DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA

SNI DT 91 -0006-2007 Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan 6.1 Menggali 1 m3 tanah biasa sedalam 1 meter 6.2 Menggali 1 m3 tanah biasa sedalam 2 meter 6.3 Menggali 1 m3 tanah biasa sedalam 3 meter 6.4 Menggali 1 m3 tanah keras sedalam 1 meter 6.5 Menggali 1 m3 tanah cadas sedalam 1 meter 6.6 Menggali 1 m3 tanah lumpur sedalam 1 meter 6.7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter 6.8 Membuang 1 m3 tanah sejauh 30 meter 6.9 Mengurug kembali 1 m3 galian 6.10 Memadatkan 1 m3 tanah (per 20 cm) 6.11 Mengurug 1 m3 pasir urug 6.12 Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL 6.13 Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL 6.14 Memasang 1 m2 lapisan ijuk tebal 10 cm 6.15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan

SNI DT 91 -0007-2006 Tata cara perhitungan harga satuan pekerjaan pondasi untuk konstruksi bangunan gedung dan perumahan 6 Penetapan indeks harga satuan pekerjaan pondasi 6.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP 6.2 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP 6.3 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP 6.4 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP 6.5 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 8 PP 6.6 Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP 6.7 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP 6.8 Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP 6.9 Memasang 1 m3 batu kosong (aanstamping) 6.10 Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah 6.11 Memasang 1 m3 pondasi sumuran, diameter 100 cm SNI DT 91 -0008-2007 Tata cara perhitungan harga satuan pekerjaan beton untuk konstruksi bangunan gedung dan perumahan 6.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 6.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 6.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 6.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 6.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 6.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 6.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 6.8 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 6.9 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53

Page 1 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 6.10 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 6.11 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49 6.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48 6.13 Membuat 1 m3 beton kedap air dengan strorox – 100 6.14 Memasang 1 m’ PVC Waterstop lebar 150 mm 6.15 Memasang 1 m’ PVC Waterstop lebar 200 mm 6.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm 6.17 Pembesian 10 kg dengan besi polos atau besi ulir 6.18 Memasang 10 kg kabel presstressed polos/strands 6.19 Memasang 10 kg jaring kawat baja/wire mesh 6.20 Memasang 1 m2 bekisting untuk pondasi 6.21 Memasang 1 m2 bekisting untuk sloof 6.22 Memasang 1 m2 bekisting untuk kolom 6.23 Memasang 1 m2 bekisting untuk balok 6.24 Memasang 1 m2 bekisting untuk lantai 6.25 Memasang 1 m2 bekisting untuk dinding 6.26 Memasang 1 m2 bekisting untuk tangga 6.27 Memasang 1 m2 jembatan untuk pengecoran beton 6.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 6.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting) 6.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting) 6.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 6.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 12 6.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) 6.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) 6.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 6.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.1 Membuat 1 m3 beton f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 SNI DT 91 -0009-2007 Tata cara perhitungan harga satuan pekerjaan dinding untuk konstruksi bangunan gedung dan perumahan 6.1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP 6.2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP 6.3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 4 PP 6.4 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 5 PP 6.5 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 6 PP 6.6 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 KP : 10 PP 6.7 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP 6.8 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP 6.9 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP 6.10 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP 6.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 6 PP 6.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 1 PC : 8 PP 6.13 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 KP : 10 PP 6.14 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 1 PP 6.15 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 2 PP 6.16 Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP 6.17 Memasang 1 m2 dinding HB 20, cam puran spesi 1 PC : 4 PP 6.18 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP 6.19 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP 6.20 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP

Page 2 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 6.21 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP 6.22 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP 6.23 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP 6.24 Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1 PC : 3 PP SNI DT 91 -0010-2007 Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumahan 6.1 Memasang 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm 6.2 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm 6.3 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm 6.4 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm 6.5 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm 6.6 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm 6.7 Memasang 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm 6.8 Memasang 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm 6.9 Memasang 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm 6.10 Memasang 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm 6.11 memasang 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm 6.12 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm 6.13 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm 6.14 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm 6.15 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm 6.16 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm 6.17 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm 6.18 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm 6.19 Memasang 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm 6.20 Memasang 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mm 6.21 Memasang 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm 6.22 Memasang 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm 6.23 Memasang 1 m2 Plesteran Ciprat 1 PC : 2 PP 6.24 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’) 6.25 Memasang 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’) 6.26 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP 6.27 Memasang 1 m2 acian

SNI DT 91-0011-2007 Tata cara perhitungan harga satuan pekerjaan kayu untuk konstruksi bangunan gedung dan perumahan 6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I 6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III 6.3 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II 6.4 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III 6.5 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II 6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II 6.7 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II 6.8 Membuat 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm) 6.9 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II 6.10 Memasang 1 m2 jalusi kusen, kayu kelas I atau II

Page 3 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 6.11 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I 6.12 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II 6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter 6.14 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I 6.15 Memasang 1 m3 konstruksi gordeng, kayu kelas II 6.16 Memasang 1 m2 rangka atap genteng keramik, kayu kelas II 6.17 Memasang 1 m2 rangka atap genteng beton, kayu kelas II 6.18 Memasang 1 m2 rangka atap sirap, kayu kelas II 6.19 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III 6.20 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 6.21 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 6.22 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II 6.23 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III 6.24 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II 6.25 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II 6.26 Memasang 1 m2 dinding lambriziring dari papan kayu kelas I 6.27 Memasang 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm 6.28 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV

SNI DT 91 -0012-2007 Tata cara perhitungan harga satuan pekerjaan penutup lantai dan dinding untuk konstruksi bangunan gedung dan perumahan 6.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm 6.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm 6.3 Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm 6.4 Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm 6.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm 6.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm 6.7 Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm 6.8 Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm 6.9 Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm 6.10 Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm 6.11 Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm 6.12 Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm 6.13 Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm 6.14 Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm 6.15 Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm 6.16 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm 6.17 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm 6.18 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm 6.19 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm 6.20 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm 6.21 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm 6.22 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm 6.23 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm 6.24 Memasang 1 m plint ubin granit ukuran (10 x 40) cm 6.25 Memasang 1 m plint ubin granit ukuran (10 x 30) cm 6.26 Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm 6.27 Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm

Page 4 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 6.28 Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm 6.29 Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm 6.30 Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm 6.31 Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm 6.32 Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm 6.33 Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm 6.34 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm 6.35 Memasang 1 m2 lantai keramik ukuran (30 x 30) cm 6.36 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm 6.37 Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border 6.38 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP 6.39 Memasang 1 m’ plint keramik ukuran (10 x 20) cm 6.40 Memasang 1 m’ plint keramik ukuran (10 x 10) cm 6.41 Memasang 1 m’ plint keramik ukuran (5 x 20) cm 6.42 Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm 6.43 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm 6.44 Memasang 1 m2 lantai karpet 6.45 Memasang 1 m2 underlayer 6.46 Memasang 1 m2 lantai parquet 6.47 Memasang 1 m2 lantai kayu (gym floor) 6.48 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm 6.49 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm 6.50 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm 6.51 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm 6.52 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm 6.53 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm 6.54 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm 6.55 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm 6.56 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm 6.57 Memasang 1 m2 dinding batu paras 6.58 Memasang 1 m2 dinding batu tempel hitam 6.59 Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I 6.60 Memasang 1 m2 wall paper, lebar 50 cm 6.61 Memasang 1 m2 floor hardener 6.62 Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat 6.63 Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm

SNI DT 91 -0013-2007 Tata cara perhitungan harga satuan pekerjaan langit-langit untuk konstruksi bangunan gedung dan perumahan -

6 Penetapan indeks harga satuan pekerjaan langit-langit 6.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 6.2 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm 6.3 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm 6.4 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm 6.5 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm 6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm 6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium

Page 5 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA - 6.9 Memasang 1 m’ list langit-langit kayu profil

SNI DT 91 -0014-2007 Tata cara perhitungan harga satuan pekerjaan besi dan aluminium untuk konstruksi bangunan gedung dan perumahan 5 Penetapan indeks harga satuan pekerjaan besi dan aluminium 6.1 Memasang 1 kg besi profil 6.2 Memasang 1 kg rangka kuda-kuda baja IWF 6.3 Mengerjakan 100 kg pekerjaan perakitan 6.4 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 6.5 Mengerjakan 10 cm pengelasan dengan las listrik 6.6 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm 6.7 Memasang 1 m2 pintu rolling door besi 6.8 Memasang 1 m2 pintu lipat (Folding door) 6.9 Memasang 1 m2 sunscreen alluminium 6.10 Memasang 1 m2 rolling door alluminium 6.11 Memasang 1 m kusen pintu alluminium 6.12 Memasang 1 m2 pintu alluminium strip lebar 8 cm 6.13 Memasang 1 m2 pintu kaca rangka alluminium 6.14 Memasang 1 m2 venetions blinds dan Vertical blinds 6.15 Memasang 1 m2 terali besi strip (2 x 3) mm 6.16 Memasang 1 m2 kawat nyamuk 6.17 Memasang 1 m2 jendela nako & tralis 6.18 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 6.19 Memasang 1 m’ talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm

RSNI. T-15-2002 PEKERJAAN PERSIAPAN 1 m' Pagar Sementara dari Kayu tinggi 2 m 1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m 1 m' Pagar Sementara dari Kawat Duri tinggi 1.8 m 1 m' Pek. Pengukuran & Pemasangan Bowplank 1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran 1 m² Pembuatan Gudang Semen dan Alat - alat 1 m² Pembuatan Rumah Jaga / Konstruksi Kayu 1 m2 Membersihkan Lapangan dan Perataan 1 m² Pembuatan Bedeng Buruh 1 m² Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm 1 m² Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm 1 m² Pembuatan Jalan Sementara 1 m³ Bongkaran Beton Bertulang 1 m³ Bongkaran Dinding Tembok Bata Merah

SNI. 03-3436-1994 PEKERJAAN PENTUP ATAP

Page 6 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 1m² Pasang Atap Genteng Palentong Kecil 1m² Pasang Atap Genteng Kodok / Glazzur 1m² Pasang Atap Genteng Palentong Super / Besar 1m' Pasang Genteng Bubung Palentong 1m' Pasang Genteng Bubung Kodok Glazzur 1m' Pasang Genteng Bubung Palentong Besar 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm 1m' Pasang Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm 1m² Pasang Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 240 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm 1m' Pasang Bubung Stel Gelombang 0.92m 1m' Pasang Nok Stel Gelombang 0.92m 1m' Pasang Nok Stel Gelombang 1.05m 1m' Pasang Nok Stel Gelombang 1.08m 1m' Pasang Nok Paten 0.92m 1m' Pasang Nok Paten 1.05m 1m' Pasang Nok Paten 1.08m 1m' Pasang Nok Stel rata 0.92m 1m' Pasang Nok Stel rata 1.05m 1m² Pasang Atap Genteng Beton 1m² Pasang Atap Genteng Aspal 1m² Pasang Atap Genteng Metal 1m² Pasang Atap Sirap 1m' Pasang Nok Genteng Beton 1m' Pasang Nok Genteng Aspal 1m' Pasang Nok Genteng Metal 1m' Pasang Nok Genteng Metal 1m' Pasang Nok Sirap 1m² Pasang Atap Seng Gelombang 1m² Pasang Atap Nok Seng 1m² Pasang Atap Alluminium 1m² Pasang Nok Alluminium 1m² Pasang Alluminium Foil / Sisalation RSNI. T-15-2002 PEKERJAAN SANITASI Memasang 1 buah Kloset Duduk / Monoblok Memasang 1 buah Kloset Jongkok Porselen Memasang 1 buah Kloset Jongkok Teraso Memasang 1 buah Urinoir

Page 7 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA Memasang 1 buah Wastafel Memasang 1 buah Bak Mandi Teraso, volume 0.30 m³ Memasang 1 buah Bak Mandi Fiberglass, volume 0.30 m³ Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³ Memasang 1 buah Badkip Porselen Memasang 1 buah Bak Fiberglass volume 1 m³ air Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø15 cm Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 20 cm Memasang 1 m' Pipa Beton Ø 5 cm - 20 cm Memasang 1 m' Pipa Beton Ø 30 cm - 100 cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm Memasang 1 m' Pipa Galvanis Ø ½" Memasang 1 m' Pipa Galvanis Ø ¾" Memasang 1 m' Pipa Galvanis Ø 1" Memasang 1 m' Pipa Galvanis Ø 1½" Memasang 1 m' Pipa Galvanis Ø 3" Memasang 1 m' Pipa Galvanis Ø 4" Memasang 1 m' Pipa PVC tipe AW Ø ½" Memasang 1 m' Pipa PVC tipe AW Ø ¾" Memasang 1 m' Pipa PVC tipe AW Ø 1" Memasang 1 m' Pipa PVC tipe AW Ø 1½" Memasang 1 m' Pipa PVC tipe AW Ø 2" Memasang 1 m' Pipa PVC tipe AW Ø 2½" Memasang 1 m' Pipa PVC tipe AW Ø 3" Memasang 1 m' Pipa PVC tipe AW Ø 4" Memasang 1 bh Bak Cuci Piring Stainles Steel Memasang 1 bh Bak Cuci Piring Teraso Memasang 1 bh Kran Ø ¾" atau ½" Memasang 1 bh Floor Drain

PT. T-30.2000-C PEKERJAAN KUNCI DAN KACA 1 Buah Pasang kunci Tanam Antik 1 Buah Pasang kunci Tanam Biasa 1 Buah Pasang kunci Tanam Kamar Mandi 1 Buah Pasang kunci Silinder 1 Buah Pasang Engsel Pintu 1 Buah Pasang Engsel Jendela Kupu - kupu 1 Buah Pasang Engsel Angin 1 Buah Pasang Spring Knip 1 Buah Pasang Kait angin 1 Buah Pasang Door Closer 1 Buah Pasang Kunci Selot 1 Buah Pasang Pegangan Pintu / Door Holder 1 Buah Pasang Door Stop 1 Buah Pasang Rel Pintu Dorong 1 Buah Pasang Kunci Lemari 1 Buah Pasang Kaca tebal 3 mm 1 Buah Pasang Kaca tebal 5 mm

Page 8 of 209

DAFTAR ISI ANALISA BIAYA KONSTRUKSI DENGAN MENGGUNAKAN INDEX STANDAR NASIONAL INDONESIA 1 Buah Pasang Kaca tebal 8 mm 1 Buah Pasang Kaca Buram tebal 12 mm 1 Buah Pasang Kaca Cermin tebal 5 mm 1 Buah Pasang Kaca Cermin tebal 6 mm 1 Buah Pasang Kaca Cermin tebal 8 mm 1 Buah Pasang Kaca Wireglass tebal 5 mm 1 Buah Pasang Kaca Patri tebal 5 mm

PT. T.38-2000-C PEKERJAAN PENGECATAN 1 m² Mengikis / Mengerok Permukaan Cat Tembok Lama 1 m² Mencuci Bidang Permukaan Tembok yang Pernah dicat 1 m² Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual 1 m² Menyabun Permukaan Tembok Lama 1 m² Mengerok Karat atau Cat Lama Permukaan Baja dgn Pancar Pasir ( Sanblasting ) dgn Tingkat Kebersihan Sa 2½. 1 m² Mendempul dan Menggosok Kayu 1 m² Mengecatan Bidang Kayu Lama 1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup 1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup 1 m² Pelaburan Bidang Kayu dengan Teak Oil 1 m² Pelaburan Bidang Kayu dengan Pelitur 1 m² Pelaburan Bidang Kayu dengan Cat Residu dan Ter 1 m² Pelaburan Bidang Kayu dengan Vernis 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 1 m² Melabur Tembok dengan Kapur Sirih 1 m² Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan ) 1 m² Pemasangan Wall Paper 1 m² Pengecatan Permukaan Baja dengan Meni Besi 1 m² Pengecatan Permukaan Baja dengan Meni Besi dan Perancah 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 4 Lapis Cat Konvensional, tebal 200 um

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 1 Lapis Cat Mutakhir, tebal 200 um 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 3 Lapis Cat Konvensional, tebal 200 um 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot ( Airless Spray ) dgn Sistem 1 Lapis Cat Mutakhir, tebal 200 um

Page 9 of 209

DAFTAR HARGA SATUAN UPAH KERJA NO

Uraian

Satuan

Harga Satuan Rp )

(

1 Pekerja

OH

Rp

25,000

2 Tukang Gali

Oh

Rp

30,000

3 Tukang Cat

Oh

Rp

25,000

4 Tukang

OH

Rp

30,000

5 Tukang batu

OH

Rp

39,500

6 Tukang batu/pipa

OH

Rp

39,500

7 Tukang besi

OH

Rp

39,500

8 Tukang besi konstruksi

OH

Rp

39,500

9 Tukang kayu

OH

Rp

39,500

10 Kepala tukang

OH

Rp

42,500

11 Tukang las

OH

Rp

42,500

12 Mandor

OH

Rp

50,000

Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

DAFTAR HARGA SATUAN MATRIAL NO

Uraian 1 Air

Harga Satuan

Satuan

Rp

liter Lembar

Rp

1,000

2 Akustik Ukuran 60 cm x 120 cm

Rp

1,000

3 akustik ukuran (30 x 30) cm

Lembar

4 akustik ukuran (30 x 60) cm

1,000 1,000

Lembar

Rp Rp

5 Alang - alang

ikat

Rp

1,000

6 Alluminium B

Kg Kg

Rp Rp

1,000 1,000

m’ Lbr lbr

Rp

1,000

9 Ampelas 10 Asbes Gelombang

Rp Rp

1,000 1,000

11 Asbes semen

m2

12 Atap Alluminium Gelombang tebal 0.55

1,000 1,000

7 Alluminium C 8 Alluminium strip

m2

Rp Rp

13 Badkip

bh

Rp

1,000

14 Bahan teraso cor

m3

15 Baja strip (0,2 x 2) cm

kg

Rp Rp

1,000 1,000

16 Bak Teraso

bh

Rp

1,000

17 Bak cuci Stainless steel 18 Bak cuci Teraso

bh bh

Rp Rp

1,000 1,000

19 Bak Fiberglass

bh

Rp

1,000

20 Balok kayu

m

3

Rp

1,000

21 Balok Kayu Borneo

Kg

Rp

1,000

22 Balok kayu kelas II

m m3

Rp

1,000

23 Balok kayu, ukuran (6 x 12) cm 24 Bambu Ø 6 - 8 / 600 cm

btg

Rp Rp

1,000 1,000

Rp Rp

1,000 1,000

3

25 Bata berongga ekspose

Buah

26 Bata merah

buah

Page 10 of 209

DAFTAR HARGA SATUAN MATRIAL NO

Uraian

Harga Satuan

Satuan

Rp Rp Rp

1,000 1,000

m3

Rp Rp

1,000 1,000

31 Batu Belah 5 / 20

m3

Rp

1,000

32 Batu Belah 5 / 7

m3

33 Batu granit

kg

Rp Rp

1,000 1,000

34 Batu Kerikil

m3

Rp

1,000

35 Batu Koral

m3

Rp

1,000

36 Batu paras

m2

Rp

1,000

37 Batu tempel hitam

m

38 Batu teraso

kg

Rp Rp

1,000 1,000

39 BBM

Ltr

Rp

1,000

41 Besi angkur ö=8 mm

kg

Rp Rp

1,000 1,000

42 Besi baja IWF

kg

Rp

1,000

43 Besi beton

kg

44 Besi beton (polos/ulir)

kg

Rp Rp

1,000 1,000

45 Besi beton polos

kg

46 Besi lis kaca (1 x 1) cm 47 Besi plat baja

m kg

48 Besi profil

kg

Rp Rp Rp Rp

1,000 1,000 1,000 1,000

49 Besi scuare tube

m

Rp

1,000

kg kg

Rp Rp

1,000 1,000

kg

Rp

1,000

53 Bilik bambu

m

2

Rp

1,000

54 Cat Tembok

Kg

Rp

1,000

55 Cat Antara 56 Cat Dasar

Kg Kg

Rp Rp

1,000 1,000

57 Cat Kayu glotek

Kg

Rp

1,000

58 Cat Meni 59 Cat Penutup

Kg Kg

Rp Rp

1,000 1,000

60 Dempul

Kg

Rp

1,000

Kg Batang

Rp Rp

1,000 1,000

Batang Batang

Rp Rp

1,000 1,000

65 Dolken Kayu Ø 8 - 10/400 cm

btg

Rp

1,000

66 Door Closer 67 Door Holder

Bh Bh

Rp Rp

1,000 1,000

68 Door Stop

Bh

Rp

1,000

69 Engsel Angin

Bh Bh

Rp Rp

1,000 1,000

71 Engsel Pintu

Bh

72 Floor hardener

kg

Rp Rp

1,000 1,000

bh

Rp

1,000

Lembar

Buah

Rp Rp

1,000 1,000

lbr

Rp

1,000

lbr

Rp

1,000

27 Bata pelapis dinding

Buah

28 Batu Apung

Kg

29 Batu belah

m3

30 Batu belah 15 cm/20 cm

2

40 bekisting/spacer

  siku L 30.30.3 50 Besi

Mandor 51 Besi OHstrip Besi strip tebal 5 mm 52 0,075

61 Dempul Jadi 62 Dolken kayu galam (kaso), ö(8-10) cm, panjang 4 m 63 Dolken kayu galam, 64 Dolken kayu galam, ö(8-10) cm, panjang 4 m

70 Engsel Jendela

73 Floor Drain 74 Formika 75 Formite/penjaga jarak bekisting/spacer 76 Genteng Aspal 77 Genteng Beton

Page 11 of 209

DAFTAR HARGA SATUAN MATRIAL NO

Uraian

Harga Satuan

Satuan

78 Genteng Bubung Kodok

Rp

bh bh

Rp Rp

1,000 1,000

81 Genteng Kodok

lbr bh

Rp Rp

1,000 1,000

82 Genteng Metal

lbr

Rp

1,000

83 Genteng Palentong 84 Genteng Palentong Super

bh bh

Rp Rp

1,000 1,000

85 Genteng Sirap

lbr

Rp

1,000

86 Gymfloor

m

Rp Rp

1,000 1,000

79 Genteng Bubung Palentong 80 Genteng Decra Bond

2

87 Gypsum board

Lembar

88 Hollow Block 10

Buah

89 Hollow Block 15

Buah

Rp Rp

1,000 1,000

90 Hollow Block 20

Buah

Rp

1,000

kg

Buah

Rp Rp

1,000 1,000

93 Jaring kawat baja dilas

kg

Rp

1,000

94 Jendela nako (rangka + kaca 5 mm)

m2

95 Kaca Buram

m2

Rp Rp

1,000 1,000

96 Kaca Cermin

m2

Rp

1,000

97 Kaca Patri

m2 m2

Rp Rp

1,000 1,000

m2 Bh

Rp Rp

1,000 1,000

101 Kapur Sirih

Kg

Rp

1,000

102 Karpet

m2

103 Kaso 5 / 7 ( albasiah )

m3

Rp Rp

1,000 1,000

104 Kaso-kaso (5 x 7) cm

m3

Rp

1,000

105 Kawat beton

kg

106 Kawat diameter 4 mm

kg

Rp Rp

1,000 1,000

107 Kawat Duri

Kg

108 kawat las

kg

Rp Rp

1,000 1,000

109 Kawat las listrik

kg

Rp

1,000

110 Kawat nyamuk

m

1,000 1,000

91 Ijuk 92 Internal cove

98 Kaca Polos 99 Kaca Wireglass 100 Kait Angin

111 Kayu Balok Borneo

m3

Rp Rp

112 Kayu Kaso 5 / 7 (borneo)

m3

Rp

1,000

113 Kayu kelas II

m

3

Rp

1,000

114 Kayu kelas II balok

m3

Rp

1,000

115 Kayu kelas III

m

3

Rp

1,000

116 Kayu kelas III (papan)

m

3

Rp

1,000

117 Kayu papan

m3

Rp

1,000

118 Kayu Papan 3 / 20 borneo

m3

Rp

1,000

m3

119 Kayu Terentang

2

120 Keramik

Buah

Rp Rp

1,000 1,000

121 Keramik artistik

Buah

Rp

1,000

123 Kloset Jongkok Porselen

bh bh

Rp Rp

1,000 1,000

124 Kloset Jongkok Teraso

bh

Rp

1,000

125 Kapur padam

3

m

Rp

1,000

126 Koral Beton 127 koral beton kg

m3 kg

Rp

1,000

Rp

1

122 Kloset Duduk / Monoblok

Page 12 of 209

DAFTAR HARGA SATUAN MATRIAL NO

Uraian

Harga Satuan

Satuan

Rp

128 Kran Air

bh

Rp

1,000

129 Kuas 130 Kunci Lemari 131 Kunci Selot

Bh

Rp

1,000

Bh Bh

Rp

1,000

Rp

1,000

132 Kunci Tanam 133 kunci Silinder 134 kunci Tanam Antik

bh

Rp

1,000

Bh Bh

Rp

1,000

Rp

1,000

135 kunci Tanam Biasa

Bh

Rp

1,000

Bh kg kg kg m3 m’ Buah

Rp Rp Rp Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000

136 137 138 139

kunci Tanam Kamar Mandi

Lem Lem kayu Lem vinyl 140 List kayu 2/4 141 List kayu profil 142 Marmer 143 Meni ( Read Lead ) A

Kg

144 Meni ( Read Lead ) B

Kg Lt Liter Kg Liter Buah lbr

Rp

1,000

Rp

1,000

Rp

1,000

Rp Rp Rp

1,000 1,000 1,000

Rp

1,000

m2

Rp

1,000

lbr kg kg kg kg kg kg kg kg kg kg kg kg kg Kg

Rp

1,000

Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000

Kg Kg

Rp

1,000

168 Paku Biasa 2" - 5"

Rp

1,000

169 Paku Hak Pnjang 15 cm

Kg

Rp

1,000

Kg kg Buah kg bh kg kg m3 m3 m3 m3 m2

Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000

Rp Rp Rp

1,000 1,000 1,000

Rp

1,000

Rp

1,000

Rp

1,000

Rp

1,000

m3 kg

Rp Rp

1,000 1

145 Meni Besi 146 Minyak bekisting 147 Minyak Cat 148 Minyak pelumas 149 Mosaik 150 Nok Paten 151 Nok standar 40 cm 18, swg 22 152 153 154 155 156 157 158 159 160 161 162 163 164 165

Nok Stel rata Paku Paku 1 cm - 2,5 cm Paku 1 cm dan 2,5 cm Paku 10 cm Paku 12 cm Paku 3 cm Paku 5 cm – 10 cm Paku 5 cm – 12 cm Paku 5 cm - 7 cm Paku 5 cm dan 10 cm Paku 5 cm dan 7 cm Paku 5 cm-12cm Paku 7 cm – 10 cm

166 Paku Biasa ½" - 1" 167 Paku Biasa 1/2" - 1"

170 171 172 173

Paku Pancing 60 x 230 Paku skrup Paku skrup 1 cm – 2,5 cm Paku skrup 10 cm

174 Paku Skrup 3.5" 175 Paku skrup 5 cm 176 Paku tripleks 177 Papan kayu 178 Papan Kayu Borneo tebal 3cm 179 Papan kayu kelas II 180 Papan kayu kelas II atau III 181 Parquet 182 Pasir beton 183 Pasir beton ( kg )

Page 13 of 209

DAFTAR HARGA SATUAN MATRIAL NO

Uraian

Harga Satuan

Satuan

Rp

183 Pasir Pasang

m3

Rp

1,000

184 Pasir Silika

Kg

185 Pasir urug

m3

186 Pelitur

Ltr

Rp Rp Rp

1,000 1,000 1,000

187 Pelitur Jadi 188 Pengelasan

Ltr cm

Rp Rp

1,000 1,000

189 Pengencer

Ltr

Rp

1,000

190 Perancah Kayu

m3

Rp

1,000

191 Perekat

Rp Rp Rp

1,000 1,000 1,000

Rp

1,000

195 Pipa Beton

Kg m m2 m2 bh

Rp

1,000

196 Pipa Galvanis

m'

Rp

1,000

197 Pipa Galvanis D 4"

m' m'

Rp

1,000

198 Pipa PVC D 1/2"

Rp

1,000

199 Pipa PVC tipe AW Ø ¾"

m'

