JOB SAFETY ANALYSIS (JSA) WORK SHEET Doc no Rev: 0
RISK MATRIX
PROJECT /JOB DETAILS
INCREASE PROBABILITY
Potential Severity
People
Asset /Production
Environment
Reputation
Project Ref./Job Title/Work Order:
JSA No.
Brief Description of Job RADIOGRAPHY WORK
REVISION
Job Location:
A
B
C
D
E
Never heard of in industry
Has occurred in industry
Has occurred in QP
Occurs several times a year in QP
Occurs several times a year at this site
0
No injury
No damage
No effect
No impact
No Risk
Low
Low
Low
Low
1
Slight injury or health effects
Slight damage, No disruption to operation
Slight effect
Slight impact
Low
Low
Low
Low
Low
2
Minor injury or health effects
Minor damage (=QR 250,000)
Minor effect
Limited impact
Low
Low
Medium
Medium
Medium
3
Major injury or health effects
Local damage (=QR1 300,000)
Localized effect
National effect
Low
Medium
Medium
Medium
High
4
Single fatality or permanent total disability
Minor damage (=QR 25,000,000)
Major effect
Regional effect
Low
Medium
Medium
High
High
5
Multiple fatalities
Extensive (=QR 25,000,000)
Massive effect
International impact
Medium
Medium
High
High
High
DATE
Hazard Area Classification Permit Requirements: Hot/Cold/Radiography Participant (Parties involve in JSA) Site engineer, supervisor and safety officer
Sponsoring Department Performing Department Permit Authority JSA Approved by
All the mitigation measures identified in JSA are in place before starting the activities
Probability Factor Work Site Supervisor
Page 1 of 4 DOC. NO.:
REV.0
JOB SAFETY ANALYSIS (JSA) WORK SHEET Doc no Rev: 0
Sl. No. 1
2
Activity (Job Steps) Tool box Meeting And JHA Discussion
Work Permit
Potential Hazard
People Not Understanding What The Plan Or Hazards Are; People Afraid To Ask Questions Presence of H2S gas and Toxic gas In Work Areas. Presence of chemical or flammable items Unauthorized commencement of works May result in exposing people and/or potential to harm or danger.
Severity Before Mitigation Medium C
Required Control/Mitigation Measures & Checks
Make Sure Everyone Is Involved With The JSA/JHA
Severity After Mitigation Low C
Site radiation supervisor & radiation workers
Low C
Site radiation supervisor & radiation workers
Discussion And Understands; Encourage Everyone To Ask Questions And Participate. Don't Make Anyone Feel For Speaking Up Or Questioning Try To Identify These Types Of things In Your Work Areas Before Starting the work; Clear Carefully Work Areas By gas testing and daily site inspection Medium C
Authorized work permit holders shall ensure obtaining and
Action party
maintaining valid work permits. The supervisor responsible for this activity has to check the PPE of his staff to ensure that all required items are available and properly used. Inform all people regarding permit conditions before work starts. Supervisors must conduct daily toolbox talk about nature of work and associated potential hazards and their essential precautionary measures.
4
HSE check list &Prior to commencing mobilization to site
Lack of safety awareness
Medium C
All personnel shall be H2S trained Obtain work permits Comply with all general job requirements mentioned on PTW TBT on possible emergency and response procedure. All safety requirements stated on the work permit must be fulfilled
Low C
5
Radiography
Radiation exposure Over dose Property loss Ionizing radiation Vomiting Nausea
Medium C
Complete PTW Requirement Controlled area classification Prior to visual inspection of the area, the safety barriers shall be erected on all access ways, to prevent people from entering the restricted area during the inspection. This
Low B
Site radiation supervisor & radiation workers
Site radiation supervisor & radiation workers
Page 2 of 4 DOC. NO.:
REV.0
JOB SAFETY ANALYSIS (JSA) WORK SHEET Doc no Rev: 0
Paleness Loss of hairs Loss of appetite Damage of geneses
includes preventing access above and below the area. The Radiographer and Assistant Radiographer shall check the area to ensure that all non-authorized personnel have left the area P.A. announcement shall be made 30 minutes prior to radiography commencing, advising all affected personnel to make safe their workplaces and vacate the area. Another P.A. announcement shall be made 5 minutes prior to radiography commencing, advising affected personnel to vacate the area immediately. A final PA announcement shall be made to announce the commencing of the radiography. Each announcement shall be repeated twice RPO must have PTW (Dukhan QP)card Approved radiation safety procedure and radiation emergency procedure. Radiography shall be done by experienced trained and MOE (minister of environment, Qatar) authorized technicians. Source under lock and key. Personal Monitoring. Area monitoring using radiation survey meters Daily equipments check list by RPO. Maintain daily and monthly dose record through film badge. Personal monitoring through dosimeter. Dosimeter shall be calibrated to “0”reding prior to start the job
Page 3 of 4 DOC. NO.:
REV.0
JOB SAFETY ANALYSIS (JSA) WORK SHEET Doc no Rev: 0
Reduce radiation exposure. Retract source back to container. Spare container. qualified driver Handling and transportation to be performed as per standing instructions. Radiation dose records keeping. All activities shall be accordance with QP radiography procedure.QPR-HSSD-03 5
Housekeeping Clean up worksite
Engineer (
Slips trips and falls due to poor
Medium C
housekeeping
Project Engineer
Remove tools equipment and rubbish from worksite and maintain a clean work environment. Arrange housekeeping on daily and every shift bases Supervisor shall conduct tool box meeting in this regards
Production Supervisor
Low C
Site radiation supervisor & radiation workers
Asst.Manager(if Required)
Page 4 of 4 DOC. NO.:
REV.0