1st Draft ID

Solutions That Work Wind Farm Work Breakdown Structure Task Name

Duration

Start

Sun 8/17/08 Finish Jun

1

Initiation

2

Planning

3

Wind Resource Assessment and Site Selection

1 day?

Thu 7/10/08

413 days?

Fri 7/11/08

Tue 2/9/10

403 days?

Fri 7/11/08

Tue 1/26/10

Thu 7/10/08

4

Preliminary Area Identification

1 day?

Fri 7/11/08

Fri 7/11/08

5

Review Wind Resource Map

1 day?

Fri 7/11/08

Fri 7/11/08

6

Identify Candidates

1 day?

Fri 7/11/08

Fri 7/11/08

7

Initial Site Visits

11 days?

Fri 7/11/08

Fri 7/25/08

8

Interconnection Assessment

10 days

Fri 7/11/08

Thu 7/24/08

9

Lease or Buy

10 days

Fri 7/11/08

Thu 7/24/08

10

Identify Regulatory Framework

10 days

Fri 7/11/08

Thu 7/24/08

11

Identify Critical Issues Analysis

1 day?

Fri 7/25/08

Fri 7/25/08

23

Telecommunications interference

1 day?

Fri 7/11/08

Fri 7/11/08

10 days

Mon 7/28/08

Fri 8/8/08

1 day?

Fri 7/11/08

Fri 7/11/08

24

Initial Economic Analysis

25

Prioritization of Sites

26

Wind Assessment

403 days?

Fri 7/11/08

Tue 1/26/10

27

Develop Assessment Plan

1 day?

Fri 7/11/08

Fri 7/11/08

28

Acquire wind analyst resource

1 day?

Fri 7/11/08

Fri 7/11/08

29

Selection of Tower locations

1 day?

Mon 7/14/08

Mon 7/14/08

30

Validation (Meteorological Towers)

387 days?

Tue 7/15/08

Wed 1/6/10

31

Permission if needed

10 days

Tue 7/15/08

Mon 7/28/08

32

Permit if height restriction

10 days

Tue 7/15/08

Mon 7/28/08

33

Acquire meteorological towers

10 days

Tue 7/29/08

Mon 8/11/08

34

Install meteorological towers

3 days?

Tue 8/12/08

Thu 8/14/08

35

Tower

1 day?

Tue 8/12/08

Tue 8/12/08

36

Anemometers

1 day?

Wed 8/13/08

Wed 8/13/08

37

Data Logger

1 day?

Thu 8/14/08

Thu 8/14/08

38

Lights or power

1 day?

Tue 8/12/08

Tue 8/12/08

39

Backup or redundant anemometer

1 day?

Tue 8/12/08

Tue 8/12/08

365 days

Thu 8/14/08

Wed 1/6/10

40

Record data for year

41

Obtain nearby airport data 10-20 years

1 day

Wed 1/6/10

Wed 1/6/10

42

Determine if anomalies

4 days

Thu 1/7/10

Tue 1/12/10

43

Wind roses

5 days

Wed 1/6/10

Tue 1/12/10

44

Peak season, time of day, hours of power

5 days

Wed 1/13/10

Tue 1/19/10

Page 1

3rd Quarter Jul Aug

Lawyer

Sep

4th Quarter Oct Nov

Dec

2009 1st Q Jan

1st Draft ID

Solutions That Work Wind Farm Work Breakdown Structure Task Name

Duration

Start

Sun 8/17/08 Finish Jun

45 46

Recommendation & prioritization Critical Issues Analysis/Regulatory Framework

5 days

Wed 1/20/10

Tue 1/26/10

91 days?

Mon 8/11/08

Mon 12/15/08

30 days

Mon 8/11/08

Fri 9/19/08

47

Acquire biologist/permitting resource

48

Develop constraints map

1 day?

Mon 8/11/08

Mon 8/11/08

49

Include setbacks

1 day?

Mon 8/11/08

Mon 8/11/08 Mon 9/22/08

50

Determine impacted species

30 days

Tue 8/12/08

51

Plan mitigation, remediation

30 days

Tue 9/23/08

Mon 11/3/08

52

Plan regulatory approvals

30 days

Tue 11/4/08

Mon 12/15/08

54 days

Thu 11/26/09

Tue 2/9/10

30 days

Thu 11/26/09

Wed 1/6/10

53

Micrositing

54

Acquire micrositing resource

55

Potential tower locations

5 days

Wed 1/27/10

Tue 2/2/10

56

Micrositing software?

5 days

Wed 1/27/10

Tue 2/2/10

Site layout

5 days

Wed 2/3/10

Tue 2/9/10

5 days

Wed 2/3/10

Tue 2/9/10

57 58 59

Economic Analysis, Site

728 days?

Thu 7/10/08

Mon 4/25/11

60

Execution & Control Acquire Land Rights

365 days

Mon 8/11/08

Fri 1/1/10

61

Transmission Capacity Analysis

375 days

Mon 8/11/08

Fri 1/15/10

62

Environmental Impact Analysis, Avoidance & Mitigation

395 days

Tue 12/16/08

Mon 6/21/10

63

Power Purchase Agreements

90 days

Tue 12/16/08

Mon 4/20/09

64

Permitting / Regulatory approvals

508 days?

Thu 7/10/08

Mon 6/21/10

65

Obtain environmental approvals

305 days

Tue 4/21/09

Mon 6/21/10

66

ASTM ESA compliance

45 days

Tue 4/21/09

Mon 6/22/09

67 68 75

1 day?

Thu 7/10/08

Thu 7/10/08

Financing

Litigation & Appeals

204 days?

Thu 7/10/08

Tue 4/21/09

Construction

728 days?

Thu 7/10/08

Mon 4/25/11

755 days

Mon 7/28/08

Fri 6/17/11

127

Community Outreach

128

Operation

65 days

Tue 2/1/11

Mon 5/2/11

129

O&M Planning & Prep

30 days

Tue 3/15/11

Mon 4/25/11

130

Staffing (1 per 10-20 towers)

60 days

Tue 2/1/11

Mon 4/25/11

5 days

Tue 4/26/11

Mon 5/2/11

1 day?

Thu 7/10/08

Thu 7/10/08

131 132

Commissioning Closing

Page 2

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Dec

2009 1st Q Jan

1st Draft

arter Feb

Mar

Solutions That Work Wind Farm Work Breakdown Structure 2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Dec

2010 1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Page 3

Jun

3rd Quarter Jul Aug

Sun 8/17/08

Sep

4th Quarter Oct Nov

Dec

2011 1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun

1st Draft

arter Feb

Mar

Solutions That Work Wind Farm Work Breakdown Structure 2nd Quarter Apr May

Jun

3rd Quarter Jul Aug

Sep

4th Quarter Oct Nov

Dec

2010 1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Developer

Page 4

Jun

3rd Quarter Jul Aug

Sun 8/17/08

Sep

4th Quarter Oct Nov

Dec

2011 1st Quarter Jan Feb

Mar

2nd Quarter Apr May

Jun