Rp

1,000

200 Pipa PVC tipe AW Ø 1"

m' m'

Rp

1,000

201 Pipa PVC tipe AW Ø 1½"

Rp

1,000

202 Pipa PVC tipe AW Ø 2"

m'

Rp

1,000

203 Pipa PVC tipe AW Ø 2½"

m' m'

Rp

1,000

Rp

1,000

Rp

1,000

206 Pipa Tanah

m' bh

Rp

1,000

207 Plamir

Kg

Rp

1,000

Rp Rp Rp Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000

Rp

1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000

192 Pintu alluminium 193 Pintu gulung besi 194 Pintu lipat

204 Pipa PVC tipe AW Ø 3" 205 Pipa PVC tipe AW Ø 4"

208 209 210 211 212 213 214 215

Plastic Aerator

216 217 218 219 220 221 222

Plywood 4 mm

223 224 225 226 227 228

Porselen ( 11 x 11 ) cm

Bh Buah Buah Buah Buah Buah Buah Buah lbr Lembar Lembar Lembar Lembar Lbr Buah bh

Portland Cement Profil alluminium Profil Alluminium "T" Profil kaca Ramset

kg m m’ m Buah

Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp

229 Rel Pintu Dorong

Bh

Rp

1,000

230 Reng (2 x 3) cm

m3

Rp

1,000

231 Reng (3 x 4) cm

m3

Rp

1,000

232 Residu

Lt

Rp

1,000

233 Residu atau Ter

Ltr

Rp

1,000

234 Rolling door alluminium

m2

Rp

1,000

235 Roof Light Fiberglass

Rp

1,000

236 Sabun

lbr Kg

Rp

1,000

237 Seal tape

bh

Rp

1,000

Plint keramik artistik Plint Ubin Plint ubin granit Plint ubin PC warna Plint ubin teralux kerang Plint ubin teralux marmer Plint ubin teraso Plywood 9 mm Plywood tebal 4 mm Plywood tebal 4 mm Ukuran (90 x 220) cm Plywood tebal 4 mm, ukuran 120 cm x 240 cm Plywood tebal 9 mm Porselen

Page 14 of 209

DAFTAR HARGA SATUAN MATRIAL NO

Uraian

Harga Satuan

Satuan Tube

238 Sealant 239 Semen abu -abu

Kg Kg

240 Semen Nat

Rp Rp Rp

1,000 1,000

Rp

1,000

Kg kg Kg

Rp

1,000

Rp Rp

1,000 1,000

Lbr lbr

Rp

1,000

Rp

1,000

lbr m’ Lbr Jam

Rp

1,000

Rp Rp

1,000 1,000

m3

Rp Rp

1,000 1,000

251 Sisalation / Alluminium Foil 252 Skrup fixer 253 Semen Merah

m2 Buah m3

Rp Rp Rp

1,000 1,000 1,000

254 Soda Api 255 Solar

Kg Liter

Rp Rp

1,000 1,000

Bh kg m2 Kg Ltr Lembar Lembar Buah

Rp

1,000

Rp

1,000

Rp

1,000

Rp

1,000

m2

Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000

275 Urinoir

bh

Rp

1,000

276 Venetions blinds dan vertical blinds (tirai)

m2

Rp

1,000

Ltr Buah Buah m

Rp Rp Rp Rp Rp

1,000 1,000 1,000 1,000 1,000

Rp

1,000

Rp

1,000

Rp

1,000

241 Semen Portland 242 Semen warna 243 Semen Warna 244 Seng Gelombang 3" x 6" BJLS 28 245 Seng gelombang 3"-5" 246 Seng Gelombang BJLS 32 247 Seng plat 248 Seng Plat 3" x 6" BJLS 28 249 Sewa alat perakitan baja 250 Sirtu

256 Spring Knip 257 Strorox – 100 258 Sunscreen alluminium 259 Tali Ijuk 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274

277 278 279 280

Teak Oil Teakwood tebal 4 mm ukuran (90 x 220) cm Teakwood tebal 4 mm, Ukuran 120 cm x 240 cm Terawang (roster) Tanah Liat Tripleks Ubin abu-abu Ubin granit Ubin keramik Ubin keramik artistik Ubin teralux kerang Ubin teralux marmer Ubin teraso Ubin warna Underlayer irubber corrugated

m3 Lembar Buah Buah Buah Buah Buah Buah Buah Buah

Vernis Vinyl Vinyl karet Wall paper

281 Water Drain + Asesories 282 Waterstop 283 Waterstop lebar 150 mm

set m’ m’

284 Waterstop lebar 200 mm

m

Page 15 of 209



Rekapitulasi volume -

Page 16 of 209

Rekapitulasi volume -

Page 17 of 209

Rekapitulasi volume -

Page 18 of 209

Rekapitulasi volume -

Page 19 of 209

Rekapitulasi volume -

Page 20 of 209

Rekapitulasi volume -

Page 21 of 209

SNI DT 91 -0006-2007 Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata ii Pendahuluan iii 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan tanah 3 6.1 Menggali 1 m3 tanah biasa sedalam 1 meter 3 6.2 Menggali 1 m 3 tanah biasa sedalam 2 meter 3 6.3 Menggali 1 m 3 tanah biasa sedalam 3 meter 3 6.4 Menggali 1 m3 tanah keras sedalam 1 meter 3 6.5 Menggali 1 m 3 tanah cadas sedalam 1 meter 3 6.6 Menggali 1 m3 tanah lumpur sedalam 1 meter 3 6.7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter 4 6.8 Membuang 1 m3 tanah sejauh 30 meter 4 6.9 Mengurug kembali 1 m3 galian 4 6.10 Memadatkan 1 m3 tanah (per 20 cm) 4 6.11 Mengurug 1 m3 pasir urug 4 6.12 Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL 4 6.13 Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL 5 6.14 Memasang 1 m2 lapisan ijuk tebal 10 cm 5 6.15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan 5 Lampiran A 6 Bibliografi 7

Page 22 of 209

Prakata Standar Nasional Indonesia (SN I) tentang Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SNI 03-2835-2002 Tata cara perhitungan harga satuan pekerjaan tanah, yang disesuaikan dengan keadaan di Indonesia dengan melakukan modifikasi terhadap indeks harga satuan. Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan. SNI disusun melalui proses/prosedur perumusan standar dan telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s/d 8 Desember 2006 di Bandung yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Analisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan tanah untuk konstruksi bangunan gedung dan perumahan 1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan tanah yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan tanah untuk bangunan gedung dan perumahan. Jenis pekerjaan tanah yang ditetapkan meliputi: a)Pekerjaan galian tanah biasa dan tanah keras dalam berbagai kedalaman; b)Pekerjaan stripping atau pembuangan humus;

Page 23 of 209

c)Pekerjaan pembuangan tanah; d)Pekerjaan urugan kembali, urugan pasir, pemadatan tanah, perbaikan tanah sulit dan urugan sirtu. 2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi. 3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar penghitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi

Page 24 of 209

3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, I luas, volume dan unit s t 4 Singkatan istilah i l a Si ngkatan Kepanjangan h / a Satuan cm centimeter r panjang Satuan t kg kilogram berat i meter persegi Satuan luas m2 Satuan meter kubik m3 Satuan volume Agregat OH Orang Hari tenaga kerja halus per hari Pasir yang PP Pasir pasang ukuran ≤ 5 digunakan PU Pasir urug mm Kapur untuk tohor KP Kapur padam yang uruganyang Tanah Bahan dipadamkan TL Tanah liat lekat, galian yang lempung Sirtu Pasir batu terdiri dari pasir dan batu 5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan.

5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari. 6 Penetapan indeks harga satuan pekerjaan tanah 6.1 Menggali 1 m3 tanah biasa sedalam 1 meter

Rp

- #N/A

Page 25 of 209

Satuan OH OH

Indeks

6.2 Menggali 1 m3 tanah biasa sedalam 2 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.3 Menggali 1 m3 tanah biasa sedalam 3 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.4 Menggali 1 m3 tanah keras sedalam 1 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.5 Menggali 1 m3 tanah cadas sedalam 1 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.6 Menggali 1 m3 tanah lumpur sedalam 1 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

6.8 Membuang 1 m3 tanah sejauh 30 meter Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

Tenaga kerja

Kebutuhan Pekerja Mandor

6.9 Mengurug kembali 1 m3 galian

Harga Satuan Bahan

Jml Harga Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

1.050 0.067

1.000 0.032

1.500 0.060

1.200 0.045

0.050 0.005

-

Jml Harga upah #N/A #N/A

Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A

Harga Satuan Bahan 0.900 0.045

0.330 0.010

Harga Satuan upah

#N/A Rp #N/A Rp

0.750 0.025

Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A Mengurug kembali 1 m3 galian dihitung dari 1/3 kali upah pekerjaan galian

Page 26 of 209

Mengurug kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian 6.10 Memadatkan 1 m3 tanah (per 20 cm) Kebutuhan Pekerja Tenaga kerja Mandor

Satuan OH OH

Indeks

Satuan m3 OH OH

Indeks

Harga Satuan upah

Harga Satuan Bahan

Harga Satuan upah

0.500 0.050

6.11 Mengurug 1 m3 pasir urug Bahan Tenaga kerja

Kebutuhan Pasir urug Pekerja Mandor

1.200 0.300 0.010

Rp - #N/A Jml Harga Bahan Jml Harga upah #N/A Rp #N/A #N/A Rp #N/A

Harga Satuan Bahan

#N/A

#N/A #N/A Jml Harga Bahan Jml Harga upah #N/A #N/A #N/A #N/A #N/A

6.12 Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL Kebutuhan Bahan

Tenaga kerja

Kapur padam Pasir Pasang Tanah Liat Pekerja Tukang batu Kepala tukang Mandor

#N/A Satuan

Indeks

Harga Satuan Bahan

0.135 0.400 0.948 0.800 0.400 0.040 0.080

m3 m3 m3 OH OH OH OH

Harga Satuan upah

Bahan

Tenaga kerja

Kapur padam Tanah Liat Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

Indeks

Harga Satuan Bahan

0.248 1.240 0.800 0.400 0.040 0.080

m3 m3 OH OH OH OH

6.14 Memasang 1 m2 lapisan ijuk tebal 10 cm Kebutuhan Bahan Ijuk Pekerja Tenaga kerja Mandor

Satuan kg OH OH

Indeks

6.15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan Kebutuhan Bahan Sirtu

Satuan m3

Indeks

#N/A

#N/A

#N/A

Jml Harga Bahan

Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

1.200

Harga Satuan upah

#N/A #N/A

Harga Satuan Bahan

6.000 0.150 0.015

Jml Harga upah

#N/A #N/A #N/A

6.13 Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL Kebutuhan

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A Jml Harga Bahan Jml Harga upah #N/A #N/A #N/A #N/A #N/A

Harga Satuan upah

Harga Satuan upah

#N/A #N/A Jml Harga Bahan Jml Harga upah #N/A

Page 27 of 209

Pekerja Mandor

Tenaga kerja

#N/A #N/A

0.250 0.025

OH OH

#N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Menggali 1 m3 tanah biasa sedalam 1 meter

Kebutuhan

Tenaga kerja

Satuan

Harga Satuan Bahan / Upah (Rp.)

Indeks

Jumlah (Rp.)

Pekerja

OH

0.750

Rp

30,000

Rp

22,500

Mandor

OH

0.025

Rp

60,000

Rp

1,500

Jumlah harga per-satuan pekerjaan Rp

24

Bi bliog rafi SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (Bahan bangunan bukan logam) Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991

SNI DT 91 -0007-2006

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan pondasi untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Page 28 of 209

Daftar isi Daftar isi i Prakata ii Pendahuluan iii 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan pondasi 3 6.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP 3 6.2 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP 3 6.3 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP 3 6.4 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP 4 6.5 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 8 PP 4 6.6 Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP 4 6.7 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP 5 6.8 Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP 5 6.9 Memasang 1 m3 batu kosong (aanstamping) 5 6.10 Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR 6 6.11 Memasang 1 m3 pondasi sumuran, diameter 100 cm 6 Lampiran A 7 Bibliografi 8

Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan pondasi untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SNI 03-28362002, Tata cara perhitungan harga satuan pekerjaan pondasi batu belah untuk ban gunan sederhana, dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja. Standar ini disusun oleh Panitia Teknik Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan. SNI disusun melalui proses/prosedur perumusan standar dan telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s/d 8 Desember 2006 di Bandung yang melibatkan para nara sumber, pakar dan lembaga terkait.

Page 29 of 209

Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Analisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan pondasi untuk konstruksi bangunan gedung dan perumahan 1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan pondasi yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan pondasi untuk bangunan gedung dan perumahan. Jenis pekerjaan pondasi yang ditetapkan meliputi : a)Pekerjaan pembuatan pondasi batu belah dalam berbagai komposisi campuran; b)Pemasangan anstamping / batu kosong; c)Pembuatan pondasi sumuran dan pondasi siklop. 2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi. 3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat

Page 30 of 209

3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali / koefisien sebagai dasar penghitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan I satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, s luas, volume dan unit t i 4 Singkatan istilah l a Si ngkatan Kepanjangan h Satuan / cm centimeter panjang Satuan a kg kilogram berat r Satuan m’ meter panjang tpanjang meter persegi Satuan luas m2 i Satuan m3 meter kubik Satuan volume OH Orang Hari tenaga kerja Semen per hari PC Portland Cement Portland Page 31 of 209

PU PP KR KP SM PB

Pasir urug Pasir pasang Kerikil Kapur padam Semen merah Pasir beton

5 Persyaratan

Pasir yang digunakan Agregat untuk Agregat halus urugan ≤ 5 kasar ukuran ukuran 5 mm tohor Kapur mm – 40 yang Semen hasil mm dipadamkan Agregat tumbukan halus bata merah ukuran ≤ 5 mm

5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan.

5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari. 6 Penetapan indeks harga satuan pekerjaan pondasi 6.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP Kebutuhan Bahan

Tenaga kerja

Batu belah 15 cm/20 cm Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A Satuan m3 kg m3 OH OH OH OH

Indeks

1.200 202.000 0.485 1.500 0.750 0.075 0.075

Harga Satuan Bahan

Harga Satuan upah

Bahan

Batu belah 15 cm/20 cm Portland Cement

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m kg

3

Indeks

1.200 163.000

Jml Harga upah

#N/A #N/A #N/A

6.2 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP Kebutuhan

#N/A

Harga Satuan Bahan

#N/A #N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

Jml Harga upah

#N/A #N/A

Page 32 of 209

Bahan

Tenaga kerja

Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

m3 OH OH OH OH

0.520 1.500 0.750 0.075 0.075

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.3 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP Kebutuhan Bahan

Tenaga kerja

Batu belah 15 cm/20 cm Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A Satuan m3 kg m3 OH OH OH OH

Indeks

1.200 136.000 0.544 1.500 0.750 0.075 0.075

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Batu belah 15 cm/20 cm Portland Cement Pasir Pasang Bahan Pekerja Tukang batu Kepala tukang   Tenaga kerja Mandor Mandor OH 3 6.5 Memasang 1 m pondasi batu belah,0,075 campuran 1 PC : 8 PP

Bahan

Tenaga kerja

Kebutuhan Batu belah 15 cm/20 cm Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A

Satuan

Indeks

m3 kg m3 OH OH OH OH

1.200 117.000 0.561 1.500 0.750 0.075 0.075

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

m3 OH OH OH OH

Indeks 1.200 91.000

#N/A #N/A #N/A #N/A

0.584 1.500 0.750 0.075 0.075

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3 kg

Jml Harga upah

#N/A #N/A #N/A

6.4 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP Kebutuhan

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 33 of 209

6.6 Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP Kebutuhan Batu belah 15 cm/20 cm Kapur padam Semen Merah Bahan

Tenaga kerja

Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan m3 m3 m3 m3 OH OH OH OH

Indeks 1.200 0.170 0.170 0.340 1.500 0.750 0.075 0.075

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Batu belah 15 cm/20 cm Portland Cement Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Indeks

m kg

1.200 61.000

m3 m3 OH OH OH OH

0.147 0.492 1.500 0.750 0.075 0.075

3

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Batu belah 15 cm/20 cm Portland Cement Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A #N/A #N/A #N/A

Bahan

Batu belah 15 cm/20 cm Pasir urug

#N/A #N/A #N/A #N/A #N/A

Satuan

Indeks

m3 kg m3

1.200 41.000 0.131

m3 OH OH OH OH

0.523 1.500 0.750 0.075 0.075

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

m3 m3

Indeks 1.200 0.432

#N/A #N/A

Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A

#N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

Jml Harga upah

#N/A

6.9 Memasang 1 m3 batu kosong (aanstamping) Kebutuhan

Jml Harga Bahan

#N/A

#N/A #N/A

6.8 Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP Kebutuhan

#N/A #N/A #N/A #N/A #N/A

Satuan

Jml Harga upah

#N/A

6.7 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP Kebutuhan

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 34 of 209

Tenaga kerja

Pekerja Tukang batu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

0.780 0.390 0.039 0.039

6.10 Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah Kebutuhan Batu belah 15 cm/20 cm Portland Cement Pasir beton Koral Beton Besi beton Kawat beton

Satuan m3 kg m3 m3 kg kg

Indeks 0.480 194.000 0.312 0.468 126.000 1.800

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Pekerja Tukang batu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

3.400 0.850 0.085 0.170

6.11 Memasang 1 m3 pondasi sumuran, diameter 100 cm

Bahan

Tenaga kerja

Kebutuhan Batu belah 15 cm/20 cm Portland Cement Pasir beton Koral Beton Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg m m3 OH OH OH OH 3

Indeks 0.450 194.000 0.312 0.468 2.400 0.800 0.080 0.119

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP

Kebutuhan Batu belah Portland Cement

Satuan m3 kg

I ndeks 1.200 202.000

Harga Satuan Bahan/U pah (Rp.) Rp 40,000 Rp 400

Jumlah (Rp.) Rp Rp

48,000 80,800

Bahan Page 35 of 209

Bahan

Tenaga kerja

Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

m3 OH OH OH OH

0.485 Rp 45,000 1.500 Rp 30,000 0.750 Rp 40,000 0.075 Rp 50,000 0.075 Rp 60,000 Jumlah harga per satuan pekerjaan

Rp Rp Rp Rp Rp

21 .825 45,000 30,000 3,750 4,500 233,875

Bi bliog rafi Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991. SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) SNI 03-6861.2-2002, Spesifikasi bahan bangunan bagian B (Bahan bangunan dari besi / baja)

SNI DT 91 -0008-2007

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan beton untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1

Page 36 of 209

4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan beton 3 6.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 3 6.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 3 6.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, 3 6.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 4 6.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, 4 6.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, 4 6.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, 4 6.8 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 5 6.9 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, 5 6.10 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, 5 6.11 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, 5 6.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, 6 6.13 Membuat 1 m3 beton kedap air dengan strorox – 100 6 6.14 Memasang 1 m’ PVC Waterstop lebar 150 mm 6 6.15 Memasang 1 m’ PVC Waterstop lebar 200 mm 6 6.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm 7 6.17 Pembesian 10 kg dengan besi polos atau besi ulir 7 6.18 Memasang 10 kg kabel presstressed polos/strands 7 6.19 Memasang 10 kg jaring kawat baja/wire mesh 7 6.20 Memasang 1 m2 bekisting untuk pondasi 7 6.21 Memasang 1 m2 bekisting untuk sloof 8 6.22 Memasang 1 m2 bekisting untuk kolom 8 6.23 Memasang 1 m2 bekisting untuk balok 8 6.24 Memasang 1 m2 bekisting untuk lantai 9 6.25 Memasang 1 m2 bekisting untuk dinding 9 6.26 Memasang 1 m2 bekisting untuk tangga 9 6.27 Memasang 1 m2 jembatan untuk pengecoran beton 10 6.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 10 6.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting) 10 6.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 11 6.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 12 6.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) 12 6.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) 13 6.35 Membuat 1 m ’ kolom praktis beton bertulang (11 x 11) cm 13 6.36 Membuat 1 m ’ ring balok beton bertulang (10 x 15) cm 14

Prakata Standar Nasional Indonesia (SN I) tentang Tata cara perhitungan harga satuan pekerjaan beton untuk konstruksi bangunan dan perumahan merupakan revisi dari SNI Tata cara perhitungan

Page 37 of 209

harga satuan pekerjaan beton dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja. Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur, dan Konstruksi Bangunan. SNI disusun melalui proses/prosedur perumusan standar dan telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 Desember 2006 di Bandung yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Analisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan beton untuk konstruksi bangunan gedung dan perumahan 1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan beton yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan beton untuk bangunan gedung dan perumahan. Jenis pekerjaan beton yang ditetapkan meliputi : a)Pekerjaan pembuatan beton f’c = 7,4 MPa (K 100) sampai dengan f’c = 31,2 MPa (K 350) untuk pekerjaan beton bertulang; b)Pekerjaan pemasangan water stop dan bekisting berbagai komponen struktur bangunan; c)Pekerjaan pembuatan pondasi, sloof, kolom, balok, dinding beton bertulang, kolom praktis dan ring balok.

Page 38 of 209

2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisa BOW 1921 dan penelitian analisa biaya konstruksi. 3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar penghitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan 3.6 indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi

Page 39 of 209

3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, volume dan unit 3.10 semen portland tipe I semen Portland yang umum digunakan tanpa persyaratan khusus 4 Singkatan istilah Singkatan Kepanjangan Istilah cm centimeter Satuan panjang kg kilogram Satuan berat m’ meter panjang Satuan panjang m2 meter persegi Satuan luas m3 meter kubik Satuan volume OH Orang Hari Satuan tenaga kerja per hari PC Portland Cement Semen Portland PB Pasir beton Agregat halus ukuran < 5 mm KR Kerikil Agregat kasar ukuran 5 mm – 40 mm 5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan pada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan;

c) Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari. 6 Penetapan indeks harga satuan pekerjaan beton

Page 40 of 209

6.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 2) cm, w/c = 0,87

#N/A

±

Kebutuhan Portland Cement

Satuan kg kg kg Liter OH OH OH OH

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 247.000 869.000 999.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 276.000 828.000 1,012.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 299.000 799.000 1,017.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 2) cm, w/c = 0,72 Kebutuhan Portland Cement

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 2) cm, w/c = 0,78 Kebutuhan Portland Cement

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

CATATAN Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %

6.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87

#N/A

#N/A

Page 41 of 209

Kebutuhan Portland Cement

Satuan kg kg kg Liter OH OH OH OH

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 230.000 893.000 1,027.000 200.000 1.200 0.200 0.020 0.060

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 326.000 760.000 1,029.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 352.000 731.000 1,031.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Air

Indeks 371.000 698.000 1,047.000 215.000

Harga Satuan Bahan

#N/A #N/A #N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 2) cm, w/c = 0,58 Kebutuhan Portland Cement

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 2) cm, w/c = 0,61 Kebutuhan Portland Cement

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66 Kebutuhan Portland Cement

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

Page 42 of 209

Tenaga kerja

Pekerja Tukang batu Kepala tukang Mandor

OH OH OH OH

1.650 0.275 0.028 0.083

#N/A #N/A #N/A #N/A

6.8 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 2) cm, w/c = 0,56

#N/A

±

Kebutuhan Portland Cement

Satuan kg kg kg Liter OH OH OH OH

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 384.000 692.000 1,039.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 406.000 684.000 1,026.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 413.000 681.000 1,021.000 215.000 1.650 0.275 0.028 0.083

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg m3 m3 Liter OH OH OH OH

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.10 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 2) cm, w/c = 0,52 Kebutuhan Portland Cement Pasir beton Koral Beton Air Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.9 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 2) cm, w/c = 0,53 Kebutuhan Portland Cement

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 43 of 209

6.11 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 2) cm, w/c = 0,49

#N/A

±

Kebutuhan Portland Cement

Satuan kg kg kg Liter OH OH OH OH

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 439.000 670.000 1,006.000 215.000 2.100 0.350 0.035 0.105

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Pasir beton ( kg ) koral beton kg

Bahan

Tenaga kerja

Air Pekerja Tukang batu Kepala tukang Mandor

Indeks 448.000 667.000 1,000.000 215.000 2.100 0.350 0.035 0.105

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg m3 m3 kg OH OH OH OH

Indeks 400.000 0.480 0.800 1.200 2.100 0.350 0.035 0.105

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

Indeks

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.14 Memasang 1 m’ PVC Waterstop lebar 150 mm Kebutuhan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.13 Membuat 1 m3 beton kedap air dengan strorox – 100 Kebutuhan Portland Cement Pasir beton Koral Beton Strorox – 100 Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

#N/A

±

Satuan kg kg kg Liter OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 2) cm, w/c = 0,48 Kebutuhan Portland Cement

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 44 of 209

Bahan

Tenaga kerja

Waterstop lebar 150 mm Pekerja Tukang batu/pipa Kepala tukang Mandor

m’ OH OH OH OH

1.050 0.060 0.030 0.003 0.003

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A

6.15 Memasang 1 m’ PVC Waterstop lebar 200 mm Bahan

Tenaga kerja

Kebutuhan Waterstop lebar 200 mm Pekerja Tukang batu/pipa Kepala tukang Mandor

Satuan m’ OH OH OH OH

Indeks 1.050 0.070 0.035 0.004 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

m’ OH OH OH OH

Indeks 1.050

Harga Satuan Bahan

Harga Satuan upah

#N/A

0.080 0.040 0.004 0.004

Bahan

Tenaga kerja

Indeks 10.500 0.150 0.070 0.070 0.007 0.004

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 10.500 0.100 0.050 0.050

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan kg kg OH OH

#N/A

#N/A

6.18 Memasang 10 kg kabel presstressed polos/strands Kebutuhan Besi beton (polos/ulir) Kawat beton Pekerja Tukang besi

Jml Harga Bahan

#N/A

Satuan kg kg OH OH OH OH

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan

#N/A

#N/A

6.17 Pembesian 10 kg dengan besi polos atau besi ulir Kebutuhan Besi beton (polos/ulir) Kawat beton Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

6.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm Kebutuhan Waterstop lebar 230 mm - 320 mm Pekerja Tukang batu/pipa Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga kerja Page 45 of 209

Tenaga kerja

Kepala tukang Mandor

OH OH

0.005 0.003

#N/A #N/A

6.19 Memasang 10 kg jaring kawat baja/wire mesh

Bahan

Tenaga kerja

Kebutuhan Jaring kawat baja dilas Kawat beton Pekerja Tukang besi Kepala tukang Mandor

#N/A

Satuan kg kg OH OH OH OH

Indeks 10.200 0.050 0.025 0.025 0.025 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m3 kg Liter OH OH OH OH

Indeks 0.040 0.300 0.100 0.520 0.260 0.026 0.026

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 0.045 0.300 0.100 0.520 0.260 0.026 0.026

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 0.040 0.400 0.200 0.015

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg Liter m3

#N/A

#N/A #N/A #N/A

6.22 Memasang 1 m2 bekisting untuk kolom Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Balok kayu kelas II

Jml Harga Bahan

#N/A

Satuan m3 kg Liter OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.21 Memasang 1 m2 bekisting untuk sloof Kebutuhan Kayu kelas III Paku 5 cm – 10 cm Minyak bekisting Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.20 Memasang 1 m2 bekisting untuk pondasi Kebutuhan Kayu kelas III Paku 5 cm – 10 cm Minyak bekisting Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

Page 46 of 209

Bahan

Tenaga kerja

φ

Plywood tebal 9 mm Dolken kayu galam, (8–10) cm, panjang 4 m Pekerja Tukang kayu Kepala tukang Mandor

Lbr Batang

0.350 2.000

OH OH OH OH

0.660 0.330 0.033 0.033

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

6.23 Memasang 1 m2 bekisting untuk balok

Bahan

Tenaga kerja

#N/A

Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Balok kayu kelas II Plywood tebal 9 mm Dolken kayu galam, φ (8-10) cm, panjang 4 m Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg Liter m3 Lbr

Indeks 0.040 0.400 0.200 0.018 0.350

Batang OH OH OH OH

2.000 0.660 0.330 0.033 0.033

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Balok kayu kelas II Plywood tebal 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg Liter m3 Lbr

