Broomfield Hospital Project Title:

Broomfield Hospital, Chelmsford

Project Client:

Bouygues (U. K.) Ltd

Project Value:

£500,000

Project Duration: 15 weeks Overview Project Entailed: Recycling Package (Breaking up and Crushing of existing car parks); Bulk Excavation and Reduce Level Digs; Drainage Package; Foundation and Sub Base Formation.