S10

Página

2

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO MUNICIPALIDAD DISTRITAL DE YARINACOCHA Costo al UCAYALI - CORONEL PORTILLO - YARINACOCHA

|ltem

Descripción

Presupuesto Subpresupuesto Cliente

07.02.06 07.02.07 07.02.08 07.03

0492001

Metrado

Und.

ACERO DE REFUERZO F'Y=4200 KG/CM2 CANALETAS ACERO DE REFUERZO F'Y=4200 KG/CM2 WATER STOP NEOPRENE 6" EN CANALETAS

Precio S/.

20/08/2012

Parcial SI.

kg

111,149.16

5.15

kg

1.00

5.15

5.15

M

1,327.90

30.84

40,952.44

572,418.17

SARDINELES

108,392.28

07.03.01

CONCRETO FC= 175 KGTOM2 EN SARDINELES

m3

117.00

359.56

07.03.02

ENCOFRADO Y DESENCOFRADO DE SARDINEL

m2

1,559.88

25.66

40,026.52

07.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2 SARDINELES

kg

5,105.26

5.15

26,292 09

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

1.00

5.15

5.15

07.03.04 08

42,068.52

CONCRETO EN MARTILLOS y RAMPAS

335,048.64

08.01

ENCOFRADO Y DESENCOFRADO DE MARTILLOS Y INTERSECCIONES

m2

578.96

25.95

15,024.01

08.02

CONCRETO F'C=175 KG/CM2 PARA MARTILLOS

m2

2,381.49

134.38

320,024.63

09 09.01

SISTEMA DE MURO DE CONTENCION (TERRAMESH VERDE)

3,903,964.85

TRABAJOS PROVISIONALES

945.96

^ _ 0 9 .0 1 .0 1

UMPtEZA DE TERRENO

m2

300.00

^ P ^ 9 .0 1 .0 2

TRAZO, NIVEL Y REPLANTEO

m2

SEÑALIZACION Y SEGURIDAD EN ZONA DE TRABAJO

und

09.01.03 09.02

0.81

243.00

300.00

1.85

555.00

2.00

73.98

147.96

MOVIMIENTO DE TIERRAS

30,778.07

09.02.01

CORTE DE TERRENO A MAQUINA

m3

1,048.95

25.65

09.02.02

NIVELACION Y COMPACTADO DEL TERRENO

m2

300.00

4.40

1,320.00

09.02.03

CONFORMACION DE LA SUB RASANTE

m2

250.00

10.21

2,552.50

09.03

SISTEMA DE MURO DE CONTENCION - SUELO REFORZADO(TERRAMESH VERDE)

3,872,240.82

09.03.01

SUMINISTRO E INSTALACION SISTEMA TERRAMESH VERDE (2.00 X 4.00 X 0.60)und

09.03.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

10 10.01

m3

3,390.00

660.71

2,239,806.90

44,096.00

37.02

1,632,433.92

CONSTRUCCION DE ALCANTARILLA N° 1 (1.60m * 1.00Mm x 32.50) PROGRESIVA: 0+126.95

46,084.76

TRABAJOS PRELIMINARES

1,013.43

10.01.01

LIMPIEZA DE TERRENO MANUAL {Con pío®, Lampa y carreSHa)

ra2

138.00

6.51

10.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

65.00

1.77

10.02

26,905.57

888.38 115.05

MOVIMIENTO DE TIERRAS

9,364.26

10.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

74.75

32.58

2,435.36

10.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

74.75

85.96

6,425.51

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

97.18

5.18

m2

74.75

31.08

10.02.03 JO-03 " 0 03 01 10-04 10 8481 10.04.01.01 10.04.01.02 10.04.02

503,200 //r v 2,33MS U vijiO N

OBRAS DE CONCRETO SIMPLE SOLAD01:10 E= 4"

2 , ^ 3 E SS

OBRAS DE CONCRETO ARMADO

«

LOSA INFERIOR

9,634.8^

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

15.20

373.53

768.38

5.15

5,677.66 3,957.16

MUROS REFORZADOS

13,416.91

10.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

13.96

367.13

5,125.13

10.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

139.60

27.02

3,771.99

10.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

877.63

5.15

10.04.03

4,519.79

LOSA SUPERIOR

10,168.92

10.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

13.00

373.53

HS.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

65.80

27.02

1,777.82

10.04.03.03

ACERO DE REFUERZO F’Y=4200 KG/CM2

kg

686.43

5.15

3,535.11

5.90

27.66

10.04.04 10.04.04.01 11 11.01 11.01.01 11.01.02 11.02

4,855.89

JUNTA DE DILATACION

163.19

JUNTAS DE DILATACION CON WATER STOP

ML

163.19

CONSTRUCCION DE ALCANTARILLA N° 2 (2.00m x 2.00m x 13.00) - PROGRESIVA: 0+620

29,948.71

TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla) TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

t f f l

484.88 m2 ^m 2.

|

66.00

6.51

31.20

1.77 ^

MOVIMIENTO DE TIERRAS

429.66 -

55.22~ 4.397.12

EXCAVACION MANUAL DE MATERIAL ORGANICO

3 2 .^ ^ r c io M á ^ ^ C O Ijju L T IN G E N IE R O C W H-

.

______ r e v a lo

Rcpic&c?iI¿íUti Legal

1

f o j p

3

Página

S10

P re s u p u e s to

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Costo al MUNICIPALIDAD DISTRITAL DE YARINACOCHA UCAYALI - CORONEL PORTILLO - YARINACOCHA

|nem

Descripción

Presupuesto Subpresupuesto Cliente

0492001

Und.

Metrado

20/08/2012

Parcial SI.

Precio SI.

11.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

35.10

85.96

3,017.20

11.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

45.63

5.18

236.36

m2

35.10

31.08

11.03 11.03.01 11.04 11.04.01 11.04.01.01 11.04.01.02 11.04.02

1,090.91

OBRAS DE CONCRETO SIMPLE SOLAD01:10 E= 4"

1,090.91 23,975.80

OBRAS DE CONCRETO ARMADO

6,098.70

LOSA INFERIOR CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

ACERO DE REFUERZO F‘Y=4200 KG/CM2

kg

7.31

373.53

654.02

5.15

2,730.50 3,368.20 11,691.91

MUROS REFORZADOS

11.04.02.01

CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS

m3

10.35

367.13

3,799.80

11.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

103.52

27.02

2,797.11

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

989.32

5.15

5,095.00

6.24

373.53

2,330.83

11.04.02.03 11.04.03 ^^11 .0 4 .0 3 .0 1 1.04.03.02 11.04.03.03 12 12.01 12.01.01 12.01.02 12.02

6,185.19

LOSA SUPERIOR CONCRETO FC= 216 KG/CM2. EN LOSA SUPERIOR

m3

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

32.16

27.02

868.96

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

579.69

5.15

2,985.40 20,326.58

CONSTRUCCION DE ALCANTARILLA N° 3 (1,00m x 1,50m x 12.95) - PROGRESIVA: 1+028.60

362.99

TRABAJOS PRELIMINARES LIMPIEZA DE TERRENO MANUAL (Con pico. Lampa y carretilla)

m2

50.83

6.51

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

18.13

1.77

330.90 32.09 2,758.50

MOVIMIENTO DE TIERRAS

12.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

22.02

32.58

717.41

12.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

22.02

85.96

1,892.84

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

28.62

5.18

12.02.03 12.03 12.03.01 12.04 12.04.01

OBRAS DE CONCRETO SIMPLE SOLAD01:10 E= 4"

m2

LOSA INFERIOR

12.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

12.04.02.03 12.04.03

684.38

3,194.56 m3

12.04.02.01

31.08

16,520.71

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

Pf2.04.02.02

22.02

OBRAS DE CONCRETO ARMADO

12.04.01.01

1204.02

148.25 684.38

4.59

373.53

1,714.50

287.39

5.15

1,480.06

MUROS REFORZADOS CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS

m3

12.10

367.13

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

120.96

27.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

585.71

5.15

LOSA SUPERIOR

2,599.13

12.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

2.59

373.53

12.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

13.35

27.02

360.72

12.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

246.79

5.15

1,270.97

13 13.01 13.01.01 13.01.02 13.02

967.44

20,356.61

CONSTRUCCION DE ALCANTARILLA N° 4 (1.00m x 1.50m x 12.35) - PROGRESIVA: 1+928.40 TRABAJOS PRELIMINARES

348.22

LIMPIEZA DE TERRENO MANUAL (Con pico. Lampa y carretilla)

m2

48.79

6.51

TRAZO, NIVELACION Y REPUNTEO DE ALCANTARILLADO

m2

17.29

1.77

MOVIMIENTO DE TIERRAS

317.62 30.60 2,630.70

13.02.01

EXCAVACION MANUAL DE MATERIA! ORGANÍCO

m3

21.00

32.58

684.18

13.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

21.00

85.96

1,805.16

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

27.29

5.18

13.02.03 13.03 13.03.01 13.04 13.04.01

OBRAS DE CONCRETO SIMPLE SOLAD01:10 E= 4“

31.08

OBRAS DE CONCRETO ARMADO

652.68 16,725.01

LOSA INFERIOR

3,076.41

13.04.01.01

CONCRETO F'C= 210 KG/CM2 ENJJ3SA-fNHERJOR

13.04.01.02

ACERO DE REFUERZO F’Y=4200 KG/CM2

13.04.02

141.36 652.68

MUROS REFORZADOS/

/

/

Cansorcio Rf¡ ^S Ó A S C I WSULT

n p a r t n t f i u z s ir u v u R e p je s e n la n tfc L e g a l

373.53 5.15

1,628.59 1,447.82 10,669.65

( ¡ o jo ) 4

Página

S10

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Costo al MUNICIPALIDAD DISTRITAL DE YARINACOCHA UCAYALI - CORONEL PORTILLO - YARINACOCHA

|ltem

Descripción

Presupuesto Subpresupuesto Cliente

13.04.02.01 13.04.02.02 13.04.02.03 13.04.03

0492001

Und.

Metrado

Precio S/.

20/08/2012

Parcial S/.

m3

12.10

367.13

4,442.27

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

120.96

27.02

3,268.34

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

574.57

5.15

2,959.04

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

2,978.95

LOSA SUPERIOR

13.04.03.01

CONCRETOF'C= 210 KG/CM2. ENLOSA SUPERIOR

m3

3.46

373.53

1,292.41

13.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

15.38

27.02

415.57

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

246.79

5.15

13.04.03.03 14 14.01

CONSTRUCCION DE ALCANTARILLA N° 5 (0.80m x 1.00m x 12.30) PROGRESIVA: 3+273.50 TRABAJOS PRELIMINARES

324.03

14.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

45.76

6.51

14.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

14.76

1.77

14.02 14.02.01 4 fc l4 .0 2 .0 2 ^ ^ 1 4 .0 2 .0 3 14.03 14.03.01 14.04 14.04.01

MOVIMIENTO DE TIERRAS

26.13

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

18.45

32.58

601.10

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

18.45

85.96

1,585.96

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

23.99

5.18

OBRAS DE CONCRETO SIMPLE

124.27 573.43

SOLAD01:10 E= 4*

m2

18.45

31.08

OBRAS DE CONCRETO ARMADO

573.43 10,021.77

LOSA INFERIOR

2,441.00

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

14.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

14.04.02.01

297.90

2,311.33

14.04.01.01

14.04.02

1,270.97 13,230.56

3.85

373.53

1,438.09

194.74

5.15

1,002.91

5.60

367.13

2,055.93

MUROS REFORZADOS

5,253.36

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

14.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

56.00

27.02

1,513.12

14.04.02.03

ACERO DE REFUERZO FYM200 KG/CM2

kg

327.05

5.15

1,684.31

2.95

373.53

1,101.91

14.04.03 14.04.03.01

LOSA SUPERIOR

2,327.41

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

14.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

12.70

27.02

343.15

14.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

171.33

5.15

882.35

15

K

15.01

CONSTRUCCION DE ALCANTARILLA N° 6 (1.20m x 1.60m x 32.80) 3+563.45

PROGRESIVA:

55,140.92

TRABAJOS PRELIMINARES

5.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

125.28

6.51

5.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

52.48

1.77

15.02

MOVIMIENTO DE TIERRAS

1502.01

EXCAVACION MANUAL OE MATERIAL ORGANICO

fn3

106.07

32.58

3,455.76

15.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

62.32

85.96

5,357.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

137.89

5.18

15.02.03 15.03 15.03.01 15.04 15.04.01 15.04.01.01 15.04.01.02 15.04.02

OBRAS DE CONCRETO SIMPLE

714.27 1,936.91

SOLAD01:10 E= 4"

m2

62.32

31.08

OBRAS DE CONCRETO ARMADO

1,936.91 42,768.49

LOSA INFERIOR

8,724.14

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR

m3

ACERO DE REFUERZO F'Y=4200 KG/CM2

12.67

373.53

775.05

5.15

MUROS REFORZADOS

4,732.63 3,991.51 25,421.99

15.04.02.01

CONCRETO F’C=210 KG/CM2 EN MUROS REFORZADOS

m3

28.10

367.13

10,316.35

15.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

281.04

27.02

7,593.70

15.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

1,458.63

5.15

7,511.94

373.53

4,654.18

15.04.03 15.04.03.01

LOSA SUPERIOR

8,622.36

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

15.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

15.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

16 16.01

CONSTRUCCION DE ALCANTARILLAN” 3+85230 TRABAJOS PRELIMINARES

0m x1

Con$ rcl° FR^

^

x 12.1 A:

A m p a fo v ttr r A r e v u lo ¿p resentante Legal

PROGRESIVA:

27.02

1,428.82

5.15

2,539.36 21,791.60

Jerm náffftafael Lean

363.83

Página

S10

5

Presupuesto

Lugar

MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VlA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Costo al MUNICIPALIDAD DISTRITAL DE YARINACOCHA UCAYALI - CORONEL PORTILLO - YARINACOCHA

frtem

Descripción

Presupuesto Subpresupuesto Cliente

16.01.01 16.01.02 16.02

0492001

Und.

LIMPIEZA DE TERRENO MANUAL (Con pico. Lampa y carretilla) TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

Metrado

Precio SI.

20/08/2012

Parcial SI.

m2

50.32

6.51

m2

20.48

1.77

327.58 36.25 3,046.69

MOVIMIENTO DE TIERRAS

16.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

24.32

32.58

792.35

16.02.02

RELLENO COMPACTADO CON MATERIAL OE PRESTAMO - TIERRA ROJA

m3

24.32

85.96

2,090.55

16.02.03

ELIMINACION DE MATERIAL EXCEDENTE C I EQUIPO

m3

31.62

5.18

163.79

m2

24.32

31.08

755.87

16.03 16.03.01 16.04 16.04.01

755.87

OBRAS DE CONCRETO SIMPLE SOLADO 1:10 E= 4'

17,625.21

OBRAS DE CONCRETO ARMADO

4,082.09

LOSA INFERIOR

16.04.01.01

CONCRETO F’C= 210 KG/CM2. EN LOSA INFERIOR

m3

16.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

16.04.02 ',6.04.02.01 Pl6.04.02.02 16.04.02.03 16.04.03

5.07

373.53

1,893.80

424.91

5.15

2,188.29

8.87

367.13

3,256.44

9,504.07

MUROS REFORZADOS CONCRETO F 'O 210 KG/CM2 EN MUROS REFORZADOS

m3

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

88.70

27.02

2,396.67

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

747.76

5.15

3,850.96 4,039.05

LOSA SUPERIOR

16.04.03.01

CONCRETO FC= 210 KG/CM2 EN LOSA SUPERIOR

m3

4.10

373.53

16.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

21.08

27.02

569.58

16.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

376.31

5.15

1,938.00

17 17.01

CONSTRUCCION DE ALCANTARILLA N° 8 (1.20m x 1.70m x 12.30) - PROGRESIVA: 3+951.80

15,168.96

TRABAJOS PRELIMINARES

17.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

42.90

6.51

17.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

17.22

1.77

17.02

MOVIMIENTO DE TIERRAS

17.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

20.91

32.58

17.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

20.91

85.96

17.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

27.18

5.18

m2

20.91

31.08

17.03 17.03.01 17 04 17.04.01 ^7.04.01.01 17.04.01.02 17.04.02

OBRAS DE CONCRETO SIMPLE SOLAD01:10 E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

4.37

373.53

233.25

5.15

MUROS REFORZADOS

17.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

6.59

367.13

17.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

65 86

27.02

17.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

349.32

5.15

17.04.03

LOSA SUPERIOR

17.04.03.01

CONCRETO F 'O 210 KG/CM2. EN LOSA SUPERIOR

m3

3.45

373.53

17.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

17.62

27.02

17.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

192.93

5.15

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

42.90

6.51

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

24.60

1.77

18 18.61 18.01.01 18.01.02 18.02

CONSTRUCCION DE ALCANTARILLA N“ 9 (1.60m x 1.50m x 12.30) - PROGRESIVA: 4+491.50 TRABAJOS PRELIMINARES

322.82

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL DE MATERIAL ORGANICO

18.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

18.02.03

ELIMINACION DE MATERIAL EXCEDENTE CI EQUIPO

18.03.01 18.04

279.28 43.54 3,544.02

18.02.01

18.03

1,531.47

OBRAS DE CONCRETO SIMPLE

921.69 2,431.81 190.52 764.57

SOLAD01:10 E= 4"

764.57

OBRAS DE CONCRETO ARMADO

19,103.49

: A r e va lo «epresttntante Le^sl

Página

S10

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VlA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Costo al MUNICIPALIDAD DISTRITAL DE YARINACOCHA UCAYALI - CORONEL PORTILLO - YARINACOCHA

jltem

Descripción

Presupuesto Subpresupuesto Cliente

18.04.01

0492001

Und.

Parcial SI.

Precio SI.

4,785.24

LOSA INFERIOR

18.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

18.04.01.02

ACERO DE REFUERZO FY=4200 KG/CM2

kg

18.04.02

Metrado

20/08/2012

5.91

373.53

2,207.56

500.52

5.15

2,577.68

4,251.37

9,709.50

MUROS REFORZADOS

18.04.02.01

CONCRETO F'C=2',rO KGÍCM2 Eí» MUROS REFORZADOS

m3

11.58

367.13

18.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

115.58

27.02

3,122.97

18.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

453.43

5.15

2,335.16

18.04.03

4,608.75

LOSA SUPERIOR

18.04.03.01

CONCRETO F'Cí 210 KG/CM2. EN LOSA SUPERIOR

m3

4.92

373.53

18.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

25.40

27.02

686.31

18.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

404.79

5.15

2,084.67

19 19.01 19.01.01

1,837.77

40,683.73

INSTALACIONES ELECTRICAS

40,683.73

SEMAFORO SEMAFORO TRIPLE T'iPO LEDS 10W

und

2.00

6,088.01

12,176.02

SEMAFORO CUADRUPLE TIPO LEDS 10W

und

1.00

8,078.01

8,078.01

19.01.03

POSTE DE F*G DE 0 6" X 11 MM

und

3.00

1,696.30

5,088.90

19.01.04

TABLERO ELECTRICO DE CONTROL AUTOMATICO

und

3.00

2,517.56

7,552.68

19.01.05

MEDIDOR DE ENERGIA MONOFASICA

und

3.00

1,840.12

5,520.36

19.01.06

CONDUCTOR ELECTRICO 2 -1 X 6 MM2 NYY

m

3.00

22.21

66.63

19.01.07

AUMENTADOR AL MEDIDOR DE ENERGIA

m

3.00

66.43

199.29

19.01.08

CABLE DE ACERO DE 05/16"

m

3.00

15.72

47.16

19.01.09

POZO DE PUESTA DE TIERRA

und

3.00

651.56

1,954.68

und

66.00

67.76

4,472.16

und

132.00

97.87

12,918 84

^ ^ 1 9 .0 1 .0 2

20 20.01 20.02

VARIOS

90,550.38

REJILU METALICA CON MARCO 0.52x0.80 TAPAS DE CONCRETO PARA INSPECCION Y LIMPIEZA 0.60X0.53 F C=210 KG/CM2

20.03

PINTURA ALTO TRAFICO EN PAVIMENTO

KM

4.69

3,668.03

17.203.06

20.04

PINTURA ALTO TRAFICO EN CRUCE PEATONAL

m2

870.00

12.29

10,692.30 27,500.00

20.05

SEÑALIZACION VERTICAL

und

55.00

500.00

20.06

LIMPIEZA FINAL DE OBRA

GLB

1.00

4,000.00

20.07

BUZONES

2007.01

ENCOFRADO Y DESENCOFRADO EN LOSA DE BUZON

m2

2.25

27.02

20.07.02

CONCRETO F’C= 210 KG/CM2. EN LOSA DE BUZONES

m3

5.82

373.53

ACERO DE REFUERZO F'Y=4200 KGTCM2

kg

248.90

5.22

MARCO Y TAPA DE BUZON

und

9.00

195.01

k 0 .0 7 .0 3 20.07.04 20.08 20.08.01 20.08.01.01 20.08.02

PARADEROS

4,oos m

2,17: 1,299.26 1,755.09 8,47493

TRABAJOS PRELIMINARES

20.36

TRAZO, NIVELACION Y REPUNTEO

m2

11.50

1.77

MOVIMIENTO DE TIERRAS

20.36

265.20

20.08.02.01

EXCAVACION DE ZANJA MANUAL

m3

4.31

32.58

20.08,02,02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

m3

1.17

69.15

80.91

20.08.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

5.61

7.82

43.87

20.08.03

OBRAS DE CONCRETO ARMADO

140.42

1,095.94

20.08.03.01

CONCRETO F'C=140 KG/CM2 EN CIMIENTO DE PARADERO

m3

3.23

52.50

20.08.03.02

CONCRETO F'C= 175 KG/CM2 EN BASE PARA BANCAS

m3

0.06

338.14

20.29

20.08.03.03

ENCOFRADO Y DESENCOFRADO EN BASE DE C A DE BANCAS

m2

1.21

19.22

23.26

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

171.42

5.15

20.08.03.04 20.08.04

ESTRUCTURAS Y COBERTURAS DE MADERA

169.58

882.81

4.648.70

20.08.04.01

ESTRUCTURA DE MADERA EN BANCAS

35.30

176.50

20.08.04.02

ENTRAMADO DE MADERA EN PARADEROS

50.93

25465

20 08.04.03

COLUMNAS DE MADERA (quinilla y/o similar)

112.09

3.362.70

20.08.04.04

COBERTURA CON PLANCHAS DE CALAMINA ONDULINE COLOR ROJO

20.08.05

28.12

ACCESORIOS METALICOS

854.85

1.843.28

20.08.05.01

COLOCACION DE DETÜBOS P G EN fARADI IROS

68.65

1.613.28

20.08.05.02

PLATINA METALICAS PAR/ÍFlJAREi

11.50

230.00

TJTdz A r e v a l o ■««presentóme Lec^l

iEROS

Presupuesto

lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO MUNICIPALIDAD DISTRITAL DE YARINACOCHA Costo al UCAYALI - CORONEL PORTILLO - YARINACOCHA

jttem

Descripción

Presupuesto Subpresupuesto Cliente

20 08.06

0492001

Und.

