Unit Cost Derivation

  • June 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Unit Cost Derivation as PDF for free.

More details

  • Words: 3,564
  • Pages: 48
OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTEE Barangay of Aslum Municipality of Julita Province of Leyte

SUB-PROJECT PROGRAM OF WORK Sub-Project Title Sub-Project Category Physical Target Total Sub-Project Cost

Diversion Works Structure 1

Project Description Construction of Diversion Work Structure Item No. 1.00 2.00 3.00 3.10 3.20 3.30 3.40 3.50 3.60 4.00 4.10 4.20 4.30 5.00 5.10 5.20 5.30 6.00 6.10 6.20 6.30 6.40

Scope of Work Coffer Dam Diversion of Water & Care of Creek Intake Weir Structure Excavation Boulder Fill Gravel Bedding Concrete Class "A" (3000 psi) Reinforcing Steel Bars Structural Backfill Handlaid Riprap Excavation Gravel Bedding Riprap (Handlaid) Grouted Riprap Excavation Gravel Bedding Riprap (Grouted) Intake Works Excavation Concrete Class "A" (3000 psi) Reinforcing Steel Bars Structural Backfill Total Breakdown of Estimated Sub-Project Cost A. Direct Cost Material Cost Equipment Rental Labor Cost a.) Skilled b.) Unskilled Sub-Total A B. Indirect Cost Pre-Engineering Engineering Supervision Contractor's Profit Taxes Hand Tools Materials Testing Capability Building Administrative & Overhead Sub-Total B TOTAL (A+B) Add: Contingency Percent Total Estimated Cost Add: O & M (other amenities) GRAND TOTAL

Implementation Mode Sub-Project Duration Equipment Needed Technical Personnel Percentage

Administration 1 Bagger Concrete Mixer, Water Pump 2

Quantity 20.00 123.25

Unit LM cu.m.

Unit Price 1,597.33 50.45

261.51 42.50 17.00 83.88 4,131.67 130.38

cu.m. cu.m. cu.m. cu.m. kgs. cu.m.

68.37 1,035.29 832.29 4,255.66 43.77 78.70

24.00 8.00 16.00

cu.m. cu.m. cu.m.

62.08 953.00 1,036.25

cu.m. cu.m. cu.m. cu.m. cu.m. kgs cu.m.

KALAHI-CIDSS Grant

Prepared by:

Source of Fund Community

LGUs

Other Source

Total 31,946.50 6,217.80 17,880.00 44,000.00 14,149.00 356,956.50 180,861.00 10,260.00 1,490.00 7,624.00 16,580.00 687,964.80 Total Cost

Approved by: BUENAVENTURA L. PITAO Engr.II, Prov'l. Agr'l. Office - Leyte

Reviewed by:

Chairperson - Brgy. Sub-Project Mgt. Com. Noted by:

Deputy Area Coordinator

Note: a.) Costing to be used on the MIBF will be the Total Cost Estimate b.) Costing of O & M will be monitored during the conduct of the SET *Costing to be supported with detailed Training Schedules

Regional Infrastructure Engineer

CONCRETE VOLUME: Thickness, m. Width, m. Height, m. Length,m. Volume, cu.m. Retaining Wall: Retain Wall Left Retain Wall Right Cut-off Wall: Left Ret. Wall Right Ret. Wall Upstream Downstream Wall Footing Left Abutment Right Abutment Pier

Flooring: Wier R/L Abutment Cut Walk: Total Concrete Volume Boulder Fill (200-400mmØ) Gravel Bedding

