ADMINISTRATION BLOCK ( BLOCK A )
PROJEK RUNDING TERUS SEKOLAH SECARA REKA DAN BINA SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR KONTRAKTOT TURNKEY : BAKTI INSANI SDN. BHD. BLOK PENTADBIRAN TENDER REF
ELEMENT/DESCRIPTION
AMOUNT (RM)
BUDGET TOTAL LAB.
TOTAL MATL
ACTUAL TOTAL
MARGIN
TOTAL LABOUR TOTAL MATERIAL
PROFIT TOTAL SUB RATE
TOTAL AMOUNT
BUDGET
ACTUAL
SUMMARY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Piling works Work Below Lowest Floor Level Frame Upper Floor Construction Roof and roof covering Staircases External wall Internal wall and partition Door and window Floor finishes Wall finishes Ceiling finishes Sanitary appliances Apron and perimeter drain Internal signages TOTAL
139,519.00 145,740.00 271,696.45 233,055.00 161,442.00 29,397.25 46,105.20 16,243.20 174,960.00 30,044.00 54,498.00 58,572.50 26,940.00 15,699.20 15,000.00 1,418,911.80
153,973.00 36,905.90 77,041.04 61,564.25 20,278.20 4,865.00 8,545.80 4,323.90 1,844.00 14,904.00 24,059.00 27,799.60 2,830.40 438,934.09
11,300.00 87,050.00 138,790.55 147,494.10 102,641.40 17,790.95 32,924.60 10,557.60 102,214.00 13,590.00 21,529.20 13,316.50 23,000.00 8,305.00 13,000.00 743,503.90
165,273.00 123,955.90 215,831.59 209,058.35 122,919.60 22,655.95 41,470.40 14,881.50 104,058.00 28,494.00 45,588.20 41,116.10 23,000.00 11,135.40 13,000.00 1,182,437.99
(25,754.00) 21,784.10 55,864.86 23,996.65 38,522.40 6,741.30 4,634.80 1,361.70 70,902.00 1,550.00 8,909.80 17,456.40 3,940.00 4,563.80 2,000.00 236,473.81
26,353.51 2,794.27
29,147.77
118,298.54 10,951.61
129,250.14
82,121.24 20,408.00 7,063.20
109,592.44
82,121.24 165,060.04 20,809.07 267,990.35
(25,754.00) 21,784.10 24,217.38
20,247.48
57,397.76 (19,320.04) 101,038.28
139,116.00
ADMINISTRATION BLOCK
REF
ELEMENT/DESCRIPTION
UNIT
TENDER
QTY
LAB. RATE RATE 1 A B C
D E F G
H I
PILING WORKS Mobilisation equipments & demobilisation Setting out,piling record & as-built drawings Supply PC G45 250mm x 250mm piles 12m extension 9m extension
LS LS M NO NO
1 1 2877
Handle,transport and pitch for 250mm x 250mm piles Drive only for 250mm x 250mm piles Jointing/extension for 250mm x 250mm piles Cut off pile head for 250mm x 250mm piles Chainsaw Hacking
No M No No No No
274 2877 137 137
Preliminary testing Subsequent testing
No No
2 2
Sub-total
32.00
6.00 8.00 15.00 20.00
4,500.00 3,000.00
MATL. RATE