Parcial SI. 601.45

PINTURA EN BANCAS DEL PARADERO

und

20.08.06.02

PINTURA BARNIZ EN ESTRUCTURA DE MADERA PINTURA ZICROMATICO EN CARPINTERIA METALICA

20.08.06.03

Precio SI.

PINTURA

20.08.06.01

21

Metrado

20/08/2012

5.00

10.04

50.20

m

47.50

5.97

283.58

m

23.50

11.39

267.67 U AOO Aft WjOW.UU

IMPACTO AMBIENTAL

21.01

COSTOS AMBIENTALES DURANTE LA PAVIMENTACION

GLB

1.00

12,500.00

21.02

PRESUPUESTO DEL PROGRAMA DE MONITOREO AMBIENTAL

GLB

1.00

12,500.00

12,500.00

21.03

PRESUPUESTO DEL PROGRAMA DE EDUCACION Y CAPACITACION AMBIENTAL GLB

100

25,000.00

25,000.00

COSTO DIRECTO

12,500.00

14,581,295.04

GASTOS GENERALES (10.00%)

1.458.129.50

UTILIDAD (10.00%)

1.458.129.50

SUBTOTAL

17,497,554.04

ÍGV (18.80%)

3,149,559.73

TOTAL PRESUPUESTO SON :

VEINTE MILLONES SEISCIENTOS CUARENTISIETE MIL CIENTO TRECE Y 77/100 NUEVOS SOLES

20,647,113.77

1

Página

S10

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 002 MEJORAMIENTO DE PUENTE SAN LORENZO Costo al MUNICIPALIDAD DISTRITAL DE YARINACOCHA UCAYALI ■CORONEL PORTILLO - YARINACOCHA

ptem

Descripción

22

TRABAJOS PRELIMINARES

Presupuesto Subpresupuesto Cliente

Und.

Metrado

20/08/2012

Parcial SI.

Precio SI.

18,023.84

22.01

SEÑALIZACION INFORMATIVA DE DESVIO

und

2.00

167.72

335.44

22.02

DEMOLICION DE ESTRUCTURAS DE CONCRETO

m3

48.35

202.60

9,795.71

22.03

RETIRO DE DESPERDICIOS

m2

81.60

6.41

523.06

22.04

DESVIO DE CAUCE

ML

23 00

5864

1,34872

22.05

DESBROCE DE TERRENO

m2

147.03

1.54

226.43

22.06

LIMPIEZA DE TERRENO

m2

273.00

0.81

221.13

22.07

TRAZO Y REPLANTEO

m2

835.32

1.72

1,436.75

22.08

ALMACEN DE OBRA

m2

60.00

25.61

1,536.60

22.09

CARTEL DE OBRA (3.00 X 5.00) BANNER INC. COLOCACION

und

2.00

800.00

1,600.00

22.10

TRANSPORTE DE MATERIALES EQUIPOS Y HERRAMIENTAS

GLB

1.00

1,000.00

1,000.00

23 23.01

m

0492001

MOVIMIENTO DE TIERRAS

149,685.53

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA

m3

1,520.09

8.77

¿3.02

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA BAJO LECHO H 0 60M.

m3

249 08

658

1,638.95

13.03

RELLENO CON GRAVILLA O PIEDRA CHANCADA DE 1/2“

m3

83.89

113.96

9,560.10

23.04

RELLENO COMPACTADO CON MATERIAL MEJORADO 80% HOR. + 20% TR.

m3

279.62

98.16

27,447 50

RELLENO CON MATERIAL DE PRESTAMO EN REPOSICION DE VIA DE INGRESO Ym3 SALIDA.

967.20

97.15

93,963.48

m3

722.84

5.18

3,744.31

m2

245.75

16.15

3,968.86

23.05 23.06 24 24.01 25 25.01

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO 0= 5 KM. OBRAS DE CONCRETO SIMPLE

13,331.19

3,968.86

SOLADO DE CONCRETO F'C= 100 KG/CM2 E=0.10 M OBRAS DE CONCRETO ARMADO

334,300.43

LOSA INFERIOR DE ESTRIBO

38,331.23

25.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSAS

m3

52.72

367.53

25.01.02

ENCOFRADO Y DESENCOFRADO

m2

35.14

22.86

803.30

25.01.03

ACERO DE REFUERZO FY=4200 KG/CM2

3,644.93

4.98

18,151.75

25.02

kg

LOSA INFERIOR DE MURO CABEZAL

19,376.18

69,859.16

25.02.01

CONCRETO FC= 210 KG/CM2 EN LOSAS

(1)3

52,72

367 53

25.02.02

ENCOFRADO Y DESENCOFRADO

m2

35.14

22.86

803.30

25.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

9,975.84

4.98

49,679.68

CONCRETO FC= 210 KG/CM2 EN MUROS

m3

114.26

384.78

ENCOFRADO Y DESENCOFRADO

m2

25.03 25.03.01 25.03.02 ^5.03.03 25.04

MUROS CABEZAL

92,933.

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

43,964.

406.61

22.86

9,295

7,966.47

4.98

39,673

124.20

384.78

MUROS DE ENCAUSAMIENTO

84,885.42

25.04.01

CONCRETO FC= 210 KG/CM2 EN MUROS

m3

25.04.02

ENCOFRADO Y DESENCOFRADO

m2

25.04.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

25.05

19,376.18

47,789.68

36243

22.86

8^8515

5,785.26

4.98

28,810.59

VIGA LONGITUDINAL

7,966.46

25.05.01

CONCRETO F'C= 210 KG/CM2 EN VIGA TENSOR

m3

2.64

375.20

25.05.02

ENCOFRADO Y DESENCOFRADO

m2

43.09

22.86

985.04

25.05.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

1,202.99

4.98

5.990.89

2.64

375.20

21.81

22.86

498.58

273.34

498

1,36123

2.54

375.20

953.01

13.09

22.86

299.24

152.74

4.98

25.06

VIGA TRANSVERSAL

25.06.01

CONCRETO FC= 210 KG/CM2 VIGA

25.06.02

ENCOFRADO Y DESENCOFRADO

25.06.03

ACERO DE REFUERZO FY=4200 KG/CM2

25.07

CONCRETO F'C= 210 KG/CM2 VIGA

25.07.02

ENCOFRADO Y DESENCOFRADO

25.07.03

ACERO DE REFUERZO FY=4200 KG/CM2

25.08

2,850.34

VIGA DIAFRAGMA

25.07.01

LOSA SUPERIOR Y VEREDAS

760.65 35,461.84

CONCRETO F'C= 210 KG/CM2. EN LOSAS

25.08.02

ENCOFRADO Y DESENCOFRADO DE LOSA SUPERIOR (TIPO Fi

26

990.53

2.012.90

25.08.01

25.08.03

990.53

ACERO DE REFUERZO F'Y=4200 KG/CM2

22.72

367.53

8,350.28

105.74

138.23

14,616.44

2,509.06

VARIOS

12,495.12 8,800.74

Affípiit'o U iaz A rev a lo R ep re s e n ta n te L egal

S10

Página

2

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 002 MEJORAMIENTO DE PUENTE SAN LORENZO MUNICIPALIDAD DISTRITAL DE YARINACOCHA Costo al UCAYALI - CORONEL PORTILLO - YARINACOCHA

|ltem

Descripción

Presupuesto Subpresupuesto Cliente

0492001

Und.

Precio SI.

Parcial SI.

26.01

BARANDA METALICA INC. PINTADO

ML

20.84

115.89

26.02

DRENAJE EN LOSA SUPERIOR

pto

6.00

31.41

188.46

26.03

PLACA RECORDATORIA (INC. COLOCACION)

und

1.00

200.00

200.00

26.04

CARTEL DE IDENTIFICACION DEL PUENTE

und

2.00

1,200.00

2,400.00

26.05

JUNTAS DE DILATACION METALICA

ML

1440

100 08

1,441 15

26.06

APOYO MOVIL DE NEOPRENE SHORE 70.

und

3.00

344.50

1,033.50

26.07

APOYO FIJO DE NEOPRENE SHORE 70.

und

3.00

374.16

1,122.48

27

MONTAJE DE TUBERIA MATRIZ DE 10"

ML

24.00

109.77

2,634.48

28

MONTAJE DE TUBERIA MATRIZ DE 16"

ML

24.00

199.75

4,794.00

28.01

PINTURA EN BARANDAS METALICAS

ML

20.84

13.73

286.13

28.02

LIMPIEZA FINAL DE OBRA

GLB

1.00

200.00

COSTO DIRECTO

m

Metrado

20/08/2012

2,415.15

200.00 522,694.01

GASTOS GENERALES (10.00%)

52,269.40

UTILIDAD (10.00%)

52,269.40

SUB TOTAL

627,232.81

IGV (18.00%)

119,174.23

TOTAL PRESUPUESTO

746,407.04

SON :

SETECIENTOS CUARENTISEIS MIL CUATROCIENTOS SIETE Y 04/100 NUEVOS SOLES

Página

S10

1

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO MUNICIPALIDAD DISTRITAL DE YARINACOCHA Costo al UCAYALI - CORONEL PORTILLO - YARINACOCHA

[Item

Descripción

29

AGUA POTABLE

Presupuesto Subpresupuesto Cliente

29.01 29.01.01 29.02

0492001

Und.

Metrado

20/08/2012

Parcial SI.

Precio SI.

458,545.00 5,160.13

TRABAJOS PRELIMINARES TRAZO, NIVELES Y REPLANTEO DE REDES

ML

4,777.90

1.08

5,160.13 269,186.88

MOVIMIENTO DE TIERRAS

29.02.01

EXCAVACION DE ZANJA DE 0 6 * 120 M

m

4,777 90

6 77

29.02.02

REFINE Y NIVELACION COMPACTADO MANUAL

m

4,777.90

2.78

13,282.56

29.02.03

CAMA DE ARENA SELECTA E=0.30

m

4,777.90

11.70

55,901.43

29.02.04

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

m

4,777.90

35.09

167,656.51

m

4,777.90

20.58

98,329.18

29.03 29.03.01 29.04

32,346 38

98,329.18

INSTALACION DE TUBERIAS SUMINISTRO Y COLOCACION DE TUBERIAS PVC UF ACCESORIOS DE PVC DIAM. 110 MM S-13.3 ISO 4422 RED MATRIZ INC. ANILLO

34,363.05

INSTALACION DE ACCESORIOS Y VALVULAS

29.04.01

SUMINISTRO E INSTALACION DE VALVULA LUFLEX ISO 7259 FFD 110 MM.

29.04.02

SUM. EINST. DE CODO PVC UF 0 110 mm. DE 45"

t9.04.03

SUMINISTRO E INSTALACION DE TEE FF TIPO LUFLEX ISO 7259 110 MM. SUMINISTRO E INSTALACION DE TAPON PVC UF DIAM. 110 MM.

und

33.00

34.12

1,125.96

und

14.00

165.60

2,318.40 6,141.60

29.04.04 29.04.05

SUMINISTRO E INSTALACION DE UNION DE REPARACION PVC UF DIAM. 110 MM.

und

7,957.92

12.00

663.16

und

17.00

224.16

3,810.72

und

43.00

177.27

7,622.61

29.04.06

SUMINISTRO E INSTALACION DE GRIFO CONTRA INCENDIO

und

10.00

614.16

29.04.07

DADO DE CONCRETO

und

32.00

42.72

1,367.04

29.04.08

CAJA DE PROTECCION DE VALVULA

und

20.00

200.94

4,018.80

4,777.90

10.78

51,505.76

29.05 29.05.01 30 30.01 30.01.01 30.02

PRUEBA HIDRAULICA

51,505.76

DOBLE PRUEBA HIDRAULICA Y DESINFECCION

m

ALCANTARILLADO (4.50 KM).

560,599.31

TRABAJOS PRELIMINARES

2,330.91

TRAZO, NIVELES Y REPLANTEO 3 ETAPAS (P/EXCAV, P/RELLENO.P/PAVIMENTO)

m

3,237.37

0.72

MOVIMIENTO DE TIERRAS

2,330.91 243,935.82

30.02.01

EXCAVACION DE ZANJA DE 0.8 X 1.60 - 2.60 M.

m

3,237.37

6.77

30.02.02

REFINE Y NIVELACION DE ZANJAS

m

3,237.37

1.31

4,240.95

30.02.03

CAMA DE ARENA SELECTA E= 0.20

m

3,237.37

10.16

32,891.68

RELLENO COMPACTADO ZANJA 0.80 M. X (1.60 - 2.60M)

m

3,237.37

57.11

184,886.20

m

3,237.37

31.10

100,682.21

m3

123.05

32.58

4,008.3T

30.02.04 30.03 30.03.01 ÍS0.04 30.04.01

INSTALACION DE TUBERIAS

21,916.99

100,682.21

SUMINISTRO Y COLOCACION DE TUBERIA PVC DIAM. 200 MM. S25 UF - KM BUZONES

89,538.4^

EXCAVACION DE ZANJAS - BUZONES

30.04.02

BUZON DE CONCRETO ARMADO, H= 1.50 M, D= 1.20 M. INC. TAPA DE C 'A ‘ , MARCO F"F*

und

30.00

1,300.54

39,016.215

30.04.03

BUZON DE CONCRETO ARMADO, H= 1.80 M, D= 1.20 M. INC. TAPA DE C*A*, MARCO F*F*

und

15.00

1,331.61

19,974.15

30.04.04

BUZON DE CONCRETO ARMADO, H= 2.20 M, D= 1.20 M. INC. TAPA DE C"A*, MARCO F*F*

und

8.00

1,542.32

12,338.56

30.04.05

BUZON DE CONCRETO ARMADO, H= 2.40 M, D= 1.20 M. INC. TAPA DE C 'A - , MARCO F’ F*

und

8.00

1,775.07

14,200.56

und

1.00

331.29

331.29

3,237.37

1.40

4.532.32

30.05 30.05.01 30.06 30.06.01 30.07

EMPALMES

331.29

PERFORACION Y EMPALME A TUBERIA MATRIZ PRUEBAS

4.532.32

PREUBA DE REDES CONEXIONES DOMICILIARAS

41.148.86

30.07.01

CONEXIONES DOMICILIARIAS CORTAS (1= 5.00 M. APROX.)

und

87.00

190.00

16,530.00

30.07.02

CONEXIONES DOMICILIARIAS LARGAS (L= 17.00 M. APROX.)

und

82.00

300.23

24.618.86

30.08 30.08.01 30.09 30.09.01

RED DE DESAGÜE

75.091.30

CONEXIONES DOMICILIARIAS DE DESAGÜE NUEVAS (INC. Ti VARIOS

75.091.30 3.008.16

ELIMINACION DE MATERIAL CONTAMINANTE

3.008.16

COSTO DIRECTO

1,019,144.31

GASTOS GENERALES (10.00%)

101,914.43

Amn'artr-’SfiaZ'A revulo S e p re se n ta n te Legal

Oi S10

Página

2

Presupuesto

Lugar

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO MUNICIPALIDAD DISTRITAL DE YARINACOCHA Costo al UCAYALI - CORONEL PORTILLO - YARINACOCHA

[ttem

Descripción

Presupuesto Subpresupuesto Cliente

0492001

Und.

Metrado______ Precio SI.______ Parcial SI. 101,914.43

UTILIDAD (10.00%)

1,222,973.17

SUBTOTAL

220,135.17

IGV (18.00%)

1,443,108.34

TOTAL DE PRESUPUESTO SON :

20/08/2012

UN MILLON CUATROCIENTOS CUARENTITRES MIL CIENTO OCHO Y 34/100 NUEVOS SOLES

to D ía z A r e v a lo Legal

FACTIBILIDAD DEL PROYECTO: “ M EJO R AM IENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JO S É DESDE PUERTO CALLAO, D ISTRITO DE YA RINACOCHA - C O R O N EL PORTILLO - U C A YA LI”

ANALISIS DE COSTOS FA C TIB ILID A D DEL PROYECTO:

"M EJO RAM IENTO DE IN T E R C O N E X IO N AL C. P. SAN JOSE DESDE PUERTO CALLAO, D IS T R IT O DE YARINACOCHA CORONEL PO RTILLO - U C A Y A LI "

DIVISION DE ESTUDIOS Y O B R A S E IN FR AESTR U C TU R A S O C iA L Y P R O D UC TIVA

< g íZ > Página:

S10

1

Análisis de precios unitarios Presupuesto

0492001

MEJORAMIENTO CORONEL

001

Subpresupuesto

DE VÍA DE INTERCONEXIÓN

PORTILLO

MEJORAMIENTO

AL C.P.

SAN JOSÉ

DESDE

PUERTO

CALLAO,

DISTRITO

DE YARINACOCHA,

- UCAYALI

DE VÍA DE INTERCONEXIÓN

AL C.P. SAN JOSÉ DESDE

PUERTO

Fecha presupuesto

20/08/2012

CALLAO Partida

01.01

ALQUILER DE ALMACEN

Rendimiento

MES/DIA

Código

Descripción Recurso

MO.

EQ.

1.0000

683.33

Costo unitario directo por: MES

1.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Materiales 0239130017

1.0000

m2

ALMACEN

583.33

583.33 583.33

Partida

01.02

Rendimiento

und/DIA

Código

Descripción Recurso

REUBICACION DE POSTES DE TELEFONO MO.

4.0000

EQ.

268.58

Costo unitario directo por : und

4.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

20000

4.0000

15.14

60.56

0147010003

OFICIAL

hh

2.0000

4.0000

13.16

52.64

0147010004

PEON

hh

3.0000

6.0000

11.86

71.16 184.36

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349180010

GRUA HIDRAULICA AUTOP. 127HP18TON-9M.

hm

0.2500

5.0000

184.36

9.22

0.5000

150.00

75.00 84.22

Partida

01.03

Rendimiento

und/DIA

Código

Descripción Recurso

REUBICACION DE TEMPLADORES DE POSTES

MO

10.0000

EQ.

75.95

Costo unitario directo por : und

10.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

2.0000

1.6000

15.14

0147010003

OFICIAL

hh

2.0000

1.6000

13.16

21.06

0147010004

PEON

hh

3.0000

2.4000

11.86

28.46

2422

73.74 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

73.74

2.21 2.21

Partida

01.04

Rendimiento

und/DIA

Código

Descripción Recurso

TALA DE ARBOLES MO

10.0000

EQ

Costo unitario directo por : und

10.0000 Unidad

Cuadrilla

Cantidad

19.93

Precio SI.

Parcial SI.