0.20 0.20 0.20 0.20

2.50 2.00 2.50 2.00

10.41 14.00 10.41 14.00

5.21 5.60 5.21 5.60

21.61

0.20 0.20 0.20 0.20 0.20 0.20

1.00 1.00 1.00 1.00 1.00 1.00

24.41 14.00 24.41 14.00 6.00 8.00

4.88 2.80 4.88 2.80 1.20 1.60

18.17

5.28 5.28

10.56

0.20 0.20

1.20 1.20

0.20 0.30 0.20 0.30 0.30

0.85 0.30 0.05 0.10 0.30

0.20 0.20 0.10 0.10 0.10

6.00 1.00 5.12 5.12 0.60

0.20 0.20

6.00 1.00

0.50 0.50

6.00 1.00

Grouted Riprap:(200-400mm) Right Abutment Left Abutment

0.30 0.30

4.83 4.83

Handlaid Riprap:(300-400mm) Gravel Bedding

0.40 0.20

8.00 8.00

Boulder (200-400mmØ)

22.00 22.00 No. of Units 2.50 2 2.50 2 2.50 2 2.50 2 2.50 2

0.85 0.45 0.05 0.15 0.23

14 1 14 14 8 Total

16.80 0.20 7.17 7.17 0.48 83.88

14 1 Total 14 1 Total

16.80 0.20 17.00 42.00 0.50 42.50

5.00 5.00 Total 5.00 5.00 Total

7.24 7.24 14.49 16.00 8.00 24.00

31.33 60.06

Reinf. Steel Bars Retain Wall Left Bar A 12mm Bar B 12mm Temp. Bars 10mm Retain Wall Right Bar A 12mm Bar B 12mm Temp. Bars 10mm Wall Footing: Left Footing 12mm

Width, m. Height, m. Length,m. 0.75 1.25 24.00 1.10 2.45 24.00 3.50 24.00 0.75 1.10

Flooring:

Discharge end (Two sides) Vert. 12mm Hor.12mm Cut-off 12mm Vert.12mm

24.00 24.00 24.00

121.00 121.00 9.33

242.00 429.55 224.00

22.00 22.00 22.00 22.00 14.00 14.00

111.00 8.50 111.00 8.50 31.00 71.00

166.50 187.00 166.50 187.00 434.00 426.00

1.50 1.00

37.41 37.41

188.07 6.00

282.11 224.49

1.50 1.00

37.41 37.41

188.07 6.00

282.11 224.49

1.30 1.00

6.00 6.00

31.00 6.00

40.30 36.00

1.30 1.00

8.00 8.00

41.00 6.00

53.30 48.00

2.40

5.25 14.00 7.00 14.00

28.35 23.80 37.80 67.20

8.00 8.00

4.00 41.00

32.00 24.60

20.00 20.00

101.00 19.00

363.60 380.00

3.50 5.50

9.38 5.50

10.00 3.25

4.50 5.85

1.50 1.50 1.50 1.50 6.00 6.00

Right Footing 12mm

Cut-off Wall: Left Abutment: Vertical Bars (12mm) Temp. Bars (12mm) Right Abutment: Vertical Bars (12mm) Temp. Bars (12mm) Upstream Vertical Bars (12mm) Temp. Bars (12mm) Downstream Vertical Bars (12mm) Temp. Bars (12mm) Pier: Bracing (Vert.) 12mm Horizontal 12mm Pier Post 12mm Stirrups 10mm Cut Walk: Longitudinal 12 mm Temp. Bars 10mm Intake Wall: 12mm Bothways

1.25 2.45 2.50

No. of Units 2.00 2.00 2.00 2.00

0.85 0.85

2.70 2.60 2.70 2.60

0.60 0.60

2.00 2.00

No. of pcs. Total Length, m 121.00 242.00 121.00 429.55 12.67 304.00

0.90 0.90

0.90 0.90

0.50 0.50

1.34 0.90 0.45 0.45

1.80 1.80 Total

Excavation: Retaining Wall: Retain Wall Left U/S

Top,m. 2.00

12mm dia. 10mm dia.