BUDGET TOTAL LAB. TOTAL MATL
TOTAL
MARGIN
QTY
ACTUAL MATERIAL TOTAL RATE
LABOUR
AMOUNT
AMOUNT (RM)
2,000.00 1,000.00 92,064.00
1,644.00 23,016.00 2,055.00 2,740.00
9,000.00 6,000.00 139,519.00
GROSS PROFIT BUDGET
1,800.00 9,500.00 40.00
9.00 6.00 20.00 25.00
3,500.00 3,000.00
115,080.00
1,800.00 9,500.00 -
2,466.00 17,262.00 2,740.00 3,425.00
7,000.00 6,000.00 153,973.00
-
11,300.00
1,800.00 9,500.00 115,080.00
2,466.00 17,262.00 2,740.00 3,425.00
7,000.00 6,000.00 165,273.00
200.00 (8,500.00) (23,016.00)
(822.00) 5,754.00 (685.00) (685.00)
2,000.00 (25,754.00)
LS LS
-
-
4,000.00 5,227.00
4,000.00 5,227.00
118 58
-
-
320.00 278.78
0 1968 91
-
-
7.00 21.00
37,760.00 16,169.24 53,929.24 13,776.00 1,911.00 630.00 1,580.00 2,210.00 1,068.00
18 79
35.00 20.00
LS
1,068.00
82,121.24
200.00 (8,500.00)
REMARKS ACTUAL
(2,000.00) (4,227.00)
(23,016.00) (822.00) 5,754.00 (685.00) (685.00)
38,134.76 1,644.00 rate incl. In drive 9,240.00 144.00
2,000.00 (25,754.00)
530.00 7,932.00 6,000.00 rate incl. In prelime test 57,397.76
BLOK PENTADBIRAN TENDER REF 2 A B C D E F G H I J K L
M N
O P Q R S T
ELEMENT/DESCRIPTION WORK BELOW LOWEST FLOOR LEVEL Exc. oversite 250mm deep Exc. pile caps/footing not exc. 1.50m deep Ditto exc. 3.00m deep Exc. for ground beam ditto 150mm thick hardcore 50mm thick lean concrete G15 beneath pile cap 50mm ditto ground beam VRC G25 in pile cap/pad footing Ditto Column stumps Ditto ground beam Ditto 125mm thick in ground floor slab VRC G30 in pile cap/pad footing Reinforcement bar in pile cap/footing Y 16 R 10 Reinforcement in column stumps Reinforcement in ground beam Y16 Y20 Y25 R10 BRC B6 in floor slab BRC A10 in floor slab Sawn formwork to sides of pile cap/footing Ditto column stump Ditto ground beam 0.25mm thick damp proof membrance Prepare and apply termite treatment Sub-total
BUDGET
QTY
RATE
M2 M3 M3 M3 M2 M2 M2 M3 M3 M3 M2 M3 Kg Kg Kg Kg Kg Kg Kg Kg Kg
1230 114 4 102 1230 76 161 43 8 94 1230
2.50 8.50 10.00 8.50 8.50 7.00 7.00 185.00 185.00 185.00 18.50
3,075.00 969.00 40.00 867.00 10,455.00 532.00 1,127.00 7,955.00 1,480.00 17,390.00 22,755.00
8.00 8.00 8.00 2.50 1.30 1.30 28.60 28.60 28.60 3.60
1769
1.85
3,272.65
2598 1.85 15373 1.85
4,806.30 28,440.05
1230
12.00
129 79 787 1230 1230
24.00 24.00 24.00 2.00 1.20
M2 M2 M2 M2 M2 M2 M2
AMOUNT (RM)
LAB. RATE
UNIT
MATL. RATE
2.00
TOTAL LAB.
