TRANSMISSION BUSINESS GROUP, HSE NOIDA
Format No.: TBG/HSE/FMT-19 Rev. No.: 00 Date: 21.05.2018 Page No.: 01 of 01
INDUCTION TRAINING RECORD
Name of Agency: _____________________________________________________ Date: - _____________ Location: -_____________________ _____
Project Details: - ____________________________________
Nature of Work Person Does: - _______________________ Induction given by: - ________________________
Detail of Persons Inducted Sr. No.
Name
Designation
Age
Signature
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Points Discussed (Tick out): Importance of PPE’s Emergency Assembly Point Precaution during Concreting Precaution while working at height Seven Steps of safety / Temporary Electricity Material Handling Important Numbers Overview of Project Health & Safety Policy General site safety Rules
Housekeeping Driving Precaution in Excavation Precaution in Electrical Location of First-Aid Precaution in Erection Work Operation of Fire Extinguisher Hazards at Project sites Drugs & Alcohols Customer Requirement
Any Special Point Discussed: _________________________________________________ ____________________________________________________________________________ Signature of Safety Officer Note: -
Signature of Site Manager
It should be kept at site for record It is mandatory for all new inductees & to be repeated once in six months. Induction training must be given by site safety officer or by site manager in local language.