IRCON International Limited J&K Rail Project, Srinagar

1

Name of work

Construction of Platform etc. at various Railway stations in Zone PF-1 between km0.00 to 45.00 (Package PF-1) on Qazigund Baramulla section of new BG Rail line Project, J&K.

2

Name of Contractor

AM Contractors, Gaziabad, Anchidora, Anantnag, J&K

3

LoA No& Date

5

Oiginal Contract value

Rs5,22,08,012.14.

6

Revised Contract value

NA

7

Scheduled Date of completion of work:

8 9 10

IRCON/ 1008/ J&K- DLI/ Platform/ PF-1/6762; Dated: 05/01/2006

As per Original contract

04/01/2006

Reference of contractor’s Letter seeking extension of time: Time Extension Recommended up to:

Reference of contractors letter no:AMC/8111/42 Dt:19-122006 and Letter no:AMC/8111/44; Dt:31-12-2006 31-07-2007

Present status of work Financial

Rs.2,50,58,950.43

Physical

40%

11

Expected time required for Completion:

Three months

12

Details of time lost due to: Variation in quantities/ scope of work

1. Due to variation of quantity- 225 Days 2. For fixation of rate ----- days. NA

Snow fall & weather condition.

3. Snow fall-16 days 4. Rainfall-61 days

Law and Order Situation

NA

Land Acquisition:

NA TOTAL: 317 Days

13

Reasons details for granting time extension:

a) the work remained suspended due to bad weather for a long period from in different periods due to Heavy snow/rain fall. b) Qty of work has increased 62% above the BOQ, so it requires additional 225 days for completing the revised volume of work. c) There were so many days work has stopped due to local strikes, holiday etc in the working season.

14

15

Delay in completion of work is attributable to : Contractor

Nil

IRCON

Nil

Neither to IRCON or contractor: Time extension Recommended upto:

Neither to IRCON or contractor 31-07-2007

With or without penalty

Without penalty

With or without PVC

With PVC

Submitted for kind approval.

(Surajit Ghosh) Assistant Manager / Civil (Samir Haloi) Manager/ Civil

JGM/ Civil

AGM/ Finance

GM/ Srinagar

Related Documents

Pf-1 1st Time Extension
November 2019 8
Time Extension
May 2020 5
Pf1
November 2019 8
Motion For Extension Of Time
November 2019 41
M-12 2nd Time Extension
November 2019 5
Extension
May 2020 27