ACTUAL TOTAL MATL
TOTAL
5.70 5.50 5.50 122.10 122.10 122.10 15.30
912.00 32.00 816.00 3,075.00 98.80 209.30 1,229.80 228.80 2,688.40 4,428.00
2,460.00 7,011.00 418.00 885.50 5,250.30 976.80 11,477.40 18,819.00
2,460.00 912.00 32.00 816.00 10,086.00 516.80 1,094.80 6,480.10 1,205.60 14,165.80 23,247.00
0.32
1.15
566.08
2,034.35
2,600.43
0.32 0.32
1.15 1.15
831.36 4,919.36
2,987.70 17,678.95
3,819.06 22,598.31
14,760.00
1.10
7.20
1,353.00
8,856.00
10,209.00
3,096.00 1,896.00 18,888.00 2,460.00 1,476.00 145,740.00
13.00 13.00 13.00 0.50 1.60
7.00 7.00 7.00 1.00
1,677.00 903.00 2,580.00 1,027.00 553.00 1,580.00 10,231.00 5,509.00 15,740.00 615.00 1,230.00 1,845.00 1,968.00 1,968.00 36,905.90 87,050.00 123,955.90
QTY
% W/DONE QTY W/DONE LAB. RATE
MATE. RATE
SUB. RATE
GROSS TOTAL LAB
TOTAL MATE
TOTAL SUB
TOTAL AMOUNT
1,230.00 114.00 4.00 102.00 1,062.00 80.00 100.00 71.00 568.00 58.99 3,088.00 295.00 123.00 1,313.00 13,128.00 2,719.00
100% 100% 100% 100% 100% 100% 100% 0% 0% 100% 100% 100% 0% 100% 100% 0% 0% 100% 100% 100% 100%
1,230.00 114.00 4.00 102.00 1,062.00 80.00 100.00 71.00 568.00 58.99 3,088.00 295.00 123.00 1,313.00 13,128.00 2,719.00
2.00 2.00 2.00 23.50 23.50 23.50 0.29 0.29 0.29 0.29 0.29 0.29
2.10 5.50 5.50 111.00 111.00 117.50 1.12 1.19 1.12 1.12 1.12 1.19
2.00 6.00 8.00 8.00 -
2,124.00 160.00 200.00 1,668.50 13,348.00 1,386.27 895.52 85.55 35.67 380.77 3,807.12 788.51
2,230.20 440.00 550.00 7,881.00 63,048.00 6,931.33 3,458.56 351.05 137.76 1,470.56 14,703.36 3,235.61
2,460.00 684.00 32.00 816.00 -
2,460.00 684.00 32.00 816.00 4,354.20 600.00 750.00 9,549.50 76,396.00 8,317.59 4,354.08 436.60 173.43 1,851.33 18,510.48 4,024.12
1,155.00 165.00 79.00 609.00 1,062.00 1,062.00
0% 100% 100% 100% 100% 100% 100%
1,155.00 165.00 79.00 609.00 1,062.00 1,062.00
1.00 0.30 -
10.87 1.23 -
18.00 18.00 18.00 1.00
1,155.00 318.60 26,353.51
12,554.85 1,306.26 118,298.54
2,970.00 1,422.00 10,962.00 1,062.00 20,408.00
13,709.85 2,970.00 1,422.00 10,962.00 1,624.86 1,062.00 165,060.04
PROFIT BUDGET
615.00 57.00 8.00 51.00 369.00 15.20 32.20 1,474.90 274.40 3,224.20 (492.00) 672.22 987.24 5,841.74 4,551.00 516.00 316.00 3,148.00 615.00 (492.00) 21,784.10
REMARKS
PROFIT ACTUAL
615.00 285.00 8.00 51.00 6,100.80 (68.00) diff. qty 377.00 7,955.00 1,480.00 7,840.50 (53,641.00) diff. Qty (8,317.59) diff. Concrete 3,272.65 (4,354.08) diff. qty (436.60) diff. qty 4,806.30 28,440.05 (173.43) diff. qty (1,851.33) diff. qty (18,510.48) diff. qty (4,024.12) diff. qty 14,760.00 (13,709.85) diff. qty 126.00 474.00 7,926.00 835.14 414.00 (19,320.04)
BLOK PENTADBIRAN TENDER REF
3 A B C D
E
F
G H I
4 A B C D
