CUADRO COMPARATIVO DE AVANCE DE OBR
Nº VALORIZACION
SEMANA 1
SEMANA 2
1
2
0.00 0.00
31.20% 31.20%
17.62% 48.82%
VALORIZACION EJECUTADA ACUMULADA
0.00 0.00
60.68% 60.68%
5.00% 65.68%
P O R C E N TAJ E AVAN C E A C U M U L A D O
VALORIZACION PROGRAMADA ACUMULADA
CURVA S DE AVANCE DE 100.00% 86.18% 84.89%
90.00% 80.00% 70.68% 70.00%
65.68% 61.15%
60.68% 60.00% 48.82%
50.00% 40.00% 31.20% 30.00% 20.00% 10.00% 0.00%
; 0.00% ; 0.00%
SEMANA 1
SEMANA 2
SEMANA 3
SEMANA 4
N°04 DE VALORI Z PROGRAMADO
EJECU
LA OBRA SE ENCUENTRA:
PARATIVO DE AVANCE DE OBRA SEMANA 3
SEMANA 4
SEMANA 5
SEMANA 6
SEMANA 7
3
4
5
6
7
12.33% 61.15%
23.74% 84.89%
11.87% 96.76%
2.43% 99.19%
0.81% 100.00%
5.00% 70.68%
15.50% 86.18%
6.00% 92.18%
3.91% 96.09%
3.91% 100.00%
99.19%
100.00%
CURVA S DE AVANCE DE OBRA
96.76%
86.18% 84.89%
92.18%
SEMANA 4
SEMANA 5
96.09%
70.68% 65.68% 61.15%
.68% 48.82%
.20%
ANA 1
SEMANA 2
SEMANA 3
SEMANA 6
N°04 DE VALORI ZA CI ON PROGRAMADO
EJECUTADO
LA OBRA SE ENCUENTRA: CONCLUIDA
SEMANA 7