Mano de Obra 0147010004

PEON

hh

2 0000

1.6000

11.86

1898 18.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

5.0000

18.98

095 0.95



y#—

"Haz A r e v a la ¿{¿•«sentante Legal

(¡ 61§ ) Página:

S10

2

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI 20/08/2012 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Fscfta presupuesto

Partida

01.05

Rendimiento

UND/DIA

Código

Descripción Recurso

SEÑALIZACION INFORMATIVA DE DESVIO - VIAS ALTERNAS MO. 2.0000

Costo unitario directo por: UND

EQ. 2.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

264.02 Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0 4000

14.36

5.74

0147010003

OFICIAL

hh

1.0000

4.0000

13.16

52.64

0147010004

PEON

hh

1.0000

4,0000

11.86

47.44 105.82

Materiales 0.45

0202010005

CLAVOS PARA MADERA C/C 3”

kg

0.1000

4.50

0239060024

WAYPE INDUSTRIAL

kg

1.6000

2.00

320

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

60.0000

2.00

120.00

0244030021

TRIPLAY DE 4'xB'x 4 mm

pin

0.5000

12.00

6.00

0253000000

KEROSENE INDUSTRIAL

gln

4.0000

630

25.20

0254110090

PINTURA ESMALTE

gln

0.0050

35.00

0.18 155.03

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

105.82

3.17 3.17

Partida

02.01

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO MO 500.0000

EQ. 500.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

1.03

Precio SI.

Parcial SI. 0.24

Mano de Obra 0147000032

TOPOGRAFO

hh

1.0000

0.0160

15.14

0147010002

OPERARIO

hh

1.0000

0.0160

1514

024

0147010004

PEON

hh

2.0000

0.0320

11.86

0.38 0.86

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0050

21.00

0.11

0244010000

ESTACA DE MADERA

p2

0.0200

1.15

0.02 0.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

5.0000

0.86

0.04 0.04

Partida

02.02

Rendimiento

GLB/DIA

Código

Descripción Recurso

TRANSPORTE DE EQUIPOS Y HERRAMIENTAS MO 10.0000

EQ. 10.0000

Costo unitario directo por: GLB Unidad

Cuadrilla

1,200.00

Cantidad

Precio SI.

Parcial SI.

1.0000

1,200.00

1,200.00

Materiales 0232010097

TRANSPORTE DE MATERIALES EQUIPOS Y H. • PUCALLPA A OBRA

GLB

1,200.00 Partida

02.03

Rendimiento

und/DIA

Código

Descripción Recurso

CARTEL DE IDENTIFICACION DE LA OBRA 3.60 x 2.20M MO 0.5000

EQ. 0.5000

Costo unitario directo por: und Unidad

678.73

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 242.24

Mano de Obra 0147010002

OPERARIO

hh

1.0000

16.0000

15.14

0147010004

PEON

hh

0.5000

8.0000

11.86

94.88 337.12

Materiales 0243150008

MADERA SHIHUAHUACO

p2

90.0000

250

0254110090

PINTURA ESMALTE

gln

0.3000

35.00

10.50

0261010002

CALAMINA LISA GALVANIZADA

pin

6.0000

16.00

96.00

22500

331.50 Equipos 0337010001

HERRAMIENTAS MANUALES

10.11 10.11

(894 si r e va lo . «sentante Legal

w

q Página:

S10

e s p 3

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

02.03

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CARTEL DE IDENTIFICACION DE LA OBRA 3.60 x 2.20M MO 0.5000

EQ

Costo unitario directo por: und

0.5000 Unidad

678.73

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 242.24

Mano de Obra 0147010002

OPERARIO

hh

10000

16.0000

15.14

0147010004

PEON

hh

0.5000

8.0000

11.86

94.88 337.12

Materiales 225.00

0243150008

MADERA SHIHUAHUACO

p2

90.0000

2.50

0254110090

PINTURA ESMALTE

gln

0.3000

35.00

10.50

0261010002

CALAMINA LISA GALVANIZADA

pin

6.0000

16.00

96.00 331.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

337.12

10.11 10.11

Partida

02.04

Rendimiento

m2/DtA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL MO 250.0000

EQ

250.0000

Costo unitario directo p o r. m2 Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

0.0320

11.86

0.39 Parcial SI.

Mano de Obra 0147010004

PEON

hh

0.38 0.38

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.38

0.01 0.01

Partida

03.01.01

Rendimiento

GLB/DIA

Código

Descripción Recurso

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD YSALUD EN EL TRABAJO MO 1.0000

EQ

1.0000

Costo unitario directo por: GLB Unidad

Cuadrilla

5,000.04

Cantidad

Precio SI.

Parcial SI.

1.0000

5,000.04

5.000.04

Mano de Obra 0198010048

PLAN DE SEGURIDAD Y SALUD

und

5.000.04 Partida

03.01.02

Rendimiento

und/DIA

Código

Descripción Recurso

EQUIPOS DE PROTECCION INDIVIDUAL MO 1.0000

EQ

1.0000

Costo unitario directo por: und Unidad

Cuadrilla

76.50

Cantidad

Precio SI.

Parcial SI.

Equipos 0337010100

CASCO DE SEGURIDAD

und

1.0000

28.00

28.00

0337530073

GUANTES DE JEBE

PAR

0.3000

25.00

7.50

0337600001

GUANTES DE CUERO

PAR

0.4000

10.00

4.00

0337620030

PROTECTOR DE OIDOS

pza

0.2500

7.00

1.75

0337620035

RESPIRADOR CONTRA POLVO

und

0.2500

20.00

5.00

0337620037

CHALECOS REFLECTIVOS

und

0.3000

30.00

9.00

0337990055

BOTAS DE JEBE NUEVAS

PAR

1 0000

20.00

20.00

0337990101

GAFAS

und

0.2500

5.00

1.25 76.50

Partida

03.01.03

Rendimiento

GLB/DIA

Código

Descripción Recurso

EQUIPOS DE PROTECCION COLECTIVA MO 1.0000

EQ

1.0000

Costo unitario directo por: GLB Unidad

Equipos

Cuadrilla

Cantidad

Precio SI.

4,000.00 Parcial SI.

(ló g p Página:

S10

4

Análisis de precios unitarios Presupuesto Subpresupuesío

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 20/08/2012 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Fecha presupuesto

Partida

03.01.04

Rendimiento

GLB/DIA

Código

Descripción Recurso

SEÑALIZACION TEMPORAL DE SEGURIDAD Costo unitario directo por: GLB

EQ. 1.0000

MO 1.0000

Unidad

Cuadrilla

19,750.00

Cantidad

Precio SI.

Parcial SI.

50 0000

70.00

3,500.00

Materiales 0207900003

ROL

CINTA DE SEÑALIZACION

3,500.00 Equipos 0348760055

CONOS REFLECTIVOS

und

50,0000

25.00

1,25000

0348880002

CARTELES DE SEGURIDAD

und

50.0000

150.00

7,500.00

0348880003

CARTELES DE CONSERVACION DEL AMBIENTE

und

50.0000

150.00

7,500.00 16,250.00

Partida

03.01.05

Rendimiento

GLB/DIA

Código

Descripción Recurso

CAPACITACION EN SEGURIDAD Y SALUD MO.

EQ.

Costo unitario directo por: GLB Unidad

Cuadrilla

5,000.00

Cantidad

Precio SI.

Parcial SI.

10.0000

500.00

5,000.00

Mano de Obra 0198010049

CAPACITACION EN SEGURIDAD Y SALUD

GLB

5,000.00 Partida

03.02.01

Rendimiento

GLB/DIA

Código

Descripción Recurso

RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO MO 1.0000

EQ

1.0000

Costo unitario directo por: GLB Unidad

Cuadrilla

Cantidad

Precio SI.

5,400.00 Parcial SI.

Equipos 0348880004

BOTIQUINES

und

20 0000

50,00

1,000.00

0348880005

EXTINTORES

und

20.0000

220.00

4,400.00 5,400.00

Partida

04.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CORTE DE MATERIAL A NIVEL DE SUB-RASANTE MO 400.0000

EQ

400.0000

Costo unitario directo por: m3 Unidad

5.48

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0400

11.86

0.47

Mano de Obra 0147010004

PEON

hh

0.47 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349040096

TRACTOR A ORUGAS 140 HP

hm

1.0000

3.0000

0.47

0.0200

250.00

0.01 5.00 5.01

Partida

04.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO CON MATERIAL PROPIO PARA NIVELAR SUB RASANTE MO 300.0000

EQ

300.0000

Costo unitario directo p o r: m3 Unidad

12.08

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0533

11.86

0.63

Mano de Obra 0147010004

PEON

hh

/fV re * i

Materiales 0239050000

AGUA

0.83

'A

|

m3

0.18!»

5.00

0.90 0.90

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.63

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

0.5000

0.0133

100.00

1.33

0349030007

RODILLO LISO VIBR AUTOP101-135HP10-12T

hm

0,5000

0.0133

150.00

2.00

0349040093

CARGADOR FRONTAL CAT- 930

hm

■~^L5000

0349090000

MOTONIVELADORA DE 125 HP

hm

\

0.0133

180.00

2.39

0.0267

180.00

4.81

----- 1 /

Consorcio

/

10.55

i/ / iSULT

A m p u t o ¿ í u z A r a v a lo Representante Legal

0.02

i.Fern

’lLean

d£5p Página:

S10

5

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO___________________ Fecha presupuesto___________ 20108/2012

Partida

04.03

COMPACTACION Y CONFORMACION DE SUB-RASANTE

Rendimiento

m2/DIA

Código

Descripción Recurso

MO. 800.0000

EQ. 800.0000

Costo unitario directo por: m2 Unidad

4.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0100

11.86

0.12

Mano de Obra 0147010004

PEON

hh

0.12

Materiales 0239050000

0.0200

m3

AGUA

5.00

010 0.10

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.12

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

0.5000

0.0050

100.00

0349030007

RODILLO LISO VIBR AUTOP101-135HP10-12T

hm

1.0000

0.0100

150.00

150

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0100

180 00

1.80

0.50

3.80 Partida

04.04

Rendimiento

m3/DIA

Código

Descripción Recurso

CORTE DE TERRENO CON EQUIPO EN ZONA DE MATERIAL ORGANICO MO 350.0000

EQ

350.0000

Costo unitario directo p o r: m3 Unidad

4.68

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0457

11.86

0.54

Mano de Obra 0147010004

PEON

hh

0.54 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

3.0000

0.54

0.0229

180.00

002 4.12 4.14

Partida

04.05

Rendimiento

M3/DIA

Código

Descripción Recurso

RELLENO CON MATERIAL DE PRESTAMO EN ZONA DE MATERIAL ORGANICO MO 250.0000

EQ. 250.0000

Costo unitario directo por: M3 Unidad

28.84

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

00640

11.86

076

Mano de Obra 0147010004

PEON

hh

0.76 Materiales 0204020002

MATERIAL DE PRESTAMO SELECCIONADA EN ZONA DE MAT. ORGANICO

m3

1.2000

15.00

0239050000

AGUA

m3

0.0600

5.00

18.00 0.30 18.30

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

076

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

0.5000

0.0160

100.00

1.60

0349030007

RODILLO USO VIBR AUTOP 101-135HP10-12T

hm

0.5000

0.0160

150.00

2.40

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0320

180.00

5.76

0.02

0.78

Rendimiento

m3/DtA

MO. 12.0000

Código

Descripción Recurso

EQ. 12.0000

Costo unitario directo por: n»3 Unidad

27.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

1.3333

11.86

15.81

Mano de Obra 0147010004

PEON

hh

15.81 Materiales 0239050000

AGUA

m3

0.1800

5.00

0.90

Página:

S10

6

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI 20/08/2012 Fecha presupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A l C.P. SAN JOSÉ DESDE PUERTO CALLAO

04.07

EXCAVACION MANUAL SARDINEL

Rendimiento

m3/DIA

MO 3.0000

Código

Descripción Recurso

EQ

Costo unitario directo por: m3

3.0000 Unidad

32.68

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

1.0000

2.6667

11.86

31.63

Mano de Obra 0147010004

hh

PEON

31.63 Equipos 0337010001

3.0000

%MO

HERRAMIENTAS MANUALES

31.63

0.95 0.95

04.08

RELLENO Y COMP.MATERIAL PROPIO SARDINEL

Rendimiento

m3/DIA

MO 12.0000

Código

Descripción Recurso

EQ

12.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

2.0000

1.3333

11.86

26.68 Parcial SI.

Mano de Obra 0147010004

PEON

hh

15.81 15.81

Materiales 0239050000

AGUA

m3

0.0600

5.00

0.30 0.30

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349030001

COMPACTADOR VIBR. TIPO PLANCHA 4 HP

hm

1.0000

3.0000

15.81

0.47

0.6667

15.00

10.00 10.47

04.09

EXCAVACION MANUAL PARA CANALETAS

Rendimiento

M3/DIA

MO 3.0000

Código

Descripción Recurso

EQ

3.0000

Costo unitario directo por: M3 Unidad

32.68

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1 0000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

31.63

0.95 0.95

04.10

RELLENO COMPACTADO CON MATERIAL PROPIO - CANALETAS

Rendimiento

m3/DIA

Código

Descripción Recurso

MO. 12.0000

EQ

12.0000

Costo unitario directo p o r: m3 Unidad

26.58

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Z0000

1.3333

11.86

15.81

Mano de Obra 0147010004

PEON

hh

(

d^

>

Página:

S10

7

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

04.11

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ELIMINACION DE MATERIAL EXCEDENTE MO 500.0000

Costo unitario directo por: m3

EQ. 500.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

2.0000

0.0320

11.86

6.47 Parcial SI.

Mano de Obra 0147010004

hh

PEON

0.38 0.38

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.38

0.01

0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

2.88

0349070069

VOLQUETE VOLV015 M3

hm

2 0000

0.0320

100.00

3.20 6.09

Partida

05.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SUB BASE GRANULAR MO 1,200.0000

EQ

1,200.0000

Costo unitario directo por: m2 Unidad

20.36

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2 0000

0.0133

11.86

0.16

Mano de Obra 0147010004

PEON

hh

0.16 Materiales 0204110023

TIERRA ROJA

m3

0.0480

25.00

120

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1920

80.00

15.36

0239050000

AGUA

m3

0.1000

5.00

050 17.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.16

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

0.5000

0.0033

100.00

0349030007

RODILLO LISO VIBR AUTOP 101-135HP 10-12T

hm

1.0000

0.0067

150.00

1.01

0349040093

CARGADOR FRONTAL CAT- 930

hm

0.5000

0.0033

180.00

0.59

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0067

180.0)

0.33

1.21 3.14

Partida

05.02

Rendimiento

ra2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO LOSA DE CONCRETO MO 18.0000

EQ. 18.0000

Costo misario directo p o r: m2 Unidad

26.14

Cuadrilla

Cantidad

Precio SI.

Pardal SI. 6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85 12.58

Materiales 0202010005

CLAVOS PARA MADERA C/C 3“

kg

0,3300

450

0202040010

ALAMBRE NEGRO N°8

kg

0.3000

4.30

1.29

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

2 2000

2.00

4.40

0260000011

TEKNOPORT DE 12 MM.

m2

0.3500

8.00

2.80

026000)012

TEKNOPORT DE 25 MM.

m2

0.2000

16.00

,í 0'v' \ 5

Equipos 0337010001

HERRAMIENTAS MANUALES

M \

y

1.49

3.20 13.18

N

V '

%MO

3.0000

12.58

0.38 0.38

A m p a ro D íaz A revala R e p re s e n ta n te Legal

<&) Página:

S10

8

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

05.03

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

PAVIMENTO DE CONCRETO FC= 210 KG/CM2 E=0.20 M MO 100.0000

EQ

100.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

76.99

Cantidad

Precio SI.

Pardal SI. 242

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.1600

15.14

0147010003

OFICIAL

hh

1.0000

0.0800

13.16

1.05

0147010004

PEON

hh

8.0000

0.6400

11.86

7.59 11.06

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

2.0000

2150

43 00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.2500

80.00

20.00

0239050000

AGUA

m3

0.0400

5.00

0.20 63.20

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

11.06

0.33

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.0800

25.00

2.00

0349070003

VIBRADOR DE CONCRETO 4 HP 1.50"

hm

1.0000

0.0800

5.00

0.40 2.73

Partida

05.04

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO EN BERMAS FT=4200 KG/CM2 MO 200.0000

EQ. 200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

Cantidad

Precio SI.

5.15 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0 0400

1316

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0203010007

ACERO DE REFUERZO FV=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

0.30 368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

05.05

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO EN CALZADA F'Y=4200 KG/CM2 MO 200.0000

EQ

200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N” 16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 6 0 ^ ^ ^

kg

1.0500

3.50

368

,

. Equipos 0337010001

HERRAMIENTAS MANUALES

3.98 y f r w j v i //$ V ,,;, ... VVl U X & r

1

%MO

3.0000

1.14

0.03 0.03

\.Fernti»do Rafael Lean C 'TD1fM

A taparo D íaz A revalo ''R e p r e s e n t a n t e Legal

(M G E M E R O e n m .

9

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P, SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI 20/08/2012 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO Fecha presupuesto

Partida

05.06

Rendimiento

KG/DIA

Código

Descripción Recurso

ACERO CORRUGADO (BASTONES EN JUNTAS TIP 0 1) MO. 200.0000

EQ

Costo unitario directo por: K6

200.0000 Unidad

4.85

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

10000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

1.0500

kg

3.50

368 3.68

Equipos 0337010001

%MO

HERRAMIENTAS MANUALES

3.0000

1.14

0.03 0.03

Partida

05.07

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO CORRUGADO (BASTONES EN JUNTAS TIPO 3) MO 200.0000

EQ

200.0000

Costo unitario directo por: kg Unidad

5.93

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0203010007

ACERO OE REFUERZO Fy-4200 kgfcm2 GRADO 60

kg

1.0700

3.50

3.75

0210140079

TUBO PVC SAP 11/4"

ML

0.1000

4.00

0.40

0253910011

GRASA

kg

0,0500

5.20

0.26

0254110090

PINTURA ESMALTE

gln

0.0100

35.00

0.35 4.76

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

06.01

Rendimiento

m/DIA

Código

Descripción Recurso

RELLENO DE JUNTAS ASFALTICAS DE 9 mm MO 40.0000

EQ

40.0000

Costo unitario directo por: m Unidad

Cuadrilla

Cantidad

1.0000

0.2000

Precio SI.

3.03 Parcial SI.

Mano de Obra 0147010004

PEON

hh

2.37 2.37

Materiales 0204000000

ARENA FINA

m3

0.0005

50.00

0.03

0213000006

ASFALTO RC-250

gln

0.0225

7.00

0.16 0.19

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348080066

COCINA DE ASFALTO

hm

1.0000

3.0000

237

0.07

0.2000

2.00

0.40 0.47

06.02

RELLENO DE JUNTAS ASFALTICAS DE E= 20 mm

Rendimiento

m/DIA

Código

Descripción Recurso

MO 20.0000

EQ

20.0000

Costo unitario directo por: m Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

0.4000

11.86

6.07 Parcial SI.

Mano de Obra 0147010004

PEON

hh

4.74 4.74

Materiales 0204000000

ARENA FINA

m3

0.0010

50.00

0.05

0213000006

ASFALTO RC-250

gln

0.0480

7 00

0.34 0.39

S10

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

06.02

Rendimiento

m/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

RELLENO DE JUNTAS ASFALTICAS DE E= 20 mm EQ

MO 20.0000

Costo unitario directo por: m

20.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

0.4000

11.86

6.07 Parcial S/.

Mano de Obra 0147010004

hh

PEON

4.74 4.74

Materiales 0204000000

ARENA FINA

m3

0.0010

50.00

005

0213000006

ASFALTO RC-250

gln

0.0480

7.00

0.34 0.39

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348080066

COCINA DE ASFALTO

hm

1.0000

3.0000

4.74

0.14

0.4000

2.00

0.80 0.94

Partida

07.01.01

Rendimiento

ML/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO MO 1,000.0000

EQ

1,000.0000

Costo unitario directo por. ML Unidad

80.61

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra hh

1.0000

0.0080

15.14

0.12

PEON

hh

3.0000

0.0240

11.86

8 d

0229030006

CAL

kg

0.0300

1.50

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

0.0200

2.00

0.04

0254110090

PINTURA ESMALTE

gln

0.0030

35.00

0.11

S

TOPOGRAFO

0147010004

o

0147000032

Materiales 0.05

0.20 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349880001

EQUIPO TOPOGRAFICO

hm

1,000.0000

3.0000

0.40

0.01

8.0000

10.00

80.00 80.01

Partida

07.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO CANALETAS (losa de fondo y paredes fe = 210 kg/cm2) MO 15.0000

EQ

15.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

367.43 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hit

1.0000

0.5333

15.14

8.07

0147010003

OFICIAL

hh

1.0000

0.5333

13.16

7.02

0147010004

PEON

hh

8.0000

4.2667

11.86

50.60 65.69

Materiales 0221000000

CEMENTO PORTLAND TiPO t (42.5KG)

0238000004

HORMIGON (PUESTO EN OBRA)

0239050000

AGUA

ifjff

SOL

8.6600

21.50

186.19

m3

1.1000

80.00

88.00

m3

0.1840

5.00

092 275.11

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.00GG

6569

1.97

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

05333

25.00

13.33

0349070003

VIBRADOR DE CONCRETO 4 HP 1.50'

hm

0 5000

0.2667

5.00

133 16.63

A ntff/fro 15íaz A r e v a lo Legal

(¡69? Página:

S10

11

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE yÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

07.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO CANALETAS (TECHO fe = 210 kg/cm2) MO 18.0000

Costo unitario directo por: m3

EQ. 18.0000 Unidad

Cuadrilla

Cantidad

Precio SI.