5 A B C **D E
ELEMENT/DESCRIPTION
FRAME VRC G25 in column/stiffener VRC G30 in column/stiffener VRC G25 in suspended floor beam Ditto in roof beam Reinforcement bar in column/stiffener Y16 Y25 R8 Ditto in floor beam Y16 Y20 Y25 R10 Ditto in roof beam Y16 Y20 Y25 R10 Sawn formwork to sides of column/stiffener Ditto suspended floor beam Ditto roof beam Sub-total UPPER FLOOR CONSTRUCTION 125mm thick suspended floor slab BRC A10 ditto BMC A6 ditto Sawn formwork to soffit suspended floor slab Sub-total
UNIT
QTY
RATE
M3
86
185.00
M3 M3 Kg Kg Kg Kg Kg Kg Kg Kg Kg Kg Kg Kg Kg Kg M2 M2 M2
M2 M2 M2 M2
174 185.00 83 185.00 10946 1.85
35132 1.85
19419 1.85
872 1771 985
3417 6038 0 3417
ROOF STRUCTURE AND COVERING Roof Structure (prefabricated roof trusses) M2 1782 125mm thick VRC G25 in roof slab M2 0 Concrete roof covering, sisalation, wiremesh andM2etc 1782 Fascia board and painting M 285 Gutter and rainwater downpipe M 285 Sub-total
24.00 24.00 24.00
23.00 12.00 12.00 24.00
38.00 19.00 43.00 15.00 45.00
BUDGET
AMOUNT (RM) LAB. RATE MATL. RATE
15,910.00 32,190.00 15,355.00 20,250.10
64,994.20
35,925.15
26.00 26.00 26.00 0.32
0.32
0.32
20,928.00 42,504.00 23,640.00 ###
13.00 13.00 13.00
78,591.00 72,456.00 82,008.00 ###
3.25 1.00 1.00 13.00
67,716.00 76,626.00 4,275.00 12,825.00 ###
5.80 3.60 4.30 6.00 2.00
111.00 111.00 111.00 1.15
1.15
1.15
7.00 7.00 7.00
13.90 12.60 4.00 7.00
32.00 15.30 23.20 5.00 10.00
TOTAL LAB.
2,236.00 4,524.00 2,158.00 3,502.72
11,242.24
6,214.08
ACTUAL TOTAL MATL
9,546.00 19,314.00 9,213.00 12,587.90
40,401.80
22,331.85
TOTAL
QTY
% W/DONE
11,782.00 23,838.00 11,371.00 16,090.62
45%
329.00
0%
12.00
0%
17,440.00 35,420.00 19,700.00 215,831.59
11,105.25 6,038.00 44,421.00 61,564.25
47,496.30 76,078.80 23,919.00 ###
58,601.55 82,116.80 68,340.00 209,058.35
10,335.60 7,662.60 1,710.00 570.00 20,278.20
57,024.00 41,342.40 1,425.00 2,850.00 ###
67,359.60 49,005.00 3,135.00 3,420.00 122,919.60
MATE. RATE
SUB. RATE
38.70
GROSS TOTAL LAB
909.45
TOTAL MATE
TOTAL SUB
4,547.25
-
TOTAL AMOUNT
PROFIT BUDGET
5,456.70
REMARKS
PROFIT ACTUAL
4,128.00
23.50
117.50
-
23.50
111.00
-
-
-
-
-
-
23.50
111.50
-
-
-
-
-
-
-
-
-
-
-
4,159.48
15,910.00 (5,456.70) 20,250.10
225.00
45%
101.25
0.29
1.12
29.36
113.40
-
142.76
-
(142.76)
16,334.00
45%
7,350.30
0.29
1.12
2,131.59
8,232.34
-
10,363.92
-
(10,363.92)
5,078.00
45%
2,285.10
0.29
1.19
662.68
2,719.27
-
3,381.95
-
-
-
-
-
13,350.16
(3,381.95) 64,994.20
322.00
0%
-
0.29
1.12
-
-
-
-
-
-
600.00
0%
-
0.29
1.12
-
-
-
-
-
-
36,102.00
0%
-
0.29
1.12
-
-
-
-
-
-
6,485.00
0%
-
0.29
1.19
-
-
-
-
-
-
-
-
-
28,545.93
6,104.00 12,397.00 6,895.00 ###
LAB. RATE
