Radiogram No. 4855u Form 24 for 03/13/07 PROGRESS 358 UNLOADING AND IMS OPS GMT
CREW
ACTIVITY
06:00-06:10
Morning inspection
06:10-06:40
Post-sleep
06:40-07:30
BREAKFAST
07:30-07:45
Prep for Work
07:45-08:00
Daily Planning Conference (S-band)
08.00-08.15
Prep for Work
08:15-09:20 CDR
PMA3 pressurization
08:15-09:15 FE-2
Progress 358 Unloading and IMS Ops
08:15-11:35 FE-1
Progress 358 Unloading and IMS Ops
09:20-09:35 CDR
PMA3 ingress
09:35-09:55 CDR, FE-2 Disk cover dismantling in Node 1 09:55-11:25 FE-2
Progress 358 Unloading and IMS Ops
09:55-11:25 CDR
CBM CPA Dismantling
11:25-12:10 CDR, FE-2 PMA3 Equipment Unstow 11:35-12:35 FE-1
Physical Exercise (VELO+RED) day 4
12:10-12:25 CDR
Private Medical Conference (Ku + S-band)
12:10-13:40 FE-2
Physical Exercise (TVIS)
12:35-12:55 FE-1
Cleaning БВН [Heater Fan ] screen in Soyuz
12:40-13:40 CDR
Physical Exercise (RED)
12:55-13:10
БСР-ТМ. SW Reboot Tagup with specialists (S-band)
13:10-13:30
FE-1
13:40-14:40 .
IMS update LUNCH
14:40-17:10 CDR, FE-2 Node 1 Starboard Hatch window installation 14:40-15:05
АОК ГАНК-4М [Real-time harmful contaminant gas analyzer] Calibration and Readings (To calibrate analyzer for СО, enter coefficient В=-62.7 (minus 62.7)). Tagup with specialists (as necessary, S-band)
15:05-15:35 FE-1
Filling and disinfection of US/RSA-B hose. Tagup with specialists (as necessary) (S-band)
15:35-16:15
Filling EDV [KOB] (separation) for Elektron
16:15-16:45
СОЖ Maintenance
16:45-18:15
Physical Exercise (TVIS), Day 4
17:10-17:25 FE-2
Private Medical Conference (Ku + S-band)
17:10-18:40 CDR
Physical Exercise (CEVIS)
17:25-17:55
Boeing Bearing Motor Roll Ring Module (BMRRM) Tie Down
17:55-18:55 18:15-18:30 18:30-18:55
FE-2 FE-1
Physical Exercise (RED) Private Medical Conference (Ku + S-band) Evening work prep
18.40-18.45
РМА3 hatch closure
18:45-18:50 CDR
Transfer TVIS/RED/CEVIS/HRM data to MEC
18:50-18:55
Evening work prep
18:55-19:10
Daily Planning Conference (S-band)
19:10-19:30
Evening work prep
19:30-20:00
DINNER
20:00-20:30
Daily Food Prep
20:30-21:30
Pre-sleep
21:30-06:00
SLEEP
Task List
FE-1
ТБУ (Universal Bioengineering Thermostat). Temperature check
URAGAN. Observation and photography Note: See OSTP for references to US activities. End of Radiogram