3.3 Perhitungan Volume Galian dan Timbunan No
STA
Luas Penampang (m²) Galian
Timbunan
1
0+000
8,388
0
2
0+100
7,282
0
3
0+200
0
7,912
4
0+300
6,032
0
5
0+400
8,829
0
6
0+500
8,187
0
7
0+600
9,172
0
8
0+700
6,070
0
9
0+800
6,755
0
10
0+900
10,496
0
11
1+000
13,052
0
12
1+100
15,007
0
13
1+200
7,210
5,314
14
1+300
2,456
4,530
15
1+400
2,363
2,447
16
1+500
2,556
0
17
1+600
1,720
0,231
18
1+700
0
5,799
19
1+800
0
8,112
20
1+900
0
9,371
Jarak (m)
Volume Penampang (m³) Galian
Timbunan
100
783,5
0
100
364,1
395,6
100
301,6
395,6
100
743,05
0
100
850,8
0
100
867,95
0
100
762,1
0
100
641,25
0
100
862,55
0
100
1177,4
0
100
1402,95
0
100
1110,85
265,70
100
483,30
492,20
100
240,95
348,85
100
245,95
122,35
100
213,80
11,55
100
0
301,50
100
0
695,55
100
0
874,15
79
No
STA
21
Luas Penampang (m²) Galian
Timbunan
2+000
0
6,697
22
2+100
2,928
0,245
23
2+200
3,938
0,479
24
2+300
2,350
4,007
25
2+400
0
3,047
26
2+500
1,944
1,515
27
2+600
3,331
2,609
28
2+700
4,829
1,689
29
2+800
5,445
0,030
30 31 32 33 34 35 36 37
2+900 3+000 3+100 3+200 3+300 3+400 3+500 3+600
8,280 9,709 9,817 9,578 6,790 0 0 0
Jarak (m)
Volume Penampang (m³) Galian
Timbunan
100
0
803,40
100
146,40
347,10
100
343,30
36,20
100
314,40
224,30
100
117,50
352,70
100
97,20
230,81
100
263,75
206,20
100
408,00
214,90
100
513,70
85,95
100
686,25
1,50
100
899,45
0
100
976,30
0
100
969,75
0
100
818,40
0
100
339,50
426,85
100
0
1058,70
100
0
1300,20
100
107,60
858,40
100
478,35
190,05
0 0 0 0 0 8,537 12,637 13,367
38
3+700
2,152
3,801
39
3+800
7,415
0
80
Jadi, dari total hasil perhitungan luasan galian dan timbunan yang dihitung persegmen stasioning adalah sebagai berikut : - Total Pekerjaan Galian
= 16287,9 M3
- Total Pekerjaan Timbunana
= 7138,81 M3 = 7138,81 x Faktor gembur tanah (1,2) = 8566,57 M3