86.00
51,644.04
11,336.00 23,023.00 12,805.00 77,041.04
QTY W/DONE
-
7,379.22
35,925.15
1,246.00
0%
-
0.29
1.12
-
-
-
-
-
-
8,445.00
0%
-
0.29
1.12
-
-
-
-
-
-
604.00
0%
-
0.29
1.12
-
-
-
-
-
-
2,445.00
0%
-
0.29
1.19
-
-
-
-
-
872.00
45%
18.00
-
-
1,553.00
0%
-
18.00
-
-
-
-
-
851.00
0%
-
18.00
-
-
-
-
-
392.40
2,794.27
10,951.61
7,063.20
7,063.20
7,063.20
20,809.07
3,488.00
24,217.38
13,864.80 101,038.28
2,232.00
0%
-
-
-
-
-
-
-
4,338.00
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
-
-
-
-
-
-
2,108.00
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
0%
-
-
-
-
-
-
-
-
-
-
-
-
-
REF
ELEMENT/DESCRIPTION
6 A B C D E F G H I J K L
STAIRCASES AND FINISHES VRC G25 in staircase Ditto in landing beam Ditto in landing slab Reinforcement in staircase Ditto in landing beam Ditto in landing slab Sawn formwork to sloping soffit of staircase Ditto of landing beam Ditto of landing slab Ditto to undercut of riser Ditto to raking open string Staircases finishes and railing Sub-total
7 A B C D E
EXTERNAL WALLS 115mm thick common brickwall Damp proof course 6mm bonding ties Mild steel railing 50mm Upvc spout pipe 250mm long
UNIT
QTY
RATE
M3 M3 M3 KG KG KG M2 M2 M2 M M Flight
14 5 38 1793 846 1506 48 62 38 165 39 4
185.00 185.00 185.00 1.85 1.85 1.85 24.00 24.00 24.00 8.00 8.00 1,500.00
2,590.00 925.00 7,030.00 3,317.05 1,565.10 2,786.10 1,152.00 1,488.00 912.00 1,320.00 312.00 6,000.00 29,397.25
26.00 26.00 26.00 0.32 0.32 0.32 13.00 13.00 13.00 0.65 0.65
111.00 111.00 111.00 1.15 1.15 1.15 7.00 7.00 7.00 0.30 0.30 1,400.00
364.00 130.00 988.00 573.76 270.72 481.92 624.00 806.00 494.00 107.25 25.35 4,865.00
1,554.00 555.00 4,218.00 2,061.95 972.90 1,731.90 336.00 434.00 266.00 49.50 11.70 5,600.00 17,790.95
1,918.00 685.00 5,206.00 2,635.71 1,243.62 2,213.82 960.00 1,240.00 760.00 156.75 37.05 5,600.00 22,655.95
672.00 240.00 1,824.00 681.34 321.48 572.28 192.00 248.00 152.00 1,163.25 274.95 400.00 6,741.30
M2 M No M No
1198 483 652 100 80
26.00 2.00 0.60 120.00 20.00
31,148.00 966.00 391.20 12,000.00 1,600.00 46,105.20
7.10
17.00 1.00 0.30 118.00 1.00
8,505.80 40.00 8,545.80
20,366.00 483.00 195.60 11,800.00 80.00 32,924.60
28,871.80 483.00 195.60 11,800.00 120.00 41,470.40
2,276.20 483.00 195.60 200.00 1,480.00 4,634.80
M2 M No
609 183 72
26.00 2.00 0.60
15,834.00 366.00 43.20 16,243.20
7.10
17.00 1.00 0.30
4,323.90 4,323.90
10,353.00 183.00 21.60 10,557.60
14,676.90 183.00 21.60 14,881.50
1,157.10 183.00 21.60 1,361.70
Sub-total 8 A B C
INTERNAL WALLS 115mm thick common brickwall Damp proof course 114mm Wide 6mm bonding ties Sub-total
AMOUNT (RM)
LAB. RATE
0.50
MATL. RATE
TOTAL LAB.
