ANALISA HARGA SATUAN ALAT BERAT PADA PEKERJAAN TANAH (Studi Kasus Perencanaan Bandar Udara Lokasi Desa Pusungi Kec. Ampana Tete Kab. Tojo Una-una, Sulawesi Tengah) *Sumber: Stefi Priescha Tauro Jermias Tjakra, Grace Y. Malingkas Fakultas Teknik, Jurusan Teknik Sipil, Universitas Sam Ratulangi Manado email: [email protected]

Tabel 1. Analisis Harga Satuan Metode SNI, Pekerjaan clearing, stripping dan grubbing pada perpanjangan runway Bulldozer Excavator Dump Truck

Jam Jam Jam

Koefisie n 0.0331 0.0063 0.0044

-

-

0.0000

Kebutuhan Alat

Material/Bah an Tenaga Kerja

Satuan

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Harga Satuan (Rp/Jam) 458,400.00 502,500.00 292,300.00 Jumlah (A)

Jumlah (Rp/Hari) 15181.56 3182.50 1282.54 19646.60

0.00

0.00

Jumlah (B)

0.00

Oh

0.0333

5,000.00

166.25

Oh

0.0333

3,928.57

130.62

Oh Oh Oh Oh

0.1108 0.1108 0.0222 0.0055

4,285.71 2,857.14 2,857.14 3,214.29 Jumlah (C) Jumlah (A) + (B) + (C)

475.00 316.67 63.33 17.81 1151.87 20798.47

Tabel 2. Analisis Harga Satuan Metode SNI, Pekerjaan clearing, stripping dan grubbing pada parkir terminal. Kebutuhan Alat

Satuan Koefisien Harga Satuan (Rp/Jam) Bulldozer

Jam

0.0331

Excavator Dump Truck

Jam Jam

0.0063 0.0044

Material/Bahan

-

-

Tenaga Kerja

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Oh Oh Oh Oh Oh Oh

458,400.00

502,500.00 292,300.00 Jumlah (A) 0.0000 0.00 Jumlah (B) 0.0222 5,000.00 0.0222 3,928.57 0.0333 4,285.71 0.0333 2,857.14 0.0222 2,857.14 0.0055 3,214.29 Jumlah (C) Jumlah (A) + (B) + (C)

Jumlah (Rp/Hari) 15181.56 3182.50 1282.54 19646.60 0.00 0.00 110.83 87.08 142.50 95.00 63.33 17.81 498.75 20145.35

Tabel 3. Analisis Harga Satuan Metode SNI, Pekerjaan clearing, stripping dan grubbing pada terminal VVIP Kebutuhan Alat

Bulldozer Excavator Dump Truck

Material/Ba han Tenaga Kerja

Koefisie n Jam 0.0331 Jam 0.0063 Jam 0.0044

Satuan

-

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

-

0.0000

Harga Satuan (Rp/Jam) 458,400.00 502,500.00 292,300.00 Jumlah (A)

Jumlah (Rp/Hari) 15181.56 3182.50 1282.54 19646.60

0.00

0.00

Jumlah (B)

0.00

Oh

0.0333

5,000.00

166.25

Oh

0.0333

3,928.57

130.62

Oh

0.0831

4,285.71

356.25

Oh

0.0831

2,857.14

237.50

Oh Oh

0.0222 0.0055

2,857.14 3,214.29 Jumlah (C) Jumlah (A) + (B) + (C)

63.33 17.81 953.96 20600.56

Tabel 4. Harga Satuan Metode SNI, pekerjaan Galian Tanah Konstruksi Kebutuhan Alat

Satuan Koefisien Excavator Dump Truck

Jam Jam

0.0600 0.1271

-

-

0.0000

Material/Bah an Tenaga Kerja

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Tabel

Harga Satuan (Rp/Jam) 502,500.00 292,300.00 Jumlah (A)

Jumlah (Rp/Hari) 30150.00 37146.46 67296.46

0.00

0.00

Jumlah (B)

0.00

Oh

0.1050

5,000.00

525.00

Oh

0.1050

3,928.57

412.50

Oh Oh Oh Oh

0.1050 0.1050 0.2100 0.0525

4,285.71 2,857.14 2,857.14 3,214.29 Jumlah (C) Jumlah (A) + (B) + (C)

450.00 300.00 600.00 168.75 2287.50 69583.96

5. Analisis Harga Satuan Metode SNI, pekerjaan Galian, Pemadatan, dan Pembuangan Kebutuhan Alat

Material/Bah an Tenaga Kerja

Satuan Koefisien

Harga Satuan (Rp/Jam) 267,100.00 664,500.00 502,500.00 292,300.00 Jumlah (A)

Jumlah (Rp/Hari) 4290.76 5847.60 30150.00 31056.88 71345.24

Vibrator Roller Motor Greder Excavator Dump Truck

Jam Jam Jam Jam

0.0161 0.0088 0.0600 0.1063

-

-

0.0000

0.00

0.00

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Oh

0.2625

Jumlah (B) 5,000.00

0.00 1312.50

Oh

0.2625

3,928.57

1031.25

Oh Oh Oh Oh

0.1050 0.1050 0.2100 0.0525

4,285.71 2,857.14 2,857.14 3,214.29 Jumlah (C) Jumlah (A) + (B) + (C)

