Fast Track Construction Of Projects

  • Uploaded by: pinku291
  • 0
  • 0
  • May 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Fast Track Construction Of Projects as PDF for free.

More details

  • Words: 1,773
  • Pages: 36
FAST TRACK CONSTRUCTION OF PROJECTS Case Study - Tapovan Vishnugad Hydro Power Project By P&S Department, Dated 24.07.2009

PESENTATION BRIEF ◦ Experiences Aspects for timely execution of projects Case Studies of TVHPP

◦ Conclusions ◦ Recommendations

KEY ASPECTS FOR TIMELY EXECUTION ◦ Geological Investigations ◦ Land Acquisition ◦ Shifting of Structures ◦ Infrastructure Inputs ◦ Resistance to blasting ◦ Use of Latest Technology ◦ Timely decisions in coherent manner

INVESTIGATION PHASE Proper and adequate investigation averts delays during execution stage by: • Choosing best methodology of execution. • Avoiding geological surprises. • Making realistic designs and estimates thereby avoiding contractual complicacies in later stages. • Proper investigations backed the decision of deployment of TBM at TVHPP thereby crashing the construction period.

CONSTRUCTION PHASE o

o

o o

Knowledgeable & Trained Land Acquisition team. Effective R&R Policy Implementation. Creation of Infrastructure Use of Latest Technology to reduce execution time and mitigate environmental concerns

LAND ACQUISITION ◦ Liaison with State Departments helps in speedy approval of land acquisition and other proposals. ◦ Liasion office has been established in Dehradun (State capital) to expedite the proposals. ◦ Know How of land acquisition procedures to the executives engaged in ground work is crucial. ◦ Trained Patwaris were hired to help in ground works.

R&R WORKS ◦ Community development works were finalized in consultation with local bodies. ◦ Medical camps helped in developing good-will. ◦ Community development works helped villagers in terms of facilities and job. ◦ Co-operative societies of the same village were involved for CD works of a village.

R&R WORKS ◦ Shifting of Structures to ensure unhindered progress of work and to avoid inconvenience to population using the structures. ◦ Crucial structures like Temples, Govt. Inter College, Ayurvedic hospitals, suspension bridges and houses were to be shifted from Barrage area.

SHIFTING OF STRUCTURES ◦ Public was educated about the need of shifting. ◦ All Govt. bodies and local bodies like Panchayat, Youth club, Mahila Mangal Dals etc were taken into confidence. ◦ Alternative arrangements were made prior to shifting of original structures. ◦ Due respect was paid to local population’s sentiments with the structures especially Temples. ◦ Special care taken to maintain the original architecture of ancient temples to be shifted. ◦ Works of construction of new structures and removal/shifting of old ones was

RELOCATED ANCIENT TEMPLE

INFRASTRUCTURE INPUTS Approach Roads: ◦ Agencies like BRO & PWD are available at the start of the project to commence approach works. ◦ Our experience – They are not good at maintaining schedules. After the award of main packages, the approach roads should be included in main packages. All approach roads should be concrete paved to avoid problems during monsoon

INFRASTRUCTURE INPUTS Construction Power: ◦ Construction power is crucial for execution especially when we are using technologies like TBM & Road Header. ◦ Augmentation of Power network was done from Srinagar to Joshimath. ◦ Un-reliability of power was hampering progress. ◦ To tackle the voltage fluctuations in peak hours, OLTC transformer is installed. ◦ Contract should have provision for

INFRASTRUCTURE Before

the completion of land acquisition activities, residences and offices are accommodated in hired buildings. As an early solution Pre-fabricated offices and porta-cabins are being used as site offices. Phased construction taken up for Township. Phase -1 of prefab structures for office & Bachelor accommodation has been started.

CONSTRUCTION PHASE Use of Latest Technology to reduce execution time

USE OF LATEST TECHNOLOGY ◦ Location & No. of Adits: Normally 12 km long tunnel needs 2 intermediate adits due to lead distance and ventilation considerations. Deployment of TBM obviated the need of 2nd adit and this HRT needs only 1 intermediate adit resulting in time & cost savings.

◦ Selection of Excavation methodology: Mechanized tunneling such as TBM and Road header have been used. A conference was held in Delhi and decision to deploy TBM was taken after elaborate discussions with TBM suppliers. TBM gives 3-5 times the progress rate of conventional excavation. TBM & Road Header cause less vibration and pollution and provide much safer working

USE OF LATEST TECHNOLOGY

◦ Selection of latest Equipment:

Drill Jumbos being used for drill & blast and rock bolting operations provide better progress & efficiency. High capacity excavators and dumpers for faster excavation and mucking. Grabs are being used for excavation of cut off wall Raise climber being used for inclined Pressure Shaft excavation. Raise Borer deployed for pilot bore and reaming of surge shaft excavation.

USE OF LATEST TECHNOLOGY ◦ Raise Borer deployed for Surge shaft pilot boring and reaming. ◦ Offers higher progress rate, pilot bore completed in 3 days and reaming completed in 12 days. ◦ Excavation of Surge Shaft close to populated area by this technology caused practically no disturbance to adjacent population.

