Project, received a much deserved recognition last April 14, 2009 for achieving 1 million manhours without Loss Time Accident (LTA) during the course of the construction of the project from February 15, 2008 to March 19, 2009.
The celebration at the construction site was also dubbed as “Safety Day.” To recall, with the guidance of KSPC, Doosan has launched the Environmental, Health and Safety (EHS) Program in line with KSPC’s commitment of protecting the safety of the environment, the affected community and the people at the construction site.
“One Million Manhours Without Lost Time Accident (LTA)” Ceremony 1
1 Million Manhours without LTA (Con’t.)
C a
ertificates of appreciation and commendation were given to the engineers
of Doosan and its sub-contractors for their full support and cooperation in achieving the EHS Program’s policies and goals.
Doosan assured to continue to enhance the EHS Program in order to boost the safety culture they have started on the project as it emphasized that safety starts from everyone.
Workers are reminded to do safety practices with a
mindset: “We must come home to our family safe and complete.”
On the otherhand, KSPC extended its appreciation not only to the main contractor and subcontractors but to the entire workforce for their big contribution in attaining another milestone of the project, this time the “Zero Accident” Target. The program was capped by the partaking of lunch by the engineers, guests and all the workers.
Giving of Certificates of Appreciation (April 14, 2009) 2
Slipforming Works
A
nother state of the art technology in the field of construction industry is
slipforming. Although slip forming is not new in the construction industry, this is not applicable for all types of structures. This is most effective only to special constructions such as silos, smokestack and any round structure.
KSPC will use this technology in order to enhance and attain a timely completion of its project. In this way, the construction process will be done continuously from start to finish, especially in the construction of our smokestack. The structure has a total height of 110 meters above ground with a diameter of 9 meters.
Construction of Starter Platform at Smokestack (April 15, 2009)
3
KSPC Conducts Tree Planting
K T
SPC Power Corporation conducted a tree planting activity in Colon, Naga,
Cebu on April 17, 2009 in line with the program of the Board of Investments (BOI) of the Department of Trade and Industry.
A total of 200 seedlings of Narra and Neem trees were planted along the highway in front of the gate of the existing Naga Power Plant Complex. Local officials of Barangay Colon and Naga City Government and representatives of the Community Environment and Natural Resources Office (CENRO) were invited to partake in the important event.
The participants in the tree planting activity promised to see to it that the planted seedlings will be taken care of to make sure they grow to the fullest.
Tree Planting Activity (April 17, 2009)
4
Local World Youth Day
W
hen the City of Naga, Cebu was chosen by the Catholic Church to host
the 24th Local World Youth Day (LWYD) in April 2-5, 2009, KEPCO SPC Power Corporation at once agreed to become a major sponsor to be able to assist its host community in the huge preparation that it needs to undertake.
The LWYD gathers young people around the archdiocese of Cebu and the neighboring dioceses of Eastern and Central Visayas to build bridges of friendship and hope between parishes, people and cultures.
The theme of this year’s celebration is “Youth: Growing Together in Grace as the Body of Christ” (Ephesians 2:21 and 4:15).
24th Local World Youth Day (April 2, 2009)
5
Project Progress
Boiler Unit No. 1 Building, 4th Tier Steel Structure Erection (April 16, 2009)
Boiler Unit No. 2 Building, 1st Tier Steel Structure Erection (April 16, 2009) 6
Project Progress
On-going Works of the Discharge Tunnel after Concrete Pouring (April 16, 2009)
On-going Fabrication of Coal Silo Shell for Boiler Unit No. 1 April 16, 2009 (April 19, 2009) 7
Project Progress
Rebar and Form Works, Turbine Unit No. 1 Generator Pedestal (April 16, 2009)
View of the On-going Works for the Administration Building (April 16, 2009) 8
Project Information
PROJECT PROPONENT :
KEPCO SPC Power Corporation (KSPC)
CAPACITY
:
100 MW x 2 Units
PLANT TECHNOLOGY
:
CFBC (Circulating Fluidized Bed Combustion)
LOCATION
:
Colon, City of Naga (20 Km from Cebu City)
TARGET COMPLETION :
Unit No. 1: February 2011; Unit No. 2: May 2011