Bottom,m. Height, m. Length,m. Volume, cu.m. 1.40

1.90

5.00

16.15

D/S Retain Wall Right U/S D/S Cut-off Wall Left U/S D/S Right U/S D/S Flooring:

Grouted Excav. Left Abutment Right Abutment

Handlaid Riprap:Excav. Struc. Backfill:

1.80 2.00 0.30 2.00 1.80 2.00 0.30

1.40 1.40 0.30 1.40 1.40 1.40 0.30

1.90 1.90 0.25 2.10 1.75 1.75 0.50

12.00 5.00 14.00 5.00 12.00 5.00 14.00

36.48 16.15 1.05 17.85 33.60 14.88 2.10

0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 6.00 1.20 0.50 0.15

0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.50 0.15 0.40

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.70 1.00 2.00 3.00

5.00 12.00 5.00 6.00 5.00 12.00 5.00 8.00 14.00 14.00 14.00 14.00 Total

2.75 6.60 2.75 3.30 2.75 6.60 2.75 4.40 58.80 11.90 9.10 11.55 261.51

2.30 2.00

0.50 0.50 2.00

2.50 3.00 0.50

5.00 5.00 5.00 Total 5.00

17.50 15.00 5.00 37.50 24.00

8.00 Top,m.

Retaining Wall: Retain Wall Left

Retain Wall Right

Cut-off Wall

1.80 1.55 1.80 5.00 1.80 1.55 1.80 5.00 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50

0.60

Bottom,m. Height, m. Length,m. Volume, cu.m. 1.20 1.20 1.20 1.20 1.20 1.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20

1.70 1.70 1.70 0.60 1.70 1.70 1.70 0.20 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

5.00 12.00 5.00 14.00 5.00 12.00 5.00 14.00 5.00 12.00 5.00 6.00 5.00 12.00 5.00 8.00 Total

12.75 28.05 12.75 42.00 12.75 28.05 12.75 14.00 1.75 4.20 1.75 2.10 1.75 4.20 1.75 2.80 183.40

Intake Works: Excavation

Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m. 1.10 1.10 0.40 20.00 8.80

138.26

31.90

123.25

Backfill

0.30 1.00 0.24

Concrete Volume

Division Box: Flooring CHB Footing

Length,m.

No. of CHB's Mortar/Plaster

0.20 1.00

0.28 20.00 0.20 5.00 0.24 20.00 1.80 1.34 0.12 0.80 0.92 0.12 Total Concrete Volume Top, m

Concrete Height, m. Width, m. Volume, cu.m. 0.30 Total -

(3.00) pcs. (0.02) Concrete Mortar Cement Sand Gravel

Reinforcing Bars Vertical Bar Horizontal Bar CHB Found.

1.40 1.00 1.15 0.29 (0.09) 1.35

Length,m.

Total -

Width, m. Height, m. No. of Pcs. Total Bar Length Total Bar nos. -

2.40

Weight, kgs. 214.90 381.44 187.26 214.90 381.44 137.98 147.85 166.06 147.85 166.06 385.39 378.29

250.51 199.34 250.51 199.34 35.79 31.97 47.33 42.62 25.17 21.13 33.57 41.40 28.42 15.15 322.88 337.44

660.32

8.33 4.88 4.00 5.19 22.40 3,749.88 381.80 Conc. Vol. Backfill

21.61

116.64

18.17

13.73

130.38

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

Unit

1.00

Coffer Dam

20

Linear Meter (Lm)

A 1 2 3

Material 1/2" X 4' X 8' Marine Plyboard 2" X 2" Coco Lumber (False work) Assorted Common Wire Nails

Quantity 7.50 180.00 12.00

Unit pcs. bd.ft. kgs.

