Project Kick off Meeting Project Name : SalesBoom Location : Hyderabad Date:18/08/2008 2.00 P.M
Agenda
Project Goals
Project Introduction
Project Team
Roles & Responsibilities
High Level Project plan
Communication Plan
Issue Escalation Matrix
STC Delivery methodology
Project Goals
Finish the project within the scheduled timetable.
Finish the project with the same level of quality.
Finish the project within the scheduled budget.
Finish the project within the specified guidelines.
Do the best you can with what you have been given.
Project Sponsor: SalesBoom Inc Project Description:
Salesboom is a world leader in on demand Customer Relationship Management (CRM) and Enterprise Resource Planning software (ERP) business software solutions for the SMB market.Salesboom has over 23,000 subscribers, 3000 customers in over 148 countries around the world. Salesboom on demand platform drives innovation, enables business change, and enriches customer relations across the enterprise.
Salesboom is a thought leader in CRM and enterprise applications. By building our software completely from the ground up, Salesboom has created what has come to be one of the most powerful and dynamic hosted CRM & ERP solutions available in the market today.
Project Team Testing Head
Project Manager
Test Lead
Test Engineer
Test Engineer
Test Engineer
Testing Team
Karna Ganapathi D.SivaramaRaju B.Shekar Vishnuvardhan.K Spandana Saiabano Vinod Kumar R.veena
Roles and Responsibilities Project Manager: Client coordination, escalation & reporting. Test planning, progress tracking and status reporting. Conduct defect review meetings. Publish defect reports. Preparation of Test Summary Test lean/project Lead Team Coordination Test ware Review Incident Reports review. Review defect logs & test logs. Conduct defect review meetings. Preparation of test exit Report. Test Engineer Prepare Test Conditions and Test cases. Prepare Data Guidelines/Requirements. Prepare Test execution plan. Execute Test cases and record results. Prepare defect Logs and defect reporting
High Level Project Plan
Stage Knowledge Transfer Test Planning Test Execution Test Closure and Summary
Planned Start Date 18/08/2008
Planned End date 28/08/2008
29/08/2008
30/09/2008
1/10/2008
23/10/2008
24/10/2008
28/10/2008
Communication Plan Communication Channels: Mails and Conf Calls
Daily Status
Project Review Meeting
Weekly Status
Attending Con-Calls
Attending Minutes of Meeting
Project Plan Deliverables
Issue Escalation Matrix Issue
1st Level
2nd Level
Project related
[email protected]
[email protected]
Software Infrastructure
[email protected]
[email protected]
HR
[email protected]
[email protected]
General
[email protected]
[email protected]
?
Thank You