IRCON International Limited J&K Rail Project, Srinagar
1
Name of work
Construction of Platform etc. at various Railway stations in Zone PF-1 between km0.00 to 45.00 (Package PF-1) on Qazigund Baramulla section of new BG Rail line Project, J&K.
2
Name of Contractor
AM Contractors, Gaziabad, Anchidora, Anantnag, J&K
3
LoA No& Date
5
Oiginal Contract value
Rs5,22,08,012.14.
6
Revised Contract value
NA
7
Scheduled Date of completion of work:
8 9 10
IRCON/ 1008/ J&K- DLI/ Platform/ PF-1/6762; Dated: 05/01/2006
As per Original contract
04/01/2006
Reference of contractor’s Letter seeking extension of time: Time Extension Recommended up to:
Reference of contractors letter no:AMC/8111/42 Dt:19-122006 and Letter no:AMC/8111/44; Dt:31-12-2006 31-07-2007
Present status of work Financial
Rs.2,50,58,950.43
Physical
40%
11
Expected time required for Completion:
Three months
12
Details of time lost due to: Variation in quantities/ scope of work
1. Due to variation of quantity- 225 Days 2. For fixation of rate ----- days. NA
Snow fall & weather condition.
3. Snow fall-16 days 4. Rainfall-61 days
Law and Order Situation
NA
Land Acquisition:
NA TOTAL: 317 Days
13
Reasons details for granting time extension:
a) the work remained suspended due to bad weather for a long period from in different periods due to Heavy snow/rain fall. b) Qty of work has increased 62% above the BOQ, so it requires additional 225 days for completing the revised volume of work. c) There were so many days work has stopped due to local strikes, holiday etc in the working season.
14
15
Delay in completion of work is attributable to : Contractor
Nil
IRCON
Nil
Neither to IRCON or contractor: Time extension Recommended upto:
Neither to IRCON or contractor 31-07-2007
With or without penalty
Without penalty
With or without PVC
With PVC
Submitted for kind approval.
(Surajit Ghosh) Assistant Manager / Civil (Samir Haloi) Manager/ Civil
JGM/ Civil
AGM/ Finance
GM/ Srinagar