NANDED CITY DEVELOPMENT & CONSTRUCTION COMPANY LIMITED
METHOD STATEMENT GRANITE FRAME
NAME PREPARED BY :
INFINI INSTITITUTE (GROUP A)
REVIEWED BY :
Mr. Vipul Patil
DATE
SIGNATURE
REVISION STATUS
Rev No.
Date of Rev.
Description
00
12.01.2019
Initial Submission for Approval
TABLE OF CONTENTS
1. Flow Chart ……………………………………………………... 2. Scope …………………………………………………………… 3. Resources ……………………………………………………… 4. References …..………………………………………………… 5. Construction Procedure …………………………………….. 6. Control Measures …………………………………………….. 7. Records ………………………………………………………… 8. RACI Matrix ……………………………………………………. 9. Check List ………………………………………………………
WORK METHOD STATEMENT FOR GRANITE FRAME: Flow Chart:
Issuing of Granite
Material Receiving & Cutting
Applying crush sand at the rear side and waiting for over night.
SHOP DRAWI NG
Measuring of dimesion and cutting of granite accordingly if required
Fixing of Sill sub frame and check for any slope
Checking to be done to see if granite projections are matching with that of skirting or not
Fixing of Both the vertical sub frame and check for its plum
Fixing of Lintel sub frame and check for right anglr for all the four sides
Support to be given for one day
Scope:
Procedure to fix the granite frame for a window & w/c doors over the concrete surface in Pancham building for all flats.
RESOURCES: A. Tools and Machinery:
Electric Cutting Machine (800W) Plumb bob/spirit level Accent Trowel(4”) M S Pan Rubber Hammer String M S Angle
B. Materials: Bamboos for supporting purpose Granite(black pearl) Cement OPC 53 Water Bontite ( Type A & B) Crushed sand C. Manpower: 1 Mason 1 Helper Procedure: Application of crushed sand at the rear side with the help of araldite (Type A & B) for bonding purpose.
Should be kept for 24 Hrs. before commencement of actual work. Checking for actual dimension and cutting accordingly (if required). Fixing of sill sub frame with the cement paste. Check for any slope if there with the help of spirit level. Fixing of two vertical sub frame with help of cement paste. Check for plum level and its projection which should match ith the skirting. Fixing of lintel sub frame. Apply support with the help of bamboo.
CONTROL MEASURES:
Projection of sill sub frame and skirting should coincide. Dimensions should be as per the drawings.
RACI MATRIX
Responsibility:
Accountable
Consult to
Informed to
Vendor/Contractor - The Vendor/Contractor should start the work only after the clearance from the site engineer. Site Engineer – The engineer should provide the Vendor/Contractor with Architectural drawing, Shop drawings and Specifications for the work and should request the consultant for the visit prior to the work. Also the check list for each activity should be produced by the site engineer. Architect, Manufacturer – Checking should be done by consultant as per site engineers request and approval for work shall be given. Project Manager – Daily reporting shall be done to the project manager by the site engineer.
REFERENCES
Architectural drawing GFC drawings Technical data sheet (Araldite by Bondtite) Cement Specification BOQ
RECORDS:
Work Inspection requests Material Inspection requests Check List Test samples
CHECK LIST ACTIVITY: PROJECT: LOCATION:
SR.NO.
PARTICULARS
1 2 3
Material Receiving & Cutting as per shop drawing Application of Araldite on rear surface of granite Applying crush sand at the rear side after araldite and waiting for over night Cleaning the surface Checking the mix proportion of water and cement as per specification Fixing of Sill sub frame and check for any slope Checking to be done to see if granite projections are matching with that of skirting or not Fixing of Both the vertical sub frame and check for its plum Fixing of Lintel sub frame and check for right angle for all the four sides and fixing temporary support for it Cleaning the area after work is done
4 5 6 7 8 9 10
ACTION REQUIRED (IF ANY):
REPORTED TO: CHECKED BY: COMMENTS:
DATE:
YES
NO