ECONOMIC STIMULUS PROJECT LIST ROADWAY PROJECTS
1/13/2009 18:05
PROJECT SPONSOR
PROJECT NAME
CONST COST
COMMENTS AND DELIVERY ISSUES
PROJECTS WITH HIGH CONFIDENCE OF READINESS IN 90 - 180 DAYS
ITD/City of Hayden
US95 Wyoming to Ohio Match (including signals at Lancaster and Wyoming)
$
Existing federal aid project. City of Hayden offers contribution 21,000,000 for corresponding local system improvements. Direct tie to job creation and safety for employees at Warren K Industrial Park.
ITD
US95 Worley North
$
15,000,000
City of Coeur d’Alene
Atlas Bike Path
$
Existing federal aid project. National studies show pathways 500,000 are tied to economic benefits for communities. Concept report is almost complete. Simple project, no right of way required.
City of Coeur d’Alene
Kathleen/Howard Signal
$
300,000
New fed-aid project. Improves safety and access to growing commercial area of Coeur d'Alene.
City of Post Falls
Seltice/Cedar Signal
$
300,000
New federal-aid project. Improves safety and access at busy intersection that meets signal warrants.
Lakes Hwy District Lakes Hwy District Lakes Hwy District
Worley Hwy District
Worley Hwy District
ESHD ESHD ESHD ESHD ESHD ESHD ESHD
ESHD
ESHD
Lancaster Overlay from US 95 to Huetter Ramsey Road Overlay, from Scarcello to Brunner East Hayden Lake Road Overlay, from Dodd to Mokins Bay Watson Road , from Vogul to terminus Safety improvements Conkling Road, US95 to Heyburn State Park Cement treated base and pave 5.76 miles French Gulch Rd Cement-treated base and pave 3.5 miles Yellowstone Trail Rd Level and overlay 5.2 miles Fernan Hill Rd Cement treated base and pave 1 mile Canyon Rd Level and overlay 8.7 miles Burma Rd Cement treated base and pave 2.4 miles. O'Gara Rd Level and overlay 7.4 miles Bell Canyon Rd Ballast, base, drainage and pave 1.2 miles Hells Gulch Rd Ballast, base, drainage and pave 2.4 miles Sunnyside Road Overlay existing pavement 2 miles
$ $
Highway improvement project through the town of Worley. Ready to go.
New fed-aid project. 3 mile overlay of existing pavemetn at 36ft width New fed-aid project. 2.8 mile overlay of existing pavement at 500,000 28-ft width 600,000
New fed-aid project. 6.75 mile overlay of existing pavement at 28-ft width.
$
1,200,000
$
New fed-aid project. This will be a reconstructed roadway into 1,000,000 a primarily summer use community on lake CDA, (recreation). Benefits tourism and safety.
$
2,500,000
$
1,400,000 New fed-aid project.
$
1,800,000 New fed-aid project.
$
400,000 New fed-aid project.
$
3,100,000 New fed-aid project.
$
1,000,000 New fed-aid project. Not part of the current STP Rural project
$
2,500,000 New fed-aid project.
$
800,000 New fed-aid project.
$
1,500,000 New fed-aid project.
$
400,000 New fed-aid project.
New fed-aid project. Cement recycled asphalt base stabilization is planned. Benefits tourism.
PROJECT SPONSOR
ESHD
PROJECT NAME Sunnyside Road Ballast, base and pave 1.8 miles
TOTAL "180 DAY" PROJECTS
CONST COST
$
$
COMMENTS AND DELIVERY ISSUES
1,300,000 New fed-aid project.
57,100,000
HIGH-RISK PROJECTS POTENTIALLY READY IN 180 DAYS Construction cost does not include right of way acquisition.
ITD/WSDOT City of Rathdrum
Bridging the Valley Main Street Extension
$
Existing federal-aid project. Environmental Clearance complete. Final design needs to be funded immediately so that HDR can assess feasibility of immediate possession and 9,000,000 use agreements for right of way. This project would impact a commercial property that is currently for sale, and several mobile homes. Benefits both commerce and safety.
TOTAL "HIGH RISK" PROJECTS
$
9,000,000
TOTAL KMPO ROADWAY PROJECTS
$
66,100,000