379.67 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0 4444

15.14

6.73

0147010003

OFICIAL

hh

2.0000

0.8889

13.16

11.70

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 60.60

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

10.0000

2150

215.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.1000

80.00

88.00

0239050000

AGUA

m3

0.1840

5.00

0.92 303.92

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

60.60

1,82

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25 00

11.11

0349070003

VIBRADOR DE CONCRETO 4 HP 1.50"

hm

1.0000

0.4444

5.00

2.22 15.15

Partida

07.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 175 KG/CM2- LOSA/FONDO Y PAREDES MO 15.0000

EQ

Costo unitario directo por: m3

15.0000 Unidad

357.43

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 8.07

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5333

15.14

0147010003

OFICIAL

hh

1 0000

05333

13.16

7.02

0147010004

PEON

hh

80000

4.2667

11.86

50.60 65.69

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

8.6600

21.50

186.19

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.1000

80.00

88.00

0239050000

AGUA

m3

0.1840

5.00

092 275.11

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

65.69

1.97

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

10000

0.5333

25.00

13.33

0349070003

VIBRADOR DE CONCRETO 4 HP 1.50’

hm

0.5000

0.2667

5.00

1.33 16.63

Partida

07.02.04

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2 EN TECHOS 1TAPAS MO 18.0000

EQ. 18.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

379.67 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

6.73

0147010003

OFICIAL

hh

2.0000

0.8889

13.16

11.70

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 60.60

Materiales

022100)000

CEMENTO PORTLAND TIPO I ¡42.5KG)

BOL

10.0000

21.50

215.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.1000

80.00

88.00

0239050000

AGUA

m3

0.1840

5.00

0.92 303.92

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

60 60

1.82

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4444

25 00

11.11

0349070003

VIBRADOR DE CONCRETO 4 HP 1.50"

hm

1.0000

0.4444

5.00

2.22 15.15

A m p tfr o D ía z A r e v a lo R ep re s e n ta n te Legal

d Página:

S10

12

Análisis de precios unitarios Presupuesto Subpresupuesto

0482001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI 20/08/2012 Fechapresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

07.02.05

Rendimiento

M2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO DE CANALETAS MO 18.0000

EQ

Costo unitario directo por: M2

18.0000 Unidad

Cuadrilla

Cantidad

25.62

Precio SI.

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.0444

14.36

0.64

0147010002

OPERARIO

hh

1.0000

0.4444

15.14

673

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85 13.22

Materiales 0202010005

CLAVOS PARA MADERA C/C 3‘

kg

0.0800

4.50

0.36

0202040010

ALAMBRE NEGRO N” 8

kg

0.2000

430

086

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

2.5000

2.00

5.00

0244030023

TRIPLAY DE 4'x8'x 8 mm

pin

0.1700

34.00

578 12.00

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

13.22

0.40 0.40

Partida

07,02.06

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FT=4200 KG/CM2 CANALETAS MO 200.0000

EQ

200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1 0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0203010007

ACERO DE REFUERZO F”y=4200 kgfcm2 GRADO 60

kg

1.0500

3.50

0.30 3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

07.02.07

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2 MO 200.0000

EQ

200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

Cantidad

Precio SI.

5.15 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°Í6

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

__ T %MO

3.0000

1.14

003 0.03

A m p a r o D ía z A r e v u lo R e p re s e n ta n te . L e g a l

Q ó ^ > Página:

S10

13

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

07.02.08

Rendimiento

M/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08Í2012

WATER STOP NEOPRENE 8" EN CANALETAS MO 48.0000

EQ

Costo unitario directo por: M

48.0000 Unidad

30.84

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 2.52

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1667

15.14

0147010004

PEON

hh

1.0000

0.1667

11.86

1.98 4.50

Materiales 0230650005

JUNTA INPER WATER STOP NEOPRENE 6’

1.0500

m

25.00

26 25 26.25

Equipos 0337010001

HERRAMIENTAS MANUALES

2.0000

%MO

4.50

009 0.09

Partida

07.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 175 KG/CM2 EN SARDINELES MO 15.0000

EQ

15.0000

Costo unitario directo por: m3 Unidad

359.58

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.0533

14.36

0.77

0147010002

OPERARIO

hh

1.0000

0.5333

15.14

807

0147010003

OFICIAL

hh

1.0000

0.5333

13.16

7.02

0147010004

PEON

hh

8.0000

4.2667

11.86

50.60 66.46

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

8.6600

21.50

186.19

0238000004

HORMIGON [PUESTO EN OBRA)

m3

1.1000

80.00

88.00

0239050000

AGUA

m3

0.1840

5.00

092 275.11

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

66.46

1.99

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.5333

25.00

13.33

0349070003

VIBRADOR DE CONCRETO 4 HP 150"

hm

1.0000

0.5333

5.00

2.67 17.99

Partida

07.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO DE SARDINEL MO 18.0000

EQ

18.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

25.66

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.0444

14.36

0.64

0147010002

OPERARIO

hh

1.0000

0.4444

15.14

6.73

0147010003

OFICIAL

hh

1.0000

04444

13.16

5.85 13.22

Materiales 0202040010

ALAMBRE NEGRO N”8

0202100099

CLAVOS DE 3"

0243000025 0244030023

y%

•<9

0.2000

430

kg

0.0800

5.00

0.40

MADERA NACIONAL PARA ENCOFRADO

p2

2.5000

2.00

5.00

TRIPLAY DE f»S« 8 mm

pin

0.1700

34.00

t p f t l n a ¡p ff' - j i jt 'f y

086

5.78 12.04

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1322

0.40 0.40

Página:

S10

14

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

07.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO 1=7=4200 KG/CM2 SARDINELES MO 200.0000

Costo unitario directo por: kg

EQ. 200.0000 Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

10500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

07.03.04

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F7=4200 KG/CM2 MO 200.0000

EQ. 200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

350

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

30000

1.14

003 0.03

Partida

08.01

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO DE MARTILLOS Y INTERSECCIONES MO 12.0000

EQ. 12.0000

Costo unitario directo por: m2 Unidad

25.95

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 10.09

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.6667

15.14

0147010003

OFICIAL

hh

1.0000

0.6667

13.16

877 18.86

Materiales 0202040010

ALAMBRE NEGRO N°8

kg

0.2600

4.30

1.12

0202100099

CLAVOS DE 3"

kg

0.0800

5.00

0.40

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

2.5000

2.00

5.00 6.52

0337010001

Equipos HERRAMIENTAS MANUALES

¡l¡ V .

%MO

3.0000

18.86

0.57 0.57

Q Página:

S10

15

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI 20/08/2012 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

08.02

CONCRETO F'C=175 KG/CM2 PARA MARTILLOS

Rendimiento

m2/DIA

MO 10.0000

Código

Descripción Recurso

EQ

Costo unitario directo por: m2

10.0000 Unidad

134.38

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.8000

13.16

10.53

0147010004

PEON

hh

5.0000

4.0000

11.86

47 44 70.08

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

1.1300

21.50

24.30

0238000000

HORMIGON

m3

0.2000

80.00

16.00

0239050000

AGUA

m3

0.1000

5.00

0.50 40.80

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349100007

MEZCLADORA CONCRETO TAMBOR 18HP11P3

hm

1.0000

5.0000

70.08

350

0.8000

25.00

20.00 23.50

09.01.01

LIMPIEZA DE TERRENO

Rendimiento

m2/DIA

MO. 120.0000

Código

Descripción Recurso

EQ

120.0000

Costo unitario directo por: m2 Unidad

0.81

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0667

11.86

079

Mano de Obra 0147010004

PEON

hh

0.79 Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

0.79

0.02 0.02

09.01.02

TRAZO, NIVEL Y REPUNTEO

Rendimiento

m2/DIA

MO 500.0000

Código

Descripción Recurso

EQ

500.0000

Costo unitario directo por; m2 Unidad

1.85

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 014700)032

TOPOGRAFO

hh

1.0000

0.0160

15.14

0.24

0147010003

OFICIAL

hh

1.0000

0.0160

13.16

0.21

0147010004

PEON

hh

3.0000

0.0480

11.86

0.57 1.02

Materiales 0202100099

CLAVOS DE 3'

kg

0.0090

5.00

0.05

0229220001

CORDEL

ML

0.1500

0.20

0.03

0243160052

REGLA DE MADERA

p2

0.2000

2.00

0.40

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349880001

EQUIPO TOPOGRAFICO

hm

0.48

2.0000

3.0000

1.02

0.03

0.0320

10.00

0.32 0.35

Partida

09.01.03

SEÑALIZACION Y SEGURIDAD EN ZONA DE TRABAJO

Rendimiento

und/DIA

Código

Descripción Recurso

MO. 2.5000

EQ

2.5000

Costo unitario directo por: und Unidad

73.98

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

0.5000

1.6000

11.86

18.98

Mano de Obra 0147010004

PEON

hh

18.98 Materiales 0229040091

CINTA SEÑALADORA AMARILLA

ROL

1.0000

55.00

55.00

g )

Q Página:

S10

o W 16

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

09.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CORTE DE TERRENO A MAQUINA MO 120.0000

EQ

Costo unitario directo por: m3

120.0000 Unidad

26.66

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.1333

11.86

158

Mano de Obra 0147010004

hh

PEON

1.58 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.58

0.05

0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0667

180.00

12.01

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0667

180.00

12.01 24.07

Partida

09.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

NIVELACION Y COMPACTADO DEL TERRENO MO 100.0000

EQ

100.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

4.40 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

00800

15.14

1.21

0147010004

PEON

hh

20000

0.1600

11.86

1 90 3.11

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349030001

COMPACTADOR VIBR. TIPO PLANCHA 4 HP

hm

1.0000

3.0000

3.11

0.0800

15.00

0.09 1.20 1.29

09.02.03

CONFORMACION DE LA SUB RASANTE

Rendimiento

m2/DIA

Código

Descripción Recurso

MO 2,500.0000

EQ

2,500.0000

Costo unitario directo por: m2 Unidad

10.21

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

00064

11.86

0.08

Mano de Obra 0147010004

PEON

hh

0.08 Materiales 0204110023

TIERRA ROJA

m3

0.0300

25.00

0238000000

HORMIGON

m3

0.1000

80.00

0.75 8.00 8.75

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.08

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

1.0000

0.0032

100.00

0.32

0349030007

RODILLO LISO VIBR AUTOP101-136HP10-12T

hm

1.0000

0.0032

150.00

0.48

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0032

180.00

0.58 1.38

09.03.01

SUMINISTRO E INSTALACION SISTEMA TERRAMESH VERDE (2.00 X 4.00 X 0.80)

Rendimiento

und/DIA

Código

Descripción Recurso

MO 40.0000

EQ

40.0000

Costo unitario directo por: und Unidad

660.71

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.2000

15.14

3.03

0147010003

OFICIAL

hh

1.0000

0.2000

13.16

263

0147010004

PEON

hh

2.0000

0.4000

11.86

4.74 10.40

Materiales 0202130031

ELEMENTO TERRAMESH VERDE) 4.00 X 2.00 X 0.60 - 70°)M

und

1.0000

650.00

650.00 650.00

Equipos

)

<¡ Página:

S10

55 > 17

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO ■UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

09.03.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupueste

20/08/2012

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO MO 720.0000

EQ

720.0000

Costo unitario directo por: m3 Unidad

37.02

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

2.0000

0.0222

11.86

0.26

Mano de Obra 0147010004

PEON

hh

0.26 Materiales 0204110021

TIERRA SELECCIONADA (PUESTA EN OBRA)

m3

1.3000

25 00

0239050000

AGUA

m3

0.0600

5.00

32.50 0.30 32.80

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.26

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

1 0000

0.0111

100.00

1.11

0349030007

RODILLO USO VIBR AUTOP 101-135HP 10-12T

hm

0.5000

0.0056

150.00

0.84

0349090000

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0111

180.00

200

0.01

3.96 Partida

10.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla) MO 60.0000

EQ. 60.0000

Costo unitario directo por: m2 Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

632

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

10.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO MO 500.0000

EQ. 500.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

1.77

Precio SI.

Parcial SI. 0.24

Mano de Obra 0147010002

OPERARIO

0147010004

PEON

f

hh

1.0000

0.0160

15.14

hh

2.0000

0.0320

11.86

0.38 0.62

Materiales 0230020001

YESO DE 28 Kg

0244010000

ESTACA DE MADERA

K 'S

I

/ . B

BOL

0.0500

21.00

1.05

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

10.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO MO 3.0000

EQ. 3.0000

Costo unitario directo por: m3 Unidad

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

2.6667

11.86

3163

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3 0000

31.63

095 0.95

(J V t p p Página:

S10

^ - 4 8 -----

Análisis de precios unitarios Presupuesto Subpresupueste

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA MO 9.0000

EQ. 9.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

85.96 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

08889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

08889

20.00

17.78 18.82

Partida

10.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE CI EQUIPO MO 500.0000

EQ

500.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

2.0000

0.0320

11.86

5.18 Parcial SI.

Mano de Obra 0147010004

PEON

hh

0.38 0.38

Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VOLV014 M3

hm

1.0000

0.0160

120.00

288 1.92 4.80

Partida

10.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SOLADO 1:10 E= 4"

MO 70.0000

EQ. 70.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

31.08 Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

173

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO 1(42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3 ---------------------------------------------------------------- i

%MO I

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

286

/ i/ ¥ Dl\ Y mu í j fsninol U CMKí/é

3.16

£ idfpae: MCh k

r o D ía z A r e v a lo Representante Legal

INiSUEMERO CWHL

S10

Página:

19

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

fecha presapuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR MO 20.0000

EQ. 20.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI. 12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

526

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

2150

193.50

0238000000

HORMIGON

m3

1.3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3,0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0,4000

20.00

8.00 19.66

Partida

10.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO 200.0000

EQ. 200.0000

Costo unitario directo por: kg Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3,0000

1.14

0.03 0.03

Partida

10.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS MO 18.0000

EQ

18.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

367.13

Cantidad

Precio SI.

Parcial SI. 6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0,4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipas 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

222 13.88

.Amparo D ía z A revala R e p re s e n ta n te Legal

( jn p Página:

S10

20

Análisis de precios unitarios Presupuesto

0492001

Subpresapuesio

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VlA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO. 14.0000

EQ.

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

8.65

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3'

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANDALES

3.0000

%MO

15.43

0.46 0.46

Partida

10.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F’y=4200 kg/cm2 GRADO 60

kg

1 0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

10.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario árecto p o r: m3

Unidad

Cuadrilla

373.53

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13 16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000000

HORMIGON

jf p

0239050000

AGUA

M * ' ™ ) P * 3 ¡ bS u

A m

BOL

9.0000

2150

193,50

m3

1.3000

80 00

104.00

m3

0.2100

5.00

. ¡i

1 05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40-

%MO A

3.0000

55.32

1.66

hm

1.0000

0.4000

25.00

10.00

hm

1.0000

0.4000

20.00

8.00 19.66

AlffptU'O D ía z A r e v u l o R e p re s e n ta n te L e g a l

(jftfp Página:

S10

21

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.04.03.02

Rendimiento

m2/DlA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO. 14.0000

Costo unitario directo p o r: m2

EQ. 14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

10000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3*

kg

0.2000

5.00

1.13 1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

3.1X00

%MO

15.43

0.46 0.46

Partida

10.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO. 200.0000

EQ. 200.0000

Costo unitario directo p o r . kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0203010007

ACERO DE REFUERZO F'y=4200 kgfcm2 GRADO 60

kg

0.0600

5.00

0.30

kg

1.0500

350

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

10.04.04.01

Rendimiento

ML/DIA

Código

Descripción Recurso

JUNTAS DE DILATACION CON WATER STOP

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: ML

Unidad

Precio SI.

27.66

Cuadrilla

Cantidad

hh

1.0000

0.4000

15.14

6.06

hh

1.0000

0.4000

1316

5.26

Parcial SI.

Mano de Obra 0147010002

OPERARIO

0147010003

OFICIAL

\ i

11.32 Materiales 0237020049

\

i y

WATER STOP

ml

1.0000

16.00

16.00 16.00

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

11.32

0.34 0.34

Partida

11.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

EQ. 60.0000

Costo unitario directo p o r: m2

Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

A m p p r o D ía z A r e v a lo ^ s p íe s a n U n tfc L e g a l

(M p’ Página:

S10

22

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20(08(2012

TRAZO, NIVELACION Y REPUNTEO DE ALCANTARILLADO

MO. 500.0000

EQ

500.0000

Costo unitario directo p o r: m2

Unidad

1.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

00160

15.14

0.24

0147010004

PEON

hh

2.0000

0.0320

11.86

038 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

008 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

11.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ. 3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio Sí.

1.0000

2.6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

3163

0.95 0.95

Partida

11.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ

9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

/ ' "

Materiales

"

' • A

0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

f r

32 50 0.10 32.60

. J Equipos 0337010001

HERRAMIENTAS MANUALES

%MQ

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

Partida

11.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C1 EQUIPO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m3 Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O LV 014 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Representante Legal

(jg n j Página:

S10

23

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

SOLADO 1:10 E= 4"

MO

70.0000

EQ.

Costo unitario directo por :m 2

70.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86 3.16

Partida

11.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2 0000

0.8000

15.14

0147010003

OFICIAL

íih

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80 00

10400

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

11.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Cosío unitario directo por kg Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53

KTH* Materiales

1.14

,t.

0202040009

ALAMBRE NEGRO N"16

0203010007

ACERO DE REFUERZO F>=4200 kg/cm2 GRAD^

1

uJHm* r j j

XV :i'u

!

kg

0.0600

5.00

0.30

kg

1.0500

3.50

3.68

kfTi

3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

003

Página:

S10

24

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Facha presupuesto

20/08/2012

CONCRETO PC=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

367.13

Precio SI.

Parcial S/.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40'

hm

1.0000

0.4444

500

2.22 13.88

Partida

11.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial Sí.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

865

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

046 0.46

11.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

Rendimiento

kg/DIA

Código

Descripción Recurso

MO

200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5 .1 5

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N*16

i
0.0600

5.00

030

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60 (

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

fít. «.

%MO ■
3.0000

Coi ^ tP U ° 4 0 8 9

Representante Legal

0.03 0.03

'• 'II

A m g á r o D ía z A r e v a l o

1.14

m u tn o B R O a v u

Análisis de precios unitarios Presupuesto

0492001

Subpresapuesio

«01

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

1211

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO l (42.5KG)

BOL

9.0000

21.50

193 50

0238000000

HORMIGON

m3

1.3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40”

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

11.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

10000

0.5714

15.14

0147010004

PEON

hh

1.0000

0,5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

0.2500

4.50

0202100099

CLAVOS DE 3*

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Prtda

11.04.03.03

ACERO DE REFUERZO FY=4200 KG/CM2

Rendimiento

kg/DIA

Código

Descripción Recurso

MO. 200.0000

EQ.

200,0000

Costo unitario directo p o r: kg Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

.3.0000

114

0.03 0.03

12.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

Rendimiento

m2/DIA

Código

Descripción Recurso

MO

60.0000

EQ

60.0000

Costo unitario directo p o r : m2 Unidad

Cuadrilla

Cantidad

Mano de Obra 0147010004

6.51

Precio SI.

Pardal SI.

11.86

6.32

t

PEON

hh

4.0000

0.5333

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

A m p a v ó D í a z A r a va la Representante kegal

W rtftfeM tK R Q C t V t L

Página:

26

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

Costo unitario directo p o r: m2

EQ. 60.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

4.0000

0.5333

11.86

6.51

Parcial SI.

Mano de Obra 0147010004

hh

PEON

6.32 6.32

Equipos 0337010001

3.0000

%MO

HERRAMIENTAS MANUALES

6.32

0.19 0.19

Partida

12.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ

Costo unitario directo p o r: m2

500.0000

Unidad

Cuadrilla

Cantidad

1.77

Precio SI.

Parcial SI.

0.24

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0147010004

PEON

hh

2.0000

0.0320

11.86

038 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

P2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

12.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

2.6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

31.63

0.95 0.95

12.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

Rendimiento

m3/DIA

MO. 9.0000

Código

Descripción Recurso

EQ

9.0000

Costo unitario directo p o r : m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

20000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50

0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

Ip ip a r o

D ía z A r e va lo

Representante Legal

Página:

S10

27

Análisis de precios unitarios Presupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m3

Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL C A Í- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O L V 0 14 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Partida

12.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SO LA D01:10 E= 4"

MO. 70.0000

H3. 78.0000

Costo unitario directo p o r : m2

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6 0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86 3.16

Partida

12.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3 Unidad

373.53

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

3795 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DÉ CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

1000

0349070055

VIBRADOR DE CONCRETO 4 HP 2,40"

hm

1.0000

0.4000

20.00

8.00 19.66

Mmip a rv D ía z A re va lo Represantem e Legal

S10

Página:

28

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO F,Y=4200 KG/CM2

MO. 200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

00400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

k9

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

12.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

367.13

Cantidad

Precio SI.