RESISTANCE TO BLASTING The

project faced a major obstacle by people alleging that the blasts for excavation are causing cracks in their houses. This was motivated by experience of nearby Vishnuprayag HPP. To tackle the issue: ◦ Local administration taken into confidence, ◦ Frequent interaction & communication with villagers and representatives, ◦ An investigation on impact of blasts on the structures in project vicinity carried out by independent agency which gave us clean chit.

TIMELY DECISION IN COHERENT MANNER Speed of project depends on the speed of decision making

Decision to change the alignment of Chormi Adit approach road. New alignment: Is 3.5 km long against earlier planned of 8.5 km. At least 20 ha land acquisition is avoided, resulting in direct saving of approx Rs. 25 Cr. and also saving of land acquisition time. Also serves as approach road to SFT outfall resulting in time & cost saving. Provides much shorter approach between 2nd and 3rd adit of HRT thereby improving the accessibility and ease of supervision.

APPROACH TO CHORMI ADIT Barrage Site Intake (3rd ) Adit Portal

Alignment - 2

Chormi (2nd ) Adit Portal Proposed alignment -1

The decision to introduce third adit near Intake end of HRT ◦ The decision resulted in: Early opening of front – Before the opening of front of 2nd adit approx. 1 km excavation of HRT from this new adit is achieved. Considerable gain in time & cost.

Construction of Part of Third adit through separate contract ◦ Construction of part of third adit was awarded to M/s Highway & Hydel on 31.08.06. ◦ Main HRT package was awarded to M/s L&T AM JV on 28.11.06 ◦ Thus awarding this small contract helped in early start of work. ◦ Before the mobilization of HRT agency: Approach up to the adit was completed. Open excavation was completed. Part of slope protection works were completed.

Decision to shift the location of TBM adit

◦ Earlier location involved major support works with huge amount of overburden to be removed. ◦ The overburden was likely to disturb the NH 58 which is lifeline of Joshimath Town. ◦ A calculated risk was taken by shifting the Portal location closer to ridge line. ◦ The decision involved well good coordination in Site & Engineering. ◦ Decision involved a lot of survey & geological appraisals and need of

Decision to shift the location of TBM adit Earlier Location Final Location HRT

TBM assembly in Two Phases ◦ Against the area requirement of 15X235m for TBM assembly, area available was 10X70m. ◦ An innovative decision to assemble TBM in 2 phases was taken. ◦ First- Adit was excavated up to 130m chainage ◦ After part assembly of TBM up to BU # 11, TBM was pushed up to the face and TBM excavation was started. ◦ At Ch. 294m, TBM was stopped and Assembly up to BU # 21 was completed.

Decision to change the alignment of approach road to Surge Shaft Top. New alignment:

◦ Involved only 200m length (against 1km) of fresh construction thereby resulting in cost saving. ◦ This shorter length involved very small blasting and hence found no hindrance to work. ◦ The road is being used by the villagers too thus the strengthening of road is giving goodwill to NTPC among PAPs. ◦ The strengthening works were executed through PAPs resulting in improved relation with the village. ◦ Pilot hole and reaming of Surge Shaft

completed well within time besides cost saving.

scheduled

APPROACH TO SURFGE SHAFT Proposed Alignment 1

Existing Road to Shelong Village

Alignment - 2

Decision to include approach road to Pressure Shaft Intermediate adit in PH package: ◦ BRO and PWD were unable to take up the work due to other priorities in the district. ◦ Decision to include road in PH package resulted in: Utilization of equipment and mobilization of agency saving NTPC from idling claims. Saved a lot of time of award & mobilization. Started Pressure shaft excavation from intermediate adit before schedule.

SELECTION OF GOOD CONTRACTOR WITH WORKABLE RATES

Experience with SSJV - ZVS ◦ SSJV-ZVS emerged as L1 and got the Barrage & De - Silting Basin package of TVHPP. ◦ Due to unprecedented rise in rates of Steel & Cement, the rate of concreting items became unworkable. ◦ Situation got aggravated by coinciding financial meltdown of Satyam group. ◦ Barrage package is suffering. ◦ A better formula to compensate for such unusual price hikes of steel & cement should be developed. ◦ Employer bears the market fluctuations where Cement & Steel are provided by the employer.

CONCLUSIONS ◦ When it comes to Fast Track Execution of Hydro Projects, speed of decision making is crucial ◦ Investment in geological investigations give high returns. ◦ Geologists are the insurance policy of project. ◦ Hydro Projects are generally constructed in scarcely/less populated areas where even small group of people can affect the progress.

CONCLUSIONS ◦ Selection of good contractor with workable rates is a must. ◦ Efficient construction methodology and latest technologies reduce construction time. ◦ Innovations should be encouraged. ◦ Capturing of best practices through initiatives like this is also important. ◦ And the most important… A highly motivated and enthusiastic team of professionals.

RECOMMENDATIONS Following can help in fast track project implementation: Effective R&R policy and implementation. Accommodations to be constructed in early phases of project. Mechanism for compensating unusual hike in rates of steel & cement. We should be open to revisions in construction methodology even at the cost of revision in TS. Designers should pay regular visit to

RECOMMENDATIONS ◦ Following can help in fast track project implementation: Agency for survey and geological investigation should be available during construction phase. Dispute resolution mechanism is a must for Hydro. TOC should be accompanied with Engg. Team & designers for effective implementation of their suggestions. Construction power network should choose alignment involving least land acquisition & Forest patches rather than

Related Documents


More Documents from ""