Indeks 0.040 0.400 0.200 0.015 0.350

Batang OH OH OH OH

6.000 0.660 0.330 0.033 0.033

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

Indeks 0.030

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A

Jml Harga upah

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3

#N/A

#N/A #N/A #N/A #N/A #N/A

6.25 Memasang 1 m2 bekisting untuk dinding Kebutuhan Kayu kelas III

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

ö

Tenaga kerja

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A

6.24 Memasang 1 m2 bekisting untuk lantai

Bahan

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Page 47 of 209

Paku 5 cm – 12 cm Minyak bekisting Balok kayu kelas II Plywood tebal 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Formite/penjaga jarak bekisting/spacer Pekerja Tukang kayu Kepala tukang Mandor

kg Liter m3 Lbr

0.400 0.200 0.020 0.350

#N/A #N/A #N/A #N/A

Batang

3.000

#N/A

Buah OH OH OH OH

4.000 0.660 0.330 0.033 0.033

#N/A

#N/A #N/A #N/A #N/A #N/A

ö

Bahan

Tenaga kerja

#N/A

#N/A #N/A #N/A #N/A

6.26 Memasang 1 m2 bekisting untuk tangga

#N/A

Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Balok kayu kelas II Plywood tebal 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg Liter m3 Lbr

Indeks 0.030 0.400 0.150 0.015 0.350

Batang OH OH OH OH

2.000 0.660 0.330 0.033 0.033

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m3 kg

Indeks 0.026 0.600

Batang OH OH OH OH

0.500 0.150 0.050 0.005 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

6.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

ö

Tenaga kerja

#N/A #N/A #N/A #N/A #N/A

Kebutuhan Kayu kelas III (papan) Paku 5 cm – 12 cm Dolken kayu galam (kaso), (8-10) cm, panjang 4 m Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah

#N/A

#N/A

6.27 Memasang 1 m2 jembatan untuk pengecoran beton

Bahan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A

ö

Bahan

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 48 of 209

Bahan

Tenaga kerja

Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

Satuan m3 kg Liter kg kg kg m3 m3 OH OH OH OH OH OH

Indeks 0.200 1.500 0.400 157.500 2.250 336.000 0.540 0.810 5.300 0.275 1.300 1.050 0.262 0.265

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 0.270 2.000 0.600 210.000 3.000 336.000 3.500 0.540 0.810 5.650 0.275 1.560 1.400 0.323 0.283

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A

Indeks 0.400 4.000 2.000

Harga Satuan Bahan

#N/A #N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3 kg Liter

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

6.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting) Kebutuhan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3 kg Liter kg kg kg Lembar m3 m3 OH OH OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

6.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting) Kebutuhan Kayu kelas III Paku 5 cm-12cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Plywood 9 mm Pasir beton Koral Beton Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

Page 49 of 209

Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Kayu kelas II balok Plywood 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

kg kg kg m3 m3 m3 Lembar

315.000 4.500 336.000 0.540 0.810 0.150 3.500

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Batang OH OH OH OH OH OH

20.000 7.050 0.275 1.650 2.100 0.403 0.353

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

ö

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A #N/A #N/A

6.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Kayu kelas II balok Plywood 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

#N/A

Satuan m3 kg Liter kg kg kg m3 m3 m3 Lembar

Indeks 0.320 3.200 1.600 210.000 3.000 336.000 0.540 0.810 0.140 2.800

Batang OH OH OH OH OH OH

16.000 6.350 0.275 1.650 1.400 0.333 0.318

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Tenaga kerja

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3

Indeks 0.320

Harga Satuan Bahan

#N/A

Jml Harga upah

#N/A

#N/A

6.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) Kebutuhan Kayu kelas III

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

ö

Bahan

#N/A #N/A #N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Page 50 of 209

Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Kayu kelas II balok Plywood 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

kg Liter kg kg kg m3 m3 m3 Lembar

3.200 1.600 157.500 2.250 336.000 0.540 0.810 0.120 2.800

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Batang OH OH OH OH OH OH

32.000 5.300 0.275 1.300 1.050 0.265 0.265

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

ö

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A #N/A #N/A

6.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Kayu kelas II balok Plywood 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

#N/A

Satuan m3 kg Liter kg kg kg m3 m3 m3 Lembar

Indeks 0.240 3.200 1.600 157.500 2.250 336.000 0.540 0.810 0.160 2.800

Batang OH OH OH OH OH OH

24.000 5.300 0.275 1.300 1.050 0.262 0.265

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Tenaga kerja

6.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

ö

Bahan

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A

Page 51 of 209

Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Kayu kelas II balok Plywood 9 mm Dolken kayu galam, (8-10) cm, panjang 4 m Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

Satuan m3 kg Liter kg kg kg m3 m3 m3 Lembar

Indeks 0.250 3.000 1.200 210.000 3.000 336.000 0.540 0.810 0.105 2.500

Batang OH OH OH OH OH OH

14.000 5.650 0.275 1.560 1.400 0.323 0.283

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Tenaga kerja

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan m3 kg Liter kg kg kg m3 m3 OH OH OH OH OH OH

Indeks 0.002 0.010 3.000 0.450 4.000 0.006 0.009 0.180 0.020 0.020 0.020 0.006 0.009

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A

Indeks

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

6.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm Kebutuhan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

6.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm Kebutuhan Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

ö

Bahan

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 52 of 209

Bahan

Tenaga kerja

Kayu kelas III Paku 5 cm – 12 cm Minyak bekisting Besi beton polos Kawat beton Portland Cement Pasir beton Koral Beton Pekerja Tukang batu Tukang kayu Tukang besi Kepala tukang Mandor

m3 kg Liter kg kg kg m3 m3 OH OH OH OH OH OH

0.003 0.020

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

3.600 0.050 5.500 0.009 0.015 0.297 0.033 0.033 0.033 0.010 0.015

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A

Lampiran A (Informatif) Contoh penggunaan standar untuk menghitung satuan pekerjaan A.1 Membuat 1 m3 beton f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87

Kebutuhan

Bahan

Tenaga kerja

Portland Cement Pasir beton ( kg ) koral beton kg Air Pekerja Tukang batu Kepala tukang Mandor

Satuan kg kg kg liter OH OH OH OH

Harga Satuan Bahan/Upah (Rp.)

Indeks

247,000.000 869.000 999.000 215.000 1,650.000 0.275 0.028 0.083

Rp Rp Rp Rp Rp Rp Rp Rp

400 63 57 5 30 40 50 60

Jumlah (Rp.) Rp Rp Rp Rp Rp Rp Rp Rp

99 55 57 1 50 11 1 5

Jumlah harga per satuan pekerjaan Rp

278

Bibliografi SNI 03-2834-2000, Tata cara pembuatan rencana campuran beton normal

Page 53 of 209

SNI 03-3976-1995, Tata cara pengadukan pengecoran beton SNI 03-2847-1992, Tata cara penghitungan struktur beton untuk bangunan gedung SNI 03-2445-1991, Spesifikasi ukuran kayu untuk bangunan rumah dan gedung SNI 03-2495-1991, Spesifikasi bahan tambahan untuk beton SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (Bahan bangunan bukan logam) SNI 03-6861.2-2002, Spesifikasi bahan bangunan bagian B (Bahan bangunan dari bes i/baja) SNI 03-6861.3-2002, Spesifikasi bahan bangunan bagian C (Bahan bangunan dari logam bukan besi) Pusat Penelitian dan Pengembangan Permukiman, Analisa Biaya Konstruksi (hasil penelitian), tahun 1988–1991.

SNI DT 91 -0009-2007

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan dinding untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata iii Pendahuluan iv

Page 54 of 209

1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 3 6 Penetapan indeks harga satuan pekerjaan dinding 3 6.1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP 3 6.2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP 3 6.3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 4 PP 4 6.4 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 5 PP 4 6.5 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 6 PP 4 6.6 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 KP : 10 PP 4 6.7 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP 5 6.8 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP 5 6.9 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP 5 6.10 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP 5 6.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 6 PP 6 6.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 1 PC : 8 PP 6 6.13 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 KP : 10 PP 6 6.14 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 1 PP 6

Page 55 of 209

6.15 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 2 PP 7 6.16 Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP 7 6.17 Memasang 1 m2 dinding HB 20, campuran spesi 1 PC : 4 PP 7 6.18 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP 7 6.19 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP 8 6.20 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP 8 6.21 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP 8 6.22 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP 8 6.23 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP 9 6.24 Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1 PC : 3 PP 9 Lampiran A 10 Bibliografi 11

Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan dinding untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SNI 03-6897-2002 Tata cara perhitungan harga satuan pekerjaan dinding, yang disesuaikan dengan keadaan di Indonesia dengan melakukan modifikasi terhadap indeks harga satuan. Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan. Standar ini telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s.d. 8 Desember 2006 oleh Subpanitia Teknis yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer

Page 56 of 209

sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan dinding untuk konstruksi bangunan gedung dan perumahan 1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan dinding yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan dinding untuk bangunan gedung dan perumahan. Jenis pekerjaan dinding yang ditetapkan meliputi : a)Pekerjaan dinding bata merah dengan berbagai ketebalan dan spesi; b)Pekerjaan dinding hollow block dengan berbagai dimensi dan spesi; c)Pekerjaan pemasangan terawang (roster) atau bata berongga. 2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar perhitungan biaya bahan dan upah kerja

Page 57 of 209

3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, volume dan unit I s t 4 Singkatan istilah i l a Si ngkatan Kepanjangan h Satuan / cm centimeter panjang Satuan a kg Kilogram berat rSatuan m’ meter panjang tpanjang m2 meter persegi Satuan luas i Satuan m3 meter kubik Satuan volume OH Orang Hari tenaga kerja Semen Agregat per hari PC Portland Cement Portland halus PP Pasir pasang Kapur ukurantohor ≤ 5 KP Kapur padam yang mm dipadamkan Semen hasil SM Semen merah tumbukan bata merah

Page 58 of 209

HB

Hollow block

Bata berlubang di bagian tengahnya dari bahan tras kapur atau semen pasir

5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

6.1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP

Bahan

Tenaga kerja

Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 OH OH OH OH

Indeks 140.000 43.500 0.080 0.600 0.200 0.020 0.030

#N/A Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 59 of 209

6.2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP

Bahan

Tenaga kerja

Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 OH OH OH OH

Indeks 140.000 32.950 0.091 0.600 0.200 0.020 0.030

#N/A Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 140.000 26.550 0.093 0.600 0.200 0.020 0.030

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 140.000 22.200 0.102 0.600 0.200 0.020 0.030

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Satuan Buah kg m3 OH OH

Indeks 140.000 18.500 0.122 0.600 0.200

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.5 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 6 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.4 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 5 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A

6.3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 4 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga kerja Page 60 of 209

Tenaga kerja

Kepala tukang Mandor

OH OH

#N/A #N/A

0.020 0.030

6.6 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 KP : 10 PP

Bahan

Tenaga kerja

Kebutuhan Bata merah Portland Cement Pasir Pasang Kapur padam Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 m3 OH OH OH OH

Indeks 140.000 10.080 0.093 0.028 0.600 0.200 0.020 0.030

#N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 18.950 0.038 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 14.370 0.040 0.300 0.100 0.010 0.015

Harga Satuan upah

#N/A #N/A #N/A

Satuan Buah kg

Indeks 70.000 11.500

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A

#N/A #N/A #N/A

6.9 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP Kebutuhan Bata merah Portland Cement

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.8 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.7 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Bahan Page 61 of 209

Bahan

Tenaga kerja

Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

m3 OH OH OH OH

#N/A

0.043 0.300 0.100 0.010 0.015

#N/A

#N/A #N/A #N/A #N/A

6.10 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP

Bahan

Tenaga kerja

Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 9.680 0.045 0.300 0.100 0.010 0.015

#N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 8.320 0.049 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 6.500 0.050 0.300 0.100 0.010 0.015

Harga Satuan upah

#N/A #N/A #N/A

Satuan

Indeks

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A

#N/A #N/A #N/A

6.13 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 KP : 10 PP Kebutuhan

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 1 PC : 8 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 6 PP Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 62 of 209

Bahan

Tenaga kerja

Bata merah Portland Cement Pasir Pasang Kapur padam Pekerja Tukang batu Kepala tukang Mandor

Buah kg m3 m3 OH OH OH OH

#N/A #N/A #N/A #N/A

70.000 4.500 0.050 0.015 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.14 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 1 PP

Bahan

Tenaga kerja

Kebutuhan Bata merah Semen Merah Pasir Pasang Kapur padam Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah m3 m3 m3 OH OH OH OH

Indeks 70.000 0.018 0.018 0.018 0.300 0.100 0.010 0.015

#N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah m3 m3 m3 OH OH OH OH

Indeks 70.000 0.014 0.028 0.014 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

ö

Jml Harga Bahan

Indeks 12.500 30.320 0.728 0.280 0.300 0.150

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.16 Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP Kebutuhan Hollow Block 20 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.15 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM : 2 PP Kebutuhan Bata merah Semen Merah Pasir Pasang Kapur padam Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga kerja Page 63 of 209

Tenaga kerja

Kepala tukang Mandor

OH OH

#N/A #N/A

0.015 0.015

6.17 Memasang 1 m2 dinding HB 20, cam puran spesi 1 PC : 4 PP

Bahan

Tenaga kerja

Kebutuhan Hollow Block 20 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu Kepala tukang Mandor ö

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 12.500 24.260 0.772 0.280 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

ö

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 12.500 22.740 0.550 0.280 0.360 0.120 0.012 0.018

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

ö

Indeks 12.500 18.200 0.582 0.280 0.360 0.120 0.012 0.018

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A #N/A #N/A #N/A

6.20 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP Kebutuhan

Jml Harga Bahan

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.19 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP Kebutuhan Hollow Block 15 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.18 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP Kebutuhan Hollow Block 15 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 64 of 209

Bahan

Tenaga kerja

Hollow Block 10 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu Kepala tukang Mandor ö

Buah kg m3 kg OH OH OH OH

12.500 15.160 0.364 0.280 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.21 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP

Bahan

Tenaga kerja

Kebutuhan Hollow Block 10 Portland Cement Pasir Pasang Besi angkur =8 mm Pekerja Tukang batu Kepala tukang Mandor ö

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 12.500 12.130 0.388 0.280 0.300 0.100 0.010 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 30.000 14.000 0.032 0.300 0.100 0.010 0.015

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan Buah kg m3 OH OH OH OH

Indeks 30.000 11.000 0.035 0.300 0.100 0.010 0.015

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.23 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP Kebutuhan Terawang (roster) Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.22 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP Kebutuhan Terawang (roster) Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 65 of 209

6.24 Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1 PC : 3 PP

Bahan

Tenaga kerja

Kebutuhan Bata berongga ekspose Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 OH OH OH OH

Indeks 70.000 14.000 0.032 0.300 0.150 0.015 0.015

#N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 campuran spesi 1 PC : 2 PP

Bahan

Tenaga kerja

Memasang 1 m3 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata,

Kebutuhan Bata merah Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan buah kg m3 OH OH OH OH

Harga Satuan Bahan/Upah Indeks (Rp.) 140.000 Rp 300 43.500 Rp 700 0.080 Rp 45,000 0.600 Rp 30,000 0.200 Rp 40,000 0.020 Rp 50,000 0.030 Rp 60,000 Jumlah harga per satuan pekerjaan

Jumlah (Rp.) Rp Rp Rp Rp Rp Rp Rp Rp

28,000 17,400 3,600 18,000 8,000 1,000 1,800 77,800

Bi bliog rafi SNI 03-6862-2002, Spesifikasi peralatan pemasangan dinding bata dan plesteran SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) SNI 03-6861.2-2002, Spesifikasi bahan bangunan bagian B (bahan bangunan dari besi/baja) SNI 03-6861.3-2002, Spesifikasi bahan bangunan bagian C (bahan bangunan dari logam bukan besi) Pt-T-03-2000-C, Tata cara pengerjaan pasangan dan plesteran dinding Pusat Penelitian dan Pengembangan Permukiman, Analisa Biaya Konstruksi (hasil penelitian), tahun 1988–1991

Page 66 of 209

SNI DT 91 -0010-2007

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata iii Pendahuluan iv 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan plesteran 3 6.1 Memasang 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm 3 6.2 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm 3 6.3 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm 3 6.4 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm 4 6.5 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm 4 6.6 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm 4

Page 67 of 209

6.7 Memasang 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm 4 6.8 Memasang 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm 5 6.9 Memasang 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm 5 6.10 Memasang 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm 5 6.11 memasang 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm 5 6.12 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm 6 6.13 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm 6 6.14 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm 6 6.15 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm 6 6.16 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm 7 6.17 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm 7 6.18 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm 7 6.19 Memasang 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm 7 6.20 Memasang 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mm 8 6.21 Memasang 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm 8 6.22 Memasang 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm 8 6.23 Memasang 1 m2 Plesteran Ciprat 1 PC : 2 PP 8 6.24 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’) 9 6.25 Memasang 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’) 9 6.26 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP 9 6.27 Memasang 1 m2 acian 9 Lampiran A 10 Bibliografi 11

Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan dan perumahan adalah revisi dari SNI 03-2837-2002, Analisis Biaya Konstruksi (ABK) Ban gunan gedung dan Perumahan Pekerjaan Plesteran, dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja. Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknik Bahan, Sains, Struktur, dan Konstruksi Bangunan. Standar ini telah dibahas pada forum rapat konsensus pada tanggal 7 s.d. 8 Desember 2006 di Pusat Penelitian dan Pengembangan Permukiman Bandung dengan melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan

Page 68 of 209

Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan plesteran untuk konstruksi bangunan gedung dan perumahan

1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan plesteran yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan plesteran untuk bangunan gedung dan perumahan. Jenis pekerjaan plesteran yang ditetapkan meliputi pekerjaan plesteran dalam berbagai ketebalan dan campuran, berapen dan penyelesaian akhir.

2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisis pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan

Page 69 of 209

3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar perhitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan

indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, I volume dan unit s 4 Singkatan istilah Si ngkatan

Kepanjangan

mm kg m’ m2 m3 OH PC PP

milimeter kilogram meter panjang meter persegi meter kubik Orang Hari Portland Cement Pasir pasang

t i l a h Satuan / panjang Satuan a berat r Satuan t panjang Satuan luas i Satuan Satuan volume tenaga kerja Semen per hari Agregat portland halus ukuran ≤ 5 mm Page 70 of 209

KP SM

Kapur padam Semen merah

Kapur tohor yang Semen hasil dipadamkan tumbukan bata merah

5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan.

5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

6 Penetapan indeks harga satuan pekerjaan plesteran 6.1 Memasang 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan kg m3 OH OH OH OH

Indeks 15.504 0.016 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A #N/A

Satuan kg m3 OH

Indeks 10.224 0.020 0.300

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A

6.2 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm Kebutuhan Portland Cement Pasir Pasang Pekerja

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A

#N/A

Page 71 of 209

Tenaga kerja

Tukang batu Kepala tukang Mandor

OH OH OH

#N/A #N/A #N/A

0.150 0.015 0.015

6.3 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan kg m3 OH OH OH OH

Indeks 7.776 0.023 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH OH

Indeks 6.240 0.024 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 5.184 0.026 0.300 0.150 0.015 0.015

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 4.416 0.027 0.300 0.150 0.015

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH

#N/A

#N/A #N/A

6.6 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang

Jml Harga Bahan

#N/A

Satuan kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.5 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.4 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga kerja Page 72 of 209

Tenaga kerja

Mandor

OH

#N/A

0.015

6.7 Memasang 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan kg m3 OH OH OH OH

Indeks 3.936 0.028 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH OH

Indeks 3.456 0.029 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 5.760 0.003 0.013 0.360 0.120 0.012 0.018

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 3.000 0.005 0.020 0.360 0.120 0.012

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan kg m3 m3 OH OH OH

#N/A

#N/A #N/A

6.10 Memasang 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm Kebutuhan Portland Cement Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang

Jml Harga Bahan

#N/A

Satuan kg m3 m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.9 Memasang 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm Kebutuhan Portland Cement Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.8 Memasang 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga kerja Page 73 of 209

Tenaga kerja

Mandor

OH

#N/A

0.018

6.11 memasang 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm

Bahan

Tenaga kerja

Kebutuhan Semen Merah Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan m3 m3 m3 OH OH OH OH

Indeks 0.009 0.009 0.009 0.360 0.120 0.012 0.018

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m3 m3 m3 OH OH OH OH

Indeks 0.007 0.007 0.015 0.360 0.120 0.012 0.018

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 13.632 0.027 0.400 0.200 0.020 0.022

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 10.368 0.031 0.260 0.200 0.020

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH

#N/A

#N/A #N/A #N/A

6.14 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang

Jml Harga Bahan

#N/A

Satuan kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.13 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.12 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm Kebutuhan Semen Merah Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga kerja Page 74 of 209

Tenaga kerja

Mandor

OH

#N/A

0.013

6.15 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan kg m3 OH OH OH OH

Indeks 8.320 0.032 0.400 0.200 0.020 0.022

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH OH

Indeks 6.912 0.035 0.400 0.200 0.020 0.022

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 5.888 0.036 0.400 0.200 0.020 0.022

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga kerja

Indeks 0.009 0.009 0.018 0.440 0.220 0.022 0.022

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3 m3 m3 OH OH OH OH

#N/A

#N/A #N/A

6.18 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm Kebutuhan Semen Merah Kapur padam Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.17 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.16 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 75 of 209

6.19 Memasang 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan kg m3 OH OH OH OH

Indeks 5.184 0.026 0.150 0.075 0.008 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 0.500 0.013 0.080 0.400 0.040 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg kg OH OH OH OH

Indeks 10.000 15.000 0.450 0.225 0.023 0.023

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

6.23 Memasang 1 m2 Plesteran Ciprat 1 PC : 2 PP

Jml Harga Bahan

Indeks 10.000 15.000 0.450 0.225 0.023 0.023

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan kg kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.22 Memasang 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm Kebutuhan Portland Cement Batu teraso Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.21 Memasang 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm Kebutuhan Portland Cement Batu granit Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A

6.20 Memasang 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mm Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 76 of 209

Bahan

Tenaga kerja

Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan kg m3 OH OH OH OH

Indeks 4.320 0.006 0.300 0.100 0.010 0.015

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 3.108 0.150 0.075 0.008 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Satuan kg OH OH OH OH

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 6.340 0.012 0.300 0.150 0.015 0.015

Harga Satuan Bahan

Tenaga kerja

Satuan kg OH OH

Indeks 3.250 0.200 0.100

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Kebutuhan Portland Cement Pekerja Tukang batu

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.27 Memasang 1 m2 acian

Bahan

Jml Harga Bahan

#N/A

Satuan kg m3 OH OH OH OH

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Indeks 1.600 0.070 0.035 0.004 0.004

#N/A

#N/A

6.26 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP Kebutuhan Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

6.25 Memasang 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’) Kebutuhan Portland Cement Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan kg OH OH OH OH

Jml Harga upah

#N/A #N/A

6.24 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’) Kebutuhan Portland Cement Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A

#N/A #N/A

Page 77 of 209

Tenaga kerja

Kepala tukang Mandor

OH OH

#N/A #N/A

0.010 0.010

#N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Memasang 1 m2 acian

Bahan

Tenaga kerja

Kebutuhan Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan kg OH OH OH OH

Harga Satuan Bahan/Upah Indeks (Rp.) 3.250 Rp 400 0.200 Rp 30,000 0.100 Rp 40,000 0.010 Rp 50,000 0.010 Rp 60,000 Jumlah harga per satuan pekerjaan

Jumlah (Rp.) Rp Rp Rp Rp Rp Rp

1,300 6,000 4,000 500 450 12,250

Bi bliog rafi SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) SNI 03-6862-2002, Spesifikasi peralatan pemasangan dinding bata dan plesteran SNI 03-2410-1991, Tata cara pengecatan dinding tembok dengan cat emulsi Pt-T-03-2000-C, Tata cara pengerjaan pasangan dan plesteran dinding Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991

SNI DT 91-0011-2007

Page 78 of 209

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan kayu untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata iii Pendahuluan iv 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan kayu 3 6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I 3 6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III 3 6.3 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II 3 6.4 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III 4 6.5 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II 4 6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II 4 6.7 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II 4 6.8 Membuat 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm) 5 6.9 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II 5 6.10 Memasang 1 m2 jalusi kusen, kayu kelas I atau II 5 6.11 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I 5 6.12 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II 6 6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III 6 6.14 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I 6 6.15 Memasang 1 m3 konstruksi gordeng, kayu kelas II 6 6.16 Memasang 1 m2 rangka atap genteng keramik, kayu kelas II 7 6.17 Memasang 1 m2 rangka atap genteng beton, kayu kelas II 7 6.18 Memasang 1 m2 rangka atap sirap, kayu kelas II 7

Page 79 of 209

6.19 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III 7 6.20 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 8 6.21 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 8 6.22 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II 8 6.23 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III 8 6.24 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II 9 6.25 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II 9 6.26 Memasang 1 m2 dinding lambriziring dari papan kayu kelas I 9 6.27 Memasang 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm 9 6.28 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV 10 Lampiran A 11 Bibliografi 12

Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan kayu untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SNI 03-3434-2002, Tata cara perhitungan harga satuan pekerjaan kayu untuk bangunan gedung, yang disesuaikan dengan keadaan di Indonesia dengan melakukan modifikasi terhadap indeks harga satuan.

Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan. Standar ini telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s.d. 8 Desember 2006 oleh Subpanitia Teknis yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk

Page 80 of 209

komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan kayu untuk bangunan gedung dan perumahan

1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan kayu yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan kayu untuk bangunan gedung dan perumahan. Jenis pekerjaan kayu yang ditetapkan meliputi : a)Pekerjaan pembuatan atau pemasangan kusen pintu atau jendela jenis kayu kelas I, II atau III; b)Pekerjaan pembuatan pintu panel, pintu klamp, pintu kayu lapis (plywood, teakwood), pintu atau jendela jalusi, pintu atau jendela kaca dan pintu teakwood; c)Pekerjaan pembuatan kuda-kuda atap dan rangka atap jenis kayu kelas I, II atau III; d)Pekerjaan pembuatan rangka langit-langit jenis kayu kelas II atau III; e)Pekerjaan pembuatan rangka dinding dan pemasangan dinding pemisah jenis kayu kelas I, II atau III; f)Pekerjaan pemasangan listplank jenis kayu kelas I dan kayu kelas II.