Parcial SI.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

8.0000

3 5556

11.86

4217 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

5475

055

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

222 13.88

12.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

Rendimiento

m2/DIA

Código

Descripción Recurso

MO

14.0000

EQ

14.0000

Costo unitario directo p o r: m2

Unidad

2 7 .0 2

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

678 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

i
0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

F rn itu d ^ m L e a n < ¿ Ü C JP

40894\

«M O feM U E R O eS V IL

A th p a r o D ía z A r e v a l o Representante Legal

Q °$ > Página:

S10

29

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ.

Costo unitario directo p o r: kg

200.0000

Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kgfcm2 GRADO 60

kg

1.0500

350

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

12.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373 .53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25 00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP2.401

hm

1.0000

0.4000

20.00

800 19.66

Partida

12.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2 Unidad

27.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2600

4.50

1.13

0202100099

CLAVOS DE 3"

•<9

0.2000

500

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.48

A m ipaf-o p

A re v a lo

f t eSpissentantó om i Legal

Página:

30

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Facha pospuesto

20/08/2012

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

Costo unitario directo p o r: kg

200.0000

EQ.

Unidad

Cuadrilla

Cantidad

Precio S/.

5.15

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO FV=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

13.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO, 60.0000

EQ.

60.0000

Costo unitario directo p o r: m2

Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

13.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ.

500.0000

Costo unitario directo p o r : m2

Unidad

1.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0.24

0147010004

PEON

hh

2.0000

0.0320

11.86

0.38 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

13.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

2,6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES ¡ 5 c c n a te 1 0 * 8 f

Ia\

%MO

3.0000

31.63

i

0.95

------------------------------------------------------ --------------------- W

el lea n h *

A m p a r o D í a z A r e va la Scpresuntante Legal

0.95

tNKjÉNlERO CIVIL

( jn p Página:

S10

20

Análisis de precios unitarios Presupuesto

0492001

Subpresapuesio

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VlA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO. 14.0000

EQ.

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

8.65

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3'

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANDALES

3.0000

%MO

15.43

0.46 0.46

Partida

10.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F’y=4200 kg/cm2 GRADO 60

kg

1 0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

10.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario árecto p o r: m3

Unidad

Cuadrilla

373.53

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13 16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000000

HORMIGON

jfp

0239050000

AGUA

M *

A

m

BOL

9.0000

2150

193,50

m3

1.3000

80 00

104.00

m3

0.2100

5.00

.

'™ )P *3 ¡bS u ¡i

1 05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40-

A

%MO

3.0000

55.32

1.66

hm

1.0000

0.4000

25.00

10.00

hm

1.0000

0.4000

20.00

8.00 19.66

AlffptU'O D ía z A r e v u l o Representante Legal

(jftfp Página:

S10

21

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

10.04.03.02

Rendimiento

m2/DlA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO. 14.0000

Costo unitario directo p o r: m2

EQ. 14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

10000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3*

kg

0.2000

5.00

1.13 1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

3.1X00

%MO

15.43

0.46 0.46

Partida

10.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO. 200.0000

EQ. 200.0000

Costo unitario directo p o r . kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0203010007

ACERO DE REFUERZO F'y=4200 kgfcm2 GRADO 60

kg

0.0600

5.00

0.30

kg

1.0500

350

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

10.04.04.01

Rendimiento

ML/DIA

Código

Descripción Recurso

JUNTAS DE DILATACION CON WATER STOP

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: ML

Unidad

Precio SI.

27.66

Cuadrilla

Cantidad

hh

1.0000

0.4000

15.14

6.06

hh

1.0000

0.4000

1316

5.26

Parcial SI.

Mano de Obra 0147010002

OPERARIO

0147010003

OFICIAL

\ i

11.32 Materiales 0237020049

\

i y

WATER STOP

ml

1.0000

16.00

16.00 16.00

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

11.32

0.34 0.34

Partida

11.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

EQ. 60.0000

Costo unitario directo p o r: m2

Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

A m p p r o D ía z A r e v a lo

^spíesanUntfcLegal

(M p ’ Página:

S10

22

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20(08(2012

TRAZO, NIVELACION Y REPUNTEO DE ALCANTARILLADO

MO. 500.0000

EQ

500.0000

Costo unitario directo p o r: m2

Unidad

1.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

00160

15.14

0.24

0147010004

PEON

hh

2.0000

0.0320

11.86

038 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

008 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

11.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ. 3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio Sí.

1.0000

2.6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

3163

0.95 0.95

Partida

11.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ

9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

/ ' "

Materiales

"

' • A

0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

f r

32 50 0.10 32.60

. J Equipos 0337010001

HERRAMIENTAS MANUALES

%MQ

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

Partida

11.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C1 EQUIPO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m3 Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O LV 014 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Representante Legal

( jg Página:

S10

23

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

SOLADO 1:10 E= 4"

MO

70.0000

EQ.

Costo unitario directo por :m 2

70.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86 3.16

Partida

11.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2 0000

0.8000

15.14

0147010003

OFICIAL

íih

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80 00

10400

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

11.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Cosío unitario directo por kg Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53

KTH* Materiales

1.14

,t.

0202040009

ALAMBRE NEGRO N"16

0203010007

ACERO DE REFUERZO F>=4200 kg/cm2 GRAD^

1

uJHm* r j j

XV :i'u

!

kg

0.0600

5.00

0.30

kg

1.0500

3.50

3.68

kfTi

3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

003

n

j

Página:

S10

24

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Facha presupuesto

20/08/2012

CONCRETO PC=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

367.13

Precio SI.

Parcial S/.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40'

hm

1.0000

0.4444

500

2.22 13.88

Partida

11.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial Sí.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

865

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

046 0.46

11.04.02.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

Rendimiento

kg/DIA

Código

Descripción Recurso

MO

200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5 .1 5

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N*16

i
0.0600

5.00

030

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60 (

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

fít. «.

%MO ■
3.0000

1.14

0.03

'• 'II

Coi ^ tP U ° 4 0 8 9

A m g á ro D íaz A re v a lo

Representante Legal

0.03

mutnoBROavu

Análisis de precios unitarios Presupuesto

0492001

Subpresapuesio

«01

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

11.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

1211

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO l (42.5KG)

BOL

9.0000

21.50

193 50

0238000000

HORMIGON

m3

1.3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40”

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

11.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

10000

0.5714

15.14

0147010004

PEON

hh

1.0000

0,5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

0.2500

4.50

0202100099

CLAVOS DE 3*

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Prtda

11.04.03.03

ACERO DE REFUERZO FY=4200 KG/CM2

Rendimiento

kg/DIA

Código

Descripción Recurso

MO. 200.0000

EQ.

200,0000

Costo unitario directo p o r: kg Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

.3.0000

114

0.03 0.03

12.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

Rendimiento

m2/DIA

Código

Descripción Recurso

MO

60.0000

EQ

60.0000

Costo unitario directo p o r : m2 Unidad

Cuadrilla

Cantidad

Mano de Obra 0147010004

6.51

Precio SI.

Pardal SI.

11.86

6.32

t

PEON

hh

4.0000

0.5333

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

A m p a v ó D í a z A r a va la

Representante kegal

W rtftfeM tK R Q C t V t L

Página:

26

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

Costo unitario directo p o r: m2

EQ. 60.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

4.0000

0.5333

11.86

6.51

Parcial SI.

Mano de Obra 0147010004

hh

PEON

6.32 6.32

Equipos 0337010001

3.0000

%MO

HERRAMIENTAS MANUALES

6.32

0.19 0.19

Partida

12.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ

Costo unitario directo p o r: m2

500.0000

Unidad

Cuadrilla

Cantidad

1.77

Precio SI.

Parcial SI.

0.24

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0147010004

PEON

hh

2.0000

0.0320

11.86

038 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

P2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

12.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

2.6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

31.63

0.95 0.95

12.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

Rendimiento

m3/DIA

MO. 9.0000

Código

Descripción Recurso

EQ

9.0000

Costo unitario directo p o r : m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

20000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50

0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

I p i p a r o D í a z A r e va lo Representante Legal

Página:

S10

27

Análisis de precios unitarios Presupuesto

0492001 001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m3

Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL C A Í- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O L V 0 14 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Partida

12.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SO LA D01:10 E= 4"

MO. 70.0000

H3. 78.0000

Costo unitario directo p o r : m2

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6 0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86 3.16

Partida

12.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3 Unidad

373.53

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

3795 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DÉ CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

1000

0349070055

VIBRADOR DE CONCRETO 4 HP 2,40"

hm

1.0000

0.4000

20.00

8.00 19.66

M m ip a rv D ía z A re v a lo Represantem e Legal

S10

Página:

28

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO F,Y=4200 KG/CM2

MO. 200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

00400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

k9

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

12.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

367.13

Cantidad

Precio SI.

Parcial SI.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

8.0000

3 5556

11.86

4217 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

5475

055

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

222 13.88

12.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

Rendimiento

m2/DIA

Código

Descripción Recurso

MO

14.0000

EQ

14.0000

Costo unitario directo p o r: m2

Unidad

27.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

678 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

i
0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

F rn itu d ^ m L e a n

<¿ÜCJP 40894\ «MOfeMUEROeSVIL

A th p a r o D ía z A r e v a l o Representante Legal

Q °$ > Página:

S10

29

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ.

Costo unitario directo p o r: kg

200.0000

Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kgfcm2 GRADO 60

kg

1.0500

350

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

12.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373 .53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25 00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP2.401

hm

1.0000

0.4000

20.00

800 19.66

Partida

12.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2 Unidad

27.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2600

4.50

1.13

0202100099

CLAVOS DE 3"

•<9

0.2000

500

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.48

A m ip p a f-o A re v a lo f t eSpissentantó om i Legal

Página:

30

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

12.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Facha pospuesto

20/08/2012

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

Costo unitario directo p o r: kg

200.0000

EQ.

Unidad

Cuadrilla

Cantidad

Precio S/.

5.15

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO FV=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

13.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO, 60.0000

EQ.

60.0000

Costo unitario directo p o r: m2

Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

13.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ.

500.0000

Costo unitario directo p o r : m2

Unidad

1.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0.24

0147010004

PEON

hh

2.0000

0.0320

11.86

0.38 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

13.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

2,6667

11.86

32.58

Parcial SI.

Mano de Obra 0147010004

PEON

hh

31.63 31.63

Equipos 0337010001

HERRAMIENTAS MANUALES ¡ 5 c c n a te 1 0 * 8 f

Ia\

%MO

3.0000

31.63

i

0.95

------------------------------------------------------ --------------------- W

el lea n h *

A m p a ro D ía z A r e vala

Scpresuntante Legal

0.95

tNKjÉNlERO CIVIL

© > Página:

S10

31

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

13.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ. 9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 010 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

1778 18.82

Partida

13.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ.

500.0000

Costo unitario directo p o r: « 3

Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0,38 Equipos 0349040093

CARGADOR FRONTAL C A Í- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VOLVO 14 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Partida

13.83.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SO LA D01:10 E= 4"

MO

70.0000

EQ. 70.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

tim

1.0000

3.0000

9.86

0.30

0.1143

25 00

286 3.16

© > Página:

S10

31

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

13.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ. 9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 010 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

1778 18.82

Partida

13.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ.

500.0000

Costo unitario directo p o r: « 3

Unidad

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0,38 Equipos 0349040093

CARGADOR FRONTAL C A Í- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VOLVO 14 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Partida

13.83.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SO LA D01:10 E= 4"

MO

70.0000

EQ. 70.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

tim

1.0000

3.0000

9.86

0.30

0.1143

25 00

286 3.16

Página:

S10

32

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

13.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

EQ

20.0000

20.0000

Costo unitario directo p o r. m3

Unidad

373.53

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

08000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55 32

166

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

13.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F-Y=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg

Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13,16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

*9

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

13.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

367 .13

Cantidad

Precio SI.

Parcial SI. 6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

>

0238000004

HORMIGON (PUESTO EN OBRA)

I¿ A

0239050000

AGUA

V-

^V i J

BOL

9.0000

21.50

193.50

m3

1.3000

80.00

104.00

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40‘

hm

1.0000

0.4444

5.00

M

2.22 13.88

qap Página:

S10

33

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

13.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ. 14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

05714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8


0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

4.5000

2.00

9,00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Partida

13.04.02.03

Rendimiento

kg/DtA

Código

Descripción Recurso

ACERO DE REFUERZO FYM 200 KG/CM2

MO

200.0000

EQ

200.0000

Costo unitario árecto p o f: kg

Unidad

Cuadrilla

Cantidad

Precio Sí.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

13.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CB2. EN LOSA SUPERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

526

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

2150

193.50

0238000000

HORMIGON

m3

1.3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

105 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

03480700»

VIBRADOR DE CONCRETO 4 HP 2.40-

hm

1.0000

0.4000

20.00

V \

A m p fa o D íaz A rts vu ló ■ T ie p r e s e n ia n t fc L e g a l

8.00 19.66

I» 6 3 - j í ju e i u a s a j c f s v O jn n a j y 2 n i( f ^ < f .t p ¿ lu iy

ÍS /l!¡ jo p ío s u o 3

Página:

S10

34

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

13.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

EQ

14.0000

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial S/.

8.65

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3’

kg

0.2000

5.00

100

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

%MO

HERRAMIENTAS MANUALES

3.0000

15.43

0.46 0.46

Partida

13.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ

200.0000

Costo unitario directo p o r : kg

Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N” 16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy-4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

14.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

EQ.

60.0000

Costo unitario directo p o r: m2

Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

14.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

0147010002

OPERARIO PEON

500.0000

Costo unitario directo p o r: m2

Unidad

Mano de Obra

0147010004

EQ

,

i

$

j

r

1.77

Cuadrilla

Cantidad

Precio SI.

Pardal SI.

hh

1.0000

0.0160

15.14

0.24

hh

2.0000

0.0320

11.86

0.38

\

i fflC M PSOÍXTi»

])

0.62 Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

105

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

«V %MO

3.0000

0.62

0.02 0.02

A m payí^Oíaz A re valo R& píbóiinUit'iU» L e g a l

RafaH^etitl -¿03&4 w g é n ie r o c iv il

@ > Página:

S10

35

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

14.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

32.68

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

2 6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3 0000

31.63

0.95 0.95

Partida

14.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ. 9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

86.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1 04

0.8889

20.00

17.78 18.82

Partida

14.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE Cl EQUIPO

MO

500.0000

EQ.

500.0000

Costo unitario directo p o r: m3

Unidad

6.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O LV 014 M3

hm

1.0000

0.0160

120.00

288 192 4.80

Partida

14.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SO LAD01:10 E= 4"

MO

70.0000

EQ

70.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

500

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9-11F3

hm

1.0000

3.0000

9.86

0.1143

25.00

0.30 2.86 3.16

N° 4089X vuÉSfeWUERQ

Página:

S10

36

Análisis de precios unitarios Presupuesto

0492001 001

Subpresupuesto

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

14.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presapuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR

MO

EQ.

20.0000

Costo unitario directo p o r: m3

20.0000

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1 0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40”

hm

1.0000

0 4000

20.00

8.00 19.66

Partida

14.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FT=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

00400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N“ 16

kg

0.0600

500

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.14

3.0000

0.03 0.03

Partida

14.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

367.13

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

80000

3,5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000004

HORMIGON (PUESTO EN OBRA)

0239050000

AGUA

-

.

\

;/j

Equipos

BOL

9.0000

21.50

193.50

m3

1.3000

80.00

104.00

m3

0.2000

5.00

t m m

¡}u

so:

/ V x

1.00 298.50

h

0337010001

HERRAMIENTAS MANUALES

1.0000

54.75

055

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40'

hm

1.0000

0.4444

5.00

y

%MO

222 13.88

aelLean r ~ ~ C ÍP

4^894

tN G £ W E R O C IV IL

Página:

S10

37

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO OE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

14.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ.

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

2 7.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.5714

15.14

8.65

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3’

kg

0.2000

5.00

100

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 03370100)1

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Partida

14.04.02.03

Rendimiento

kg,'DtA

Código

Descripción Recurso

ACERO DE REFUERZO F1Y=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Costo unitario directo p o r : kg

Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

0.0600

5.00

0.30

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

003 0.03

Partida

14.04.03.01

Rendimiento

tn3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r; m3 Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

32000

11.86

37 95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1 3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

105 298.55

Equipos 0337010001 0348010011 0349070055

HERRAMIENTAS MANUALES

> LT oiv is iíw '8 .,\v / MEZCLADORA DE CONCRETO DE 9 -1 1 $ 6 E S T U O fO s /jM is ^ ll E f - II VIBRADOR DE CONCRETO 4 HP 240* \ \ . MC»i r PTOCuaiSr ¡ j

,

%MO

3 0000

55.32

1.66

hm

1.0000

0.4000

25.00

10.00

hm

1.0000

0.4000

20.00

8.00 19.66

Su c

ÁUMpíii o l i í a z A r e v u lo

Representante (_ec¡sl

( Página

S10

v 38

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

14.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO. 14.0000

EQ.

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

8.65

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3'

kg

0.2000

5.00

1.13 1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

4.5000

2.00

900 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

15.43

0.46 0.46

Partida

14.04.03.03

Rendimiento

kgIDIA

Código

Descripción Recurso

ACERO DE REFUERZO FYM200 KG/CM2

MO

200.0000

EQ, 200.0000

Costo unitario directo p o r: kg Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.14

3.0000

0.03 0.03

Partida

15.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO 60.0000

EQ. 60.0000

Costo unitario directo p o r: m2

Unidad

6.61

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

632

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

15.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

EQ

MO. 500.0000

500.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

1.77

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0.24

0147010004

PEON

hh

2.0000

0.0320

11.86

0.38 0.62

0230020001

YESO DE 28 Kg

4 k x ju tiM x ¡1E®fíM lte89' m n á a y - 1)

0244010000

ESTACA DE MADERA

V

Materiales

,j e t

BOL

0.0500

21.00

1.05

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

002 0.02

C _

____ _ A m p g / o D ía z A t e va lo

R epresentaoib Legal

\ X

(ws£«fe«oc*vn-

y

Página:

Análisis de precios unitarios Presupuesto

0492001

Subptesupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO

UCAYALI

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08/2012

Partida

15.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Factra presupuesto

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ.

3.0000

Costo unitario directo p o r: m3

Unidad

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

3163

0.95 0.95

Partida

15.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ.

9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

Partida

15.02.03

Rendimiento

m3/D!A

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C1 EQUIPO

MO

500.0000

EQ. 500.0000

Costo unitario directo p o r: m3 Unidad

5.18

Cuadrilla

Cantidad

Precio S I.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O LV 014 M3

hm

1.0000

0.0160

120 00

288 1.92 4.80

Partida

15.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SOLADO 1:10 E= 4"

MO

70.0000

EQ. 70.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000004

HORMIGON (PUESTO EN OBRA)

0239050000

\ o w L fifr sJw afcnoaK w s J a r

AGUA

BOL

0.3500

21.50

7.53

m3

0.1300

80.00

10.40

m3

0.0250

5.00

0.13 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

tim o

A y fp a r o D ía z A r e v a lo

Representante Legal

1.0000

3.0000

9.86

030

0.1143

25.00

286 3.16

S10

Página:

40

Análisis de precios unitarios Presupuesto

0492001

Subpresupueslo

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

15.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR

MO

EQ

20.0000

Costo unitario directo p o r: m3

20.0000

Unidad

373.53

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

526

0147010004

PEON

hh

8.0000

3 2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

bol

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

8000

104,00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2 40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

15.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N*16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

15.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ.

18.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

367 .13

Pardal SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

6.73

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

/ '- 5 \\

0238000004

HORMIGON (PUESTO EN OBRA)

|

0239050000

AGUA

\

.

a

O t ilio * s

m

m

BOL

9.0000

21.50

193.50

m3

1.3000

80.00

104,00

m3

0.2000

5.00

1,00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

222 13.88

Página:

S10

41

Análisis de precios unitarios Presupuesto

0492001

Subptesupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

15.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presapussto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ.

14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

27.02

Cantidad

Precio SI.

Parcial S I. 865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

100

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.40

Partida

15.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Costo unitario directo p o r : kg Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0203010007

ACERO DE REFUERZO Fy=4200 kgfcm2 GRADO 60

kg

1.0500

3.50

030 3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

15.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ.

20.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

373.53

Precio S I.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

2150

193.50

0238000000

HORMIGON

m3

1.3000

80 00

104.00

0239050000

AGUA

m3

0.2100

5.00

Equipos

A?PBS ^ ÜÜtáWGN J s j \ \ /¡s k i g t f » ? * « » P I; yS& ajM k ¡I » ¡¡

1.05 298.55

0337010001

HERRAMIENTAS MANUALES

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40‘

hm

1.0000

0.4000

20.00

%MO

8.00 19.66

( g 5 > Página:

S10

42

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

15.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

EQ.