450.00 300.00 600.00 168.75 3693.75 75038.99

Berdasarkan Analisis Harga Satuan Jadi di Lapangan Tabel 6. Analisis Harga Satuan Jadi di Lapangan, Pekerjaan clearing, stripping dan grubbing pada perpanjangan runway Kebutuhan

Satuan Koefisien

Alat

Bulldozer Excavator Dump Truck

Jam Jam Jam

0.0331 0.0063 0.0044

-

-

0.0000

Material/Bah an Tenaga Kerja

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Harga Satuan (Rp/Jam) 174,191.50 32,385.53 33,692.18 Jumlah (A)

Jumlah (Rp/Hari) 5768.98 205.11 147.83 6121.92

0.00

0.00

Jumlah (B)

0.00

Oh

0.0380

8,571.43

325.71

Oh

0.0380

7,000.00

266.00

Oh Oh Oh Oh

0.0950 0.0950 0.0253 0.0063

8,571.43 7,000.00 6,214.29 7,000.00 Jumlah (C) Jumlah (A) + (B) + (C)

814.29 665.00 157.43 44.33 2228.43 8350.35

Tabel 7. Analisis Harga Satuan Jadi di lapangan, Pekerjaan clearing, stripping dan grubbing parkir terminal Satuan

Koefisien

Harga Satuan (Rp/Jam)

Bulldozer Excavator Dump Truck

Jam Jam Jam

0.0331 0.0063 0.0044

174,191.50 32,385.53 33,692.18 Jumlah (A)

Jumlah (Rp/Hari) 5768.98 205.11 147.83 6121.92

-

-

0.0000

0.00

0.00

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Oh

0.0253

Jumlah (B) 8,571.43

0.00 217.14

Oh

0.0253

7,000.00

177.33

Oh Oh Oh Oh

0.0380 0.0380 0.0253 0.0063

Kebutuhan Alat

Material/Baha n Tenaga Kerja

8,571.43 7,000.00 6,214.29 7,000.00 Jumlah (C) Jumlah (A) + (B) + (C)

325.71 266.00 157.43 44.33 1143.62 7265.54

Tabel 8. Analisis Harga Satuan Jadi di Lapangan, Pekerjaan clearing, stripping dan grubbing Kebutuhan Alat

Material/Bah an Tenaga Kerja

Harga Satuan (Rp/Jam) 174,191.50 32,385.53 33,692.18 Jumlah (A)

Jumlah (Rp/Hari) 5768.98 205.11 147.83 6121.92

0.0000

0.00

0.00

Oh

0.0380

Jumlah (B) 8,571.43

0.00 325.71

Oh

0.0380

7,000.00

266.00

Oh Oh Oh Oh

0.0950 0.0950 0.0253 0.0063

Satuan

Koefisien

Bulldozer Excavator Dump Truck

Jam Jam Jam

0.0331 0.0063 0.0044

-

-

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

8,571.43 7,000.00 6,214.29 7,000.00 Jumlah (C) Jumlah (A) + (B) + (C)

814.29 665.00 157.43 44.33 2228.43 8350.35

Tabel 9. Analisis Harga Satuan Metode Lapangan, pekerjaan Galian Tanah Konstruksi Kebutuhan Alat

Material/Ba han Tenaga Kerja

Satuan Koefisien Excavator Dump Truck

Jam Jam

0.0600 0.1271

-

-

0.0000

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Harga Satuan (Rp/Jam) 32,385.53 33,692.18 Jumlah (A)

Jumlah (Rp/Hari) 1943.13 4281.71 6224.85

0.00

0.00

Jumlah (B)

0.00

Oh

0.1200

8,571.43

1028.57

Oh

0.1200

7,000.00

840.00

Oh Oh Oh Oh

0.1200 0.1200 0.2400 0.0600

8,571.43 7,000.00 6,214.29 7,000.00 Jumlah (C) Jumlah (A) + (B) + (C)

1028.57 840.00 1491.43 420.00 5228.57 11453.42

Tabel 10. Analisis Harga Satuan Metode Lapangan, pekerjaan Galian, Pemadatan, dan Pembuangan Kebutuhan Alat

Material/Bah an Tenaga Kerja

Satuan

Koefisien

Vibrator Roller Motor Greder Excavator Dump Truck

Jam Jam Jam Jam

0.0161 0.0088 0.0600 0.1063

-

-

0.0000

Operator Pembantu Operator Sopir Pembantu Sopir Pekerja Mandor

Harga Satuan (Rp/Jam) 62,119.18 91,787.23 32,385.53 33,692.18 Jumlah (A)

Jumlah (Rp/Hari) 997.90 807.73 1943.13 3579.79 7328.55

0.00

0.00

Jumlah (B)

0.00

Oh

0.3000

8,571.43

2571.43

Oh

0.3000

7,000.00

2100.00

Oh Oh Oh Oh

0.1200 0.1200 0.2400 0.0600

8,571.43 7,000.00 6,214.29 7,000.00 Jumlah (C) Jumlah (A) + (B) + (C)

1028.57 840.00 1491.43 420.00 8031.43 15359.98