2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan

Page 81 of 209

harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar penghitungan biaya bahan dan upah kerja indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan 3.6 indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, I volume dan unit s 4 Singkatan istilah Si ngkatan

Kepanjangan

cm kg m’ m2 m3 OH

centimeter kilogram meter panjang meter persegi meter kubik Orang Hari

t i l a h Satuan / panjang Satuan a berat r Satuan t panjang Satuan luas i Satuan Satuan volume tenaga kerja per hari

5 Persyaratan 5.1 Persyaratan umum

Page 82 of 209

Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

6 Penetapan indeks harga satuan pekerjaan kayu 6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I

Bahan

Tenaga kerja

Kebutuhan Balok kayu Paku 10 cm Lem kayu Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg kg OH OH OH OH

#N/A

Indeks 1.100 1.250 1.000 7.000 21.000 2.100 0.350

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan m3 kg kg OH OH OH OH

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Indeks

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A #N/A #N/A

6.3 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II Kebutuhan

#N/A #N/A #N/A #N/A #N/A

Indeks 1.200 1.250 1.000 6.000 18.000 1.800 0.300

Jml Harga upah

#N/A #N/A #N/A

6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III Kebutuhan Balok kayu Paku 10 cm Lem kayu Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 83 of 209

Bahan

Tenaga kerja

Papan kayu Paku 5 cm - 7 cm Pekerja Tukang kayu Kepala tukang Mandor

m3 kg OH OH OH OH

0.040 0.050 0.350 1.050 0.105 0.018

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

6.4 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III

Bahan

Tenaga kerj a

Kebutuhan Papan kayu Paku 5 cm - 7 cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m3 kg OH OH OH OH

Indeks 0.040 0.050 0.350 1.050 0.105 0.018

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m3 kg OH OH OH OH

Indeks 0.040 0.500 1.000 3.000 0.300 0.050

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan m3 kg OH OH OH OH

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Satuan m3 kg

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Indeks 0.064 0.500

#N/A

#N/A #N/A

6.7 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II Kebutuhan Papan kayu Lem kayu

Jml Harga Bahan

#N/A

Indeks 0.024 0.300 0.800 2.400 0.240 0.040

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II Kebutuhan Papan kayu Lem kayu Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.5 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II Kebutuhan Papan kayu Lem kayu Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 84 of 209

Tenaga kerja

Pekerja Tukang kayu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

1.000 3.000 0.300 0.050

6.8 Membuat 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm)

Bahan

Tenaga kerja

Kebutuhan Papan kayu Paku 1 cm - 2,5 cm Lem kayu Plywood tebal 4 mm Ukuran (90 x 220) cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg kg

Indeks 0.025 0.030 0.500

Lembar OH OH OH OH

1.000 0.700 2.100 0.210 0.035

#N/A

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga kerja

#N/A #N/A #N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A

Satuan m3 kg kg

Indeks 0.026 0.030 0.500

Lembar OH OH OH OH

1.000 0.800 2.400 0.240 0.040

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga kerja

6.11 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I

Jml Harga Bahan

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A

Indeks 0.060 0.150 0.670 2.000 0.200 0.335

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Jml Harga upah

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg OH OH OH OH

#N/A

#N/A #N/A #N/A #N/A #N/A

6.10 Memasang 1 m2 jalusi kusen, kayu kelas I atau II Kebutuhan Papan kayu Paku 1 cm - 2,5 cm Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A

6.9 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II Kebutuhan Papan kayu Paku 1 cm - 2,5 cm Lem kayu Plywood tebal 4 mm Ukuran (90 x 220) cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 85 of 209

Bahan

Tenaga kerja

Kebutuhan Papan kayu Paku 1 cm - 2,5 cm Lem kayu Teakwood tebal 4 mm ukuran (90 x 220) cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg kg

Indeks 0.025 0.030 0.300

Lembar OH OH OH OH

1.000 0.800 2.400 0.240 0.040

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.12 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II

Bahan

Tenaga kerja

Kebutuhan Papan kayu Paku 1 cm - 2,5 cm Lem kayu Teakwood tebal 4 mm ukuran (90 x 220) cm Formika Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg kg

Indeks 0.025 0.030 0.800

Lembar Lembar OH OH OH OH

1.000 0.500 0.850 2.550 0.255 0.043

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga kerja

Satuan m3 kg kg OH OH OH OH

Indeks 1.100 15.000 5.600 4.000 12.000 1.200 0.200

#N/A #N/A #N/A

#N/A #N/A

#N/A

Bahan

Indeks 1.200 15.000 5.600

#N/A Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg kg

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.14 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I Kebutuhan Balok kayu Besi strip tebal 5 mm Paku 12 cm

Jml Harga Bahan

#N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter Kebutuhan Balok kayu Besi strip tebal 5 mm Paku 12 cm Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

Page 86 of 209

Tenaga kerja

Pekerja Tukang kayu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

6.700 20.100 2.010 0.335

6.15 Memasang 1 m3 konstruksi gordeng, kayu kelas II

Bahan

Tenaga kerja

Kebutuhan Balok kayu Besi strip tebal 5 mm Paku 12 cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m3 kg kg OH OH OH OH

Indeks 1.100 15.000 3.000 2.400 7.200 0.720 0.120

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m3 m3 kg OH OH OH OH

Indeks 0.014 0.036 0.250 0.100 0.100 0.010 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 0.014 0.057 0.250 0.100 0.100 0.010 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks 0.165

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3

#N/A

#N/A #N/A #N/A

6.18 Memasang 1 m2 rangka atap sirap, kayu kelas II Kebutuhan Kayu kelas II

Jml Harga Bahan

#N/A

Satuan m3 m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.17 Memasang 1 m2 rangka atap genteng beton, kayu kelas II Kebutuhan Kaso-kaso (5 x 7) cm Reng (3 x 4) cm Paku 5 cm dan 10 cm Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.16 Memasang 1 m2 rangka atap genteng keramik, kayu kelas II Kebutuhan Kaso-kaso (5 x 7) cm Reng (2 x 3) cm Paku 5 cm dan 10 cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Bahan Page 87 of 209

Bahan

Tenaga kerja

Paku 5 cm dan 10 cm Pekerja Tukang kayu Kepala tukang Mandor

kg OH OH OH OH

0.200 0.120 0.120 0.012 0.006

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.19 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III

Bahan

Tenaga kerja

Kebutuhan Kaso-kaso (5 x 7) cm Paku 7 cm – 10 cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg OH OH OH OH

#N/A

Indeks 0.015 0.200 0.150 0.300 0.030 0.075

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Satuan m3 kg OH OH OH OH

#N/A #N/A #N/A #N/A

Indeks 0.016 0.250 0.200 0.300 0.030 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 0.011 0.100 0.100 0.200 0.020 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga kerja

Indeks 0.011 0.050 0.100

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg OH

#N/A

#N/A #N/A

6.22 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II Kebutuhan Papan kayu Paku 5 cm dan 7 cm Pekerja

Jml Harga Bahan

#N/A

Satuan m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.21 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II Kebutuhan Papan kayu Paku 5 cm dan 7 cm Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.20 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III Kebutuhan Kaso-kaso (5 x 7) cm Paku 7 cm – 10 cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A

#N/A

Page 88 of 209

Tenaga kerja

Tukang kayu Kepala tukang Mandor

OH OH OH

#N/A #N/A #N/A

0.200 0.020 0.005

6.23 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III

Bahan

Tenaga kerja

Kebutuhan Balok kayu Paku 5 cm dan 7 cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan m3 kg OH OH OH OH

#N/A

Indeks 0.028 0.150 0.150 0.450 0.045 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Indeks 0.028 0.150 0.860 0.560 0.150 0.450 0.045 0.008

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga kerja

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

Indeks 0.028 0.150

Lembar kg OH OH OH OH

0.860 0.560 0.200 0.600 0.060 0.010

Harga Satuan Bahan

Indeks

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.26 Memasang 1 m2 dinding lambriziring dari papan kayu kelas I Kebutuhan

Jml Harga Bahan

#N/A

Satuan m3 kg

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.25 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II Kebutuhan Balok kayu, ukuran (6 x 12) cm Paku 5 cm dan 10 cm Plywood tebal 4 mm, ukuran 120 cm x 240 cm Lem kayu Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.24 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II Kebutuhan Satuan Balok kayu, ukuran (6 x 12) cm m3 Paku 5 cm dan 10 cm kg Teakwood tebal 4 mm, Ukuran 120 Lembar cm x 240 cm Lem kayu kg Pekerja OH Tukang kayu OH Kepala tukang OH Mandor OH

#N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 89 of 209

Bahan

Tenaga kerja

Papan kayu Paku 5 cm dan 10 cm Paku skrup 10 cm Pekerja Tukang kayu Kepala tukang Mandor

m3 kg kg OH OH OH OH

0.007 0.100 0.150 0.600 1.800 0.180 0.030

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.27 Memasang 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm

Bahan

Tenaga kerja

Kebutuhan Plywood tebal 4 mm Paku 1 cm dan 2,5 cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan Lembar kg OH OH OH OH

#N/A

Indeks 0.400 0.050 0.025 0.075 0.008 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Indeks 1.500 0.014 0.012 0.003 0.100 0.050 0.005 0.005

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m2 m3 kg m3 OH OH OH OH

#N/A

#N/A #N/A

6.28 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV Kebutuhan Bilik bambu Kaso-kaso (5 x 7) cm Paku List kayu 2/4 Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Membuat dan memasang 1 m2 daun pintu panel kayu kelas II

Bahan

Kebutuhan Papan kayu Lem kayu Pekerja Tukang kayu Kepala tukang

Satuan m3 kg OH OH OH

Indeks 0.040 0.500 1,000.000 3,000.000 0.300

Harga Satuan Bahan/Upah (Rp.) Rp 3,000,000 Rp 80,000 Rp 30,000 Rp 40,000 Rp 50,000

Jumlah (Rp.) Rp Rp Rp Rp Rp

120,000 40,000 30,000 120,000 15,500

Tenaga kerja Page 90 of 209

Tenaga kerja

Mandor

OH

0.050 Rp 60,000 Jumlah harga per satuan pekerjaan

Rp Rp

3,000 330,500

Bi bliog rafi SNI 03-2445-1991, Spesifikasi ukuran kayu untuk bangunan rumah dan gedung SNI 03-6839-2002, Spesifikasi kayu awet untuk perumahan dan gedung SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991

SNI DT 91 -0012-2007

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan penutup lantai dan dinding untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata iv Pendahuluan v

Page 91 of 209

1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan penutup lantai dan dinding 3 6.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm 3 6.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm 3 6.3 Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm 4 6.4 Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm 4 6.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm 4 6.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm 4 6.7 Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm 5 6.8 Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm 5 6.9 Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm 5 6.10 Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm 5 6.11 Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm 6 6.12 Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm 6 6.13 Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm 6 6.14 Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm 6 6.15 Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm 7 6.16 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm 7 6.17 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm 7 6.18 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm 7 6.19 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm 8 6.20 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm 8 6.21 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm 8 6.22 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm 8 6.23 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm 9 6.24 Memasang 1 m plint ubin granit ukuran (10 x 40) cm 9 6.25 Memasang 1 m plint ubin granit ukuran (10 x 30) cm 9 6.26 Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm 9 6.27 Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm 10 6.28 Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm 10 6.29 Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm 10 6.30 Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm 10 6.31 Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm 11 6.32 Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm 11 6.33 Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm 11 6.34 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm 11

Page 92 of 209

6.35 Memasang 1 m2 lantai keramik ukuran (30 x 30) cm 12 6.36 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm 12 6.37 Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border 12 6.38 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP 12 6.39 Memasang 1 m’ plint keramik ukuran (10 x 20) cm 13 6.40 Memasang 1 m’ plint keramik ukuran (10 x 10) cm 13 6.41 Memasang 1 m’ plint keramik ukuran (5 x 20) cm 13 6.42 Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm 13 6.43 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm 14 6.44 Memasang 1 m2 lantai karpet 14 6.45 Memasang 1 m2 underlayer 14 6.46 Memasang 1 m2 lantai parquet 14 6.47 Memasang 1 m2 lantai kayu (gymfloor) 15 6.48 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm 15 6.49 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm 15 6.50 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm 15 6.51 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm 16 6.52 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm 16 6.53 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm 16 6.54 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm 16 6.55 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm 17 6.56 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm 17 6.57 Memasang 1 m2 dinding batu paras 17 6.58 Memasang 1 m2 dinding batu tempel hitam 17 6.59 Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I 18 6.60 Memasang 1 m2 wall paper, lebar 50 cm 18 6.61 Memasang 1 m2 floor hardener 18 6.62 Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat 18 6.63 Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm 18 Lampiran A 19 Bibliografi 20

Prakata Standar Nasional Indonesia (SNI) tentang Tata cara perhitungan harga satuan pekerjaan penutup lantai dan dinding untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SN I Tata cara perhitungan harga satuan pekerjaan lantai untuk ban gunan rumah dan gedung, dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja..

Standar ini disusun oleh Panitia Teknik Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Gugus Kerja Struktur dan Konstruksi Bangunan pada Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan.

Page 93 of 209

Standar ini telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s.d. 8 Desember 2006 oleh Subpanitia Teknis yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan penutup lantai dan dinding untuk konstruksi bangunan gedung dan perumahan

1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan penutup lantai dan dinding yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan penutup lantai dan dinding untuk bangunan gedung dan perumahan. Jenis pekerjaan penutup lantai dan dinding yang ditetapkan meliputi: a)Pekerjaan pemasangan lantai keramik, ubin abu-abu,teraso dan marmer; b)Pekerjaan pemasangan vinyl dan karpet; c)Pekerjaan pemasangan pelapis dinding dengan bahan keramik; d)Pekerjaan pemasangan plint dari ubin/keramik dan plint dari kayu.

2 Acuan normatif

Page 94 of 209

Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar perhitungan biaya bahan dan upah kerja indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan 3.6 indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas,

Page 95 of 209

volume dan unit

4 Singkatan istilah Si ngkatan

Kepanjangan

cm kg m’ m2 m3 OH PC PP

centimeter kilogram meter panjang meter persegi meter kubik Orang Hari Portland Cement Pasir pasang

I s t i l a h Satuan / panjang Satuan a berat r Satuan t panjang Satuan luas i Satuan Satuan volume tenaga kerja Semen per hari Agregat Portland halus ukuran ≤ 5 mm

5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a) Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat;

b) Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a)Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

6 Penetapan indeks harga satuan pekerjaan penutup lantai dan dinding 6.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm Kebutuhan

#N/A

Satuan

Indeks

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 96 of 209

Bahan

Tenaga kerja

Ubin abu-abu Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Buah kg m3 OH OH OH OH

6.630 9.800 0.045 0.250 0.125 0.013 0.013

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm

Bahan

Tenaga kerja

Kebutuhan Ubin abu-abu Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 OH OH OH OH

Indeks 11.870 10.000 0.045 0.260 0.130 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 OH OH OH OH

Indeks 26.500 10.400 0.045 0.270 0.135 0.014 0.014

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Jml Harga Bahan

Indeks 6.630 9.800 0.045 1.300 0.250 0.125 0.013 0.013

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.4 Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm Kebutuhan Ubin warna Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.3 Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm Kebutuhan Ubin abu-abu Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 97 of 209

6.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm

Bahan

Tenaga kerja

Kebutuhan Ubin warna Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 11.870 10.000 0.045 1.500 0.260 0.130 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 26.500 10.400 0.045 1.620 0.270 0.135 0.014 0.014

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 6.630 9.800 0.045 1.300 0.250 0.125 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Jml Harga Bahan

Indeks 11.870 10.000 0.045 1.500

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A #N/A #N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.8 Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm Kebutuhan Ubin teraso Portland Cement Pasir Pasang Semen warna

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.7 Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm Kebutuhan Ubin teraso Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm Kebutuhan Ubin warna Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

Page 98 of 209

Tenaga kerja

Pekerja Tukang batu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

0.260 0.130 0.013 0.013

6.9 Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm

Bahan

Tenaga kerja

Kebutuhan Ubin granit Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 6.630 9.800 0.045 1.300 0.250 0.125 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 11.870 10.000 0.045 1.500 0.260 0.130 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

6.12 Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm

Jml Harga Bahan

Indeks 6.630 9.800 0.045 1.300 0.250 0.125 0.013 0.013

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.11 Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm Kebutuhan Ubin teralux kerang Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.10 Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm Kebutuhan Ubin granit Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 99 of 209

Bahan

Tenaga kerja

Kebutuhan Ubin teralux kerang Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 kg OH OH OH OH

Indeks 11.870 10.000 0.045 1.500 0.260 0.130 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 3.100 9.600 0.045 1.500 0.240 0.120 0.012 0.012

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 6.630 9.800 0.045 1.300 0.250 0.125 0.013 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Jml Harga Bahan

Indeks 11.870 10.000 0.045 1.500 0.260

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.15 Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm Kebutuhan Ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.14 Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm Kebutuhan Ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.13 Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm Kebutuhan Ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A

#N/A

Page 100 of 209

Tenaga kerja

Tukang batu Kepala tukang Mandor

OH OH OH

#N/A #N/A #N/A

0.130 0.013 0.013

6.16 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm

Bahan

Tenaga kerja

Kebutuhan Plint Ubin Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 OH OH OH OH

Indeks 5.300 1.650 0.004 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 OH OH OH OH

Indeks 3.530 1.240 0.003 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 2.650 1.240 0.003 0.090 0.090 0.009 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks 5.300 1.140 0.003

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3

#N/A

#N/A #N/A #N/A

6.19 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm Kebutuhan Plint ubin PC warna Portland Cement Pasir Pasang

Jml Harga Bahan

#N/A

Satuan Buah kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.18 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm Kebutuhan Plint Ubin Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.17 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm Kebutuhan Plint Ubin Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

Bahan Page 101 of 209

Bahan

Tenaga kerja

Semen warna Pekerja Tukang batu Kepala tukang Mandor

kg OH OH OH OH

0.100 0.090 0.090 0.009 0.005

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.20 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm

Bahan

Tenaga kerja

Kebutuhan Plint ubin PC warna Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 3.530 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 2.650 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

6.23 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm

Jml Harga Bahan

Indeks 3.530 1.140 0.003 0.100 0.090 0.090 0.009 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.22 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm Kebutuhan Plint ubin teraso Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.21 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm Kebutuhan Plint ubin PC warna Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 102 of 209

Bahan

Tenaga kerja

Kebutuhan Plint ubin teraso Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 Kg OH OH OH OH

Indeks 2.650 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 2.650 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 3.530 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Jml Harga Bahan

Indeks 2.650 1.140 0.003 0.100 0.090

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.26 Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm Kebutuhan Plint ubin teralux kerang Portland Cement Pasir Pasang Semen warna Pekerja

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.25 Memasang 1 m plint ubin granit ukuran (10 x 30) cm Kebutuhan Plint ubin granit Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.24 Memasang 1 m plint ubin granit ukuran (10 x 40) cm Kebutuhan Plint ubin granit Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A

#N/A

Page 103 of 209

Tenaga kerja

Tukang batu Kepala tukang Mandor

OH OH OH

#N/A #N/A #N/A

0.090 0.009 0.005

6.27 Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm

Bahan

Tenaga kerja

Kebutuhan Plint ubin teralux kerang Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 Kg OH OH OH OH

Indeks 3.530 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 1.700 1.140 0.003 0.100 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 2.650 1.140 0.003 0.100 0.090 0.090 0.009 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A #N/A #N/A #N/A

6.30 Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm Kebutuhan

Jml Harga Bahan

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.29 Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm Kebutuhan Plint ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.28 Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm Kebutuhan Plint ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 104 of 209

Bahan

Tenaga kerja

Plint ubin teralux marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Buah kg m3 kg OH OH OH OH

3.530 1.140 0.003 0.100 0.090 0.090 0.009 0.005

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.31 Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm

Bahan

Tenaga kerja

Kebutuhan Bahan teraso cor Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan m3 OH OH OH OH

Indeks 0.036 0.360 0.180 0.018 0.018

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 53.000 8.190 0.045 2.750 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan Buah kg m3 kg OH OH OH OH

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Indeks 106.000 8.190 0.045 3.200 0.700 0.350 0.035 0.035

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Buah kg m3 kg OH OH OH OH

#N/A

#N/A

6.33 Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm Kebutuhan Ubin keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

6.32 Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm Kebutuhan Ubin keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 105 of 209

6.34 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm

Bahan

Tenaga kerja

Kebutuhan Ubin keramik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 10.000 8.190 0.045 1.620 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 11.870 10.000 0.045 1.500 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 26.500 10.400 0.045 1.620 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Jml Harga Bahan

Indeks 33.000 9.800 0.045 4.370

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A #N/A #N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.37 Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border Kebutuhan Ubin keramik Portland Cement Pasir Pasang Semen warna

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.36 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm Kebutuhan Ubin keramik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.35 Memasang 1 m2 lantai keramik ukuran (30 x 30) cm Kebutuhan Ubin keramik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

Page 106 of 209

Tenaga kerja

Pekerja Tukang batu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

1.050 0.525 0.053 0.053

6.38 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP

Bahan

Tenaga kerja

Kebutuhan Mosaik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 kg OH OH OH OH

#N/A

Indeks 11.870 14.150 0.039 2.000 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 5.300 1.140 0.003 0.025 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

6.41 Memasang 1 m’ plint keramik ukuran (5 x 20) cm

Jml Harga Bahan

Indeks 10.600 1.140 0.003 0.050 0.090 0.090 0.009 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.40 Memasang 1 m’ plint keramik ukuran (10 x 10) cm Kebutuhan Plint keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.39 Memasang 1 m’ plint keramik ukuran (10 x 20) cm Kebutuhan Plint keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 107 of 209

Bahan

Tenaga kerja

Kebutuhan Plint keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 kg OH OH OH OH

Indeks 5.300 0.570 0.002 0.013 0.090 0.090 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 5.300 1.140 0.003 0.100 0.750 0.750 0.075 0.038

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 1.060 8.190 0.045 0.650 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Jml Harga Bahan

Indeks 1.050 0.350 0.170 0.170 0.017

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m2 kg OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.44 Memasang 1 m2 lantai karpet Kebutuhan Karpet Lem Pekerja Tukang kayu Kepala tukang

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.43 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm Kebutuhan Marmer Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

6.42 Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm Kebutuhan Internal cove Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga kerja Page 108 of 209

Tenaga kerja

Mandor

OH

#N/A

0.009

6.45 Memasang 1 m2 underlayer

Bahan

Tenaga kerja

Kebutuhan Underlayer irubber corrugated Lem Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m2 kg OH OH OH OH

Indeks 1.050 0.350 0.120 0.120 0.012 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m2 kg OH OH OH OH

Indeks 1.050 0.600 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 1.050 0.600 0.700 0.350 0.035 0.035

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 86.000 9.300 0.018 1.500 1.000 0.500 0.050

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH

#N/A

#N/A #N/A

6.48 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm Kebutuhan Porselen Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang

Jml Harga Bahan

#N/A

Satuan m2 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.47 Memasang 1 m2 lantai kayu (gym floor) Kebutuhan Gymfloor Lem Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.46 Memasang 1 m2 lantai parquet Kebutuhan Parquet Lem Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga kerja Page 109 of 209

Tenaga kerja

Mandor

OH

#N/A

0.050

6.49 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm

Bahan

Tenaga kerja

Kebutuhan Porselen Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 53.000 9.300 0.018 2.750 0.900 0.450 0.045 0.045

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 26.500 9.300 0.018 1.940 0.900 0.450 0.045 0.045

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 53.000 9.300 0.018 2.750 0.900 0.450 0.045 0.045

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 106.000

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Buah

#N/A

#N/A #N/A #N/A #N/A

6.52 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm Kebutuhan Keramik artistik

Jml Harga Bahan

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.51 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm Kebutuhan Keramik artistik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.50 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm Kebutuhan Porselen Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Page 110 of 209

Bahan

Tenaga kerja

Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

kg m3 kg OH OH OH OH

9.300 0.018 2.900 0.900 0.450 0.045 0.045

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

6.53 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm

Bahan

Tenaga kerja

Kebutuhan Keramik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 53.000 9.300 0.018 2.750 0.900 0.450 0.045 0.045

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 26.500 9.300 0.018 1.940 0.900 0.450 0.045 0.045

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Jml Harga Bahan

Indeks 1.060 3.003 12.440 0.025 0.650 1.300 0.650

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m2 Buah kg m3 kg OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.55 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm Kebutuhan Marmer Paku 12 cm Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.54 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm Kebutuhan Keramik Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga kerja Page 111 of 209

Tenaga kerja

Kepala tukang Mandor

OH OH

#N/A #N/A

0.065 0.065

6.56 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm

Bahan

Tenaga kerja

Kebutuhan Bata pelapis dinding Portland Cement Pasir Pasang Semen warna Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan Buah kg m3 kg OH OH OH OH

Indeks 63.000 12.440 0.025 2.750 1.000 0.500 0.050 0.050

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m2 kg m3 OH OH OH OH

Indeks 1.100 11.750 0.035 0.700 0.350 0.035 0.035

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 1.100 11.750 0.035 0.700 0.350 0.035 0.035

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 11.870 0.350

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Buah kg

#N/A

#N/A #N/A #N/A

6.59 Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I Kebutuhan Vinyl Lem vinyl

Jml Harga Bahan

#N/A

Satuan m2 kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.58 Memasang 1 m2 dinding batu tempel hitam Kebutuhan Batu tempel hitam Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

6.57 Memasang 1 m2 dinding batu paras Kebutuhan Batu paras Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 112 of 209

Pekerja Tukang Kepala tukang Mandor

Tenaga kerja

OH OH OH OH

#N/A #N/A #N/A #N/A

0.150 0.150 0.015 0.008

6.60 Memasang 1 m2 wall paper, lebar 50 cm

Bahan

Tenaga kerja

Kebutuhan Wall paper Lem Pekerja Tukang Kepala tukang Mandor

#N/A

Satuan m kg OH OH OH OH

Indeks 2.200 0.250 0.350 0.175 0.017 0.002

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan kg OH OH OH OH

Indeks 5.000 0.120 0.120 0.012 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 1.760 0.080 0.080 0.080 0.008 0.004

Harga Satuan Bahan

Bahan

Tenaga kerja

Indeks 0.003 0.050 0.120 0.120 0.012 0.006

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m3 kg OH OH OH OH

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.63 Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm Kebutuhan Papan kayu kelas II Paku skrup 5 cm Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan Buah kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.62 Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat Kebutuhan Vinyl karet Lem vinyl Pekerja Tukang Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.61 Memasang 1 m2 floor hardener Kebutuhan Floor hardener Pekerja Tukang Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 113 of 209

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm Jumlah

Harga Satuan Bahan/Upah

Bahan

Tenaga kerja

Kebutuhan Ubin abu-abu Portland Cement Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

Satuan Buah kg m3 OH OH OH OH

Indeks (Rp.) 6.630 Rp 1,000 9.800 Rp 400 0.045 Rp 45,000 0.250 Rp 30,000 0.125 Rp 40,000 0.013 Rp 50,000 0.013 Rp 60,000 Jumlah harga per satuan pekerjaan

(Rp.) Rp Rp Rp Rp Rp Rp Rp Rp

6,630 3,920 2,025 7,500 5,000 650 780 26,505

Bi bliog rafi SNI 03-6862-2002, Spesifikasi peralatan pemasangan dinding bata dan plesteran. SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) Pt-T-27-2000-C, Tata cara perhitungan harga satuan pekerjaan lantai untuk bangunan rumah dan gedung Pusat Penelitian dan Pengembangan Permukiman, Analisis Biaya Konstruksi (hasil penelitian), tahun 1988–1991

SNI DT 91 -0013-2007

Standar Nasional Indonesia

Page 114 of 209

Tata cara perhitungan harga satuan pekerjaan langit-langit untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi Daftar isi i Prakata ii Pendahuluan iii 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan langit-langit 3 6.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 3 6.2 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm 3 6.3 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm 3 6.4 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm 3 6.5 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm 4 6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm 4 6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 4 6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium 4 6.9 Memasang 1 m’ list langit-langit kayu profil 5 Lampiran A 6 Bibliografi 7

Prakata

Page 115 of 209

Standar Nasional Indonesia (SN I) tentang Tata cara perhitungan harga satuan pekerjaan lan gitlan git untuk konstruksi bangunan gedung dan perumahan adalah revisi dari SNI 03-2839-2002, Analisa Biaya Konstruksi (ABK) Ban gunan Gedung dan Perumahan Pekerjaan Langit-langit, dengan perubahan pada indeks harga bahan dan indeks harga tenaga kerja. Standar ini disusun oleh Panitia Teknik Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Gugus Kerja Struktur dan Konstruksi Bangunan pada Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan.

Standar ini telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s.d. 8 Desember 2006 oleh Subpanitia Teknis yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Tata cara perhitungan harga satuan pekerjaan langit-langit untuk konstruksi bangunan gedung dan perumahan

1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan langit-langit yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan langit-langit untuk bangunan gedung dan perumahan.

Page 116 of 209

Jenis pekerjaan langit-langit yang ditetapkan meliputi pekerjaan menutup rangka plafon dengan berbagai bahan penutup dan list.

