Sno 1 a
b
c
d
Particulars
No
L
R.C.C. Column (Lintel Top to Parapet Top) C1 6 1.00 C2 8 1.00 C3 11 0.75 Slab Beam Computer Lab 1 7.25 4 15.38 4 15.25 1 23.17 3 23.82 2 15.38 2 15.25 Conference Room 1 2 7.08 2 7.18 2 12.58 2 12.46 1 23.17 2 12.71 1 12.58 2 28.17 Verandah 1 14.00 6 13.63 1 13.26 1 1.66 Stairs 2 11.00 Slab Computer Lab 1 1602.70 Conference Room 1 1 1172.40 Vrandah 1 846.40 Lintel Beam W2 4 7.00 D1 2 6.00 Stair Case Mid Landing Beam 3 11.00 Waist Slab 1 27.51 1 26.93 1 12.75 Steps 10 1.00 1 0.10
2 a
Shuttring Column
b
Slab Beam Computer Lab
B
H/D
Qty
1.33 1.67 0.75
7.50 7.50 7.50
59.85 100.20 46.41
0.75 0.75 0.75 1.00 1.00 0.75 0.75 0.75 0.75 0.75 0.75 1.00 0.75 0.75 1.00 0.75 0.75 0.75 0.75 0.75
1.61 1.11 1.11 2.11 2.11 1.11 1.11 0.61 0.61 0.98 0.98 2.11 0.98 0.98 2.36 0.86 0.86 0.86 0.86 1.25
8.74 51.06 50.65 48.81 150.57 25.53 25.32 6.45 6.53 18.53 18.35 48.81 18.72 9.27 132.79 9.00 52.56 8.52 1.07 20.63
-
0.39 0.39 0.39
628.26 459.58 331.79
0.75 0.75
0.58 0.58
16.24 6.96
0.75 5.00 5.00 1.00 5.00 5.00
1.25 0.39 0.39 0.39 0.58 Total
30.94 54.06 52.91 5.01 29.15 0.50 2533.76 Cuft
6 8 11
4.66 5.34 3.00
-
7.50 7.50 7.50
209.7 320.4 247.5
2 8 8 2 6 4
7.25 15.38 15.25 23.17 23.82 15.38
-
1.61 1.11 1.11 2.11 2.11 1.11
23.30 136.16 135.05 97.63 301.13 68.08
Unit
Conference Room 1
Verandah
c
d
Stairs Stairs All Area Sides Lintel Beam W2 D1 Staircase First Lift Second Lift Steps Riser Deduction W2 D1
3
Brick Work ( 9" Th.) Computer Lab
Conference Room 1
Stairs Parapet Wall Deduction W2 D1 Stairs Window Deduction LB Computer Lab
Conference Room 1
4 15.25 4 7.08 4 7.18 4 12.58 4 12.46 2 23.17 4 12.71 2 12.58 4 28.17 2 14.00 12 13.63 2 13.26 2 1.66 4 11.00 2 11.00 1 3834.60 1 306.64
0.75 -
1.11 0.61 0.61 0.98 0.98 2.11 0.98 0.98 2.36 0.86 0.86 0.86 0.86 1.25 0.39
67.53 17.19 17.42 49.41 48.94 97.63 49.92 24.71 265.59 24.00 140.17 22.73 2.85 55.00 16.50 3834.60 119.59
-
0.58 0.58
35.96 15.66
0.39
153.35 157.10 17.72 125.00 0.39
4 2
15.50 13.50
1 1 1 1 1
30.67 31.42 17.72 12.50 1.00
8 4
0.50 0.50
1 4 4 1 2 2 2 2 1 1 1 1
7.25 15.38 15.25 23.17 7.08 7.18 12.58 12.46 23.17 11.00 128.89 117.50
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
10.50 11.00 11.00 10.00 11.50 11.50 11.13 11.13 10.00 11.25 3.00 3.00
57.09 507.38 503.25 173.78 122.04 123.77 209.93 207.93 173.78 92.81 290.00 264.38
11 2 1
6.00 5.00 4.00
0.75 0.75 0.75
4.00 8.00 4.00
-198.00 -60.00 -12.00
1 4 3 2 2 1 1 1 1 1
16.13 15.25 15.38 6.76 7.18 12.56 7.00 5.50 4.33 5.00
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
-7.05 -26.67 -20.17 -5.91 -6.27 -5.49 -3.06 -2.40 -1.89 -2.19
5.00 5.00 1.00 10.00 0.75 0.75
Total
-3.00 -1.50 6893.40 Sqft
Deduction Column
6 8 11
1 1 0.75
1.33 1.67 0.75
3 3 3 Total
4
Plaster (Inside) Computer Lab
Conference Room
Stairs Verandah Deduction (Door, Window) W2 D1
5
Plaster (Outside) Computer Lab
Deduction W2 Stair Window
6
7
2 2 12 2 1 1 2 8 2 2 1 1
25.00 64.25 0.58 25.47 40.00 30.45 6.41 0.58 0.25 25.75 11.00 105.75
11 2
6.00 5.00
1 1 2 1 1
7.25 65.00 7.08 31.06 11.22
7 1
6.00 4.00
1 1
1
0.75 0.75
-
12.13 12.13 12.13 12.13 12.13 12.13 12.13 12.13 12.13 12.13 12.13 12.13 4.00 8.00 Total
14.05 14.05 14.05 14.05 14.05
-23.94 -40.08 -18.56 2292.43 Cuft
606.25 1558.06 84.83 617.65 485.00 369.21 155.44 56.26 6.06 624.44 133.38 1282.22 -198.00 -60.00 5720.79 Sqft
101.86 913.25 198.81 436.39 157.64
0.75 0.75
4.00 4.00 Total
-126.00 -12.00 1669.95 Sqft
117.50 128.89
-
6.75 6.75 Total
793.13 870.01 1663.13 Sqft
117.50
8.28
Plaster Parapet Wall
Plaster Verandah Wall Above Lintel
-
972.31
Total
972.31 Sqft
4.71 4.33 4.33
Total
553.43 353.07 50.14 956.63 Sqft
8
Plaster Chajja
1 1 1
9
Plaster Celling
1 5424.03
-
Total
5424.03 6380.67 Sqft
1 1602.70 1 1172.40 1 846.40 1 283.20 1 45.25 1 12.75
5.00 1.00
Total
1602.70 1172.40 846.40 283.20 226.25 12.75 4143.70 Sqft
10 Flooring Computer Lab Conference Room Verandah Stair Case Area Stairs Steps Stair Midlanding
117.50 81.54 11.58
Remarks
B19-Slab Depth B17-Slab Depth B17-Slab Depth B4-Slab Depth B4-Slab Depth B18-Slab Depth B18-Slab Depth B9-Slab Depth B9-Slab Depth B6-Slab Depth B6-Slab Depth B8-Slab Depth B7-Slab Depth B7-Slab Depth B5-Slab Depth B1-Slab Depth B1-Slab Depth B1-Slab Depth B1-Slab Depth
BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam BW-Slab Beam
2 B19 1.5 B17 1.5 B17 2.5 B4 1 B9 1 B9 1.38 B6 1.38 B6 2.5 B8 1.25 B16
GL To Lintel Bottom And Lintel Top To Slab Bottom