14.0000

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial S I. 8.65

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 1.13

0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3'

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

%MO

HERRAMIENTAS MANUALES

3.0000

15.43

0.46 0.46

Partida

15.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO. 200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

1316

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

0.0600

5.00

0.30

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0 03 0.03

Partida

16.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

EQ

60.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

4.0000

0.5333

11.86

6.51

Parcial SI.

Mano de Obra 0147010004

PEON

hh

6.32 632

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

16.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m2

Unidad

1.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0160

15.14

0.24

hh

20000

0.0320

11.86

0.38

Mano de Obra 0147010002

OPERARIO

0147010004

PEON

, f

Materiales

\

f(k \ [X flO K 2 ferunos y ow»s p \ \ II ^ £ *#MS1¡WCWW n \ . )

0.62

0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

105

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Página:

S10

43

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO

UCAYALI

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08/2012

Partida

18.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

1.0000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

31,63

0.95 0.95

Partida

16.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ

9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

2108 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANIJALES

%MQ

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1.04

0.8889

20.00

17.78 18.82

Partida

16.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ. 500.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

2.0000

0.0320

11.86

5.18

Parcial SI.

Mano de Obra PEON

0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VOLVO 14 M3

hm

1.0000

0.0160

120.00

hh

8 ©

0147010004

8 o

Equipos 2.88 1.92 4.80 Partida

16.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SOLADO 1:10 E= 4"

MO

70.0000

EQ. 70.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI. 15.14

31.08

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

0147010004

PEON

hh

6.0000

06857

1,73 8.13 9.86

Materiales

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21 50

7 53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80 00

10.40

0239050000

AGUA

m3

0.0250

5.00

0.13 18.08

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9-11F3

hm

1.0000

3.0000

9.86

0.30

0.1143

2500

2.86 3.16

IN G & M í E R O c i v i l

S Ím p a r o D ía z A revalo R e p resen ta ra* Legal

(¡& p> Página:

S10

44

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

16.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

fecha presupuesto

20/08/2012

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

EQ

20.0000

Costo unitario directo p o r: m3

20.0000

Unidad

Cuadrilla

373.53

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

3795 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9 0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80 00

10400

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

5532

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40-

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

16.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FT=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

0.0600

5.00

030

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

16.04.02.01

CONCRETO FC=210 KG/CM2 EN MUROS REFORZADOS

Rendimiento

m3/DIA

Código

Descripción Recurso

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3 Unidad

367.13

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0 4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1 0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

2.22 13.88

R epresentante Legal

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

1fl.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fechs presupuesto_____________20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

EQ.

14.0000

Costo unitario directo p o r: m2

14.0000

Unidad

27.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3'

kg

0.2000

5.00

1.13 1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

3.0000

%MO

HERRAMIENTAS MANUALES

15.43

0.46 0.46

Partida

16.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FTT=4200 KG/CM2

MO

EQ

200.0000

200.0000

Costo unitario directo p o r : kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N"16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

*
1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

16.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ. 20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI. 12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9,0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

(

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

30000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

2500

10.00

0348070055

VIBRADOR DE CONCRETO 4 HP 2.40-

hm

1.0000

0.4000

20.00

\

sfinparo D ía z A revalo Representante Legal

8.00 19.66

Página:

S10

46

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

16.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ. 14.0000

Costo unitario directo p o r: m2

Unidad

27.02

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

200

9.00

1.13

11.13

HERRAMIENTAS MANUALES

Partida

16.04.03.03

Rendimiento

kg/DIA

Código

Descripción Recurso

%MO

30000

15.43

P &

0337010001

P Íír>

Equipos

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO. 200.0000

EQ

200.0000

Costo tira ta » directo p o r : kg Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1 0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

030

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3 0000

1.14

0.03 0.03

Partida

17.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

MO

60.0000

EQ. 60.0000

Costo unitario directo p o r: m2 Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

17.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

Mano de Obra

EQ. 500.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

1.77

Parcial SI.

q Página:

S10

o

\ y 47

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO OE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

17.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha pfssüpaesto

20/08/2012

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

3.0000

EQ. 3.0000

Costo unitario directo p o r: m3

Unidad

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial S/.

10000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

31.63

0.95 0.95

Partida

17.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ. 9.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

.3.0000

34.54

1.04

0.8889

20.00

1778 18.82

Partida

17.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ. 500.0000

Costo unitario directo p o r: m3 Unidad

6.18

Cuadrilla

Cantidad

Precio SI.

Pardal SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VO LV 014 M3

hm

1.0000

0.0160

120.00

288 1.92 4.80

Partida

17.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

SOLADO 1:10 E= 4"

MO

70.0000

EQ

70.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6 0000

0.6857

11.86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000004

HORMIGON (PUESTO EN OBRA)

0239050000

AGUA

//Ac,ir l5V 1* u VTV */

BOL

0.3500

21.50

7.53

m3

0.1300

80.00

10.40

m3

0.0250

5.00

013 18.06

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11F3

hm

A m p o / o D ía z A r e v a lo Rep/esenuirité Lec¡ái

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86

Q O ^ )

S10

P á g in a :

®

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

17.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupassío

20/08/2012

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

Costo unitario directo p o r: m3

EQ. 20.0000

Unidad

Cuadrilla

Cantidad

373.53

Precio SI.

Parcial SI. 12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

526

0147010004

PEON

hh

8.0000

3.2000

11.86

37 95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

90000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55 32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

17.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F'Y=4200 KG/CM2

MO

200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.15

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

10000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N*16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

17.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ. 18.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

367.13

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

6.73

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5 85

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales

X

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

0238000004

HORMIGON (PUESTO EN OBRA)

0239050000

j

V \

AGUA

BOL

9.0000

21.50

193.50

m3

1.3000

80.00

104.00

m3

0.2000

5.00

1.00 298.50

Equipos

Í l f . í 0

^

*

0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9 -1

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40‘

hm

1.0000

0.4444

5.00

\

2.22 13.88

A r e v a lo Legal

(¡D tp Página:

S10

49

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORABÍENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

17.04.02.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupuesto

20(08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI.

8.65

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

0202100099

CLAVOS DE 3 '

0243000025

MADERA NACIONAL PARA ENCOFRADO

kg

p2

0.2500

4.50

0.2000

5.00

1.13 1.00

4.5000

2.00

9.00 11.13

HERRAMIENTAS MANUALES

Partida

17.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

3.0000

%MO

15.43

O &

0337010001

o $

Equipos

ACERO DE REFUERZO FT=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Costo uratarto directo p o r: kg

Unidad

Cuadrilla

5.15

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

%MO

1.14

0.03 0.03

Partida

17.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ.

20.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

373.53

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0003

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

.;/

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

¡ 3 7-StuDtos rbeNAS W ¡

m3

1.3000

80.00

104.00

0239050000

AGUA

i \ | (3Q S X * « o t a r , ¡ ¡

m3

0.2100

5.00

1.05 298.55

Y ***> / Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

5532

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40'

hm

1.0000

0.4000

20.00

8.00 19.66

Página:

50

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO

UCAYALI

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08/2012

Partida

17.04.03.02

Rendimiento

m2/DIA

Código

Descripción Recurso

Fecha presupueste

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ. 14.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

i
0.2500

4.50

0202100099

CLAVOS DE 3"

kg

02000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00

1.13

11.13 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Partida

17.04.03.03

ACERO DE REFUERZO FY=4200 KG/CM2

Rendimiento

kg/D)A

Código

Descripción Recurso

MO. 200.0000

EQ.

200.0000

Cosío «miaño directo p o r . ti Unidad

5.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

053 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partea

18.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

Rendimiento

m2/DIA

Código

Descripción Recurso

MO

60.0000

EQ

60.0000

Costo unitario directo p o r: m2 Unidad

6.51

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

4.0000

0.5333

11.86

6.32

Mano de Obra 0147010004

PEON

hh

6.32 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.32

0.19 0.19

Partida

18.01.02

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

1.77

Precio SI.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0.24

0147010004

PEON

hh

20000

0.0320

11.86

0.38 0.62

Materiales 0230020001

YESO DE 28 Kg

BOL

0.0500

21.00

1.05

0244010000

ESTACA DE MADERA

p2

0,0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02

(¡0 ( 0) Página:

S10

51

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

18.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

EXCAVACION MANUAL DE MATERIAL ORGANICO

MO

EQ

3.0000

3.0000

Costo unitario directo p o r: m3

Unidad

32.58

Cuadrilla

Cantidad

Precio S I.

Parcial SI.

1.0000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

31.63

0.95 0.95

Partida

18.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

MO

9.0000

EQ. 9.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

85.96

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.8889

15.14

13.46

0147010004

PEON

hh

2.0000

1.7778

11.86

21.08 34.54

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0200

5.00

32.50 0.10 32.60

Equipos Ü337010001

HERRAMIENTAS .MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

3.0000

34.54

1 04

0.8889

20.00

17.78 18.82

Partida

18.02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

MO

500.0000

EQ. 500.0000

Costo unitario directo p o r: m3

Unidad

5.18

Cuadrilla

Cantidad

Precio Sí.

Parcial SI.

2.0000

0.0320

11.86

0.38

Mano de Obra 0147010004

PEON

hh

0.38 Equipos 0349040093

CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE V O LV 014 M3

hm

1.0000

0.0160

120.00

2.88 1.92 4.80

Partida

18.03.01

Rendimiento

m2/DIA

Código

Descripción Recurso

S O LA D 01:10

MO

= 4"

70.0000

EQ

70.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

31.08

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1143

15.14

1.73

0147010004

PEON

hh

6.0000

0.6857

11 86

8.13 9.86

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3500

21.50

7.53

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.1300

80.00

10.40

0239050000

AGUA

m3

0.0250

5.00

i

0.13 18.06

0337010001

Equipos HERRAMIENTAS MANUALES

NsSS?®.

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

J iC ' %MO \

hm

1.0000

3.0000

9.86

0.30

0.1143

25.00

2.86 3.16

( ¡ c a j) Página:

S10

52

Análisis de precios unitarios Presupuesto

0482001

SubpFesupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO OE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

18.04.01.01

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

373.63

Precio SI.

Parcial SI.

12,11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

8.0000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

20.00

8.00 19.66

Partida

18.04.01.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ.

200.0000

Costo unitario directo p o r: kg

Unidad

5.16

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0,0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N*16

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

0.0600

5.00

0.30

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

18.04.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

MO

18.0000

EQ

18.0000

Costo unitario directo p o r: m3

Unidad

367.13

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

8.0000

3.5556

11.86

42.17 54.75

Materiales

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21 50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80.00

10400

0239050000

AGUA

m3

0.2000

5.00

1.00 298.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

1.0000

54.75

0.55

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4444

5.00

2.22 13.88

([D & p Página:

S10

53

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

18.04.02.02

Rendimiento

m2/D!A

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

MO

14.0000

EQ

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

27.02

Precio SI.

Parcial SI. 8.65

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

15.14

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

i
0.2500

4.50

1.13

0202100099

CLAVOS DE 3*

kg

02000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010X11

HERRAMIENTAS MANUALES

%MO

30000

15.43

0.46 0.46

Partida

18.04.02.03

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO F-Y=4200 KG/CM2

MO

200.0000

EQ. 200.0000

Costo unitario directo p o r : kg Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

030

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

18.04.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

MO

20.0000

EQ

20.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

373 .53

Cantidad

Precio SI.

Parcial SI.

12.11

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

5.26

0147010004

PEON

hh

80000

3.2000

11.86

37.95 55.32

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

bol

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1 3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

55.32

166

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

hm

1.0000

0.4000

25.00

10.00

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40*

hm

1.0000

0.4000

20.00

8.00 19.66

■ e p c e s e n ía n tó Le¿ ,¿i

Q® o^ Página:

S10

54

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA OE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

18.04.03.02

Rendimiento

m2/D)A

Código

Descripción Recurso

Fscha presupuesto

20/08/2012

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

MO

14.0000

EQ

Costo unitario directo p o r: m2

14.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

27.02

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

0.5714

15.14

8.65

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3*

kg

0.2000

5.00

100

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Partida

18.04.03.03

Rendimiento

kg/D!A

Código

Descripción Recurso

ACERO DE REFUERZO F-Y=4200 KG/CM2

MO

200.0000

EQ

200.0000

Costo unitario directo p o r . kg

Unidad

Cuadrilla

Cantidad

5.15

Precio SI.

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

10000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0500

3.50

368 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

1.14

0.03 0.03

Partida

19.01.01

Rendimiento

und/DIA

Código

Descripción Recurso

SEMAFORO TRIPLE TIPO LEDS 10W

MO

6.0000

EQ. 6.0000

Costo unitario directo p o r: und

Unidad

6,088.01

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

1.3333

15.14

20.19

0147010004

PEON

hh

1.0000

1.3333

11.86

1581 36.00

Materiales 0211900011

SEMAFORO DE UN CUERPO X 3 LENTES DE 12" X 12’ X 12"

und

3.0000

1,980.00

0229040001

CINTA AISLANTE

ROL

0.0700

3.00

0.21

0265850003

SOPORTES D E TRES BRAZOS

und

10000

110.00

11000

0337010001

Equipos HERRAMIENTAS MANUALES

5,940.00

6,050.21 /'■ '2 !s ^ O A / ) ^ 5 s . %MO jo ?

m e m k

i * « C lll'fí

R e p re se n ta n te L e g a l

5.0000

36.00

1.80 1.80

Página:

S10

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P, SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

19.01.02

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

SEMAFORO CUADRUPLE TIPO LEDS 10W

MO

6.0000

Costo unitario directo p o r: und

EQ. 6.0000

Unidad

8,078.01

Cuadrilla

Cantidad

Precio S I.

Parcial SI.

20.19

Mano de Obra 0147010002

OPERARIO

hh

1.0000

1.3333

15.14

0147010004

PEON

hh

1.0000

1.3333

11.86

15.81 36.00

Materiales 7,920.00

0211900011

SEMAFORO DE UN CUERPO X 3 LENTES DE 12" X 12* X 12"

und

4.0000

1,980.00

0229040001

CINTA AISLANTE

ROL

0.0700

300

0.21

0265850002

SOPORTE DE CUATRO BRAZOS

und

1.0000

120.00

120.00 8,040.21

Equipos 0337010001

HERRAMIENTAS MANUALES

5.0000

%MO

36.00

1.80 1.80

Partida

19.01.03

Rendimiento

und/DIA

Código

Descripción Recurso

POSTE DE F"G DE 0 6" X 11 MM

MO

2.2500

EQ. 2.2500

Costo unüario directo p o r : und

Unidad

1,696.30

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

3.5556

15.14

53.83

0147010004

PEON

hh

1.0000

35556

11.86

42.17 96.00

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

1.0000

21.50

21.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.3000

80.00

24.00

0263010013

POSTE DE F°G° DE 0 6‘ X 11 MM

und

1.0000

1,550.00

1,550.00 1,595.50

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

5.0000

96.00

4.80 4.80

Partida

19.01.04

Rendimiento

und/DIA

Código

Descripción Recurso

TABLERO ELECTRICO DE CONTROL AUTOMATICO

MO

0.5000

EQ

0.5000

Costo unitario directo p o r: und Unidad

Cuadrilla

Cantidad

2,593.09

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

0147010003

OFICIAL

0147010004

PEON

... -

hh

1.0000

16.0000

15.14

242.24

hh

1.0000

16.0000

13.16

210.56

hh

1.0000

16.0000

11.86

189.76 642.56

Materiales 0211910012

t '

CONTROLADOR 3 FASES

und

1.0000

1,875,00

1,875.00 1,875.00

Equipos 0398010037

HERRAMIENTA MANUAL

%PU

\

/

X

3.0000

2,517.56

75.53 75.53

A

) /

¿ ta p a r o D ía z A rev a lo Representante Legal

Q d ss kg »m 6u6H «pi»0

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO • UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

19.01.05

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

MEDIDOR DE ENERGIA MONOFASICA

MO

0.2500

EQ

Costo unitario directo p o r, und

0.2500 Unidad

Cuadrilla

1,895.32

Cantidad

Precio SI.

Parcial SI. 484.48

Mano de Obra 0147010002

OPERARIO

hh

1.0000

32.0000

15.14

0147010003

OFICIAL

hh

1.0000

32.0000

13.16

421.12

0147010004

PEON

hh

1.0000

32.0000

11.86

379.52 1,285.12

Materiales 0212010053

CAJA PORTA MEDIDOR

und

1.0000

145.00

145.00

0221990042

MURETE DE CONCRETO

und

1.0000

260.00

260.00

0230640100

MEDIDOR DE ENERGIA TRIFASICO

und

1.0000

150.00

150.00 555.00

Equipos 0398010037

HERRAMIENTA MANUAL

3.0000

%PU

1,840.12

55.20 55.20

Partida

19.01.06

Rendimiento

m/DIA

Código

Descripción Recurso

CONDUCTOR ELECTRICO 2 - 1 X 6 MM2 NYY

MO

50.0000

EQ. 50.0000

Costo unitario directo p o r: m

Unidad

Cuadrilla

Cantidad

Precio SI.

22.21

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1600

15.14

2.42

0147010004

PEON

hh

2.0000

0.3200

11.86

3.80 6.22

Materiales 0208020003

CONDUCTOR ELECTRICO 2 -1 X 6 MM2 NYY

m

1.0500

11.00

0273010026

TUBERIA PVC SAL 2"

m

0.5000

8,50

11.55 4.25 15.80

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

6.22

0.19 0.19

Partida

19.01.07

Rendimiento

m/DIA

Código

Descripción Recurso

ALIMENTADOR AL MEDIDOR DE ENERGIA

MO

80.0000

EQ. 80.0000

Costo unitario directo p o r: m

Unidad

Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

6643

Precio SI.

Parcial SI.

0.1000

15.14

1.51

0.1000

11.86

Mano de Obra 0147010002

OPERARIO

0147010004

PEON

s -------—

1.19 2.70

Materiales 0202130032

//S \'

n f l» O lv if OÑ/ -ty O lñ d r Z f W »

HEBILLA DE 3/4*

0229400093

TUBERIA PVC SAP DE 0 40MM

0230010030

CINTA BANDIT 3/4"

0230460037

PEGAMENTO PVC

1

‘ V W lC T »

und

4.0000

2.00

8.00

£.11 >

m

6.0000

6.50

39.00

J j

cja

40000

4.00

16.00

gln

0.0100

65.00

0.65 63.65

Equipos 0337010001

\

HERRAMIENTAS MANUALES

\

%MO

3.0000

2.70

0.08 0.08

Antf>nrJ‘ D íu z A r e va lo <

w * u ¡ iu * iu »

( lv ° p Página:

S10

57

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO OE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

19.01.08

Fecha presapaesto

20/08/2012

CABLE DE ACERO DE 0 5/16*

Rendimiento

m/DIA

MO

Código

Descripción Recurso

50.0000

EQ. 50.0000

Costo unitario directo p o r: m

Unidad

Cuadrilla

Cantidad

16.19

Precio SI.

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1600

15.14

242

0147010004

PEON

hh

0.5000

0.0800

11.86

0.95 3.37

Materiales 0230410041

CABLE DE ACERO DE 0 5 /1 6 ’

m

1.0000

7.50

7.50

0239500100

CINTILLO DE AMARRE

und

3.0000

0.24

0.72

0265870004

ACCESORIOS DE ANCLAJE

und

0.1110

3725

4.13 12.35

Equipos 0398010037

HERRAMIENTA MANUAL

%PU

3.0000

15.72

0.47 0.47

Partida

19.01.09

Rendimiento

und/DIA

Código

Descripción Recurso

POZO DE PUESTA DE TIERRA

MO

1.0000

EQ. 1.0000

Costo unitario directo p o r: und

Unidad

Cuadrilla

Cantidad

Precio SI.

651 .56

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.8000

14.36

11.49

0147010002

OPERARIO

hh

1.0000

8.0000

15.14

12112

0147010004

PEON

hh

1.0000

8.0000

11.86

94.88 227.49

Materiales 0204010003

TIERRA DE CHACRA O VEGETAL

m3

1.4000

25.00

0205010003

ARENA DE RIO

m3

0.0300

50.00

1.50

0206700007

VARILLA DE COBRE 5/8 X 8’

und

1.0000

250.00

250.00

35.00

0207010037

CABLE T H W 16 mm2 (color amarillo)

m

5.0000

3.80

19.00

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.5000

21.50

1075

0265240003

MARCO Y TAPA FO. GO. P/MEDIDOR 1/2’ -3/4"

und

1.0000

90.00

90.00

0272080011

TUB. PVC SAP P/INST. ELECT. DE 1"

m

5.0000

200

10.00

0272090002

CURVA PESADO PVC SAP P/INST. ELECT. 1*

und

1.0000

1.00

1.00 417.25

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

227.49

6.82 6.82

Partida

20.01

Rendimiento

und/DIA

Código

Descripción Recurso

REJILLA METALICA CON MARCO 0.52x0.80

MO

10.0000

EQ.