2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisa pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar penghitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis pekerjaan

indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi

Page 117 of 209

suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, I volume dan unit s 4 Singkatan istilah Si ngkatan

Kepanjangan

cm kg m’ m2 m3 OH

centimeter kilogram meter panjang meter persegi meter kubik Orang Hari

t i l a h Satuan / panjang Satuan a berat r Satuan t panjang Satuan luas i Satuan Satuan volume tenaga kerja per hari

5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan harga satuan: a)Perhitungan harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis Persyaratan teknis dalam perhitungan harga satuan pekerjaan: a) Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

6 Penetapan indeks harga satuan pekerjaan langit-langit 6.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm

#N/A

#N/A

Page 118 of 209

Bahan

Tenaga kerja

Kebutuhan Asbes semen Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

Satuan m2 kg OH OH OH OH

Indeks 1.100 0.010 0.030 0.070 0.007 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 12.000 0.050 0.120 0.120 0.012 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan Lembar kg OH OH OH OH

Indeks 5.800 0.050 0.100 0.100 0.010 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Indeks 1.500 0.050 0.100 0.100 0.010 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Satuan Lembar

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Indeks 0.375

#N/A

#N/A #N/A

6.5 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm Kebutuhan Tripleks

Jml Harga Bahan

#N/A

Satuan Lembar kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.4 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm Kebutuhan Akustik Ukuran 60 cm x 120 cm Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.3 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm Kebutuhan akustik ukuran (30 x 60) cm Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Lembar kg OH OH OH OH

Jml Harga upah

#N/A #N/A

6.2 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm Kebutuhan akustik ukuran (30 x 30) cm Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Bahan Page 119 of 209

Bahan

Tenaga kerja

Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

kg OH OH OH OH

0.030 0.100 0.100 0.010 0.005

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm

Bahan

Tenaga kerja

Kebutuhan Kayu papan Paku tripleks Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m3 kg OH OH OH OH

Indeks 0.015 0.010 0.800 0.800 0.080 0.040

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Satuan Lembar kg OH OH OH OH

#N/A #N/A #N/A #N/A

Indeks 0.364 0.110 0.100 0.050 0.005 0.005

Harga Satuan Bahan

Bahan

Tenaga kerja

Satuan m’ kg Buah Lembar OH OH OH OH

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 1.050 0.010

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m’ kg

#N/A

#N/A #N/A

6.9 Memasang 1 m’ list langit-langit kayu profil Kebutuhan List kayu profil Paku

Jml Harga Bahan

#N/A

Indeks 3.600 0.150 1.050 1.500 0.500 0.500 0.050 0.025

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium Kebutuhan Profil Alluminium "T" Kawat diameter 4 mm Ramset Akustik Ukuran 60 cm x 120 cm Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm Kebutuhan Gypsum board Paku skrup Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 120 of 209

Tenaga kerja

Pekerja Tukang kayu Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

0.050 0.050 0.005 0.003

#N/A #N/A #N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm

Bahan

Tenaga kerja

Kebutuhan Asbes semen Paku 3 cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan m2 kg OH OH OH OH

Harga Satuan Bahan/Upah Indeks (Rp.) 1,100.000 Rp 30,000 0.010 Rp 10,000 0.070 Rp 30,000 0.070 Rp 40,000 0.007 Rp 50,000 0.004 Rp 60,000 Jumlah harga per satuan pekerjaan

Jumlah (Rp.) Rp Rp Rp Rp Rp Rp Rp

33,000 100 2,100 2,800 350 240 38,590

Bi bliog rafi Pusat Penelitian dan Pengembangan Permukiman, Analisa Biaya Konstruksi (hasil penelitian), tahun 1988–1991. SNI 03-2445-1991, Spesifikasi ukuran kayu untuk bangunan rumah dan gedung SNI 03-6839-2002, Spesifikasi kayu awet untuk perumahan dan gedung SNI 03-6861.1-2002, Spesifikasi bahan bangunan bagian A (bahan bangunan bukan logam) SNI 03-6861.3-2002, Spesifikasi bahan bangunan bagian C (bahan bangunan dari logam bukan besi)

SNI DT 91 -0014-2007

Page 121 of 209

Standar Nasional Indonesia

Tata cara perhitungan harga satuan pekerjaan besi dan aluminium untuk konstruksi bangunan gedung dan perumahan ICS 91 .010.20 Badan Standardisasi Nasional

Daftar isi

Daftar isi i Prakata ii Pendahuluan iii 1 Ruang lingkup 1 2 Acuan normatif 1 3 Istilah dan definisi 1 4 Singkatan istilah 2 5 Persyaratan 2 6 Penetapan indeks harga satuan pekerjaan besi dan aluminium 3 6.1 Memasang 1 kg besi profil 3 6.2 Memasang 1 kg rangka kuda-kuda baja IWF 3 6.3 Mengerjakan 100 kg pekerjaan perakitan 3 6.4 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 3 6.5 Mengerjakan 1 cm pengelasan dengan las listrik 4 6.6 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm 4 6.7 Memasang 1 m2 pintu rolling door besi 4 6.8 Memasang 1 m2 pintu lipat (Folding door) 4 6.9 Memasang 1 m2 sunscreen alluminium 5 6.10 Memasang 1 m2 rolling door alluminium 5 6.11 Memasang 1 m kusen pintu alluminium 5 6.12 Memasang 1 m2 pintu alluminium strip lebar 8 cm 5 6.13 Memasang 1 m2 pintu kaca rangka alluminium 6

Page 122 of 209

6.14 Memasang 1 m2 venetions blinds dan Vertical blinds 6 6.15 Memasang 1 m2 terali besi strip (2 x 3) mm 6 6.16 Memasang 1 m2 kawat nyamuk 6 6.17 Memasang 1 m2 jendela nako & tralis 7 6.18 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 7 6.19 Memasang 1 m’ talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm 7 Lampiran A 8 Bibliografi 9

Prakata Standar Nasional Indonesia (SN I) tentang Tata cara perhitungan harga satuan pekerjaan besi dan alumunium untuk konstruksi bangunan gedung dan perumahan adalah revisi dari Standar tentang Tata cara perhitungan harga satuan pekerjaan besi dan aluminium, yang disesuaikan dengan keadaan di Indonesia dengan melakukan modifikasi terhadap indeks harga satuan. Standar ini disusun oleh Panitia Teknis Bahan Konstruksi Bangunan dan Rekayasa Sipil melalui Subpanitia Teknis Bahan, Sains, Struktur dan Konstruksi Bangunan. Standar ini telah dibahas dalam forum konsensus yang diselenggarakan pada tanggal 7 s.d. 8 Desember 2006 oleh Subpanitia Teknis yang melibatkan para nara sumber, pakar dan lembaga terkait. Oleh karena SNI ini belum di jajak pendapat dan dikonsensuskan melalui pemungutan suara dengan melibatkan anggota kelompok minat MASTAN yang relevan, maka agar dapat segera dipergunakan sebagai acuan normatif, dokumen ini untuk sementara ditetapkan sebagai ”SN I Dokumen Teknis”.

Pendahuluan Tata cara perhitungan harga satuan pekerjaan ini disusun berdasarkan pada hasil penelitian Aanlisis Biaya Konstruksi di Pusat Litbang Permukiman 1988 – 1991. Penelitian ini dilakukan dalam dua tahap. Tahap pertama dengan melakukan pengumpulan data sekunder analisis biaya yang diperoleh dari beberapa BUMN, Kontraktor dan data yang berasal dari analisis yang telah ada sebelumnya yaitu BOW. Dari data sekunder yang terkumpul dipilih data dengan modus terbanyak. Tahap kedua adalah penelitian lapangan untuk memperoleh data primer sebagai cross check terhadap data sekunder terpilih pada penelitian tahap pertama. Penelitian lapangan berupa penelitian produktifitas tenaga kerja lapangan pada beberapa proyek pembangunan gedung dan perumahan dan penelitian laboratorium bahan bangunan untuk komposisi bahan yang digunakan pada setiap jenis pekerjaan dengan pendekatan kinerja/performance dari jenis pekerjaan terkait.

Page 123 of 209

Tata cara perhitungan harga satuan pekerjaan besi dan aluminium untuk konstruksi bangunan gedung dan perumahan

1 Ruang lingkup Standar ini menetapkan indeks bahan bangunan dan indeks tenaga kerja yang dibutuhkan untuk tiap satuan pekerjaan aluminium yang dapat dijadikan acuan dasar yang seragam bagi para pelaksana pembangunan gedung dan perumahan dalam menghitung besarnya harga satuan pekerjaan besi dan aluminium untuk bangunan gedung dan perumahan. Jenis pekerjaan besi dan aluminium yang ditetapkan meliputi: a)Pekerjaan pemasangan rangka atap dan talang; b)Pekerjaan pemasangan pintu atau jendela besi, pintu alluminium dan jendela nako, pintu gulung, pintu lipat sunscreen, venation blinds dan vertical-horizontal blinds; c)Pekerjaan pemasangan kawat nyamuk.

2 Acuan normatif Standar ini disusun mengacu kepada hasil pengkajian dari beberapa analisis pekerjaan yang telah diaplikasikan oleh beberapa kontraktor dengan pembanding adalah analisis BOW 1921 dan penelitian analisis biaya konstruksi.

3 Istilah dan definisi 3.1 bangunan gedung dan perumahan bangunan yang berfungsi untuk menampung kegiatan kehidupan bermasyarakat 3.2 harga satuan bahan harga yang sesuai dengan satuan jenis bahan bangunan 3.3 harga satuan pekerjaan harga yang dihitung berdasarkan analisis harga satuan bahan dan upah 3.4 indeks faktor pengali atau koefisien sebagai dasar penghitungan biaya bahan dan upah kerja 3.5 indeks bahan indeks kuantum yang menunjukkan kebutuhan bahan bangunan untuk setiap satuan jenis

Page 124 of 209

pekerjaan

indeks tenaga kerja indeks kuantum yang menunjukkan kebutuhan waktu untuk mengerjakan setiap satuan jenis pekerjaan 3.7 pelaksana pembangunan gedung dan perumahan pihak-pihak yang terkait dalam pembangunan gedung dan perumahan yaitu para perencana, konsultan, kontraktor maupun perseorangan dalam memperkirakan biaya bangunan. 3.8 perhitungan harga satuan pekerjaan konstruksi suatu cara perhitungan harga satuan pekerjaan konstruksi, yang dijabarkan dalam perkalian indeks bahan bangunan dan upah kerja dengan harga bahan bangunan dan standar pengupahan pekerja, untuk menyelesaikan per-satuan pekerjaan konstruksi 3.9 satuan pekerjaan satuan jenis kegiatan konstruksi bangunan yang dinyatakan dalam satuan panjang, luas, I volume dan unit s 4 Singkatan istilah Si ngkatan

Kepanjangan

cm kg m’ m2 m3 OH

centimeter kilogram meter panjang meter persegi meter kubik Orang Hari

t i l a h Satuan / panjang Satuan a berat r Satuan t panjang iSatuan luas Satuan Satuan volume tenaga kerja per hari

5 Persyaratan 5.1 Persyaratan umum Persyaratan umum dalam perhitungan indeks harga satuan: a)Perhitungan indeks harga satuan pekerjaan berlaku untuk seluruh wilayah Indonesia, berdasarkan harga bahan dan upah kerja sesuai dengan kondisi setempat; b)Spesifikasi dan cara pengerjaan setiap jenis pekerjaan disesuaikan dengan standar spesifikasi teknis pekerjaan yang telah dibakukan. 5.2 Persyaratan teknis

Page 125 of 209

Persyaratan teknis dalam perhitungan indeks harga satuan pekerjaan: a) Pelaksanaan perhitungan satuan pekerjaan harus didasarkan kepada gambar teknis dan rencana kerja serta syarat-syarat (RKS); b)Perhitungan indeks bahan telah ditambahkan toleransi sebesar 5%-20%, dimana di dalamnya termasuk angka susut, yang besarnya tergantung dari jenis bahan dan komposisi adukan; c)Jam kerja efektif untuk tenaga kerja diperhitungkan 5 jam per-hari.

5 Penetapan indeks harga satuan pekerjaan besi dan aluminium 6.1 Memasang 1 kg besi profil

Bahan

Tenaga kerja

Kebutuhan Besi profil Pekerja Tukang las Kepala tukang Mandor

#N/A

Satuan kg OH OH OH OH

Indeks 1.150 0.060 0.060 0.006 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 1.150 0.060 0.060 0.006 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja Alat

Indeks 1.000 0.100 0.100 0.100 0.001 0.005 0.800

Harga Satuan Bahan

Satuan kg

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Indeks 15.000

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Liter Liter OH OH OH OH Jam

#N/A

#N/A

6.4 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku Kebutuhan Besi siku L 30.30.3

Jml Harga Bahan

#N/A #N/A #N/A #N/A

6.3 Mengerjakan 100 kg pekerjaan perakitan Kebutuhan Solar Minyak pelumas Pekerja Tukang besi Kepala tukang Mandor Sewa alat perakitan baja

#N/A #N/A #N/A #N/A #N/A

Satuan kg OH OH OH OH

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

6.2 Memasang 1 kg rangka kuda-kuda baja IWF Kebutuhan Besi baja IWF Pekerja Tukang las Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Bahan Page 126 of 209

Bahan

Tenaga kerja

Besi plat baja kawat las Pekerja Tukang besi Kepala tukang Mandor

kg kg OH OH OH OH

32.800 0.050 1.050 1.050 0.105 0.052

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

6.5 Mengerjakan 10 cm pengelasan dengan las listrik

Bahan

Tenaga kerja Alat

Kebutuhan Kawat las listrik Solar Minyak pelumas Pekerja Tukang besi Kepala tukang Mandor Sewa alat

#N/A

Satuan kg Liter Liter OH OH OH OH Jam

Indeks 0.400 0.300 0.040 0.040 0.020 0.002 0.002 0.170

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

Satuan m m cm OH OH OH OH

Indeks 4.760 4.522 20.000 0.650 0.650 0.065 0.032

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 1.000 1.200 1.200 0.120 0.006

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Kebutuhan Pintu lipat

Indeks 1.000

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m2

#N/A

#N/A #N/A #N/A

6.8 Memasang 1 m2 pintu lipat (Folding door)

Bahan

Jml Harga Bahan

#N/A

Satuan m2 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A

6.7 Memasang 1 m2 pintu rolling door besi Kebutuhan Pintu gulung besi Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

6.6 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm Kebutuhan Besi scuare tube Besi lis kaca (1 x 1) cm Pengelasan Pekerja Tukang besi Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Page 127 of 209

Tenaga kerja

Pekerja Tukang besi Kepala tukang Mandor

OH OH OH OH

#N/A #N/A #N/A #N/A

0.440 0.440 0.044 0.022

6.9 Memasang 1 m2 sunscreen alluminium

Bahan

Tenaga kerja

Kebutuhan Sunscreen alluminium Pekerja Tukang besi Kepala tukang Mandor

#N/A

Satuan m2 OH OH OH OH

Indeks 1.000 0.080 0.800 0.080 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 1.000 1.000 1.000 0.100 0.050

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga kerja

Indeks 1.100 2.000 0.060 0.043 0.043 0.004 0.002

Harga Satuan Bahan

Bahan

Tenaga kerja

Indeks 4.400 14.600 0.085 0.085 0.009 0.004

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m’ m’ OH OH OH OH

#N/A

#N/A

#N/A #N/A #N/A #N/A

6.12 Memasang 1 m2 pintu alluminium strip lebar 8 cm Kebutuhan Profil alluminium Alluminium strip Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan m Buah Tube OH OH OH OH

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan m2 OH OH OH OH

#N/A

#N/A

6.11 Memasang 1 m kusen pintu alluminium Kebutuhan Profil alluminium Skrup fixer Sealant Pekerja Tukang besi konstruksi Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

6.10 Memasang 1 m2 rolling door alluminium Kebutuhan Rolling door alluminium Pekerja Tukang besi Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 128 of 209

6.13 Memasang 1 m2 pintu kaca rangka alluminium

Bahan

Tenaga kerja

Kebutuhan Pintu alluminium Profil kaca Sealant Pekerja Tukang besi Kepala tukang Mandor

#N/A

Satuan m m Tube OH OH OH OH

Indeks 4.400 4.500 0.270 0.085 0.085 0.009 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

OH OH OH OH

Indeks 1.000

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga kerja

#N/A #N/A #N/A #N/A

0.350 0.350 0.035 0.018

Satuan kg cm OH OH OH OH

Indeks 6.177 27.080 1.670 1,670.000 0.167 0.083

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga kerja

Jml Harga Bahan

Indeks 1.100 11.110 1.716 0.100 0.100 0.010 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m2 cm kg OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

6.16 Memasang 1 m2 kawat nyamuk Kebutuhan Kawat nyamuk Pengelasan Baja strip (0,2 x 2) cm Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A

#N/A

6.15 Memasang 1 m2 terali besi strip (2 x 3) mm Kebutuhan Besi strip Pengelasan Pekerja Tukang besi Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan m2

Jml Harga upah

#N/A #N/A #N/A

6.14 Memasang 1 m2 venetions blinds dan Vertical blinds Kebutuhan Venetions blinds dan vertical blinds (tirai) Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 129 of 209

6.17 Memasang 1 m2 jendela nako & tralis

Bahan

Tenaga kerja

Kebutuhan Jendela nako (rangka + kaca 5 mm) Paku skrup 1 cm – 2,5 cm Besi strip Pekerja Tukang besi Kepala tukang Mandor

#N/A

Satuan

Indeks

m2 Buah m’ OH OH OH OH

1.100 10.000 7.000 0.200 0.200 0.020 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga kerja

Indeks 1.050 0.015 0.019 0.200 0.400 0.025 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga kerja

Satuan m kg kg OH OH OH OH

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Indeks 1.050 0.010 0.500 0.150 0.300 0.030 0.008

#N/A

#N/A #N/A #N/A

6.19 Memasang 1 m’ talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm Kebutuhan Seng plat Paku 1 cm - 2,5 cm Besi strip Pekerja Tukang besi Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan m’ kg m3 OH OH OH OH

Jml Harga upah

#N/A #N/A #N/A

6.18 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm Kebutuhan Seng plat Paku 1 cm - 2,5 cm Papan kayu kelas II atau III Pekerja Tukang besi Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Lampiran A (I nformatif) Contoh penggunaan standar untuk menghitung harga satuan pekerjaan A.1 Memasang 1 m2 rolling door alluminium

Bahan

Tenaga kerja

Kebutuhan Rolling door alluminium Pekerja

Satuan m2 OH

Indeks 1.000 1.000

Harga Satuan Bahan/Upah (Rp.) Rp 100,000 Rp 30,000

Jumlah (Rp.) Rp Rp

100,000 30,000

Page 130 of 209

Tenaga kerja

Tukang besi Kepala tukang Mandor

OH OH OH

1.000 Rp 40,000 0.100 Rp 50,000 0.050 Rp 60,000 Jumlah harga per satuan pekerjaan

Rp Rp Rp Rp

40,000 5,000 3,000 178,000

Bi bliog rafi SNI 03-6861.2-2002, Spesifikasi bahan bagunan bagian B (bahan bangunan besi/baja) SNI 03-6861.3-2002, Spesifikasi bahan bagunan bagian C (bahan bangunan dari logam bukan besi) RSNI T-16-2002 Tata cara perhitungan harga satuan pekerjaan besi dan aluminium Pusat Penelitian dan Pengembangan Permukiman, Analisa Biaya Konstruksi (hasil penelitian), tahun 1988–1991

ANALISA BIAYA KONSTRUKSI 2002 RSNI. T-15-2002 PEKERJAAN PERSIAPAN 1 m' Pagar Sementara dari Kayu tinggi 2 m

Bahan

Tenaga

Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Semen Portland Pasir beton Koral Beton Kaso 5 / 7 ( albasiah ) Paku Biasa 2" - 5" Residu Tukang kayu Pekerja

#N/A

Satuan btg Kg m3 m3 m3 Kg Lt Oh Oh

Indeks 1.250 2.500 0.005 0.009 0.072 0.060 0.400 0.200 0.400

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

Page 131 of 209

Tenaga

Kepala tukang Mandor

Oh Oh

0.020 0.020

#N/A #N/A #N/A

1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m

Bahan

Tenaga

Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Semen Portland Seng gelombang 3"-5" Pasir beton Koral Beton Kaso 5 / 7 ( albasiah ) Paku Biasa 2" - 5" Meni Besi Tukang kayu Pekerja Kepala tukang Mandor

Satuan btg Kg lbr m3 m3 m3 Kg Lt Oh Oh Oh Oh

Indeks 1.250 2.500 1.200 1.200 0.009 0.072 0.060 0.450 0.200 0.400 0.020 0.020

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan btg Kg Kg m3 m3 Kg Oh Oh Oh Oh

Indeks 1.000 2.000 25.000 0.005 0.009 0.060 0.200 0.300 0.020 0.020

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Jml Harga Bahan

Indeks 0.012 0.020 0.007 0.100 0.100 0.010

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3 Kg m3 Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1 m' Pek. Pengukuran & Pemasangan Bowplank Kebutuhan Kayu Kaso 5 / 7 (borneo) Paku Biasa 2" - 5" Kayu Papan 3 / 20 borneo Tukang kayu Pekerja Kepala tukang

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

1 m' Pagar Sementara dari Kawat Duri tinggi 1.8 m Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Semen Portland Kawat Duri Pasir beton Koral Beton Paku Biasa 2" - 5" Tukang kayu Pekerja Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga Page 132 of 209

Tenaga

Mandor

Oh

0.005

#N/A

1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran

Bahan

Tenaga

Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Kayu Balok Borneo Paku Besi Strip Semen Portland Pasir Pasang Pasir beton Koral Beton Bata merah Seng Plat Jendela nako (rangka + kaca 5 mm) Kaca Polos Kunci Tanam Plywood 4 mm Tukang kayu Tukang batu Pekerja Kepala tukang Mandor

#N/A

Satuan btg m3 Kg Kg Kg m3 m3 m3 bh lbr m2 m2 bh lbr Oh Oh Oh Oh Oh

Indeks 1.250 0.180 0.850 1.100 35.000 0.150 0.100 0.150 30.000 0.250 0.500 0.080 0.150 0.060 2.000 1.000 2.000 0.300 0.050

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

1 m² Pembuatan Rumah Jaga / Konstruksi Kayu

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A

Indeks 1.700 0.210 0.300 10.500 0.030 0.050 1.500 2.000 1.000 0.200 0.050

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A

Satuan btg m3 Kg Kg m3 m3 lbr Oh Oh Oh Oh

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

1 m² Pembuatan Gudang Semen dan Alat - alat Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Kayu Balok Borneo Paku Semen Portland Pasir beton Koral Beton Seng Gelombang BJLS 32 Tukang kayu Pekerja Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 133 of 209

Bahan

Tenaga

Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Kayu Balok Borneo Paku Seng Gelombang BJLS 32 Tukang kayu Pekerja Kepala tukang Mandor

Satuan btg m3 Kg lbr Oh Oh Oh Oh

Indeks 3.000 0.276 0.700 1.500 1.500 1.000 0.150 0.050

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Tenaga

Indeks 0.100 0.050

Harga Satuan Bahan

Harga Satuan upah

Bahan

Tenaga

Bahan Tenaga

1 m² Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm

Jml Harga Bahan

Satuan btg m3 Kg Kg m3 m3 lbr lbr Oh Oh Oh Oh

Indeks 1.250 0.186 0.300 18.000 0.030 0.050 1.500 1.350 2.000 1.000 0.200 0.050

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

Indeks 0.036 0.080 1.000 0.030 0.002

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan m3 Kg btg Oh Oh

#N/A

#N/A #N/A #N/A

1 m² Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm Kebutuhan Kayu Terentang Paku Kayu Kaso 5 / 7 (borneo) Tukang kayu Mandor

-

#N/A #N/A

1 m² Pembuatan Bedeng Buruh Kebutuhan Dolken Kayu Ø 8 - 10/400 cm Kayu Balok Borneo Paku Semen Portland Pasir beton Koral Beton Seng Gelombang BJLS 32 Plywood 4 mm Tukang kayu Pekerja Kepala tukang Mandor

#N/A #N/A #N/A #N/A Rp

Satuan Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A

1 m2 Membersihkan Lapangan dan Perataan Kebutuhan Pekerja Mandor

Jml Harga Bahan

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A

Page 134 of 209

Bahan

Tenaga

Kebutuhan Bambu Ø 6 - 8 / 600 cm Tali Ijuk Tukang kayu Pekerja Kepala tukang Mandor

Satuan btg Kg Oh Oh Oh Oh

Indeks 1.000 0.250 0.017 0.002 0.250 0.013

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

1 m² Pembuatan Jalan Sementara

Bahan Tenaga

Kebutuhan Batu Belah 5 / 20 Batu Belah 5 / 7 Pasir Pasang Pekerja Mandor

#N/A

Satuan m3 m3 m3 Oh Oh

Indeks 0.150 0.090 0.010 1.000 0.050

Harga Satuan Bahan

Harga Satuan upah

Tenaga

Indeks 6.667 0.333

Tenaga

#N/A #N/A

Harga Satuan Bahan

Harga Satuan upah

-

Jml Harga Bahan

Indeks 6.667 0.033

Harga Satuan Bahan

Harga Satuan upah

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A Rp

Satuan Oh Oh

Jml Harga upah

#N/A #N/A Rp

Satuan Oh Oh

#N/A

#N/A #N/A #N/A

1 m³ Bongkaran Dinding Tembok Bata Merah Kebutuhan Pekerja Mandor

Jml Harga Bahan

#N/A #N/A #N/A

1 m³ Bongkaran Beton Bertulang Kebutuhan Pekerja Mandor

Jml Harga upah

-

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah #N/A #N/A

SNI. 03-3436-1994 PEKERJAAN PENTUP ATAP 1m² Pasang Atap Genteng Palentong Kecil

Bahan

Tenaga

Kebutuhan Genteng Palentong Pekerja

#N/A

Satuan bh Oh

Indeks 25.000 0.150

Harga Satuan Bahan

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A

#N/A

Page 135 of 209

Tenaga

Tukang kayu Kepala tukang Mandor

Oh Oh Oh

0.075 0.008 0.008

#N/A #N/A #N/A

1m² Pasang Atap Genteng Kodok / Glazzur

Bahan

Tenaga

Kebutuhan Genteng Kodok Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan bh Oh Oh Oh Oh

Indeks 25.000 0.150 0.075 0.008 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 12.000 0.150 0.060 0.006 0.008

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 5.000 8.000 0.032 0.400 0.200 0.020 0.002

Harga Satuan Bahan

Bahan

Indeks 5.000 8.000 0.032 0.400 0.200 0.020

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan bh Kg m3 Oh Oh Oh

#N/A

#N/A

#N/A #N/A #N/A #N/A

1m' Pasang Genteng Bubung Kodok Glazzur Kebutuhan Genteng Bubung Kodok Semen Portland Pasir Pasang Pekerja Tukang kayu Kepala tukang

Jml Harga Bahan

#N/A

Satuan bh Kg m3 Oh Oh Oh Oh

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan bh Oh Oh Oh Oh

#N/A

#N/A

1m' Pasang Genteng Bubung Palentong Kebutuhan Genteng Bubung Palentong Semen Portland Pasir Pasang Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1m² Pasang Atap Genteng Palentong Super / Besar Kebutuhan Genteng Palentong Super Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga Page 136 of 209

Tenaga

Mandor

Oh

0.002

#N/A

1m' Pasang Genteng Bubung Palentong Besar

Bahan

Tenaga

Kebutuhan Genteng Bubung Palentong Semen Portland Pasir Pasang Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan bh Kg m3 Oh Oh Oh Oh

Indeks 4.000 8.000 0.032 0.400 0.200 0.020 0.002

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.600 0.050 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 0.500 0.120 0.140 0.075 0.008 0.008

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga

Indeks 0.600 0.120 0.140 0.075 0.008 0.008

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

#N/A

#N/A #N/A

1m' Pasang Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m' Pasang Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm Kebutuhan Roof Light Fiberglass Paku Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 137 of 209

1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm

Bahan

Tenaga

Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.600 0.120 0.140 0.070 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 0.750 0.120 0.140 0.070 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.350 0.120 0.140 0.070 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

1m² Pasang Atap Asbes Gelombang ( 240 x 1.05 m ) X 4mm

Jml Harga Bahan

Indeks 0.420 0.120 0.140 0.070 0.007 0.007

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A

1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 138 of 209

Bahan

Tenaga

Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.440 0.120 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 0.510 0.120 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.800 0.120 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 0.370 0.120 0.140 0.067 0.007 0.007

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm Kebutuhan

Jml Harga Bahan

#N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 139 of 209

Bahan

Tenaga

Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

lbr Kg Oh Oh Oh Oh

0.380 0.120 0.140 0.067 0.007 0.007

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm

Bahan

Tenaga

Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.460 0.120 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 0.490 0.120 0.140 0.067 0.007 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 0.570 0.120 0.140 0.067 0.007 0.007