Unit Cost

Unit Cost 835.00 9.50 50.00

Sub-Total B

C

Name & Capacity of Equipment None

Labor Derivation (Subsidiary Work Description) Hour/board foot Board foot per Linear meter Hour/Linear meter

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Days

1,597.33 Cost 6,262.50 1,710.00 600.00

8,572.50

Rate/Day

Cost

Quantity Manpower Number of Number of Days to Required Capability Manpower Assigned Complete the Work 0.064 180.00 11.52

3.00

28.80

Number No. of Day 1.00 29.00 2.00 29.00

Rate/Day 350.00 228.00

Cost 10,150.00 13,224.00

20.00

Sub-Total

23,374.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

2.00

Diversion of Water and Care of Creek

A 1

Material Diesel Fuel

Quantity

Unit

123.25 Quantity 8.00

Unit Cost

cu.m. Unit liters

50.45

Unit Cost 39.85

Total B

Name & Capacity of Equipment 4"Ø Water Pumps and accessories

Number No. of Day 1.00 17.00

Labor Derivation (Subsidiary Work Description) Dewatering/pumping ( cu.m./day)

Labor Requirement Water Pump Operator

318.80

318.80

Rate/Day 119.00

Total C

Cost

Cost 2,023.00

2,023.00

Quantity Manpower Number of Number of Days to Required Capability Manpower Assigned Complete the Work 123.25

7.25

1.00

17.00

Number No. of Days 1.00 17.00

Rate/Day 228.00

Cost 3,876.00

Total

3,876.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. 3.10

Work Description

Quantity

Unit

Unit Cost

Excavation

261.51

A

Material None

Quantity

Unit

Unit Cost

Cost

B

Name & Capacity of Equipment None

Number

No. of Day

Rate/Day

Cost

C

Labor Derivation (Subsidiary Work Description) Cu.m./Man-day @ 0-4m throwing dist

Labor Requirement Skilled Laborer Unskilled Laborer

cubic meter (cu.m.)

68.37

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 261.51

3.50

6.00

12.45

Number No. of Days 1.00 12.00 5.00 12.00

Rate/Day 350.00 228.00

Cost 4,200.00 13,680.00

Sub-Total

17,880.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. 3.40 A 1 2 3 4 5 6

Work Description Concrete Class "A" (3000 psi) Material Portland Cement Fresh Sand Gravel (G1) 1/4" X 4' X 8' Ordinary Plywood Coco Lumber (False Work) Nails and Hardware

Quantity

Unit

83.88 Quantity 800.00 53.00 70.00 57.00 5,033.00 210.00

cubic meter (cu.m.) Unit bags cu.m. cu.m. pcs. bd.ft. kgs.

Unit Cost 195.00 350.00 725.00 385.00 10.50 52.50

Total B

Name & Capacity of Equipment Concrete Mixer (1 bagger)

Number No. of Day 1.00 24.00

Rate/Day 298.00

Total C

Unit Cost 4,255.66 Cost 156,000.00 18,550.00 50,750.00 21,945.00 52,846.50 11,025.00

311,116.50 Cost 7,152.00

7,152.00

Labor Derivation (Subsidiary Work Description) Concrete Works (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 83.88 3.50 6.00 23.97

Labor Requirement Skilled Laborer Unskilled Laborer

Number No.of Days 2.00 24.00 4.00 24.00

Rate/Day 350.00 228.00

Total

Cost 16,800.00 21,888.00

38,688.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

Unit

3.50

Reinforcing Steel Bars

4,131.67

Kgs.

A 1 2 3 4

Material 12mm Ø X 20' Reinforcing Bars 10mm Ø X 20' Reinforcing Bars # 16 Tie Wire Hacksaw Blade

Quantity 704.00 103.00 124.00 6.00

Unit pcs. pcs. kgs. pcs.

Unit Cost 180.00 165.00 55.00 45.00

Total B

C

Name & Capacity of Equipment None

Number

No. of Day

Rate/Day

Unit Cost 43.77 Cost 126,720.00 16,995.00 6,820.00 270.00

150,805.00 Cost

Labor Derivation (Subsidiary Work Description) Cutting, Bending & Placing of RSB (kgs/day)

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 4,131.67 80.00 2.00 51.65

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Days 1.00 52.00 1.00 52.00

Rate/Day 350.00 228.00

Total

Cost 18,200.00 11,856.00

30,056.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Location: Item No.

