MOM conducted between ISGEC and Kirti Develop Sl.No
Description
Reported On
Target Date
1
Re-calibration of Compression testing machine
11/4/2019
13/4/2019
2 3 4
Calibration certificate of Batching Plant Calibration certificate of Auto Level Calibration certificate of Total station
5/4/2019 5/4/2019 5/4/2019
15/4/2019 15/4/2019 15/4/2019
5
Arranging 30 No's of Cube moulds @ site
5/4/2019
18/4/2019
6
Arranging Soil Core Cutter set @ site
5/4/2019
18/4/2019
7
Arranging and setting up QC lab at site as per the attached Equipment list Format NO: 10092/ DEC'17
12/4/2019
18/4/2019
8
Compressive strength and water absorption test reports of Bricks
5/4/2019
15/4/2019
9
Test reports of Coarse Aggregates, 10 & 20 mm (Sieve analysis and Impact value)
5/4/2019
15/4/2019
10 Test reports of Sieve analysis of Sand 11 FDD and Compaction test reports of Soil
5/4/2019 5/4/2019
15/4/2019 15/4/2019
Standard Consistency, Initial and Final setting time of 12 Fineness, Cement lab test reports
5/4/2019
15/4/2019
13 Water test report 14 Submission of pending checklists
5/4/2019 9/4/2019
15/4/2019 15/4/2019
SGEC and Kirti Developers Status as on date
Remarks
Open
CTM found with Calibration error; Re-calibration required to be done.
Open Open Open Open Open Open Open Open Open Open Open Open Open
12 moulds are available @ site & the remaining 18 yet to be arranged