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 2.400 6.000

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg

#N/A

#N/A #N/A

1m' Pasang Bubung Stel Gelombang 0.92m Kebutuhan Asbes Gelombang Paku Pancing 60 x 230

Jml Harga Bahan

#N/A

Satuan lbr Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm Kebutuhan Asbes Gelombang Paku Pancing 60 x 230 Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 140 of 209

Pekerja Tukang kayu Kepala tukang Mandor

Tenaga

Oh Oh Oh Oh

0.084 0.125 0.013 0.004

#N/A #N/A #N/A #N/A

1m' Pasang Nok Stel Gelombang 0.92m

Bahan

Tenaga

Kebutuhan Asbes Gelombang Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr bh Oh Oh Oh Oh

Indeks 2.400 6.000 0.084 0.125 0.013 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr bh Oh Oh Oh Oh

Indeks 2.100 6.000 0.084 0.125 0.013 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 2.050 6.000 0.084 0.125 0.013 0.004

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 1.200 6.000 0.084 0.125

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan lbr bh Oh Oh

#N/A

#N/A #N/A

1m' Pasang Nok Paten 0.92m Kebutuhan Nok Paten Paku Skrup 3.5" Pekerja Tukang kayu

Jml Harga Bahan

#N/A

Satuan lbr bh Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m' Pasang Nok Stel Gelombang 1.08m Kebutuhan Asbes Gelombang Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1m' Pasang Nok Stel Gelombang 1.05m Kebutuhan Asbes Gelombang Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga Page 141 of 209

Kepala tukang Mandor

Tenaga

Oh Oh

0.013 0.004

#N/A #N/A

1m' Pasang Nok Paten 1.05m

Bahan

Tenaga

Kebutuhan Nok Paten Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr bh Oh Oh Oh Oh

Indeks 1.200 6.000 0.084 0.125 0.013 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr bh Oh Oh Oh Oh

Indeks 1.200 6.000 0.084 0.125 0.013 0.004

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 1.100 6.000 0.100 0.150 0.013 0.004

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga

Indeks 1.100 6.000 0.084 0.125 0.013 0.004

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan lbr bh Oh Oh Oh Oh

#N/A

#N/A #N/A

1m' Pasang Nok Stel rata 1.05m Kebutuhan Nok Stel rata Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan lbr bh Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m' Pasang Nok Stel rata 0.92m Kebutuhan Nok Stel rata Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1m' Pasang Nok Paten 1.08m Kebutuhan Nok Paten Paku Skrup 3.5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 142 of 209

1m² Pasang Atap Genteng Beton

Bahan

Tenaga

Kebutuhan Genteng Beton Paku Biasa 2" - 5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr bh Oh Oh Oh Oh

Indeks 11.000 0.030 0.200 0.100 0.010 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 6.900 0.350 0.030 0.500 0.200 0.300 0.003 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 1.020 0.200 0.200 0.100 0.010 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Tenaga

Jml Harga Bahan

Satuan lbr Kg Oh Oh Oh Oh

Indeks 60.000 0.200 0.166 0.250 0.025 0.008

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Kebutuhan Genteng Sirap Paku Biasa ½" - 1" Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m² Pasang Atap Sirap

Bahan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

1m² Pasang Atap Genteng Metal Kebutuhan Genteng Metal Paku Biasa 2" - 5" Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan lbr lbr Kg Bh Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A

1m² Pasang Atap Genteng Aspal Kebutuhan Genteng Aspal Plywood 4 mm Paku Biasa 1/2" - 1" Plastic Aerator Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 143 of 209

1m' Pasang Nok Genteng Beton

Bahan

Tenaga

Kebutuhan Genteng Beton Paku Biasa 2" - 5" Semen abu -abu Pasir Pasang Semen Warna Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan lbr Kg Kg m3 Kg Oh Oh Oh Oh

Indeks 3.500 0.050 10.800 0.032 1.000 0.400 0.200 0.020 0.020

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 2.000 0.050 0.004 0.125 0.250 0.025 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh Oh Oh

Indeks 1.100 0.050 0.250 0.150 0.015 0.013

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Jml Harga Bahan

Indeks 1.100 0.050 0.250 0.150

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m' Pasang Nok Genteng Metal Kebutuhan Genteng Decra Bond Paku Biasa ½" - 1" Pekerja Tukang kayu

Jml Harga Bahan

#N/A

#N/A #N/A #N/A

1m' Pasang Nok Genteng Metal Kebutuhan Genteng Decra Bond Paku Biasa ½" - 1" Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan lbr Kg Kg Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m' Pasang Nok Genteng Aspal Kebutuhan Genteng Aspal Paku Biasa ½" - 1" Balok Kayu Borneo Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga Page 144 of 209

Kepala tukang Mandor

Tenaga

Oh Oh

0.015 0.013

#N/A #N/A

1m' Pasang Nok Sirap

Bahan

Tenaga

#N/A

Kebutuhan Seng Plat 3" x 6" BJLS 28 Paku Biasa ½" - 1" Paku Biasa 2" - 5" Papan Kayu Borneo tebal 3cm Pekerja Tukang kayu Kepala tukang Mandor

Satuan Lbr Kg Kg m3 Oh Oh Oh Oh

Indeks 0.400 0.060 0.050 0.004 0.125 0.250 0.025 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Tenaga

Kebutuhan Seng Gelombang 3" x 6" BJLS 28 Paku Biasa ½" - 1" Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Satuan Lbr Kg Oh Oh Oh Oh

Indeks 0.700 0.020 0.120 0.060 0.006 0.006

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Tenaga

Satuan Lbr Kg Oh Oh Oh Oh

Indeks 0.300 0.040 0.015 0.070 0.008 0.006

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Kebutuhan Atap Alluminium Gelombang tebal Paku Hak Pnjang 15 cm Pekerja Tukang kayu

Indeks 1.050 0.020 0.015 0.075

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m2 Kg Oh Oh

#N/A

#N/A #N/A

1m² Pasang Atap Alluminium

Bahan

Jml Harga Bahan

#N/A

Kebutuhan Seng Plat 3" x 6" BJLS 28 Paku Biasa ½" - 1" Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1m² Pasang Atap Nok Seng

Bahan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

1m² Pasang Atap Seng Gelombang

Bahan

#N/A #N/A

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga Page 145 of 209

Kepala tukang Mandor

Tenaga

Oh Oh

0.008 0.006

#N/A #N/A

1m² Pasang Nok Alluminium

Bahan

Tenaga

Kebutuhan Nok standar 40 cm 18, swg 22 Paku Hak Pnjang 15 cm Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m2 Kg Oh Oh Oh Oh

Indeks 1.200 0.040 0.100 1.000 0.010 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Indeks 1.050 0.150 0.050 0.005 0.008

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m2 Oh Oh Oh Oh

#N/A

#N/A #N/A

1m² Pasang Alluminium Foil / Sisalation Kebutuhan Sisalation / Alluminium Foil Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

RSNI. T-15-2002 PEKERJAAN SANITASI Memasang 1 buah Kloset Duduk / Monoblok

Bahan

Tenaga

Kebutuhan Kloset Duduk / Monoblok Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh

Oh Oh Oh Oh

Indeks 1.000 30% Dari bahan 3.300 1.100 0.001 0.160

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

Indeks

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A

Memasang 1 buah Kloset Jongkok Porselen Kebutuhan

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 146 of 209

Bahan

Tenaga

Kloset Jongkok Porselen Semen Portland Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

bh Kg m3 Oh Oh Oh Oh

1.000 6.000 0.010 1.000 1.500 1.500 0.160

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Memasang 1 buah Kloset Jongkok Teraso

Bahan

Tenaga

Kebutuhan Kloset Jongkok Teraso Bata merah Semen Portland Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh bh Kg m3 Oh Oh Oh Oh

Indeks 1.000 7.000 6.000 0.010 1.000 1.500 0.300 0.110

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A

Satuan bh

Indeks 1.000

Harga Satuan Bahan

Harga Satuan upah

#N/A

6.000 0.010 1.000 1.000 0.100 0.100

#N/A #N/A

Satuan bh

Indeks 1.000

Kg m3 Oh Oh Oh

6.000 0.010 1.000 1.450 0.150

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Kebutuhan Urinoir Perlengkapan Semen Abu -abu Pasir Pasang Pekerja Tukang batu Kepala tukang

#N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Memasang 1 buah Wastafel

Bahan

Jml Harga Bahan Rp

Kg m3 Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A

Memasang 1 buah Urinoir Kebutuhan Urinoir Perlengkapan Semen Portland Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

Tenaga Page 147 of 209

Tenaga

Mandor

Oh

0.100

#N/A

#N/A

Memasang 1 buah Bak Mandi Teraso, volume 0.30 m³

Bahan

Tenaga

Kebutuhan Bak Teraso Semen Portland Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh Kg m3 Oh Oh Oh Oh

Indeks 1.000 6.000 0.010 2.100 0.750 0.070 0.110

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A

Satuan bh

Indeks 1.000

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

1.800 2.700 0.540 0.110

Bahan

Tenaga

Bata merah Semen Portland Pasir Pasang Porselen ( 11 x 11 ) cm Semen Nat Pekerja Tukang batu Kepala tukang Mandor

Indeks 0.400 120.000 0.300 360.000 6.000 6.000 3.000 0.300 0.300

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 1.000

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan bh

#N/A

#N/A #N/A #N/A #N/A #N/A

Memasang 1 buah Badkip Porselen Kebutuhan Badkip Perlengkapan Pekerja

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m3 Kg m3 bh Kg Oh Oh Oh Oh

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³ Kebutuhan

Jml Harga upah

#N/A #N/A #N/A

Memasang 1 buah Bak Mandi Fiberglass, volume 0.30 m³ Kebutuhan Bak Fiberglass Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A

#N/A Jml Harga upah

#N/A #N/A

Page 148 of 209

Tenaga

Tukang batu Kepala tukang Mandor

Oh Oh Oh

0.075 0.750 0.250

#N/A #N/A #N/A

#N/A #N/A #N/A

Memasang 1 buah Bak Fiberglass volume 1 m³ air

Bahan

Tenaga

Kebutuhan Bak Fiberglass Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh

Indeks 1.000

Harga Satuan Bahan

Harga Satuan upah

#N/A Rp

Oh Oh Oh Oh

3.000 4.500 0.900 0.900

Bahan

Tenaga

Indeks 1.600 0.680 0.013 0.011 0.060 0.030 0.003 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan bh Kg m3 m3 Oh Oh Oh Oh

Indeks 1.600 0.870 0.014 0.014 0.080 0.040 0.004 0.007

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Jml Harga Bahan

Indeks

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Satuan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Beton Ø 5 cm - 20 cm Kebutuhan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 20 cm Kebutuhan Pipa Tanah Semen Portland Pasir Pasang Pasir Urug Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan bh Kg m3 m3 Oh Oh Oh Oh

Jml Harga upah

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø15 cm Kebutuhan Pipa Tanah Semen Portland Pasir Pasang Pasir Urug Pekerja Tukang batu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 149 of 209

Bahan

Tenaga

Pipa Beton Bata merah Semen Portland Pasir Pasang Pasir Urug Pekerja Tukang batu Kepala tukang Mandor

bh m3 Kg m3 m3 Oh Oh Oh Oh

1.100 0.270 3.920 0.056 0.024 0.140 0.070 0.007 0.007

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Beton Ø 30 cm - 100 cm

Bahan

Tenaga

Kebutuhan Pipa Beton Bata merah Semen Portland Pasir Pasang Pasir Urug Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh m3 Kg m3 m3 Oh Oh Oh Oh

Indeks 1.100 0.550 10.300 0.061 0.069 0.380 0.190 0.019 0.019

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Satuan m3 Kg m3 m3 Kg m3 Oh Oh Oh Oh

#N/A #N/A #N/A #N/A

Indeks 0.145 44.000 0.070 0.070 1.600 0.060 3.200 1.015 0.002 0.016

Harga Satuan Bahan

Satuan m3 Kg

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Indeks 0.250 77.000

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm Kebutuhan Bata merah Semen Portland

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A

Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm Kebutuhan Bata merah Semen Portland Pasir Pasang Batu Kerikil Besi beton Pasir beton Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Page 150 of 209

Bahan

Bahan

Tenaga

Pasir Pasang Batu Kerikil Besi beton Pasir beton Pekerja Tukang batu Kepala tukang Mandor

m3 m3 Kg m3 Oh Oh Oh Oh

0.130 0.020 2.600 0.090 1.420 0.473 0.047 0.071

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm

Bahan

Tenaga

Kebutuhan Bata merah Semen Portland Pasir Pasang Batu Koral Besi beton Pasir beton Pekerja Tukang batu Kepala tukang Mandor Tukang Gali

Satuan m3 Kg m3 m3 Kg m3 Oh Oh Oh Oh Oh

#N/A

Indeks 0.371 114.000 0.184 0.033 4.850 0.120 2.160 0.720 0.072 0.108 0.100

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.054 0.090 0.009 0.027

Bahan

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh

0.054 0.090 0.009

#N/A #N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Galvanis Ø ¾" Kebutuhan Pipa Galvanis Perlengkapan Pekerja Tukang batu Kepala tukang

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Galvanis Ø ½" Kebutuhan Pipa Galvanis Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A

Tenaga Page 151 of 209

Tenaga

Mandor

Oh

0.027

#N/A

#N/A

Memasang 1 m' Pipa Galvanis Ø 1"

Bahan

Tenaga

Kebutuhan Pipa Galvanis Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.054 0.090 0.009 0.027

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.108 0.180 0.018 0.005

Bahan

Tenaga

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.108 0.180 0.018 0.005

Bahan

Tenaga

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.135 0.225 0.023 0.007

#N/A #N/A #N/A #N/A

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Galvanis Ø 4" Kebutuhan Pipa Galvanis D 4" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Galvanis Ø 3" Kebutuhan Pipa Galvanis Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa Galvanis Ø 1½" Kebutuhan Pipa Galvanis Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Page 152 of 209

Memasang 1 m' Pipa PVC tipe AW Ø ½"

Bahan

Tenaga

Kebutuhan Pipa PVC D 1/2" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.036 0.060 0.006 0.002

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.036 0.060 0.006 0.002

Bahan

Tenaga

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.036 0.060 0.006 0.002

Bahan

Tenaga

Memasang 1 m' Pipa PVC tipe AW Ø 2"

Indeks 1.200

Harga Satuan Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.036 0.060 0.006 0.002

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø 1½" Kebutuhan Pipa PVC tipe AW Ø 1½" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø 1" Kebutuhan Pipa PVC tipe AW Ø 1" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø ¾" Kebutuhan Pipa PVC tipe AW Ø ¾" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A

#N/A Jml Harga upah

#N/A -

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 153 of 209

Bahan

Tenaga

Kebutuhan Pipa PVC tipe AW Ø 2" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Satuan m'

Indeks 1.200

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.054 0.090 0.009 0.003

Bahan

Tenaga

#N/A #N/A #N/A #N/A #N/A

Satuan m'

Indeks 1.200

Harga Satuan Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.036 0.060 0.006 0.002

Bahan

Tenaga

Indeks 1.200

Harga Satuan Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Rp

Oh Oh Oh Oh

0.081 0.135 0.014 0.004

Bahan

Tenaga

Indeks 1.200

Harga Satuan Bahan

#N/A

Harga Satuan upah

#N/A

0.081 0.135 0.014 0.004

Indeks

Harga Satuan Bahan

Harga Satuan upah

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 bh Bak Cuci Piring Stainles Steel Kebutuhan

Jml Harga Bahan Rp

Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø 4" Kebutuhan Pipa PVC tipe AW Ø 4" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan m'

#N/A

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø 3" Kebutuhan Pipa PVC tipe AW Ø 3" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

#N/A -

#N/A #N/A #N/A #N/A

Memasang 1 m' Pipa PVC tipe AW Ø 2½" Kebutuhan Pipa PVC tipe AW Ø 2½" Perlengkapan Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 154 of 209

Bak cuci Stainless steel Water Drain + Asesories Pekerja Tukang batu Kepala tukang Mandor

Bahan

Tenaga

bh set Oh Oh Oh Oh

1.000 1.000 0.030 0.300 0.030 0.002

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

Memasang 1 bh Bak Cuci Piring Teraso

Bahan

Tenaga

Kebutuhan Bak cuci Teraso Water Drain + Asesories Semen Portland Pasir Pasang Pekerja Tukang batu Kepala tukang Mandor

#N/A

Satuan bh set Kg m3 Oh Oh Oh Oh

Indeks 1.000 1.000 20.000 0.050 0.050 0.500 0.050 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan bh bh Oh Oh Oh Oh

Indeks 1.000 0.025 0.010 0.100 0.010 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Tenaga

Jml Harga Bahan

Satuan bh Oh Oh Oh Oh

Indeks 1.000 0.010 0.100 0.010 0.005

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Kebutuhan Floor Drain Pekerja Tukang batu Kepala tukang Mandor

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Memasang 1 bh Floor Drain

Bahan

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

Memasang 1 bh Kran Ø ¾" atau ½" Kebutuhan Kran Air Seal tape Pekerja Tukang batu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

PT. T-30.2000-C Page 155 of 209

PEKERJAAN KUNCI DAN KACA 1 Buah Pasang kunci Tanam Antik

Bahan

Tenaga

Kebutuhan kunci Tanam Antik Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.060 0.600 0.060 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.000 0.010 0.500 0.010 0.005

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.000 0.005 0.500 0.005 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Jml Harga Bahan

Indeks 1.000 0.005 0.500 0.005 0.000

Harga Satuan Bahan

Harga Satuan upah

#N/A

Jml Harga Bahan

Indeks

Harga Satuan Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A #N/A #N/A #N/A

Satuan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Engsel Pintu Kebutuhan

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Bh Oh Oh Oh Oh

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Bh Oh Oh Oh Oh

#N/A

#N/A

1 Buah Pasang kunci Silinder Kebutuhan kunci Silinder Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 Buah Pasang kunci Tanam Kamar Mandi Kebutuhan kunci Tanam Kamar Mandi Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A #N/A

Satuan Bh Oh Oh Oh Oh

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang kunci Tanam Biasa Kebutuhan kunci Tanam Biasa Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 156 of 209

Bahan

Engsel Pintu Pekerja Tukang kayu Kepala tukang Mandor

Tenaga

Bh Oh Oh Oh Oh

1.000 0.015 0.150 0.015 0.001

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Engsel Jendela Kupu - kupu

Bahan

Tenaga

Kebutuhan Engsel Jendela Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.010 0.100 0.010 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.000 0.020 0.200 0.020 0.010

Harga Satuan Bahan

Harga Satuan upah

#N/A

Tenaga

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Tenaga

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.015 0.150 0.015 0.001

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Kebutuhan Kait Angin Pekerja Tukang kayu Kepala tukang Mandor

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Kait angin

Bahan

Jml Harga Bahan

#N/A

Kebutuhan Spring Knip Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Bh Oh Oh Oh Oh

#N/A

#N/A

1 Buah Pasang Spring Knip

Bahan

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 Buah Pasang Engsel Angin Kebutuhan Engsel Angin Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 157 of 209

1 Buah Pasang Door Closer

Bahan

Tenaga

#N/A

Kebutuhan Door Closer Pekerja Tukang kayu Kepala tukang Mandor

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.050 0.500 0.050 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Tenaga

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.020 0.200 0.020 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Tenaga

Kebutuhan Door Holder Pekerja Tukang kayu Kepala tukang Mandor

Indeks 1.000 0.050 0.500 0.050 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A

Tenaga

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.010 0.100 0.010 0.001

Harga Satuan Bahan

Kebutuhan Rel Pintu Dorong Pekerja Tukang kayu

Indeks 1.000 0.060 0.600

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Bh Oh Oh

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Rel Pintu Dorong

Bahan

Jml Harga Bahan

#N/A

Kebutuhan Door Stop Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Bh Oh Oh Oh Oh

#N/A

#N/A

1 Buah Pasang Door Stop

Bahan

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 Buah Pasang Pegangan Pintu / Door Holder

Bahan

#N/A #N/A #N/A #N/A #N/A

Kebutuhan Kunci Selot Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Kunci Selot

Bahan

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A

#N/A #N/A

Tenaga Page 158 of 209

Kepala tukang Mandor

Tenaga

Oh Oh

0.060 0.003

#N/A #N/A

1 Buah Pasang Kunci Lemari

Bahan

Tenaga

Kebutuhan Kunci Lemari Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan Bh Oh Oh Oh Oh

Indeks 1.000 0.025 0.250 0.025 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Bahan

Tenaga

Indeks 1.100 0.017 0.165 0.017 0.001

Harga Satuan upah

#N/A

Indeks

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan

#N/A

#N/A

1 Buah Pasang Kaca Buram tebal 12 mm Kebutuhan

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan m2 Oh Oh Oh Oh

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Kaca tebal 8 mm Kebutuhan Kaca Polos Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan m2 Oh Oh Oh Oh

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan m2 Oh Oh Oh Oh

#N/A

#N/A

1 Buah Pasang Kaca tebal 5 mm Kebutuhan Kaca Polos Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 Buah Pasang Kaca tebal 3 mm Kebutuhan Kaca Polos Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

Page 159 of 209

Bahan

Tenaga

Kaca Buram Pekerja Tukang kayu Kepala tukang Mandor

m2 Oh Oh Oh Oh

1.100 0.025 0.250 0.025 0.001

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Kaca Cermin tebal 5 mm

Bahan

Tenaga

Kebutuhan Kaca Cermin Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m2 Oh Oh Oh Oh

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

Indeks 1.100 0.017 0.165 0.017 0.001

Harga Satuan Bahan

Bahan

Tenaga

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan m2 Oh Oh Oh Oh

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 Buah Pasang Kaca Wireglass tebal 5 mm Kebutuhan Kaca Wireglass Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A

Satuan m2 Oh Oh Oh Oh

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan m2 Oh Oh Oh Oh

#N/A

#N/A

1 Buah Pasang Kaca Cermin tebal 8 mm Kebutuhan Kaca Cermin Pekerja Tukang kayu Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 Buah Pasang Kaca Cermin tebal 6 mm Kebutuhan Kaca Cermin Pekerja Tukang kayu Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 160 of 209

1 Buah Pasang Kaca Patri tebal 5 mm

Bahan

Tenaga

Kebutuhan Kaca Patri Pekerja Tukang kayu Kepala tukang Mandor

#N/A

Satuan m2 Oh Oh Oh Oh

Indeks 1.100 0.015 0.150 0.015 0.001

Harga Satuan Bahan

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

PT. T.38-2000-C PEKERJAAN PENGECATAN 1 m² Mengikis / Mengerok Permukaan Cat Tembok Lama

Bahan

Tenaga

Kebutuhan Soda Api Pekerja Tukang Cat Kepala tukang Mandor

#N/A

Satuan Kg Oh Oh Oh Oh

Indeks 0.050 0.150

Harga Satuan Bahan

Harga Satuan upah

#N/A

0.003

Bahan

Tenaga

Indeks 0.050 0.150

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Jml Harga Bahan

#N/A #N/A #N/A

0.003

Indeks 0.050 0.150

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

Satuan Kg Oh Oh Oh

#N/A

#N/A #N/A

1 m² Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual Kebutuhan Sabun Pekerja Tukang Cat Kepala tukang

#N/A #N/A #N/A #N/A #N/A

Satuan Kg Oh Oh Oh Oh

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

1 m² Mencuci Bidang Permukaan Tembok yang Pernah dicat Kebutuhan Sabun Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

Tenaga Page 161 of 209

Tenaga

Mandor

Oh

0.003

#N/A

#N/A

1 m² Menyabun Permukaan Tembok Lama

Bahan

Tenaga

Kebutuhan Sabun Pekerja Tukang Cat Kepala tukang Mandor

#N/A

Satuan Kg Oh Oh Oh Oh

Indeks 0.050 0.150

Harga Satuan Bahan

Harga Satuan upah

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

1 m² Mengerok Karat atau Cat Lama Permukaan Baja dgn Pancar Pasir ( Sanblasting ) dgn Tingkat Kebersihan Sa 2½.

Bahan

Tenaga

Kebutuhan Satuan Pasir Silika Kg BBM Ltr Peralatan Kompresor, Blasting Pot , Selang Dan Nozzle Oh Pekerja Tukang Cat Oh Kepala tukang Oh Mandor Oh

Indeks 40.000 10.000

Harga Satuan Bahan

#N/A Harga Satuan upah

Rp Rp

Bahan

Tenaga

Indeks 0.080 0.020 0.010 0.040 0.040 0.004 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A

Bahan

Jml Harga Bahan

#N/A #N/A #N/A #N/A

Indeks 0.150 0.170 0.170 0.070 0.075

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan Kg Kg Kg Oh Oh

#N/A

#N/A #N/A #N/A

1 m² Mengecatan Bidang Kayu Lama Kebutuhan Plamir Cat Dasar Cat Penutup Pekerja Tukang Cat

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

Satuan Kg Kg Kg Oh Oh Oh Oh

#N/A

#N/A #N/A -

#N/A #N/A #N/A #N/A

1 m² Mendempul dan Menggosok Kayu Kebutuhan Dempul Jadi Minyak Cat Batu Apung Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A

1.600 1.600 0.800 0.500

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

0.003

#N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

Tenaga Page 162 of 209

Tenaga

Kepala tukang Mandor

Oh Oh

0.008 0.003

#N/A #N/A

1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup

Bahan

Tenaga

Kebutuhan Cat Meni Plamir Cat Dasar Cat Kayu glotek Pekerja Tukang Cat Kepala tukang Mandor

Satuan Kg Kg Kg Kg Oh Oh Oh Oh

Indeks 0.200 0.150 0.170 0.260 0.070 0.009 0.006 0.003

#N/A Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga

Satuan Kg Kg Kg Kg Oh Oh Oh Oh

Indeks 0.200 0.150 0.170 0.350 0.070 0.105 0.004 0.003

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A #N/A #N/A

Bahan

Tenaga

Indeks 0.360 0.040 0.063 0.063 0.003

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks 0.150 0.372

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A #N/A

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Ltr Ltr

#N/A

#N/A #N/A #N/A #N/A

1 m² Pelaburan Bidang Kayu dengan Pelitur Kebutuhan Pelitur Pelitur Jadi

Jml Harga Bahan

#N/A

Satuan Ltr Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1 m² Pelaburan Bidang Kayu dengan Teak Oil Kebutuhan Teak Oil Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A

1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup Kebutuhan Cat Meni Plamir Cat Dasar Cat Kayu glotek Pekerja Tukang Cat Kepala tukang Mandor

#N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A

Bahan Page 163 of 209

Bahan

Tenaga

Ampelas Pekerja Tukang Cat Kepala tukang Mandor

Lbr Oh Oh Oh Oh

2.000 0.040 0.063 0.063 0.003

#N/A

#N/A

#N/A #N/A #N/A #N/A

1 m² Pelaburan Bidang Kayu dengan Cat Residu dan Ter

Bahan

Tenaga

Kebutuhan Residu atau Ter Pekerja Tukang Cat Kepala tukang Mandor

#N/A

Satuan Ltr Oh Oh Oh Oh

Indeks 0.350 0.100

Harga Satuan Bahan

Harga Satuan upah

#N/A

Bahan

Tenaga

0.006

Indeks 0.150 0.050 0.100 0.010 0.160 0.160 0.016 0.003

Harga Satuan Bahan

Bahan

Tenaga

Satuan Kg Kg Kg Oh Oh Oh Oh

Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Indeks 0.100

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Lbr

#N/A

#N/A #N/A #N/A #N/A

1 m² Melabur Tembok dengan Kapur Sirih Kebutuhan Ampelas

Jml Harga Bahan

#N/A

Indeks 0.100 0.100 0.260 0.020 0.063 0.006 0.003

Jml Harga upah #N/A #N/A #N/A #N/A

#N/A

Satuan Ltr Kg Lbr Bh Oh Oh Oh Oh

#N/A

#N/A

1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) Kebutuhan Plamir Cat Dasar Cat Tembok Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A #N/A #N/A #N/A

1 m² Pelaburan Bidang Kayu dengan Vernis Kebutuhan Vernis Dempul Ampelas Kuas Pekerja Tukang Cat Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Page 164 of 209

Alang - alang Perancah Kayu Kapur Sirih Pekerja Tukang Cat Kepala tukang Mandor

Bahan

Tenaga

ikat m3 Kg Oh Oh Oh Oh

0.250 0.002 0.150 0.150 0.001 0.000 0.003

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

1 m² Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan )

Bahan

Tenaga

Kebutuhan Perancah Kayu Kapur Sirih Pekerja Tukang Cat Kepala tukang Mandor

Satuan m3 Kg Oh Oh Oh Oh

#N/A

Indeks 0.002 0.300 0.040 0.005 0.001 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

#N/A #N/A #N/A #N/A

Satuan m3 Kg Oh Oh Oh Oh

Indeks 1.200 0.200 0.020 0.200 0.002 0.003

Harga Satuan Bahan

Harga Satuan upah

#N/A #N/A

Bahan

Tenaga

Indeks 0.100 0.010 0.020 0.200 0.020 0.010

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Indeks 0.100

Harga Satuan upah

#N/A #N/A

Jml Harga Bahan

#N/A

#N/A Jml Harga upah

#N/A #N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Satuan Kg

#N/A

#N/A #N/A

1 m² Pengecatan Permukaan Baja dengan Meni Besi dan Perancah Kebutuhan Meni Besi

Jml Harga Bahan

#N/A

Satuan Kg Bh Oh Oh Oh Oh

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1 m² Pengecatan Permukaan Baja dengan Meni Besi Kebutuhan Meni Besi Kuas Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A

1 m² Pemasangan Wall Paper Kebutuhan Wall Paper Perekat Pekerja Tukang Cat Kepala tukang Mandor

#N/A #N/A #N/A #N/A

Harga Satuan upah

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

Bahan Page 165 of 209

Bahan

Tenaga

Kuas Perancah Kayu Pekerja Tukang Cat Kepala tukang Mandor

Bh m3 Oh Oh Oh Oh

0.010 0.002 0.250 0.225 0.023 0.008

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 4 Lapis Cat Konvensional, tebal 200 um

Bahan

Tenaga

Kebutuhan Meni ( Read Lead ) A Meni ( Read Lead ) B Alluminium C Alluminium B Pengencer Perancah Kayu Pekerja Tukang Cat Kepala tukang Mandor

Satuan Kg Kg Kg Kg Ltr m3 Oh Oh Oh Oh

Indeks 0.100 0.100 0.040 0.040 0.010 0.002 0.006 0.006 0.023 0.008

Harga Satuan Bahan

#N/A Harga Satuan upah

#N/A #N/A #N/A #N/A #N/A #N/A

Bahan

Tenaga

Satuan Kg Oh Oh Oh Oh

Indeks 0.300 0.006 0.060 0.012 0.006

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Bahan

Tenaga

Satuan Kg Kg Kg Oh Oh Oh Oh

Indeks 0.110 0.170 0.080 0.500 0.800 0.300 0.200

Harga Satuan upah

#N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

Harga Satuan Bahan

Jml Harga upah

#N/A #N/A #N/A #N/A #N/A

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 3 Lapis Cat Konvensional, tebal 200 um Kebutuhan Cat Dasar Cat Antara Cat Penutup Pekerja Tukang Cat Kepala tukang Mandor

Jml Harga Bahan

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 1 Lapis Cat Mutakhir, tebal 200 um Kebutuhan Meni Besi Pekerja Tukang Cat Kepala tukang Mandor

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

Harga Satuan upah

#N/A #N/A #N/A

Jml Harga Bahan

#N/A Jml Harga upah

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot ( Airless Spray ) dgn Sistem 1 Lapis Cat Mutakhir, tebal 200 um

#N/A #N/A #N/A #N/A #N/A

#N/A

Page 166 of 209

Bahan

Tenaga

Kebutuhan Cat Dasar Pekerja Tukang Cat Kepala tukang Mandor

Satuan Kg Oh Oh Oh Oh

Indeks 0.300 0.400 0.700 0.200 0.200

Harga Satuan Bahan

Harga Satuan upah

#N/A

Jml Harga Bahan

Jml Harga upah

#N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

Page 167 of 209

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

-----------------------------------------------------------------------------

ITEM PEKERJAAN

I

ANALISA

VOL

SAT

PEKERJAAN PERSIAPAN

1 2 3 4 5 6 7 8 9 10 11 12 13 14

II

1 2 3 4 5 6 7 8

Pagar Sementara dari Kayu tinggi 2 m

1 m' Pagar Sementara dari Kayu tinggi 2 m

Pagar Sementara dari Seng Gelombang tinggi 2 m

1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m

Pagar Sementara dari Kawat Duri tinggi 1.8 m

1 m' Pagar Sementara dari Kawat Duri tinggi 1.8 m

Pek. Pengukuran & Pemasangan Bowplank

1 m' Pek. Pengukuran & Pemasangan Bowplank

Pek. Kantor Direksi Keet , dengan lantai plesteran

1 m² Pek. Kantor Direksi Keet , dengan lantai plesteran

Pembuatan Gudang Semen dan Alat - alat

1 m² Pembuatan Gudang Semen dan Alat - alat

Pembuatan Rumah Jaga / Konstruksi Kayu

1 m² Pembuatan Rumah Jaga / Konstruksi Kayu

Membersihkan Lapangan dan Perataan

1 m2 Membersihkan Lapangan dan Perataan

Pembuatan Bedeng Buruh

1 m² Pembuatan Bedeng Buruh

Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm

1 m² Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm

Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm

1 m² Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm

Pembuatan Jalan Sementara

1 m² Pembuatan Jalan Sementara

Bongkaran Beton Bertulang

1 m³ Bongkaran Beton Bertulang

Bongkaran Dinding Tembok Bata Merah

1 m³ Bongkaran Dinding Tembok Bata Merah

PEKERJAAN TANAH Menggali tanah biasa sedalam 1 meter Menggali tanah biasa sedalam 2 meter Menggali tanah biasa sedalam 3 meter Menggali tanah keras sedalam 1 meter Menggali tanah cadas sedalam 1 meter Menggali tanah lumpur sedalam 1 meter Mengerjakan stripping tebing setinggi 1 meter Membuang tanah sejauh 30 meter

6.1 Menggali 1 m3 tanah biasa sedalam 1 meter 6.2 Menggali 1 m3 tanah biasa sedalam 2 meter 6.3 Menggali 1 m3 tanah biasa sedalam 3 meter 6.4 Menggali 1 m3 tanah keras sedalam 1 meter 6.5 Menggali 1 m3 tanah cadas sedalam 1 meter 6.6 Menggali 1 m3 tanah lumpur sedalam 1 meter 6.7 Mengerjakan 1 m2 stripping tebing setinggi 1 meter 6.8 Membuang 1 m3 tanah sejauh 30 meter

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m m m m m2 m2 m2 m2 m2 m2 m2 m2 m3 m3

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m3 m3 m3 m3 m3 m3 m2 m3

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

---------------------------------------

ITEM PEKERJAAN Mengurug kembali galian

9 10 11 12 13 14 15 III

1 2 3 4 5 6 7 8 9

Memadatkan tanah (per 20 cm) Mengurug pasir urug Memasang Lapisan pudel campuran 1 KP : 3 PP : 7 TL Memasang Lapisan pudel campuran 1 KP : 5 TL Memasang lapisan ijuk tebal 10 cm Mengurug sirtu padat untuk peninggian lantai bangunan PEKERJAAN PONDASI Memasang pondasi batu belah, campuran 1 PC : 3 PP Memasang pondasi batu belah, campuran 1 PC : 4 PP Memasang pondasi batu belah, campuran 1 PC : 5 PP Memasang pondasi batu belah, campuran 1 PC : 6 PP Memasang pondasi batu belah, campuran 1 PC : 8 PP Memasang pondasi batu belah, campuran 1 KP : 1 SM : 2 PP Memasang pondasi batu belah, campuran 1 PC : 3 KP : 10 PP Memasang pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP Memasang batu kosong (aanstamping) Memasang pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu

10 belah 11 Memasang pondasi sumuran, diameter 100 cm IV

---------------------------------------

PEKERJAAN BETON

1 Pekerjaan beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 2 Pekerjaan beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 3 Pekerjaan beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72

ANALISA

VOL

m3

6.9 Mengurug kembali 1 m3 galian

6.10 Memadatkan 1 m3 tanah (per 20 cm) 6.11 Mengurug 1 m3 pasir urug 6.12 Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL 6.13 Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL 6.14 Memasang 1 m2 lapisan ijuk tebal 10 cm 6.15 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan

6.1 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP 6.2 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP 6.3 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP 6.4 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP 6.5 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 8 PP 6.6 Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP 6.7 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP 6.8 Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP 6.9 Memasang 1 m3 batu kosong (aanstamping)

SAT

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m3 m3 m3 m3 m2 m3

m3 m3 m3 m3 m3 m3 m3 m3 m3

10.00 m3 6.10 Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah 10.00 10.00 10.00 6.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 10.00 6.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78 10.00 6.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 10.00 6.11 Memasang 1 m3 pondasi sumuran, diameter 100 cm

m3

m3 m3 m3

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN

4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

-----------------------------------------------------------------------------

ANALISA

VOL

Pekerjaan lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 Pekerjaan beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 Pekerjaan beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 Pekerjaan beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 Pekerjaan beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 Pekerjaan beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 Pekerjaan beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 Pekerjaan beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49 Pekerjaan beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48 Pekerjaan beton kedap air dengan strorox – 100 Pemasangan PVC Waterstop lebar 150 mm Pemasangan PVC Waterstop lebar 200 mm Pemasangan PVC Waterstop lebar 230 mm – 320 mm Pembesian besi polos atau besi ulir Pekerjaan kabel presstressed polos/strands Pekerjaan jaring kawat baja/wire mesh Pekerjaan bekisting untuk pondasi Pekerjaan bekisting untuk sloof Pekerjaan bekisting untuk kolom Pekerjaan bekisting untuk balok Pekerjaan bekisting untuk lantai Pekerjaan bekisting untuk dinding Pekerjaan bekisting untuk tangga

10.00 6.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87

Pekerjaan jembatan untuk pengecoran beton

6.27 Memasang 1 m2 jembatan untuk pengecoran beton

Pekerjaan pondasi beton bertulang (150 kg besi + bekisting) Pekerjaan sloof beton bertulang (200 kg besi + bekisting)

6.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)

Pekerjaan kolom beton bertulang (300 kg besi + bekisting)

6.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)

6.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 10.00 6.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 10.00 6.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 10.00 6.8 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 10.00 6.9 Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 10.00 6.10 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,5210.00 6.11 Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,4910.00 6.12 Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,4810.00 6.13 Membuat 1 m3 beton kedap air dengan strorox – 100 6.14 Memasang 1 m’ PVC Waterstop lebar 150 mm 6.15 Memasang 1 m’ PVC Waterstop lebar 200 mm 6.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm 6.17 Pembesian 10 kg dengan besi polos atau besi ulir 6.18 Memasang 10 kg kabel presstressed polos/strands 6.19 Memasang 10 kg jaring kawat baja/wire mesh 6.20 Memasang 1 m2 bekisting untuk pondasi 6.21 Memasang 1 m2 bekisting untuk sloof 6.22 Memasang 1 m2 bekisting untuk kolom 6.23 Memasang 1 m2 bekisting untuk balok 6.24 Memasang 1 m2 bekisting untuk lantai 6.25 Memasang 1 m2 bekisting untuk dinding 6.26 Memasang 1 m2 bekisting untuk tangga

6.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

SAT

m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m m m kg kg kg m2 m2 m2 m2 m2 m2 m2 m2 m3 m3 m3

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 31 32 33 34 35 36

V

Pekerjaan balok beton bertulang (200 kg besi + bekisting) Pekerjaan kolom beton bertulang (150 kg besi + bekisting) Pekerjaan dinding beton bertulang (150 kg besi + bekisting) Pekerjaan dinding beton bertulang (200 kg besi + bekisting) Pekerjaan kolom praktis beton bertulang (11 x 11) cm Pekerjaan ring balok beton bertulang (10 x 15) cm

-----------------------------------------------------------------------------

ANALISA 6.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 6.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 6.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) 6.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) 6.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 6.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm

VOL 10.00 10.00 10.00 10.00 10.00 10.00

SAT m3 m3 m3 m3 m m

PEKERJAAN DINIDNG DAN PLESTERAN LANTAI DASAR Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran

1 spesi 1 PC : 2 PP

10.00 6.1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 2 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 2 spesi 1 PC : 3 PP

10.00 6.2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 3 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran

3 spesi 1 PC : 4 PP

10.00 6.3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 4 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 4 spesi 1 PC : 5 PP

10.00 6.4 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 5 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran

5 spesi 1 PC : 6 PP

10.00 6.5 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 6 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 6 spesi 1 PC : 3 KP : 10 PP

10.00 6.6 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 3 KP : 10 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 7 spesi 1 PC : 2 PP

10.00spesi m2 6.7 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 2 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran

8 spesi 1 PC : 3 PP

10.00spesi m2 6.8 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 3 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 9 spesi 1 PC : 4 PP

10.00spesi m2 6.9 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 4 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran

10 spesi 1 PC : 5 PP

10.00 spesim2 6.10 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 5 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 11 spesi 1 PC : 6 PP

10.00 spesim2 6.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 6 PP

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN Pekerjaan dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi

-----------------------------------------------------------------------------

ANALISA

VOL

SAT

12 1 PC : 8 PP

10.00 m2: 8 PP 6.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 1 PC

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 13 spesi 1 PC : 3 KP : 10 PP

10.00 spesim2 6.13 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 3 KP : 10 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran

14 spesi 1 KP : 1 SM : 1 PP

10.00 spesim2 6.14 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 KP : 1 SM : 1 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 15 spesi 1 KP : 1 SM : 2 PP

10.00 spesim2 6.15 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 KP : 1 SM : 2 PP

16 17 18 19 20 21

Pekerjaan dinding Hollow block 20 , campuran spesi 1 PC : 3 PP

6.16 Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 20, cam puran spesi 1 PC : 4 PP

6.17 Memasang 1 m2 dinding HB 20, cam puran spesi 1 PC : 4 PP

Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 3 PP

6.18 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 4 PP

6.19 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP

Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 3 PP

6.20 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 4 PP Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 22 PC : 3 PP Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1

6.21 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP

10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2

10.001 PC :m2 6.22 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 3 PP

23 PC : 4 PP

10.001 PC :m2 6.23 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 4 PP

Pekerjaan dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran 24 spesi 1 PC : 3 PP

10.00 6.24 Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1m2 PC : 3 PP

LANTAI ATAS Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran

1 spesi 1 PC : 2 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 2 spesi 1 PC : 3 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 3 spesi 1 PC : 4 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 4 spesi 1 PC : 5 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran 5 spesi 1 PC : 6 PP

10.00 6.1 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 2 PP 10.00 6.2 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 3 PP 10.00 6.3 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 4 PP 10.00 6.4 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 5 PP 10.00 6.5 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 6 PP

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran

-----------------------------------------------------------------------------

ANALISA

VOL

SAT

6 spesi 1 PC : 3 KP : 10 PP

10.00 6.6 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 m2 PC : 3 KP : 10 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 7 spesi 1 PC : 2 PP

10.00spesi m2 6.7 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 2 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran

8 spesi 1 PC : 3 PP

10.00spesi m2 6.8 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 3 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 9 spesi 1 PC : 4 PP

10.00spesi m2 6.9 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 4 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 10 spesi 1 PC : 5 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 11 spesi 1 PC : 6 PP

10.00 spesim2 6.10 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 5 PP

10.00 spesim2 6.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 6 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 12 1 PC : 8 PP 10.00 m2: 8 PP 6.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2 bata, campuran spesi 1 PC Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 13 spesi 1 PC : 3 KP : 10 PP 10.00 spesim2 6.13 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 PC : 3 KP : 10 PP Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran

14 spesi 1 KP : 1 SM : 1 PP

10.00 spesim2 6.14 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 KP : 1 SM : 1 PP

Pekerjaan dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 15 spesi 1 KP : 1 SM : 2 PP

10.00 spesim2 6.15 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran 1 KP : 1 SM : 2 PP

16 17 18 19 20 21

Pekerjaan dinding Hollow block 20 , campuran spesi 1 PC : 3 PP

6.16 Memasang 1 m2 dinding HB 20 , campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 20, cam puran spesi 1 PC : 4 PP

6.17 Memasang 1 m2 dinding HB 20, cam puran spesi 1 PC : 4 PP

Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 3 PP

6.18 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 15, campuran spesi 1 PC : 4 PP

6.19 Memasang 1 m2 dinding HB 15, campuran spesi 1 PC : 4 PP

Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 3 PP

6.20 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 3 PP

Pekerjaan dinding Hollow block 10, campuran spesi 1 PC : 4 PP

6.21 Memasang 1 m2 dinding HB 10, campuran spesi 1 PC : 4 PP

10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2

Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 22 PC : 3 PP

10.001 PC :m2 6.22 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 3 PP

Pekerjaan dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 23 PC : 4 PP

10.001 PC :m2 6.23 Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 4 PP

Pekerjaan dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran

24 spesi 1 PC : 3 PP

10.00 6.24 Memasang 1 m2 dinding bata berongga ekspose ukuran (5 x 11 x 24) cm, campuran spesi 1m2 PC : 3 PP

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN

VI

-----------------------------------------------------------------------------

ANALISA

VOL

SAT

PEKERJAAN PLESTERAN DAN FINISHING

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

LANTAI DASAR Pekerjaan plesteran 1 PC : 1 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 3 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 4 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 5 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 6 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 7 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 8 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm Pekerjaan plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm Pekerjaan plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 3 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 4 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 5 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 6 PP, tebal 20 mm Pekerjaan plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm Pekerjaan Berapen 1 PC : 5 PP, tebal 15 mm Pekerjaan Plesteran Skoning 1 PC : 2 PP, lebar 10 mm Pekerjaan Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm Pekerjaan Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm Pekerjaan Plesteran Ciprat 1 PC : 2 PP Pekerjaan finishing siar pasangan dinding bata merah (=20 m’) Pekerjaan finishing siar pasangan dinding conblock ekspose (=8 m’)

6.1 Memasang 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm 6.2 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm 6.3 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm 6.4 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm 6.5 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm 6.6 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm 6.7 Memasang 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm 6.8 Memasang 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm 6.9 Memasang 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm 6.10 Memasang 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm 6.11 memasang 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm 6.12 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm 6.13 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm 6.14 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm 6.15 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm 6.16 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm 6.17 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm 6.18 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm 6.19 Memasang 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm 6.20 Memasang 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mm 6.21 Memasang 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm 6.22 Memasang 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm 6.23 Memasang 1 m2 Plesteran Ciprat 1 PC : 2 PP 6.24 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’) 6.25 Memasang 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’)

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m2 m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

-----------------------------------------------------------------------------

ITEM PEKERJAAN 26 Pekerjaan finishing siar pasangan batu kali adukan 1 PC : 2 PP 27 Pekerjaan acian

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

LANTAI ATAS Pekerjaan plesteran 1 PC : 1 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 3 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 4 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 5 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 6 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 7 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 8 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm Pekerjaan plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm Pekerjaan plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm Pekerjaan plesteran 1 PC : 2 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 3 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 4 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 5 PP, tebal 20 mm Pekerjaan plesteran 1 PC : 6 PP, tebal 20 mm Pekerjaan plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm Pekerjaan Berapen 1 PC : 5 PP, tebal 15 mm Pekerjaan Plesteran Skoning 1 PC : 2 PP, lebar 10 mm Pekerjaan Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm Pekerjaan Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm Pekerjaan Plesteran Ciprat 1 PC : 2 PP Pekerjaan finishing siar pasangan dinding bata merah (=20 m’)

ANALISA 6.26 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP 6.27 Memasang 1 m2 acian

6.1 Memasang 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm 6.2 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm 6.3 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm 6.4 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm 6.5 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm 6.6 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm 6.7 Memasang 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm 6.8 Memasang 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm 6.9 Memasang 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm 6.10 Memasang 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm 6.11 memasang 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm 6.12 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm 6.13 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm 6.14 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm 6.15 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm 6.16 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm 6.17 Memasang 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm 6.18 Memasang 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm 6.19 Memasang 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm 6.20 Memasang 1 m’ Plesteran Skoning 1 PC : 2 PP, lebar 10 mm 6.21 Memasang 1 m2 Plesteran Granit , 1 PC : 2 Granit, tebal 10 mm 6.22 Memasang 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm 6.23 Memasang 1 m2 Plesteran Ciprat 1 PC : 2 PP 6.24 Memasang 1 m2 finishing siar pasangan dinding bata merah (=20 m’)

VOL

SAT

10.00 10.00

m2 m2

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

-----------------------------------------------------------------------------

ITEM PEKERJAAN 25 Pekerjaan finishing siar pasangan dinding conblock ekspose (=8 m’) 26 Pekerjaan finishing siar pasangan batu kali adukan 1 PC : 2 PP 27 Pekerjaan acian

VII 1 2 3 4 5 6 7

PEKERJAAN KAYU kusen pintu dan kusen jendela, kayu kelas I kusen pintu dan kusen jendela, kayu kelas II atau III pintu klamp standar, kayu kelas II pintu klamp sederhana, kayu kelas III daun pintu panel, kayu kelas I atau II pintu dan jendela kaca, kayu kelas I atau II pintu dan jendela jalusi kayu kelas I atau II

8 9 10 11 12

daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar sampai 90 cm) pintu plywood rangkap, rangka expose kayu kelas I atau II jalusi kusen, kayu kelas I atau II teakwood rangkap, rangka expose kayu kelas I teakwood rangkap lapis formika, rangka expose kayu kelas II

13 14 15 16 17 18 19 20 21 22 23

konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter konstruksi kuda-kuda expose, kayu kelas I konstruksi gordeng, kayu kelas II rangka atap genteng keramik, kayu kelas II rangka atap genteng beton, kayu kelas II rangka atap sirap, kayu kelas II rangka langit-langit (50 x 100) cm, kayu kelas II atau III rangka langit-langit (60 x 60) cm, kayu kelas II atau III lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II rangka dinding pemisah (60 x 120) cm kayu kelas II atau III

ANALISA

VOL

SAT

10.00 10.00 10.00

m2 m2 m2

10.00 6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I 6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau 10.00 III

m3 m3 m2 m2 m2 m2 m2

6.25 Memasang 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m’) 6.26 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP 6.27 Memasang 1 m2 acian

6.3 Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II 6.4 Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas III 6.5 Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I atau II 6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II 6.7 Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II

10.00 10.00 10.00 10.00 10.00

10.00 6.8 Membuat 1 m2 daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kelas II (lebar m2 sampai 90 cm) 6.9 Membuat 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II 6.10 Memasang 1 m2 jalusi kusen, kayu kelas I atau II 6.11 Memasang 1 m2 teakwood rangkap, rangka expose kayu kelas I 6.12 Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II

10.00 10.00 10.00 10.00

m2 m2 m2 m2

10.00 6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meterm3 6.14 Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I 6.15 Memasang 1 m3 konstruksi gordeng, kayu kelas II 6.16 Memasang 1 m2 rangka atap genteng keramik, kayu kelas II 6.17 Memasang 1 m2 rangka atap genteng beton, kayu kelas II 6.18 Memasang 1 m2 rangka atap sirap, kayu kelas II 6.19 Memasang 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III 6.20 Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 6.21 Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 6.22 Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II 6.23 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m3 m3 m2 m2 m2 m2 m2 m1 m1 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

-----------------------------------------------------------------------------

ITEM PEKERJAAN 24 25 26 27 28

dinding pemisah teakwood rangkap, rangka kayu kelas II dinding pemisah plywood rangkap, rangka kayu kelas II dinding lambriziring dari papan kayu kelas I dinding lambriziring dari plywood ukuran (120 x 240) cm dinding bilik, rangka kayu kelas III atau IV

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

PEKERJAAN KUNCI DAN KACA Pekerjaan kunci Tanam Antik Pekerjaan kunci Tanam Biasa Pekerjaan kunci Tanam Kamar Mandi Pekerjaan kunci Silinder Pekerjaan Engsel Pintu Pekerjaan Engsel Jendela Kupu - kupu Pekerjaan Engsel Angin Pekerjaan Spring Knip Pekerjaan Kait angin Pekerjaan Door Closer Pekerjaan Kunci Selot Pekerjaan Pegangan Pintu / Door Holder Pekerjaan Door Stop Pekerjaan Rel Pintu Dorong Pekerjaan Kunci Lemari Pekerjaan Kaca tebal 3 mm Pekerjaan Kaca tebal 5 mm Pekerjaan Kaca tebal 8 mm Pekerjaan Kaca Buram tebal 12 mm Pekerjaan Kaca Cermin tebal 5 mm Pekerjaan Kaca Cermin tebal 6 mm Pekerjaan Kaca Cermin tebal 8 mm Pekerjaan Kaca Wireglass tebal 5 mm

VIII

ANALISA 6.24 Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II 6.25 Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II 6.26 Memasang 1 m2 dinding lambriziring dari papan kayu kelas I 6.27 Memasang 1 m2 dinding lambriziring dari plywood ukuran (120 x 240) cm 6.28 Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV

1 Buah Pasang kunci Tanam Antik 1 Buah Pasang kunci Tanam Biasa 1 Buah Pasang kunci Tanam Kamar Mandi 1 Buah Pasang kunci Silinder 1 Buah Pasang Engsel Pintu 1 Buah Pasang Engsel Jendela Kupu - kupu 1 Buah Pasang Engsel Angin 1 Buah Pasang Spring Knip 1 Buah Pasang Kait angin 1 Buah Pasang Door Closer 1 Buah Pasang Kunci Selot 1 Buah Pasang Pegangan Pintu / Door Holder 1 Buah Pasang Door Stop 1 Buah Pasang Rel Pintu Dorong 1 Buah Pasang Kunci Lemari 1 Buah Pasang Kaca tebal 3 mm 1 Buah Pasang Kaca tebal 5 mm 1 Buah Pasang Kaca tebal 8 mm 1 Buah Pasang Kaca Buram tebal 12 mm 1 Buah Pasang Kaca Cermin tebal 5 mm 1 Buah Pasang Kaca Cermin tebal 6 mm 1 Buah Pasang Kaca Cermin tebal 8 mm 1 Buah Pasang Kaca Wireglass tebal 5 mm

VOL 10.00 10.00 10.00 10.00 10.00

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

SAT m2 m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 24 Pekerjaan Kaca Patri tebal 5 mm

IX

-----------------------------------------------------------------------------

ANALISA

VOL

1 Buah Pasang Kaca Patri tebal 5 mm

10.00

6.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm 6.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

SAT

PEKERJAAN PENUTUP LANTAI DAN DINDIG

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

LANTAI DASAR Pekerjaan lantai ubin PC abu-abu ukuran (40 x 40) cm Pekerjaan lantai ubin PC abu-abu ukuran (30 x 30) cm Pekerjaan lantai ubin PC abu-abu ukuran (20 x 20) cm Pekerjaan lantai ubin warna ukuran (40 x 40) cm Pekerjaan lantai ubin warna ukuran (30 x 30) cm Pekerjaan lantai ubin warna ukuran (20 x 20) cm Pekerjaan lantai ubin teraso ukuran (40 x 40) cm Pekerjaan lantai ubin teraso ukuran (30 x 30) cm Pekerjaan lantai ubin granit ukuran (40 x 40) cm Pekerjaan lantai ubin granit ukuran (30 x 30) cm Pekerjaan lantai ubin teralux ukuran (40 x 40) cm Pekerjaan lantai ubin teralux ukuran (30 x 30) cm Pekerjaan lantai ubin teralux marmer ukuran (60 x 60) cm Pekerjaan lantai ubin teralux marmer ukuran (40 x 40) cm Pekerjaan lantai ubin teralux marmer ukuran (30 x 30) cm Pekerjaan plint ubin PC abu-abu ukuran (15 x 20) cm Pekerjaan plint ubin PC abu-abu ukuran (10 x 30) cm Pekerjaan plint ubin PC abu-abu ukuran (10 x 40) cm Pekerjaan plint ubin PC warna ukuran (10 x 20) cm Pekerjaan plint ubin PC warna ukuran (10 x 30) cm Pekerjaan plint ubin PC warna ukuran (10 x 40) cm Pekerjaan plint ubin teraso ukuran (10 x 30) cm Pekerjaan plint ubin teraso ukuran (10 x 40) cm Pekerjaan plint ubin granit ukuran (10 x 40) cm Pekerjaan plint ubin granit ukuran (10 x 30) cm