Work Description

Quantity

A

Material

Quantity

B

Name & Capacity of Equipment

C

Labor Derivation (Subsidiary Work Description)

Unit

Unit

Number No. of Day

Unit Cost

Rate/Day

Quantity Manpower Number of Manpower Required Capability Assigned

Labor Requirement

Number No. of Day

Rate/Day

Unit Cost

Cost

Cost

Number of Days to Complete the Work

Cost

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

3.60

Structural Backfill

130.38

A

Material None

B

Name & Capacity of Equipment None

C

Quantity

Unit

Unit Cost

cubic meter (cu.m.) Unit

Number No. of Day

78.70

Unit Cost

Cost

Rate/Day

Cost

Labor Derivation (Subsidiary Work Description) Backfilling & Tamping (cu.m./man-day)

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 130.38 3.00 5.00 8.69

Labor Requirement Unskilled Laborer

Number No. of Day 5.00 9.00

Rate/Day 228.00

Cost 10,260.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

4.10

Excavation (Handlaid Riprap)

A

Material None

Quantity

Unit

Unit Cost

Cost

B

Name & Capacity of Equipment None

Number

No. of Day

Rate/Day

Cost

C

Labor Derivation (Subsidiary Work Description) Cu.m./Man-day @ 0-4m throwing dist.

Labor Requirement Skilled Laborer Unskilled Laborer

Quantity

Unit

24.00

Unit Cost

cubic meter (cu.m.)

62.08

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 24.00

3.50

6.00

Number No. of Days 1.00 1.00 5.00 1.00

Rate/Day 350.00 228.00

Sub-Total

1.14

Cost 350.00 1,140.00

1,490.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

4.30

Handlaid Riprap

16.00

A 1

Material Boulder (300mm-400mmØ)

Quantity 16.00

Unit

Unit cu.m.

Unit Cost

cubic meters (cu.m.)

1,036.25

Unit Cost 850.00

Cost 13,600.00

Total B

C

Name & Capacity of Equipment None

Labor Derivation (Subsidiary Work Description) Handlaid Riprap (cu.m./day)

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Day

13,600.00

Rate/Day

Cost

Quantity Manpower Number of Manpower Required Capability Assigned 16.00

8.50

6.00

Number No. of Day 1.00 2.00 5.00 2.00

Rate/Day 350.00 228.00

Total

Number of Days to Complete the Work 1.88

Cost 700.00 2,280.00

2,980.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

4.20

Gravel Bedding (Handlaid)

A 1

Material Gravel (G1)

Quantity

Unit

8.00 Quantity 8.00

Unit cu.m.

Unit Cost

cubic meters (cu.m.)

953.00

Unit Cost 725.00

Cost 5,800.00

Total B

C

Name & Capacity of Equipment None

Labor Derivation (Subsidiary Work Description) Bedding (cu.m./hour)

Labor Requirement Unskilled Laborer

Number No. of Day

5,800.00

Rate/Day

Cost

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 8.00

2.00

8.00

0.50

Number No. of Day 8.00 1.00

Rate/Day 228.00

Cost 1,824.00

Total

1,824.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

Unit

Unit Cost

1

Excavation (Grouted Riprap)

37.50

cubic meter (cu.m.)

79.47

A

Material None

Quantity

Unit

Unit Cost

Cost

B

Name & Capacity of Equipment None

Number

No. of Day

Rate/Day

Cost

C

Labor Derivation (Subsidiary Work Description) Cu.m./Man-day @ 0-4m throwing dist.