10.0000

Costo unitario directo p o r: und Unidad

Cuadrilla

Cantidad

Precio SI.

67.76

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.0800

14.36

1.15

0147010002

OPERARIO

hh

1.0000

0.8000

15.14

12.11 13,26

Materiales G203010007

ACERO DE REFUERZO Fy=420Q kgfcm2 GRADO 60

5.0000

3.50

17.50

0251200031

ANGULAR 2-2*3/16"

3.0000

8.20

24.60 42.10

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348210004

SOLDADORA

hm

1.0000

3.0000

0.40

0.8000

12.00 12.40

s . F m if l*

CIP N5"2 ffs u ír

( ( O Página:

S10

58

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE yiA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.02

Rendimiento

und/DIA

Código

Descripción Recurso

fecha presupuesto

20Í08/2012

TAPAS DE CONCRETO PARA INSPECCION Y LIMPIEZA 0.60X0.53 F C=210 KG/CM2

MO

4.0000

EQ

Costo unitario directo p o r: und

4.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

97.87

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.2000

14.36

2.87

0147010002

OPERARIO

hh

1.0000

2.0000

15.14

30.28

0147010003

OFICIAL

hh

0.5000

1.0000

13.16

13.16

0147010004

PEON

hh

1.0000

2.0000

1186

23 72 70.03

Materiales 0203010007

ACERO DE REFUERZO FV=4200 k g fa tó GRADO 60

kg

3.6500

350

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.3400

2150

12.78 7.31

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.0700

80.00

5.60

0239050000

AGUA

m3

0.0100

5.00

0.05 25.74

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

70.03

2.10 2.10

Partida

20.03

Rendimiento

KM/DIA

Código

Descripción Recurso

PINTURA ALTO TRAFICO EN PAVIMENTO

MO

0.5000

EQ. 0.5000

Costo unitario directo p o r: KM

Unidad

Cuadrilla

Cantidad

Precio SI.

3,668.03

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

2.0000

32.0000

15.14

484 48

0147010003

OFICIAL

hh

2.0000

32.0000

13.16

421.12

0147010004

PEON

hh

5 0000

80.0000

1186

948.80 1,854.40

Materiales 0239020082

TIZA

BOL

5.6000

5.00

28.00

0253030027

THINER

gln

10.0000

15.00

150.00

0254450100

PINTURA ALTO TRAFICO

gln

18.0000

70.00

1,260.00 1,438.00

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0349110093

DEMARCADOR DE PAVIMENTO

hm

2.0000

3.0000

1,854.40

55.63

32.0000

10.00

320.00 375.63

Partida

20.04

Rendimiento

m2/DIA

Código

Descripción Recurso

PINTURA ALTO TRAFICO EN CRUCE PEATONAL

MO

100.0000

EQ

100.0000

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

12.29

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0800

15.14

1.21

0147010004

PEON

hh

6.0000

0.4800

11.86

5.69 6.90

Materiales 0239020082

TIZA

BOL

0.0120

5.00

0253030027

THINER

gln

0.0015

15.00

002

0254450100

PINTURA ALTO TRAFICO

gln

0.0500

70,00

3.50

•II

|

\T Equipos

0.06

3.58

\

0337010001

HERRAMIENTAS MANUALES

%MO

0349110093

DEMARCADOR DE PAVIMENTO

hm

20000

3.0000

6.90

0.21

0.1600

10.00

1.60 1.81

A nl&aro D ía z A revala Representarás Le ¿al

tó )

(Col Página:

S10

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO

UCAYALI

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08,'2012

Partida

20.05

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

SEÑALIZACION VERTICAL

MO

1.0000

EQ

1.0000

Costo unitario directo p o r: und

Unidad

Cuadrilla

500.00

Cantidad

Precio SI.

Parcial SI.

1 0000

500.00

500.00

Materiales 0243400033

SEÑALIZACION VERTICAL

und

500.00 Partida

20.06

Rendimiento

GLB/DIA

Código

Descripción Recurso

LIMPIEZA FINAL DE OBRA

MO

2,000.0000

EQ

2,000.0000

Costo unitario directo p o r: GLB

Unidad

Cuadrilla

Cantidad

Precio SI.

1.0000

4,000.00

4,000.00

Parcial SI.

Materiales 0239410005

LIMPIEZA FINAL DE OBRA

GLB

4,000.00 4,000.00

Partida

20.07.01

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN LOSA DE BUZON

MO

14.0000

EQ, 14.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

27.02

Precio S/.

Parcial SI.

865

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

1514

0147010004

PEON

hh

1.0000

0.5714

11.86

6.78 15.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2500

4.50

1.13

0202100099

CLAVOS DE 3"

kg

0.2000

5.00

1.00

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

4.5000

2.00

9.00 11.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

15.43

0.46 0.46

Partida

20.07.02

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC= 210 KO/CM2. EN LOSA DE BUZONES

MO. 20.0000

EQ. 20.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

373.53

Cantidad

Precio SI.

Parcial SI.

1211

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.8000

15.14

0147010003

OFICIAL

hh

1.0000

0.4000

13.16

526

0147010004

PEON

hh

8.0000

3.2000

11.86

37 95 55.32

Materiales

0221000000

CEMENTO PORTLAND TIPO I (42 5KG)

9.0000

21.50

193.50

0238000004

HORMIGON (PUESTO EN OBRA)

13000

80 00

10400

0239050000

AGUA

0.2100

5.00

1.05 298.55

Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

5532

166

0348010011

MEZCLADORA DE CONCRETO DE 9-11P3

1.0000

0.4000

25 00

1000

0349070055

VIBRADOR DE CONCRETO 4 HP 2.40’

1.0000

0.4000

2000

8.00 19.66

((O ü p Página:

S10

60

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO • UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.07.03

Rendimiento

kg/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ

200.0000

Costo unitario directo p o r: kg

Unidad

Cuadrilla

Cantidad

Precio SI.

5.22

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.0040

14.36

0.06

0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.20

Materiales 0202040009

ALAMBRE NEGRO N*16

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg kg

0.0600

5.00

0.30

1.0500

3.50

3.68 3.98

Equipos 0337010001

HERRAMIENTAS MANUALES

3.000G

%MO

1.20

0.04 0.04

Partida

20.07.04

Rendimiento

und/DIA

Código

Descripción Recurso

MARCO Y TAPA DE BUZON

MO

4.0000

EQ

4.0000

Costo unitario directo p o r: und Unidad

Cuadrilla

Cantidad

Precio SI.

195.01

Parcial SI.

Mano de Obra 0147010001

CAPATAZ

hh

0.1000

0.2000

14.36

287

0147010002

OPERARIO

hh

1 0000

20000

15.14

30 28

0147010004

PEON

hh

0.5000

1.0000

11.86

11.86 45.01

Materiales 0250020062

MARCO Y TAPA F°F° PARA BUZON

und

1.0000

150.00

150.00 150.00

Partida

20.08.01.01

Rendimiento

m2/DIA

Código

Descripción Recurso

TRAZO, NIVELACION Y REPLANTEO

MO

500.0000

EQ

500.0000

Costo unitario directo p o r: m2 Unidad

Cuadrilla

Cantidad

Precio SI.

1.77

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0160

15.14

0.24

0147010004

PE0N

hh

2.0000

0.0320

11.86

0.38 0.62

Materiales 023GG20Q01

YESOOE 28Kg

BOL

0.0500

21.00

105

0244010000

ESTACA DE MADERA

p2

0.0680

1.15

0.08 1.13

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.62

0.02 0.02

Partida

20.08.02.01

Rendimiento

m3/DIA

Código

Descripción Recurso

EXCAVACION DE ZANJA MANUAL

MO

3.0000

EQ

3.0000

Costo unitario directo p o r: m3

Unidad

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

2.6667

11.86

31.63

Mano de Obra 0147010004

PEON

hh

31.63 Equipos 0337010001

HERRAMIENTAS MANUALES

3.0000

31.63

0.95 0.95

0NSULT im puro D ía z A revalo Representante Legal

Análisis de precios unitarios Presupuesto

0492001

Subprésupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.08.02.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

MO

10.0000

EQ.

10.0000

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

69.15

Precio SI.

Parcial S/.

10.53

Mano de Obra 0147010003

OFICIAL

hh

1.0000

0.8000

13.16

0147010004

PEON

hh

1.0000

0.8000

11.86

949 20.02

Materiales 0204110023

TIERRA ROJA

m3

1.3000

25.00

0239050000

AGUA

m3

0.0050

5.00

32.50 003 32.53

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIFO SALTARIN

hm

1.0000

3.0000

2002

0.60

0.8000

20.00

16.00 16.60

Partida

20.08.02.03

Rendimiento

raí/DIA

Código

Descripción Recurso

ELIMINACION DE MATERIAL EXCEDENTE

MO

25.0000

EQ. 25.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

Precio SI.

2.0000

0.6400

11.86

7.82

Parcial SI.

Mano de Obra 0147010004

PEON

hh

7.59 7.59

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

7.59

0.23 0.23

Partida

20.08.03.01

Rendimiento

m3/DIA

Código

Descripción Recurso

CONCRETO FC=140 KG/CM2 EN CIMIENTO DE PARADERO

MO

100.0000

EQ. 100.0000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

Cantidad

52.50

Precio SI.

Parcial SI.

1.21

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0800

15.14

0147010003

OFICIAL

hh

1.0000

0.0800

13.16

1.05

0147010004

PEON

hh

8.0000

0.6400

11.86

7.59 9.85

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

1.1300

21.50

24.30

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0,2000

80.00

16,00

0239050000

AGUA

m3

0.0100

5.00

0.05 40.35

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

3.0000

9.85

0.30

0.0800

25.00

2.00 2.30

Aa*f>aro D ía z A r e v a lo

S10

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO

UCAYALI

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08/2012

Partida

20.08.03.02

Rendimiento

m3/DIA

Código

Descripción Recurso

Fecha presupuesto

CONCRETO F 0 1 7 5 KG/CM2 EN BASE PARA BANCAS

MO

18.0000

EQ.

18.0000

338 .14

Costo unitario directo p o r: m3

Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI. 6.73

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0 4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585

0147010004

PEON

hh

8.0000

3 5556

11.86

42.17 54.75

Materiales 0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

7 5000

21.50

16125

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.3000

80 00

104.00

0239060000

AGUA

m3

0.1900

5.00

095 266.20

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

54.75

1.64

0349070001

VIBRADOR DE CONCRETO 4 HP 1.35"

hm

1.0000

0.4444

10.00

444

0349100007

MEZCLADORA CONCRETO TAMBOR 18HP 11P3

hm

1.0000

04444

2500

11.11 17.19

Partida

20.08.03.03

Rendimiento

m2/DIA

Código

Descripción Recurso

ENCOFRADO Y DESENCOFRADO EN BASE DE C*A DE BANCAS

MO

18.0000

EQ

18.0000

19.22

Costo unitario directo p o r: m2

Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

673

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.4444

15.14

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

585 12.58

Materiales 0202040010

ALAMBRE NEGRO N” 8

430

086

CLAVOS DE 3"

kg kg

0.2000

0202100099

0.0800

5.00

040

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

2.5000

200

5.00 6.26

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

12.58

038 0.38

Partida

20.08.03.04

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO DE REFUERZO FY=4200 KG/CM2

MO

200.0000

EQ. 200.0000

5.15

Costo unitario directo p o r: kg Unidad

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0400

15.14

0.61

0147010003

OFICIAL

hh

1.0000

0.0400

13.16

0.53 1.14

Materiales 0202040009

ALAMBRE NEGRO N” 16

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

0337010001

Equipos HERRAMIENTAS MANUALES

kg kg

0.0600

5.00

030

1.0500

3.50

368 3.98

J

^

aS

V*B’

^ x

%MO

3.000Q

1.14

0.03

f í é \ DIVISION ] (I$ esVqs.» ¡feys

0.03

F m ia * ic d k (fM Cr . í P

Lean

N ° 40 8 9 4

W G E N tE R O C IV H -

0NSUIT A /h p u r o U la z A r e v a lo

R epresentante

Legal

Página:

S10

63

Análisis de precios unitarios Presupuesto

0492001

Subptesupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTR(TO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORASttENTO DE VÍA DE INTERCOHEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.08.04.01

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

ESTRUCTURA DE MADERA EN BANCAS

MO

10.0000

EQ

10.0000

Costo unitario directo p o r: und

Unidad

Cuadrilla

Cantidad

35.30

Precio SI.

Parcial SI.

10.53

Mano de Obra 0147010003

OFICIAL

hh

1.0000

08000

13.16

0147010004

PEON

hh

10000

0.8000

11.86

949 20.02

Materiales 0202200100

PERNOS DE 0 3/8" X 41/2"

pza

0.0500

1.50

0.08

0292010002

MADERA QUINILLA DE 3’ X 1 1/2*

p2

23800

3.20

762

0292010003

MADERA QUINILLA DE 4* X 1 ’

P2

2.1800

3.20

6.98 14.68

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

20.02

0.60 0.60

Partida

20.08.04.02

Rendimiento

und/DIA

Código

Descripción Recurso

ENTRAMADO DE MADERA EN PARADEROS

MO

50.0000

EQ

50.0000

Costo unitario árecto p o r : und Unidad

Cuadrilla

Cantidad

5 0.93

Precio SI.

Parcial SI.

242

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1600

1514

0147010004

PEON

hh

1.0000

0.1600

11.86

190 4.32

Materiales 0202130021

CLAVOS PARA CALAMINA

•<9

0.0150

5.00

008

0292010004

MADERA QUINILLA DE 2* X 4*

p2

8.0000

3.20

25 60 1280

0292010005

MADERA QUINILLA DE 2‘ X 2*

P2

4 0000

320

0292010006

MADERA QUINILLA DE 11/2* X 1 1/2*

p2

25000

3.20

800 46.48

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

3 0000

432

0.13 0.13

Partida

20.08.04.03

Rendimiento

und/DIA

Código

Descripción Recurso

COLUMNAS DE MADERA (quinilla y/o similar)

MO

12.0000

EQ

12.0000

Costo unitario directo p o r: und Unidad

112.09

Cuadrilla

Cantidad

Precio SI.

Parcial S I.

10.09

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.6667

15.14

0147010004

PEON

hh

1.0000

0.6667

11.86

7.91 18.00

Materiales 0202830003

CLAVOS OE 4*

kg

0.1500

500

075

0292010007

MADERA QUINILLA DE 4* X 4*

p2

14.0000

3.20

44 80

P2

9.0000

3.20

28 80

p2

6.0000

3 20

0292010008

MADERA QUINILLA DE 4* X 3*

0292010009

MADERA QUINILLA DE 3* X 3*

Í tK S

fe ¥

0337010001

1920 93.55

¡ ¡ ¡i

Equipos

HERRAMIENTAS MANUALES

%MO

3.0000

18.00

0.54 0.54

(w t) Página:

S10

64

Análisis de precios unitarios Presupuesto

0492001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE WTERCQNEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.08.04.04

Rendimiento

m2/DIA

Código

Descripción Recurso

Feoha presupuesto

20/08/2012

COBERTURA CON PLANCHAS DE CALAMINA ONDULINE COLOR ROJO

MO

60.0000

EQ

60.0000

Costo unitario directo p o r: m2

Unidad

28.12

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.02

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1333

15.14

0147010003

OFICIAL

hh

1.0000

0.1333

13.16

1.75

0147010004

PEON

hh

2.0000

0.2667

11.86

3.16 6.63

Materiales 0202130021

CLAVOS PARA CALAMINA

kg

0.0150

5.00

0.08

0261010029

CALAMINA ONDULINE COLOR ROJO

pin

0.9500

22.00

20.90 20.98

Equipos 0337010001

HERRAMIENTAS MANUALES

«M O

3.0000

6.93

0.21 0.21

Partida

20.08.05.01

Rendimiento

mll/DIA

Código

Descripción Recurso

COLOCACION DE DE TUBOS P G EN PARADEROS

MO

8.0000

EQ

8.0000

Costo unitario directo p o r: mil Unidad

Cuadrilla

Cantidad

Precio SI.

68.65

Parcial S I.

Mano de Obra 0147010002

OPERARIO

hh

1 0000

1.0000

15.14

15.14

0147010003

OFICIAL

hh

1.0000

1.0000

13.16

13.16 28.30

Materiales 0202860033

TUBO DE FIERRO GALVANIZADO DE 0 T

ML

0.9000

25.00

0226000080

TORNILLO AUTOROSCANTE DE ?

und

4.0000

0.50

2.00

0229500090

SOLDADURA ELECTRICA

kg

0.5000

10.00

5 00

22 50

29.50 Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0348210003

EQUIPO DE SOLDAR

hm

1.0000

3.0000

28.30

0 85

1.0000

10.00

10.00 10.85

Partida

20.08.05.02

Rendimiento

und/DIA

Código

Descripción Recurso

PLATINA METALICAS PARA FIJAR EN LOS PARADEROS

MO

30.0000

EQ

30.0000

Costo unitario directo p o r: und Unidad

Cuadrilla

Cantidad

Precio SI.

11.50

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.2667

15.14

4.04

0147010003

OFICIAL

hh

1.0000

0.2667

13.16

3.51 7.55

Materiales

p flfe s R . S

0229500091

SOLDADURA

kg

0.0250

8.00

0256220020

PLANCHA DE ACERO

kg

0.0200

50.00

0.20 1.00 1.20

Equipos 0337010001

HERRAMIENTAS MANUALES

0348210003

EQUIPO DE SOLDAR

' %MO

\

tro

1.0000

1.0000

7.55

0.08

0.2667

10.00

2.67 2.75

R e p re s e n ta n te L e g a l

Página:

S10

65

Análisis de precios unitarios Presupuesto

0482001

Subpresupuesto

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO. DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Partida

20.08.06.01

Rendimiento

und/DIA

Código

Descripción Recurso

Fecha presupuesto

20/08/2012

PINTURA EN BANCAS DEL PARADERO

MO

25.0000

EQ. 25.0000

Costo unitario directo p o r: und

Unidad

Cuadrilla

Cantidad

Precio SI.

10.04

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

10000

0.3200

15.14

4,84

0147010004

PEON

hh

1.0000

0.3200

11.86

3.80 8.64

Materiales 0230990019

LIJA

und

0.5000

2.00

1.00

0254020080

PINTURA ESMALTE

m2

0.0060

38.00

023 1.23

Equipos 0337010001

HERRAMIENTAS MANUALES

2.0000

%MO

8.64

0.17 0.17

Partida

20.08.06.02

PINTURA BARNIZ EN ESTRUCTURA DE MADERA

Rendimiento

m/DIA

Código

Descripción Recurso

MO

40.0000

EQ. 40.0000

Costo unitario directo p o r: m

Unidad

5.97

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.2000

15.14

3.03

0147010004

PEON

hh

1.0000

0.2000

11.86

2.37 5.40

Materiales 0254080000

BARNIZ MARINO

gln

0.0080

38.00

0.30 0.30

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

5.0000

5.40

0.27 0.27

Partida

20.08.06.03

Rendimiento

m/DIA

Código

Descripción Recurso

PINTURA ZICROMATICO EN CARPINTERIA METALICA

MO

30.0000

EQ

30.0000

Costo unitario directo p o r: m Unidad

Cuadrilla

11.39

Cantidad

Precio S I.

Parcial SI. 4.04

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.2667

15.14

0147010004

PEON

hh

0.5000

0.1333

11.86

1.58 5.62

Materiales 0239020034

LIJA DE FIERRO # 8

und

0 2000

200

040

0253030027

THINER

gln

0.0200

15.00

0.30

0254060000

PINTURA ANTICORROSIVA

gln

0.0400

35 00

1.40

0254060018

PINTURA ESMALTE ANTICORROSIVO TEKNO

gln

0.0400

38 00

1.52 3.62

Equipos 0337010001

HERRAMIENTAS MANUALES

%MO

0337900050

EQUIPO DE PINTURA

hm

1.0000

5.0000

5.62

0,2667

7.00

0.28 1.87 2.15

Partida

21.01

Rendimiento

GLB/DIA

Código

Descripción Recurso

COSTOS AMBIENTALES DURANTE LA PAVIMENTACION

MO.

EQ

Costo unitario directo p o r: GLB Unidad

Cuadrilla

12,600.00

Cantidad

Precio S I.

Parcial SI.