TOTAL MATL
TOTAL
MARGIN
REF 9 A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
REF
ELEMENT/DESCRIPTION DOOR AND WINDOWS One hour fire-rated door c/w framing size 900 x 2100 Single flush door c/w framing size 900 x 2550 Ditto c/w glass panel & framing size 900 x 2100 Double flush door c/w framing size 1800x 2550 Ditto c/w glass panel & framing size 1800 x 2100 PVC door size 750 x 2100 Sliding door size 1800 x 2550 Aluminium framed casement window size 1800 x 1800 Ditto size 3600 x 1800 Ditto size 4800 x 1800 Ditto size 1800 x 1200 Ditto size 3600 x 1200 Ditto size 4800 x 1200 Ditto size 5550 x 2500 Aluminium framed top hung size 1800 x 600 Ditto size 3600 x 600 Ditto size 4800 x 600 Timber frame top hung size 1800 x 600 Ditto size 3600 x 600 Ditto size 4800 x 600 Adjustable louvres window size 600 x 1200 Ditto size 1200 x 1200 Ditto size 1200 x 1800 Ditto size 1800 x 1800 Ditto size 3600 x 1800 Ditto size 4800 x 1800 Sub-total
ELEMENT/DESCRIPTION
UNIT
QTY
No No No No No No No No No No No No No No No No No No No No No No No No No No
9 5 9 19 0 16 0 38 12 7 2 1 2 13 0 0 0 4 2 0 0 0 0 0 0 0
UNIT
QTY
RATE
550.00 780.00 500.00 1,600.00 340.00 120.00 800.00 900.00 1,800.00 2,400.00 600.00 1,200.00 1,600.00 3,850.00 300.00 600.00 800.00 130.00 260.00 350.00 150.00 250.00 380.00 550.00 1,100.00 1,500.00
RATE
AMOUNT (RM)
4,950.00 3,900.00 4,500.00 30,400.00 1,920.00 34,200.00 21,600.00 16,800.00 1,200.00 1,200.00 3,200.00 50,050.00 520.00 520.00 174,960.00
AMOUNT (RM)
LAB. RATE
28.00 23.00 23.00 50.00 23.00 20.00
11.65 23.30 35.00 52.00 104.00 140.00
LAB. RATE
MATL. RATE
605.00 268.00 270.00 536.00 270.00 128.00 790.00 560.00 1,120.00 1,490.00 372.00 745.00 1,000.00 2,400.00 200.00 400.00 500.00 116.00 232.00 310.00 67.00 134.00 201.00 302.00 604.00 804.00
MATL. RATE
TOTAL LAB.
252.00 115.00 207.00 950.00 320.00 1,844.00
TOTAL LAB.
TOTAL MATL
5,445.00 1,340.00 2,430.00 10,184.00 2,048.00 21,280.00 13,440.00 10,430.00 744.00 745.00 2,000.00 31,200.00 464.00 464.00 102,214.00
TOTAL MATL
TOTAL
5,697.00 1,455.00 2,637.00 11,134.00 2,368.00 21,280.00 13,440.00 10,430.00 744.00 745.00 2,000.00 31,200.00 464.00 464.00 104,058.00
TOTAL
MARGIN
(747.00) 2,445.00 1,863.00 19,266.00 (448.00) 12,920.00 8,160.00 6,370.00 456.00 455.00 1,200.00 18,850.00 56.00 56.00 70,902.00
MARGIN
10 A B C D E
FLOOR FINISHES 20mm Thick cement paving Homogeneous tiles with screed Carpet Ceramic tiles ditto Cementitious water proofing system Sub-total
M2 M2 M2 M2 M2
2293 114 0 55 55
8.00 65.00 35.00 60.00 18.00
18,344.00 7,410.00 3,300.00 990.00 30,044.00
5.00 21.00 5.00 19.00
2.50 46.25 20.00 19.00 28.00