Labor Requirement Skilled Laborer Unskilled Laborer

Quantity Manpower Number of Number of Days to Required Capability Manpower Assigned Complete the Work 37.50

3.50

6.00

Number No. of Days 1.00 2.00 5.00 2.00

Rate/Day 350.00 228.00

Sub-Total

1.79

Cost 700.00 2,280.00

2,980.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

A 1 2 3 4

Work Description

Quantity

Unit

Unit Cost

Grouted Riprap

14.49

cubic meters (cu.m.)

2,280.25

Material Portland Cement Fresh Sand Gravel (G1) Boulder (200mm-350mmØ)

Quantity 61.00 5.00 1.00 14.00

Unit bags cu.m. cu.m. cu.m.

Unit Cost 195.00 350.00 725.00 850.00

Total B

C

Name & Capacity of Equipment None

Number No. of Day

Rate/Day

Cost 11,895.00 1,750.00 725.00 11,900.00

26,270.00 Cost

Labor Derivation (Subsidiary Work Description) Grouted Riprap (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 14.49 7.50 13.00 1.93

Labor Requirement Foreman Skilled Laborer Unskilled Laborer

Number No. of Day 1.00 2.00 2.00 2.00 10.00 2.00

Rate/Day 400.00 350.00 228.00

Total

Cost 800.00 1,400.00 4,560.00

6,760.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

3.20

Boulder Fill

A 1

Material Boulder (200mm-400mmØ)

Quantity

Unit

42.50 Quantity 43.00

Unit cu.m.

Unit Cost

cubic meters (cu.m.)

1,035.29

Unit Cost 850.00

Cost 36,550.00

Total B

C

Name & Capacity of Equipment None

Labor Derivation (Subsidiary Work Description) Handlaid Riprap (cu.m./day)

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Day

36,550.00

Rate/Day

Cost

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 43.00

8.50

6.00

5.06

Number No. of Day 1.00 5.00 5.00 5.00

Rate/Day 350.00 228.00

Cost 1,750.00 5,700.00

Total

7,450.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

3.30

Gravel Bedding (Boulder Fill)

A 1

Material Gravel (G1)

Quantity

Unit

17.00 Quantity 17.00

cubic meters (cu.m.) Unit cu.m.

Unit Cost 725.00

Total B

C

Name & Capacity of Equipment None

Number No. of Day

Rate/Day

Labor Derivation (Subsidiary Work Description) Bedding (cu.m./hour)

Quantity Manpower Number of Manpower Required Capability Assigned 17.00 2.00 8.00

Labor Requirement Unskilled Laborer

Number No. of Day 8.00 1.00

Rate/Day 228.00

Total

Unit Cost 832.29 Cost 12,325.00

12,325.00 Cost

Number of Days to Complete the Work 1.06

Cost 1,824.00

1,824.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description Concrete Class "A" (3000 psi)

A 1 2 3 4 5 6

Material Portland Cement Fresh Sand Gravel (G1) 1/4" X 4' X 8' Ordinary Plywood Coco Lumber (False Work) Nails and Hardware

Quantity

Unit

Unit Cost

1.35

cubic meter (cu.m.)

4,262.00

Quantity 13.00 1.00 1.00 1.00 81.00 3.00

Unit bags cu.m. cu.m. pcs. bd.ft. kgs.

Unit Cost 195.00 350.00 725.00 385.00 10.50 52.50

Total B

Name & Capacity of Equipment Concrete Mixer (1 bagger)

Number No. of Day 1.00 0.40

Rate/Day 298.00

Total C

Cost 2,535.00 350.00 725.00 385.00 850.50 157.50

5,003.00 Cost 119.20

119.20

Labor Derivation (Subsidiary Work Description) Concrete Works (cu.m./day)

Quantity Manpower Number of Manpower Number of Days to Required Capability Assigned Complete the Work 1.35 3.50 6.00 0.39

Labor Requirement Skilled Laborer Unskilled Laborer

Number No.of Days 2.00 0.40 4.00 0.40

Rate/Day 350.00 228.00

Cost 280.00 364.80

Total

644.80

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

Unit

1

Excavation (Intake)

8.80

cubic meter (cu.m.)