6.3 Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm 6.4 Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm 6.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm 6.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm 6.7 Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm 6.8 Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm 6.9 Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm 6.10 Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm 6.11 Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm 6.12 Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm 6.13 Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm 6.14 Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm 6.15 Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm 6.16 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm 6.17 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm 6.18 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm 6.19 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm 6.20 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm 6.21 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm 6.22 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm 6.23 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm 6.24 Memasang 1 m plint ubin granit ukuran (10 x 40) cm 6.25 Memasang 1 m plint ubin granit ukuran (10 x 30) cm

m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m m m m m m

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55

Pekerjaan plint ubin teralux kerang ukuran (10 x 40) cm Pekerjaan plint ubin teralux kerang ukuran (10 x 30) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 60) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 40) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 30) cm Pekerjaan lantai teraso cor ditempat, tebal 3 cm Pekerjaan lantai keramik artistik ukuran (10 x 20) cm Pekerjaan lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm Pekerjaan lantai keramik ukuran (33 x 33) cm Pekerjaan lantai keramik ukuran (30 x 30) cm Pekerjaan lantai keramik ukuran (20 x 20) cm Pekerjaan lantai keramik ukuran (10 x 33) cm, variasi/border Pekerjaan lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP Pekerjaan plint keramik ukuran (10 x 20) cm Pekerjaan plint keramik ukuran (10 x 10) cm Pekerjaan plint keramik ukuran (5 x 20) cm Pekerjaan plint internal cove artistik ukuran (5 x 5 x 20) cm Pekerjaan lantai marmer ukuran (100 x 100) cm Pekerjaan lantai karpet Pekerjaan underlayer Pekerjaan lantai parquet Pekerjaan lantai kayu (gym floor) Pekerjaan dinding porselen ukuran (11 x 11) cm Pekerjaan dinding porselin ukuran (10 x 20) cm Pekerjaan dinding porselin ukuran (20 x 20) cm Pekerjaan dinding keramik artistik ukuran (10 x 20) cm Pekerjaan dinding keramik artistik ukuran (5 x 20) cm Pekerjaan dinding keramik ukuran (10 x 20) cm Pekerjaan dinding keramik ukuran (20 x 20) cm Pekerjaan dinding marmer ukuran (100 x 100) cm

-----------------------------------------------------------------------------

ANALISA

VOL

10.00 10.00 10.00 6.28 Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm 10.00 6.29 Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm 10.00 6.30 Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm 10.00 6.31 Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm 10.00 6.32 Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm 10.00 6.33 Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm 10.00 6.34 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm 10.00 6.35 Memasang 1 m2 lantai keramik ukuran (30 x 30) cm 10.00 6.36 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm 10.00 6.37 Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border 6.38 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP10.00 10.00 6.39 Memasang 1 m’ plint keramik ukuran (10 x 20) cm 10.00 6.40 Memasang 1 m’ plint keramik ukuran (10 x 10) cm 10.00 6.41 Memasang 1 m’ plint keramik ukuran (5 x 20) cm 10.00 6.42 Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm 10.00 6.43 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm 10.00 6.44 Memasang 1 m2 lantai karpet 10.00 6.45 Memasang 1 m2 underlayer 10.00 6.46 Memasang 1 m2 lantai parquet 10.00 6.47 Memasang 1 m2 lantai kayu (gym floor) 10.00 6.48 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm 10.00 6.49 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm 10.00 6.50 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm 10.00 6.51 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm 10.00 6.52 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm 10.00 6.53 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm 10.00 6.54 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm 10.00 6.55 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm 6.26 Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm 6.27 Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm

SAT m m m m m m2 m2 m2 m2 m2 m2 m2 m2 m m m m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 56 57 58 59 60 61 62 63

Pekerjaan dinding bata pelapis ukuran (3 x 7 x 24) cm Pekerjaan dinding batu paras Pekerjaan dinding batu tempel hitam Pekerjaan lantai vinyl ukuran (30 x 30) cm KL I Pekerjaan wall paper, lebar 50 cm Pekerjaan floor hardener Pekerjaan plint vinyil karet ukuran (30 x 30) cm dengan perekat Pekerjaan plint kayu kelas II ukuran (2 x 10) cm

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

LANTAI ATAS Pekerjaan lantai ubin PC abu-abu ukuran (40 x 40) cm Pekerjaan lantai ubin PC abu-abu ukuran (30 x 30) cm Pekerjaan lantai ubin PC abu-abu ukuran (20 x 20) cm Pekerjaan lantai ubin warna ukuran (40 x 40) cm Pekerjaan lantai ubin warna ukuran (30 x 30) cm Pekerjaan lantai ubin warna ukuran (20 x 20) cm Pekerjaan lantai ubin teraso ukuran (40 x 40) cm Pekerjaan lantai ubin teraso ukuran (30 x 30) cm Pekerjaan lantai ubin granit ukuran (40 x 40) cm Pekerjaan lantai ubin granit ukuran (30 x 30) cm Pekerjaan lantai ubin teralux ukuran (40 x 40) cm Pekerjaan lantai ubin teralux ukuran (30 x 30) cm Pekerjaan lantai ubin teralux marmer ukuran (60 x 60) cm Pekerjaan lantai ubin teralux marmer ukuran (40 x 40) cm Pekerjaan lantai ubin teralux marmer ukuran (30 x 30) cm Pekerjaan plint ubin PC abu-abu ukuran (15 x 20) cm Pekerjaan plint ubin PC abu-abu ukuran (10 x 30) cm Pekerjaan plint ubin PC abu-abu ukuran (10 x 40) cm Pekerjaan plint ubin PC warna ukuran (10 x 20) cm Pekerjaan plint ubin PC warna ukuran (10 x 30) cm

-----------------------------------------------------------------------------

ANALISA 6.56 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm 6.57 Memasang 1 m2 dinding batu paras 6.58 Memasang 1 m2 dinding batu tempel hitam 6.59 Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I 6.60 Memasang 1 m2 wall paper, lebar 50 cm 6.61 Memasang 1 m2 floor hardener 6.62 Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat 6.63 Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm

6.1 Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm 6.2 Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm 6.3 Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm 6.4 Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm 6.5 Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm 6.6 Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm 6.7 Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm 6.8 Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm 6.9 Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm 6.10 Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm 6.11 Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm 6.12 Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm 6.13 Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm 6.14 Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm 6.15 Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm 6.16 Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm 6.17 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm 6.18 Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm 6.19 Memasang 1 m plint ubin PC warna ukuran (10 x 20) cm 6.20 Memasang 1 m plint ubin PC warna ukuran (10 x 30) cm

VOL

SAT

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2 m m

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Pekerjaan plint ubin PC warna ukuran (10 x 40) cm Pekerjaan plint ubin teraso ukuran (10 x 30) cm Pekerjaan plint ubin teraso ukuran (10 x 40) cm Pekerjaan plint ubin granit ukuran (10 x 40) cm Pekerjaan plint ubin granit ukuran (10 x 30) cm Pekerjaan plint ubin teralux kerang ukuran (10 x 40) cm Pekerjaan plint ubin teralux kerang ukuran (10 x 30) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 60) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 40) cm Pekerjaan plint ubin teralux marmer ukuran (10 x 30) cm Pekerjaan lantai teraso cor ditempat, tebal 3 cm Pekerjaan lantai keramik artistik ukuran (10 x 20) cm Pekerjaan lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm Pekerjaan lantai keramik ukuran (33 x 33) cm Pekerjaan lantai keramik ukuran (30 x 30) cm Pekerjaan lantai keramik ukuran (20 x 20) cm Pekerjaan lantai keramik ukuran (10 x 33) cm, variasi/border Pekerjaan lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP Pekerjaan plint keramik ukuran (10 x 20) cm Pekerjaan plint keramik ukuran (10 x 10) cm Pekerjaan plint keramik ukuran (5 x 20) cm Pekerjaan plint internal cove artistik ukuran (5 x 5 x 20) cm Pekerjaan lantai marmer ukuran (100 x 100) cm Pekerjaan lantai karpet Pekerjaan underlayer Pekerjaan lantai parquet Pekerjaan lantai kayu (gym floor) Pekerjaan dinding porselen ukuran (11 x 11) cm Pekerjaan dinding porselin ukuran (10 x 20) cm Pekerjaan dinding porselin ukuran (20 x 20) cm

-----------------------------------------------------------------------------

ANALISA

VOL

10.00 10.00 10.00 6.23 Memasang 1 m plint ubin teraso ukuran (10 x 40) cm 10.00 6.24 Memasang 1 m plint ubin granit ukuran (10 x 40) cm 10.00 6.25 Memasang 1 m plint ubin granit ukuran (10 x 30) cm 10.00 6.26 Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm 10.00 6.27 Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm 10.00 6.28 Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm 10.00 6.29 Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm 10.00 6.30 Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm 10.00 6.31 Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm 10.00 6.32 Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm 10.00 6.33 Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm 10.00 6.34 Memasang 1 m2 lantai keramik ukuran (33 x 33) cm 10.00 6.35 Memasang 1 m2 lantai keramik ukuran (30 x 30) cm 10.00 6.36 Memasang 1 m2 lantai keramik ukuran (20 x 20) cm 10.00 6.37 Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border 6.38 Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP10.00 10.00 6.39 Memasang 1 m’ plint keramik ukuran (10 x 20) cm 10.00 6.40 Memasang 1 m’ plint keramik ukuran (10 x 10) cm 10.00 6.41 Memasang 1 m’ plint keramik ukuran (5 x 20) cm 10.00 6.42 Memasang 1 m’ plint internal cove artistik ukuran (5 x 5 x 20) cm 10.00 6.43 Memasang 1 m2 lantai marmer ukuran (100 x 100) cm 10.00 6.44 Memasang 1 m2 lantai karpet 10.00 6.45 Memasang 1 m2 underlayer 10.00 6.46 Memasang 1 m2 lantai parquet 10.00 6.47 Memasang 1 m2 lantai kayu (gym floor) 10.00 6.48 Memasang 1 m2 dinding porselen ukuran (11 x 11) cm 10.00 6.49 Memasang 1 m2 dinding porselin ukuran (10 x 20) cm 10.00 6.50 Memasang 1 m2 dinding porselin ukuran (20 x 20) cm 6.21 Memasang 1 m plint ubin PC warna ukuran (10 x 40) cm 6.22 Memasang 1 m plint ubin teraso ukuran (10 x 30) cm

SAT m m m m m m m m m m m2 m2 m2 m2 m2 m2 m2 m2 m m m m m2 m2 m2 m2 m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 51 52 53 54 55 56 57 58 59 60 61 62 63

X

Pekerjaan dinding keramik artistik ukuran (10 x 20) cm Pekerjaan dinding keramik artistik ukuran (5 x 20) cm Pekerjaan dinding keramik ukuran (10 x 20) cm Pekerjaan dinding keramik ukuran (20 x 20) cm Pekerjaan dinding marmer ukuran (100 x 100) cm Pekerjaan dinding bata pelapis ukuran (3 x 7 x 24) cm Pekerjaan dinding batu paras Pekerjaan dinding batu tempel hitam Pekerjaan lantai vinyl ukuran (30 x 30) cm KL I Pekerjaan wall paper, lebar 50 cm Pekerjaan floor hardener Pekerjaan plint vinyil karet ukuran (30 x 30) cm dengan perekat Pekerjaan plint kayu kelas II ukuran (2 x 10) cm

-----------------------------------------------------------------------------

ANALISA 6.51 Memasang 1 m2 dinding keramik artistik ukuran (10 x 20) cm 6.52 Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm 6.53 Memasang 1 m2 dinding keramik ukuran (10 x 20) cm 6.54 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm 6.55 Memasang 1 m2 dinding marmer ukuran (100 x 100) cm 6.56 Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm 6.57 Memasang 1 m2 dinding batu paras 6.58 Memasang 1 m2 dinding batu tempel hitam 6.59 Memasang 1 m2 lantai vinyl ukuran (30 x 30) cm KL I 6.60 Memasang 1 m2 wall paper, lebar 50 cm 6.61 Memasang 1 m2 floor hardener 6.62 Memasang 1 m plint vinyil karet ukuran (30 x 30) cm dengan perekat 6.63 Memasang 1 m plint kayu kelas II ukuran (2 x 10) cm

VOL

SAT

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m

10.00 10.00 10.00 10.00

m2 m2 m2 m2

PEKERJAAN PLAFOND

1 2 3 4

LANTAI DASAR Pekerjaan langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm Pekerjaan langit-langit akustik ukuran (30 x 30) cm Pekerjaan langit-langit akustik ukuran (30 x 60) cm Pekerjaan langit-langit akustik ukuran (60 x 120) cm

6.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 6.2 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm 6.3 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm 6.4 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm

5 Pekerjaan langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm 6.5 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 10.00 6 mm 6 Pekerjaan langit-langit lambriziring kayu, tebal 9 mm 10.00 6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm

m2 m2

7 Pekerjaan langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 8 Pekerjaan langit-langit akustik ukuran (60 x 120) cm + rangka alluminium 9 Pekerjaan list langit-langit kayu profil

m2 m2 m

LANTAI ATAS

6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 10.00 6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium 6.9 Memasang 1 m’ list langit-langit kayu profil

10.00 10.00 10.00

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 1 2 3 4

Pekerjaan langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm Pekerjaan langit-langit akustik ukuran (30 x 30) cm Pekerjaan langit-langit akustik ukuran (30 x 60) cm Pekerjaan langit-langit akustik ukuran (60 x 120) cm

-----------------------------------------------------------------------------

ANALISA 6.1 Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 6.2 Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm 6.3 Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm 6.4 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm

VOL 10.00 10.00 10.00 10.00

SAT m2 m2 m2 m2

5 Pekerjaan langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 6 mm 6.5 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm dan 10.00 6 mm 6 Pekerjaan langit-langit lambriziring kayu, tebal 9 mm 10.00 6.6 Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm

m2 m2

7 Pekerjaan langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 8 Pekerjaan langit-langit akustik ukuran (60 x 120) cm + rangka alluminium 9 Pekerjaan list langit-langit kayu profil

m2 m2 m

XI 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

PEKERJAAN BESI DAN ALUMUNIUM Pekerjaan besi profil Pekerjaan rangka kuda-kuda baja IWF pekerjaan perakitan Pekerjaan pintu besi plat baja tebal 2 mm rangkap, rangka baja siku Pekerjaan pengelasan dengan las listrik Pekerjaan rangka jendela besi scuare tube (25 x 5) cm Pekerjaan pintu rolling door besi Pekerjaan pintu lipat (Folding door) Pekerjaan sunscreen alluminium Pekerjaan rolling door alluminium Pekerjaan kusen pintu alluminium Pekerjaan pintu alluminium strip lebar 8 cm Pekerjaan pintu kaca rangka alluminium Pekerjaan venetions blinds dan Vertical blinds Pekerjaan terali besi strip (2 x 3) mm Pekerjaan kawat nyamuk Pekerjaan jendela nako & tralis

6.7 Memasang 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 10.00 6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium 6.9 Memasang 1 m’ list langit-langit kayu profil

6.1 Memasang 1 kg besi profil 6.2 Memasang 1 kg rangka kuda-kuda baja IWF 6.3 Mengerjakan 100 kg pekerjaan perakitan 6.4 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 6.5 Mengerjakan 10 cm pengelasan dengan las listrik 6.6 Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm 6.7 Memasang 1 m2 pintu rolling door besi 6.8 Memasang 1 m2 pintu lipat (Folding door) 6.9 Memasang 1 m2 sunscreen alluminium 6.10 Memasang 1 m2 rolling door alluminium 6.11 Memasang 1 m kusen pintu alluminium 6.12 Memasang 1 m2 pintu alluminium strip lebar 8 cm 6.13 Memasang 1 m2 pintu kaca rangka alluminium 6.14 Memasang 1 m2 venetions blinds dan Vertical blinds 6.15 Memasang 1 m2 terali besi strip (2 x 3) mm 6.16 Memasang 1 m2 kawat nyamuk 6.17 Memasang 1 m2 jendela nako & tralis

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

kg kg kg m2 cm m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 18 Pekerjaan talang datar/ jurai seng bjls 28 lebar 90 cm 19 Pekerjaan talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm

XII 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

PEKERJAAN PENUTUP ATAP Pekerjaan Atap Genteng Palentong Kecil Pekerjaan Atap Genteng Kodok / Glazzur Pekerjaan Atap Genteng Palentong Super / Besar Pekerjaan Genteng Bubung Palentong Pekerjaan Genteng Bubung Kodok Glazzur Pekerjaan Genteng Bubung Palentong Besar Pekerjaan Rooflight Fiberglass ( 180 x 90 ) cm Pekerjaan Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm Pekerjaan Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm Pekerjaan Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm Pekerjaan Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm Pekerjaan Asbes Gelombang ( 300 x 1.05 m ) X 4mm Pekerjaan Asbes Gelombang ( 270 x 1.05 m ) X 4mm Pekerjaan Asbes Gelombang ( 240 x 1.05 m ) X 4mm Pekerjaan Asbes Gelombang ( 210 x 1.05 m ) X 4mm Pekerjaan Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm Pekerjaan Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm Pekerjaan Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm Pekerjaan Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm Pekerjaan Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm Pekerjaan Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm Pekerjaan Bubung Stel Gelombang 0.92m Pekerjaan Nok Stel Gelombang 0.92m Pekerjaan Nok Stel Gelombang 1.05m Pekerjaan Nok Stel Gelombang 1.08m Pekerjaan Nok Paten 0.92m

-----------------------------------------------------------------------------

ANALISA

VOL

6.18 Memasang 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 6.19 Memasang 1 m’ talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm

10.00 10.00

1m² Pasang Atap Genteng Palentong Kecil

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

1m² Pasang Atap Genteng Kodok / Glazzur 1m² Pasang Atap Genteng Palentong Super / Besar 1m' Pasang Genteng Bubung Palentong 1m' Pasang Genteng Bubung Kodok Glazzur 1m' Pasang Genteng Bubung Palentong Besar 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm 1m' Pasang Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm 1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm 1m² Pasang Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 240 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm 1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm 1m' Pasang Bubung Stel Gelombang 0.92m 1m' Pasang Nok Stel Gelombang 0.92m 1m' Pasang Nok Stel Gelombang 1.05m 1m' Pasang Nok Stel Gelombang 1.08m 1m' Pasang Nok Paten 0.92m

SAT m m

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

-----------------------------------------------------------------------------

ITEM PEKERJAAN 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44

Pekerjaan Nok Paten 1.05m Pekerjaan Nok Paten 1.08m Pekerjaan Nok Stel rata 0.92m Pekerjaan Nok Stel rata 1.05m Pekerjaan Atap Genteng Beton Pekerjaan Atap Genteng Aspal Pekerjaan Atap Genteng Metal Pekerjaan Atap Sirap Pekerjaan Nok Genteng Beton Pekerjaan Nok Genteng Aspal Pekerjaan Nok Genteng Metal Pekerjaan Nok Genteng Metal Pekerjaan Nok Sirap Pekerjaan tap Seng Gelombang Pekerjaan Atap Nok Seng Pekerjaan Atap Alluminium Pekerjaan Nok Alluminium Pekerjaan Alluminium Foil / Sisalation

1 2 3 4 5 6 7 8 9 10

PEKERJAAN SANITASI Pekerjaan Kloset Duduk / Monoblok Pekerjaan Kloset Jongkok Porselen Pekerjaan Kloset Jongkok Teraso Pekerjaan Urinoir Pekerjaan buah Wastafel Pekerjaan Bak Mandi Teraso, volume 0.30 m³ Pekerjaan Bak Mandi Fiberglass, volume 0.30 m³ Pekerjaan Bak Mandi Batu bata, volume 0.30 m³ Pekerjaan Badkip Porselen Pekerjaan Bak Fiberglass volume 1 m³ air

XIII

ANALISA 1m' Pasang Nok Paten 1.05m 1m' Pasang Nok Paten 1.08m 1m' Pasang Nok Stel rata 0.92m 1m' Pasang Nok Stel rata 1.05m 1m² Pasang Atap Genteng Beton 1m² Pasang Atap Genteng Aspal 1m² Pasang Atap Genteng Metal 1m² Pasang Atap Sirap 1m' Pasang Nok Genteng Beton 1m' Pasang Nok Genteng Aspal 1m' Pasang Nok Genteng Metal 1m' Pasang Nok Genteng Metal 1m' Pasang Nok Sirap 1m² Pasang Atap Seng Gelombang 1m² Pasang Atap Nok Seng 1m² Pasang Atap Alluminium 1m² Pasang Nok Alluminium 1m² Pasang Alluminium Foil / Sisalation

Memasang 1 buah Kloset Duduk / Monoblok Memasang 1 buah Kloset Jongkok Porselen Memasang 1 buah Kloset Jongkok Teraso Memasang 1 buah Urinoir Memasang 1 buah Wastafel Memasang 1 buah Bak Mandi Teraso, volume 0.30 m³ Memasang 1 buah Bak Mandi Fiberglass, volume 0.30 m³ Memasang 1 buah Bak Mandi Batu bata, volume 0.30 m³ Memasang 1 buah Badkip Porselen Memasang 1 buah Bak Fiberglass volume 1 m³ air

VOL 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

SAT

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

XIV

Pekerjaan Penyalur Air limbah jenis Pipa Tanah Ø15 cm Pekerjaan Penyalur Air limbah jenis Pipa Tanah Ø 20 cm Pekerjaan Pipa Beton Ø 5 cm - 20 cm Pekerjaan Pipa Beton Ø 30 cm - 100 cm Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm Pekerjaan Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm Pekerjaan Pipa Galvanis Ø ½" Pekerjaan Pipa Galvanis Ø ¾" Pekerjaan Pipa Galvanis Ø 1" Pekerjaan Pipa Galvanis Ø 1½" Pekerjaan Pipa Galvanis Ø 3" Pekerjaan Pipa Galvanis Ø 4" Pekerjaan Pipa PVC tipe AW Ø ½" Pekerjaan Pipa PVC tipe AW Ø ¾" Pekerjaan Pipa PVC tipe AW Ø 1" Pekerjaan Pipa PVC tipe AW Ø 1½" Pekerjaan Pipa PVC tipe AW Ø 2" Pekerjaan Pipa PVC tipe AW Ø 2½" Pekerjaan Pipa PVC tipe AW Ø 3" Pekerjaan Pipa PVC tipe AW Ø 4" Pekerjaan Bak Cuci Piring Stainles Steel Pekerjaan Bak Cuci Piring Teraso Pekerjaan Kran Ø ¾" atau ½" Pekerjaan Floor Drain

PEKERJAAN PENGECATAN 1 Pekerjaan Mengikis / Mengerok Permukaan Cat Tembok Lama 2 Pekerjaan Mencuci Bidang Permukaan Tembok yang Pernah dicat 3 Pekerjaan Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual

-----------------------------------------------------------------------------

ANALISA

VOL

10.00 10.00 10.00 Memasang 1 m' Pipa Beton Ø 5 cm - 20 cm 10.00 Memasang 1 m' Pipa Beton Ø 30 cm - 100 cm Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (30 x 30 )cm, t = 35cm 10.00 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (45 x 45 )cm, t = 50cm 10.00 Memasang 1 m' buah Bak Kontrol pasangan Batu Bata ukuran (60 x 60 )cm, t = 65cm 10.00 10.00 Memasang 1 m' Pipa Galvanis Ø ½" 10.00 Memasang 1 m' Pipa Galvanis Ø ¾" 10.00 Memasang 1 m' Pipa Galvanis Ø 1" 10.00 Memasang 1 m' Pipa Galvanis Ø 1½" 10.00 Memasang 1 m' Pipa Galvanis Ø 3" 10.00 Memasang 1 m' Pipa Galvanis Ø 4" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø ½" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø ¾" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 1" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 1½" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 2" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 2½" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 3" 10.00 Memasang 1 m' Pipa PVC tipe AW Ø 4" 10.00 Memasang 1 bh Bak Cuci Piring Stainles Steel 10.00 Memasang 1 bh Bak Cuci Piring Teraso 10.00 Memasang 1 bh Kran Ø ¾" atau ½" 10.00 Memasang 1 bh Floor Drain Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø15 cm Memasang 1 m' Pipa Penyalur Air limbah jenis Pipa Tanah Ø 20 cm

1 m² Mengikis / Mengerok Permukaan Cat Tembok Lama 1 m² Mencuci Bidang Permukaan Tembok yang Pernah dicat 1 m² Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual

10.00 10.00 10.00

SAT

RENCANA ANGGARAN BIAYA PEKERJAAN : PROYEK : NO

ITEM PEKERJAAN 4 Pekerjaan Menyabun Permukaan Tembok Lama Pekerjaan Mengerok Karat atau Cat Lama Permukaan Baja dgn Pancar Pasir 5 ( Sanblasting ) dgn Tingkat Kebersihan Sa 2½. 6 Pekerjaan Mendempul dan Menggosok Kayu 7 Pekerjaan Mengecatan Bidang Kayu Lama Pekerjaan Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 8 Lapis Cat Penutup Pekerjaan Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup Pekerjaan Pelaburan Bidang Kayu dengan Teak Oil Pekerjaan Pelaburan Bidang Kayu dengan Pelitur Pekerjaan Pelaburan Bidang Kayu dengan Cat Residu dan Ter Pekerjaan Pelaburan Bidang Kayu dengan Vernis Pekerjaan Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat 14 Penutup ) 15 Pekerjaan Melabur Tembok dengan Kapur Sirih Pekerjaan Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan ) 16 9 10 11 12 13

17 Pekerjaan Pemasangan Wall Paper 18 Pekerjaan Pengecatan Permukaan Baja dengan Meni Besi 19 Pekerjaan Pengecatan Permukaan Baja dengan Meni Besi dan Perancah Pekerjaan Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 20 4 Lapis Cat Konvensional, tebal 200 um

-----------------------------------------------------------------------------

ANALISA 1 m² Menyabun Permukaan Tembok Lama

VOL

SAT

10.00

1 m² Mengerok Karat atau Cat Lama Permukaan Baja dgn Pancar Pasir ( Sanblasting 10.00 ) dgn Tingkat Kebersihan Sa 2½ 1 m² Mendempul dan Menggosok Kayu 1 m² Mengecatan Bidang Kayu Lama

10.00 10.00

1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat 10.00 Penutup 1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat 10.00 Penutup 1 m² Pelaburan Bidang Kayu dengan Teak Oil 1 m² Pelaburan Bidang Kayu dengan Pelitur 1 m² Pelaburan Bidang Kayu dengan Cat Residu dan Ter 1 m² Pelaburan Bidang Kayu dengan Vernis 1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 1 m² Melabur Tembok dengan Kapur Sirih 1 m² Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan ) 1 m² Pemasangan Wall Paper 1 m² Pengecatan Permukaan Baja dengan Meni Besi 1 m² Pengecatan Permukaan Baja dengan Meni Besi dan Perancah

10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00

1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 4 Lapis Cat Konvensional, tebal 200 u

10.00 Pekerjaan Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 21 1 Lapis Cat Mutakhir, tebal 200 um 10.00 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 1 Lapis Cat Mutakhir, tebal 200 um Pekerjaan Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 22 3 Lapis Cat Konvensional, tebal 200 um 10.00 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 3 Lapis Cat Konvensional, tebal 200 u Pekerjaan Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot 23 ( Airless Spray ) dgn Sistem 1 Lapis Cat Mutakhir, tebal 200 um 10.00 1 m² Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot ( Airless Spray ) dgn Sistem 1 Lapis Cat Mu

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

Jumlah Matrial

Jumlah Upah

Rp

Rp #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp

Jumlah Matrial

Jumlah Upah

Rp

Rp

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A

#N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A

#N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

----------------------

----------------------

Harga Satuan matrial Rp

Harga Satuan Upah Rp Jumlah Harga Dibulatkan

Jumlah Matrial

Jumlah Upah

Rp

Rp

Password : azzam54321

Related Documents

Analisa Physics 2004-2007
October 2019 9
Sni Analisa.xls
June 2020 27
Sni Textbook
April 2020 18
Sni Gempa
December 2019 46

More Documents from ""