TABLE OF CONTENTS
A.) Pouring Schedule 3rd Floor Slab 3rd Floor Inclined Column 4th Floor Beams & Girder 4th Floor Inclined Columns Media Room VIP Room B.) Progress Photo Coliseum Powerhouse STP MEPFS C.) Accomplishment Report D.) MEPFS Equipment Status
Issues and Concerns 1.) Site Development 2.) Powerhouse
3.)
Trusses
4.) Laydown Area/ Staging Area 5.) Materials
6.) MEPF Contractor 7.) Slab on ground
Equipments or contractor to do the site development Installation of doors Punchlisting Can start Painting first week of April 2019 Joint Survey with PEB Steel and PBDC /Gensteel Foundation design for temporary support. Presentation to owner. Grass Cutting/Roller Rebar- On going deliveries Cement – with balance for delivery. Phenolic- Critical/Stock on site (150 pcs)– with balance for delivery. Mechanical
8.) Chain Block
FDT Soil Poison Gravel Walk behind from Mataas na Kahoy Can start first week of April or upon delivery of behind For follow-up
9.) Gas & Fuel (Petron)
For follow-up