A

Material None

Quantity

B

Name & Capacity of Equipment None

C

Unit

Number No. of Day

Unit Cost

Rate/Day

Labor Derivation Quantity Manpower Number of Manpower (Subsidiary Work Required Capability Assigned Description) Cu.m./Man-day @ 0-4m throwing dist. 8.80 3.50 6.00

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Days 1.00 0.40 5.00 0.40

Rate/Day 350.00 228.00

Sub-Total

Unit Cost 67.73 Cost

Cost

Number of Days to Complete the Work 0.42

Cost 140.00 456.00

596.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

Work Description

Quantity

Unit

Unit Cost

Structural Backfill

2.40

cubic meter (cu.m.)

95.00

A

Material None

Quantity

Unit Cost

Cost

B

Name & Capacity of Equipment None

Rate/Day

Cost

C

Unit

Number No. of Day

Labor Derivation Quantity Manpower Number of Manpower Number of Days to (Subsidiary Work Required Capability Assigned Complete the Work Description) Backfilling & Tamping (cu.m./man-day) 2.40 3.00 5.00 0.16

Labor Requirement Unskilled Laborer

Number No. of Day 5.00 0.20

Rate/Day 228.00

Cost 228.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

A 1 2 3

Work Description

Quantity

Unit

Reinforcing Steel Bars (12mmØ)

682.72

Kgs.

Material 12mm Ø X 20' Reinforcing Bars # 16 Tie Wire Hacksaw Blade

Quantity 128.00 20.00 6.00

Unit pcs. kgs. pcs.

Unit Cost 180.00 55.00 45.00

Total B

C

Name & Capacity of Equipment None

Number No. of Day

Rate/Day

Labor Derivation Quantity Manpower Number of Manpower (Subsidiary Work Required Capability Assigned Description) Cutting, Bending & Placing of RSB 682.72 80.00 2.00 (kgs/day)

Labor Requirement Skilled Laborer Unskilled Laborer

Number No. of Days 1.00 9.00 1.00 9.00

Rate/Day 350.00 228.00

Total

Unit Cost 43.37 Cost 23,040.00 1,100.00 270.00

24,410.00 Cost

Number of Days to Complete the Work 8.53

Cost 3,150.00 2,052.00

5,202.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No.

A

B

C

Work Description

Quantity

Unit

Unit Cost

Trash Trap

1

LS

1,867.50

Material ¼" X 1½" X 20' Angle Bar 10mmØ X 20' RSB Welding Rod

Name & Capacity of Equipment None

Quantity 1.00 5.00 0.50

Unit pcs. pcs. kgs.

Number No. of Day

Unit Cost 650.00 165.00 85.00

Cost 650.00 825.00 42.50

Total

1,517.50

Rate/Day

Cost

Labor Derivation Quantity Manpower Number of Manpower Number of Days to (Subsidiary Work Required Capability Assigned Complete the Work Description) Trash Fabrication (days per trap) 1.00 1.00 1.00 1.00

Labor Requirement Welder

Number No. of Day 1.00 1.00

Rate/Day 350.00

Total

Cost 350.00

350.00

DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Location: Item No.

Work Description

Quantity

A

Material

Quantity

B

Name & Capacity of Equipment

C

Labor Derivation (Subsidiary Work Description)

Unit

Unit

Number No. of Day

Unit Cost

Rate/Day

Quantity Manpower Number of Manpower Required Capability Assigned

Labor Requirement

Number No. of Day

Rate/Day

Unit Cost

Cost

Cost

Number of Days to Complete the Work

Cost

Related Documents

Unit Cost Derivation
June 2020 4
Cost Unit
November 2019 12
Derivation
October 2019 26
Derivation
December 2019 12