Moorlands, Cambridgeshire Project Title:
Private Housing, Moorlands Cambridgeshire
Project Client:
ISG Jackson Limited
Project Value:
£110,000
Project Duration: 10 weeks, starting mid January Overview Project included Ground works; Drainage; Fencing; Hard and Soft Landscaping and Canopy Construction.
Moorlands, Cambridgeshire
Broomfield Hospital Project Title:
Broomfield Hospital, Chelmsford
Project Client:
Bouygues (U. K.) Ltd
Project Value:
£500,000
Project Duration: 15 weeks Overview Project Entailed: Recycling Package (Breaking up and Crushing of existing car parks); Bulk Excavation and Reduce Level Digs; Drainage Package; Foundation and Sub Base Formation.
Broomfield Hospital
Project Title:
St. John’s School, Billericay
Project Client:
John O’Neill and Partners Ltd.
Project Value:
£450,000
Project Duration: June 2008 - April 2009 Overview Project Entailed: Site Clearance, Enabling Works; Demolition; Excavation; Sub Structure; Drainage; External works package (Tennis Courts; Playgrounds; Hard and Soft Landscaping; Sports Pitches).
St. John’s School
St. John’s School