11,465.00 2,394.00 1,045.00 14,904.00
5,732.50 5,272.50 1,045.00 1,540.00 13,590.00
17,197.50 7,666.50 2,090.00 1,540.00 28,494.00
1,146.50 (256.50) 1,210.00 (550.00) 1,550.00
11 A B C D E
WALL FINISHES 20mm Thick c.s. plaster to wall & column Emulsion paint to internally plastered wall Weather sheild paint to externally ditto Ceramic wall tiles with screed Acoustic treatment Sub-total
M2 M2 M2 M2 M2
3614 2416 1198 125 0
8.00 4.50 5.50 65.00 70.00
28,912.00 10,872.00 6,589.00 8,125.00 54,498.00
6.00
2.50 2.80 2.80 19.00 28.00
21,684.00 2,375.00 24,059.00
9,035.00 6,764.80 3,354.40 2,375.00 21,529.20
30,719.00 6,764.80 3,354.40 4,750.00 45,588.20
(1,807.00) 4,107.20 3,234.60 3,375.00 8,909.80
12 A B C D
CEILING FINISHES 20mm Thick c.s. plaster to soffit of slab Asbestos free ceiling sheet Emulsion paint to plastered surfaces Ditto to asbestos ceiling Sub-total
M2 M2 M2 M2
1909 1068 1909 1068
8.00 28.00 4.50 4.50
15,272.00 29,904.00 8,590.50 4,806.00 58,572.50
2.50 8.00
11,454.00 8,010.00 5,345.20 2,990.40 27,799.60
4,772.50 8,544.00 13,316.50
16,226.50 16,554.00 5,345.20 2,990.40 41,116.10
(954.50) 13,350.00 3,245.30 1,815.60 17,456.40
13 A B C D E F G H I
PLUMBING AND SANITARY FITTINGS Cold water plumbing ( under M & E) Soil and waste plumbing ( under M & E) Water tank ( under M & E) Squatting WC complete with stool Pedestal WC Mirror Wash hand basin with counter top Kitchen sink Dentist vanity basin Sub-total
LS LS LS No No No No No No
1 1 1 10 0 4 10 0 0
7,500.00 9,500.00 1,800.00 2,250.00 300.00 1,650.00 23,000.00
7,500.00 9,500.00 1,800.00 2,250.00 300.00 1,650.00 23,000.00
500.00 500.00 200.00 1,250.00 (60.00) 1,550.00 3,940.00
350.00 300.00 60.00 320.00 250.00 1,700.00
8,000.00 10,000.00 2,000.00 3,500.00 240.00 3,200.00 26,940.00
19.00
6.00 7.50 2.80 2.80
7,500.00 9,500.00 1,800.00 225.00 340.00 75.00 165 200 1650
-
REF 14 A B C D E
ELEMENT/DESCRIPTION APRON AND PERIMETER DRAIN Exc. oversite 250mm deep 150mm Thick hardcore 100mm Thick VRC G25 apron slab One layer fabric reinforcement 230mm half round perimeter drain
UNIT
QTY
RATE
M2 M2 M2 M2 M
324 324 324 324 61
2.50 8.30 18.50 12.00 38.00
Ls
1
AMOUNT (RM)
810.00 2,689.20 5,994.00 3,888.00 2,318.00 15,699.20
LAB. RATE
2.50 2.60 1.00 14.00
MATL. RATE
2.15 6.50 11.10 4.00 10.00
TOTAL LAB.
TOTAL MATL
810.00 842.40 324.00 854.00 2,830.40
TOTAL
MARGIN
696.60 2,106.00 3,596.40 1,296.00 610.00 8,305.00
696.60 2,916.00 4,438.80 1,620.00 1,464.00 11,135.40
113.40 (226.80) 1,555.20 2,268.00 854.00 4,563.80
13,000.00
13,000.00
2,000.00
Sub-total 15 A
INTERNAL SIGNAGES Internal signages/lettering
15,000.00
15,000.00
13,000.00
-
-
13,000.00
13,000.00
2,000.00