Construction update 10/02/09:
All temporary steel shoring has been removed from the end of the existing building adjacent to the Chapel addition.
The concrete retaining wall between the Chapel and 5th street was poured.
Concrete and plumbing rough-in operations continued on the Chapel (weather permitting).
Abatement and demolition work began in the Parish House basement crawl space.
Abatement work began in the Nave undercroft. The City of Waco has issued a full building permit.