DP 2 No A

B

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP Uraian TENAGA Pekerja Tukang Batu Kepala Tukang Mandor Upah Borongan BAHAN Operator alat berat Pembantu Mekanik Pasir Pasang

C

PERALATAN

D

Jumlah (A+B+C)

Kode L.01 L.02 L.03 L.04

Satuan Koefisien

Harga Satuan (Rp)

#REF! Jumlah Harga (Rp)

OH OH OH OH

90,000.00 100,000.00 120,000.00 130,000.00 100,000.00 1.00 JUMLAH TENAGA KERJA

100,000 100,000

m3 Kg m3

200,000.00 1.20 120,000.00 136.00 160,000.00 0.54 JUMLAH HARGA BAHAN

240,000 16,320,000 87,040 16,647,040

JUMLAH HARGA ALAT

16,747,040

Related Documents

Batu Belah 1 5.xlsx
October 2019 12
Batu Belah 1 5.xlsx
October 2019 13
Barang Pecah Belah
October 2019 16
14 Batu-batu Yang Aneh
April 2020 33
Bulan Di Belah Dua
May 2020 10

More Documents from ""

Alat Topo.xlsx
October 2019 12
Batu Belah 1 5.xlsx
October 2019 12
Batu Belah 1 5.xlsx
October 2019 13
Bci Ceiling Diffusers.pdf
October 2019 9
Proposal Pbk.docx
April 2020 8