Construction Update 11/06/09: • The Chapel slab has been poured. • Masonry construction on the Chapel and foundation work on the cloister addition will begin 11/9/09. • Demolition is proceeding in the first floor of the Parish House (old office area). • Excavation in the Parish House crawl space has been completed. • Demolition on the stair addition has begun to make way for the new elevator tower. • Preparations are underway for HVAC work in the Parish Hall to begin 11/30/09.