1.0000

12,500.00

12,500.00

Mano de Obra 0147990023

MEDIDAS DE SEGURIDAD INICIO DEL PROYECTO

GLB

Página:

S10

1

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO___________________________

Partida

22.01

Rendimiento

und/DIA

Código

Unidad

0147010003

Descripción Recurso Mano de Obra OFICIAL

0147010004

PEON

SEÑALIZACION INFORMATIVA DE DESVIO MO. 2.0000

Costo unitario directo p or: und

EQ. 2.0000

167.72

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

4.0000

13.16

52.64

hh

1.0000

4.0000

11.86

47.44 100.08

Materiales 0202100099

CLAVOS DE 3"

0237020050

WAYPE INDUSTRIAL

kg ML

0.1000

5.00

0.50

1.6000

4.00

6.40 56.50

0243000031

MADERA NACIONAL PARA ENCOFRADO

2.00

TRIPLAY DE 6 mm

p2 m2

28.2500

0244020015

0.1000

22.00

2.20

0254110090

PINTURA ESMALTE

gtn

0.0010

35.00

0.04

0337010001

Equipos HERRAMIENTAS MANUALES

65.64 2.0000

%MO

100.08

2.00 2.00

Partida

22.02

Rendimiento

m3/DIA

Código 0147010003

Descripción Recurso Mano de Obra OFICIAL

hh

0147010004

PEON

hh

0337010001

Equipos HERRAMIENTAS MANUALES

DEMOLICION DE ESTRUCTURAS DE CONCRETO MO. 1.5000

EQ. 1.5000

Costo unitario directo p o r: m3 Unidad

Cuadrilla

202.60

Cantidad

Precio SI.

Parcial SI.

1.0000

5.3333

13.16

70.19

2.0000

10.6667

11.86

126.51 196.70

%MO

3.0000

196.70

5.90 5.90

Partida

22.03

RETIRO DE DESPERDICIOS

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

0337010001

Equipos HERRAMIENTAS MANUALES

MO. 50.0000

EQ. 50.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

hh

1.0000

hh

2.0000

6.41

Precio SI.

Parcial SI.

0.1600

15.14

2.42

0.3200

11.86

3.80 6.22

%MO

30000

6.22

0.19 0.19

Partida

22.04

DESVIO DE CAUCE

Rendimiento

ML/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0337010001

Equipos HERRAMIENTAS MANUALES

MO. 10.0000

EQ. 10.0000

Costo unitario directo por: ML Unidad hh

58.64

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

6.0000

4.8000

11.86

56.93 56.93

%MO

3.0000

56.93

1.71 1.71

R e p re s e n ta n te L e g a l

Página:

S10

2

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 002 MEJORAMIENTO DE PUENTE SAN LORENZO Fecha presupuesto 20/08/2012

Partida

22.05

DESBROCE DE TERRENO

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

MO. 500.0000

Costo unitario directo por: m2

EQ. 500.0000

1.54

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0160

15.14

0.24

hh

6.0000

0.0960

11.86

Unidad

1.14 1.38

Equipos 0348400001

hm

MOTOSIERRA

1.0000

0.0160

10.00

0.16 0.16

Partida

22.06

LIMPIEZA DE TERRENO

Rendimiento

m2/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0337010001

Equipos HERRAMIENTAS MANUALES

MO. 120.0000

EQ. 120.0000

Costo unitario directo por: m2 Unidad hh

0.81

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0667

11.86

0.79 0.79

%MO

3.0000

0.79

0.02 0.02

Partida

22.07

Rendimiento

m2/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

TRAZO Y REPLANTEO MO. 300.0000

EQ

300.0000

Costo unitario directo por: m2 Unidad hh

1.72

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0533

11.86

0.63 0.63

Materiales 0202100099

CLAVOS DE 3”

5.00

0.05

CORDEL

kg ML

0.0090

0229220001

0.1900

0.20

0.04

0230010002

CAL HIDRATADA DE 25 Kg

BOL

0.0030

7.00

0.02

0243000026

ESTACA DE MADERA

0.0200

1.15

0.02

0254020081

PINTURA ESMALTE

P2 gln

0.0002

35.00

0.01

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

0.63

0.02

0349880002

NIVEL TOPOGRAFICO

hm

10013

0 0267

15.00

0.40

0349880003

TEODOLITO

hm

1.0013

0.0267

20.00

0.53

0.14

0.95 Partida

22.08

ALMACEN DE OBRA

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

MO. 20.0000

EQ. 20.0000

Costo unitario directo p o r: m2 Unidad hh

Cuadrilla

25.61

Cantidad

Precio SI.

Parcial SI.

1.0000

0.4000

15.14

6.06

1.0000

0.4000

11.86

4.74 10.80

Materiales 0202100099

CLAVOS DE 3"

0202830003

CLAVOS DE 4*

0243580005

LISTONES DE MADERA DE 2* X3* X 10*

0244030005 0261100002

kg kg

0.1000

5.00

0.50

0.1200

5.00

0.60

3.1000

1.80

5.58

TRIPLAY LUPUNA DE 4’x8'x 4 mm

P2 pin

0.3460

14.00

4.84

CALAMINA CORRUGADA GALVANIZADA

pin

0.2200

13.50

2.97

Página:

S10

3

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 002 MEJORAMIENTO DE PUENTE SAN LORENZO Fecha presupuesto 20/08/2012

Partida

22.09

Rendimiento

und/DIA

Código

Descripción Recurso Materiales CARTEL DE OBRA (3.00 X 5.00) BANNER und

0290010003

CARTEL DE OBRA (3.00 X 5.00) BANNER INC. COLOCACION MO. 0.8000

EQ. 0.8000

Costo unitario directo por: und Unidad

Cuadrilla

und

800.00

Cantidad

Precio SI.

Parcial SI.

1.0000

800.00

800.00 800.00

Partida

22.10

Rendimiento

GLB/DIA

Código

Descripción Recurso Materiales TRANSPORTE DE EQUIPO Y HERRAMIENTAS

0232010096

TRANSPORTE DE MATERIALES EQUIPOS Y HERRAMIENTAS MO. 1.0000

EQ. 1.0000

Costo unitario directo por: GLB Unidad

Cuadrilla

GLB

1,000.00

Cantidad

Precio SI.

Parcial SI.

1.0000

1,000.00

1,000.00 1,000.00

Partida

23.01

Rendimiento

m3/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA MO. 150.0000

EQ. 150.0000

Costo unitario directo por: m3 Unidad hh

Cuadrilla

Cantidad

Precio SI.

2.0000

0.1067

11.86

8.77 Parcial SI. 1.27 1.27

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349040099

EXCAVADORA

hm

1.0000

3.0000

1.27

0.04

0.0533

140.00

7.46 7.50

Partida

23.02

Rendimiento

m3/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349040099

EXCAVADORA

hm

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA BAJO LECHO H 0.60M. MO. 200.0000

EQ. 200.0000

Costo unitario directo por: m3 Unidad hh

6.58

Cuadrilla

Cantidad

PrecioS/.

Parcial SI.

2.0000

0.0800

11.86

0.95 0.95

1.0000

3.0000

0.95

0.03

0.0400

140.00

5.60 5.63

Partida

23.03

Rendimiento

m3/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

RELLENO CON GRAVILLA O PIEDRA CHANCADA DE 1/2" MO. 7.0000

EQ. 7.0000

Costo unitario directo por: m3 Unidad hh

Cuadrilla

Cantidad

Precio SI.

1.0000

1.1429

11.86

113.96 Parcial SI. 13.55 13.55

0205000031

Materiales GRAVILLA PARA FILTRO DE 1/2' DE RIO O PEDRA CHANCADA m3 DE 1/2"

1.0000

100.00

100.00

100.00 0337010001

Equipos HERRAMIENTAS MANUALES

%MO

Representante

3.0000

13.55

0.41

Página:

S10

4

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Subpresupuesto________ 002 MEJORAMIENTO DE PUENTE SAN LORENZO___________________________________________ Fecha presupuesto_____ 20/08/2012 Partida

23.04

Rendimiento

m3/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

RELLENO COMPACTADO CON MATERIAL MEJORADO 80% HOR. + 20% TR. MO. 500.0000

EQ. 500.0000

Costo unitario directo por: m3 Unidad

98.16

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0160

15.14

0.24

hh

1.0000

0.0160

11.86

0.19 0.43

Materiales 0204110023

TIERRA ROJA

m3

0.2600

25.00

6.50

0238000004

HORMIGON (PUESTO EN OBRA)

m3

1.0400

80.00

83.20

0239050000

AGUA

m3

0.1000

5.00

0.50 90.20

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

0.2500

0349040100

CARGADOR FRONTAL CAT-950

hm

0349070054

VOLQUETE VOLVO 14 M3

hm

0349090000

MOTONIVELADORA DE 125 HP

0349110010

RODILLO LISO VIBRATORIO AUTOPROPULSADO

3.0000

0.43

0.01

0.0040

100.00

0.40

0.5000

0.0080

150.00

1.20

0.5000

0.0080

120.00

0.96

hm

1.0000

0.0160

180.00

2.88

hm

1.0000

0.0160

130.00

2.08 7.53

Partida

23.05

Rendimiento

m3/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

RELLENO CON MATERIAL DE PRESTAMO EN REPOSICION DE VIA DE INGRESO Y SALIDA. MO. 500.0000

EQ. 500.0000

Costo unitario directo por: m3 Unidad hh

97.15

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38 0.38

Materiales 0204110023

TIERRA ROJA

m3

0.2600

25.00

6.50

0238000000

HORMIGON

m3

1.0400

80.00

83.20

0239050000

AGUA

m3

0.1000

5.00

'L 0337010001

Equipos HERRAMIENTAS MANUALES

0348040043

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

0349040100

CARGADOR FRONTAL CAT-950

0349090000 0349110010

0.50 90.20

)j / %MO

3.0000

0.38

0.01

hm

0.2500

0.0040

100.00

0.40

hm

0.5000

0.0080

150.00

1.20

MOTONIVELADORA DE 125 HP

hm

1.0000

0.0160

180 00

2.88

RODILLO LISO VIBRATORIO AUTOPROPULSADO

hm

1.0000

0.0160

130 00

2.08

\

6.57 Partida

23.06

Rendimiento

m3/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0349040093

Equipos CARGADOR FRONTAL CAT- 930

hm

1.0000

0.0160

180.00

0349070054

VOLQUETE VOLVO 14 M3

hm

1.0000

0.0160

120.00

ELIMINACION DE MATERIAL EXCEDENTE C1EQUIPO D= 5 KM. MO. 500.0000

EQ. 500.0000

Costo unitario directo por: m3 Unidad hh

5.18

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0320

11.86

0.38 0.38 2.88 1.92 4.80

R e p re s e n ta n te L e g a l

( f

Página:

S10

t

j )

5

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

24.01

Rendimiento

m2/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.1900

21.50

4.09

0238000000

HORMIGON

m3

0.0700

80.00

5.60

0239050000

AGUA

m3

0.0040

5.00

SOLADO DE CONCRETO F C= 100 KG/CM2 E=0.10 M MO. 80.0000

EQ. 80.0000

Costo unitario directo p o r: m2 Precio SI.

16.15

Cuadrilla

Cantidad

Parcial SI.

hh

1.0000

0.1000

15.14

1.51

hh

4.0000

0.4000

11.86

4.74 6.25

0.02 9.71

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

6.25

0.19 0.19

Partida

25.01.01

Rendimiento

m3/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

3.2000

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2. EN LOSAS MO. 20.0000

EQ. 20.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

Cantidad

367.53

Precio SI.

Parcial SI.

0.8000

15.14

12.11

0.4000

13.16

5.26

11.86

37.95 55.32

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1 0000

0.4000

25 00

10.00

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

0.4000

5.00

2.00 13.66

Partida

25.01.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

22.86

Cantidad

Precio SI.

Parcial SI.

1.0000

0.4444

15.14

6.73

1.0000

0.4444

13.16

5.85 12.58

0202040010

Materiales ALAMBRE NEGRO N°8

kg

0.2100

4.30

0202100099

CLAVOS DE 3“

kg

0.2400

5.00

1.20

0229500091

SOLDADURA

0.1000

8.00

0.80

0243000025

MADERA NACIONAL PARA ENCOFRADO

kg P2

3.5000

2.00

7.00

0337010001

Equipos HERRAMIENTAS MANUALES

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

A n y /a ro D ía z A re vu lo Representante Legal

WviGfeHtRRO C íV It

(

Página:

S10

3

^

6

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

25.01.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

500

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO. 250.0000

Costo unitario directo por: kg

EQ. 250.0000

4.98

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0320

15.14

0.48

hh

1.0000

0.0320

13.16

0.42

Unidad

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.02.01

Rendimiento

m3/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

0147010004

PEON

hh

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2. EN LOSAS MO. 20.0000

EQ. 20.0000

Costo unitario directo por: m3 Cuadrilla

367.53

Cantidad

Precio SI.

Parcial SI.

2.0000

0.8000

15.14

12.11

1.0000

0.4000

13.16

5.26

8.0000

3.2000

11.86

37.95 55.32

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25.00

10.00

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

04000

5.00

2.00 13.66

Partida

25.02.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000 Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

Unidad

':?$• \

/ fe ? ( ir

f

e

|

U

0202100099

Materiales ALAMBRE NEGRO N“8 CLAVOS DE 3"

0229500091

SOLDADURA

\

0243000025

MADERA NACIONAL PARA ENCOFRADO

\

0202040010

Costo unitario directo por: m2 Precio SI.

Parcial SI.

0.4444

15.14

6.73

0.4444

13.16

5.85 12.58

\

w % J* r\

kg

0.2100

4.30

kg

0.2400

5.00

120

kg

0.1000

8.00

0.80

P2

3.5000

2.00

7.00

' 0337010001

22.86

Equipos HERRAMIENTAS MANUALES

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

Consi A m v a lo Rapresemanto i-eyoi

" X iñ p n i

(W Página:

S10

7

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Subpresupuesto________ 002 MEJORAMIENTO DE PUENTE SAN LORENZO___________________________________________ Fecha presupuesto 20)08/2012 Partida

25.02.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO. 250.0000

EQ

Costo unitario directo por: kg

250.0000

Precio SI.

Parcial SI.

0.0320

15.14

0.48

0.0320

13.16

0.42

Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

Unidad

4.98

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.03.01

Rendimiento

m3/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

4.0000

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

10400

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2 EN MUROS MO. 16.0000

EQ. 16.0000

Costo unitario directo p o r; m3 Cuadrilla

Cantidad

384.78

Precio SI.

Parcial SI.

1.0000

15.14

15.14

0.5000

13.16

6.58

11.86

47.44 69.16

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

69.16

2.07

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.5000

25.00

12.50

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40*

hm

1 0000

0 5000

5.00

2.50 17.07

Partida

25.03.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

f |=

0147010003

o f i c ia l

V

0202040010

Materiales ALAMBRE NEGRO N°8

0202100099

CLAVOS DE 3*

0229500091

SOLDADURA

0243000025

MADERA NACIONAL PARA ENCOFRADO

0337010001

Equipos HERRAMIENTAS MANUALES

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000

[

V*®' Í

Costo unitario directo p o r: m2 Unidad

Precio SI.

22.86

Cuadrilla

Cantidad

Parcial SI.

hh

1.0000

0.4444

15.14

6.73

hh

1.0000

0.4444

13.16

5.85

j ¡I

¥""■ ’

12.58 « A

kg

0.2100

4.30

V "

kg

0.2400

5.00

1.20

\

kg

0.1000

8.00

0.80

P2

3.5000

2.00

7.00

\

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

Página:

S10

8

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

25.03.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0202040009

Materiales ALAMBRE NEGRO n 6

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO FY=4200 KG/CM2 MO. 250.0000

Costo unitario directo por: kg

EQ. 250.0000

4.98

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0320

15.14

0.48

hh

1.0000

0.0320

13.16

0.42

Unidad

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.04.01

Rendimiento

m3/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

4.0000

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2 EN MUROS MO. 16.0000

EQ. 16.0000

Costo unitario directo por: m3 Cuadrilla

384.78

Precio SI.

Parcial SI.

1.0000

15.14

15.14

0.5000

13.16

6.58

11.86

47.44

Cantidad

69.16

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

69.16

2.07

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.5000

25.00

12.50

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40’

hm

1 0000

05000

5.00

2.50 17.07

Partida

25.04.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m2 Unidad

22.86

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000 1 0000

0.4444

15.14

6.73

0.4444

13.16

5.85 12.58

0202040010

Materiales ALAMBRE NEGRO N°8

kg

0.2100

4.30

0202100099

CLAVOS DE 3"

kg

0.2400

5.00

1.20

0229500091

SOLDADURA

kg

0.1000

8.00

0.80

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

3.5000

2.00

7.00

0337010001

Equipos HERRAMIENTAS MANUALES

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

Representante L e g a l

(2 f Página:

S10

9

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VIA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 20/08/2012 Subpresupuesto________ 002 MEJORAMIENTO DE PUENTE SAN LORENZO___________________________________________ Fecha presupuesto

Partida

25.04.03

Rendimiento

kg/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0.0320

15.14

0.48

0147010003

OFICIAL

hh

1.0000

0.0320

13.16

0.42

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO 250.0000

Costo unitario directo por: kg

EQ. 250.0000 Cuadrilla

Cantidad

Precio SI.

4.98 Parcial SI.

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.05.01

Rendimiento

m3/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

3.5556

0221000000

BOL

9.0000

21.50

193.50

0238000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG) HORMIGON

m3

1.3000

80.00

104 00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2 EN VIGA TENSOR MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

375.20

Precio SI.

Parcial SI.

0.8889

15.14

13.46

0.4444

13.16

5.85

11.86

42.17

Cantidad

61.48

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

61.48

1.84

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

04444

500

2.22 15.17

Partida

25.05.02

Rendimiento

m2/DIA

Código

Descripción Recurso Mano de Obra OPERARIO

0147010002 0147010003

ENCOFRADO Y DESENCOFRADO MO. 18.0000

Costo unitario directo por: m2 Unidad

°FICIAL

0202100099

Materiales ALAMBRE NEGRO N’ 8 CLAVOS DE 3"

0229500091

0202040010

EQ. 18.0000 Cuadrilla

Cantidad

Precio SI.

22.86 Parcial SI.

hh

1.0000

0.4444

15.14

6.73

hh

1.0000

0.4444

13.16

5.85 12.58

kg

0.2100

4.30

kg

0.2400

5.00

1.20

SOLDADURA

kg

0.1000

8.00

0.80

0243000025

MADERA NACIONAL PARA ENCOFRADO

p2

3.5000

2.00

7.00

0337010001

Equipos HERRAMIENTAS MANUALES

'4

) J /

0.90

9.90 \ %MO

3.0000

12.58

0.38 0.38

A m p a ro D ía z A re va lo R e p re s e n ta n te L e g a l

(

Página:

S10

5

9

10

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

25.05.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0202040009

Materiales ALAMBRE NEGRO N“ 16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO. 250.0000

Costo unitario directo por: kg

EQ. 250.0000

4.98

Cuadrilla

Cantidad

Precio SI.

hh

1.0000

0.0320

15.14

0.48

hh

1.0000

0.0320

13.16

042

Unidad

Parcial SI.

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.06.01

Rendimiento

m3/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

3.5556

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2 VIGA MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m3 Cuadrilla

Cantidad

375.20

Precio SI.

Parcial SI.

0.8889

15.14

13.46

0.4444

13.16

5.85

11.86

42.17 61.48

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

61.48

1.84

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40”

hm

1.0000

04444

5.00

222 15.17

Partida

25.06.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFidAL

0202040010 0202100099

Materiales ALAMBRE NEGRO N°8 CLAVOS DE 3"

0229500091

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m2 Unidad

22.86

Cuadrilla

Cantidad

hh

1.0000

0.4444

15.14

6.73

hh

1.0000

0.4444

13.16

5.85

Precio SI.

Parcial SI.

12.58 ffé t

cXsiJ*. i

kg

0.2100

4.30

n ji

kg

0.2400

5.00

1.20

SOLDADURA

kg

0.1000

8.00

0.80

0243000025

MADERA NACIONAL PARA E N C O F R A D ^ ^ ^ C

P2

3.5000

2.00

7.00

0337010001

Equipos HERRAMIENTAS MANUALES

L

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

A m p a ro D íaz A re va lo R e p re s e n ta n te L e g a l

Página:

S10

11

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Parüda

25.06.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0.0320

15.14

0.48

0147010003

OFICIAL

hh

1.0000

0.0320

13.16

0.42

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO FY=4200 KG/CM2 MO. 250.0000

EQ. 250.0000

Costo unitario directo por: kg Unidad

Cuadrilla

Cantidad

Precio SI.

4.98 Parcial SI.

0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.07.01

Rendimiento

m3/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

2.0000

0147010003

OFICIAL

hh

1.0000

0147010004

PEON

hh

8.0000

3.5556

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2 VIGA MO. 18.0000

EQ. 18.0000

Costo unitario directo p o r: m3 Cuadrilla

Cantidad

375.20

Precio SI.

Parcial SI.

0.8889

15.14

13.46

0.4444

13.16

5.85

11.86

42.17 61.48

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

61.48

1.84

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4444

25.00

11.11

0349070004

VIBRADOR DE CONCRETO 4 HP 240"

hm

10000

04444

5.00

2.22 15.17

Partida

25.07.02

Rendimiento

m2/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0147010003

OFICIAL

hh

1.0000

ENCOFRADO Y DESENCOFRADO MO. 18.0000

EQ. 18.0000

Costo unitario directo por: m2 Unidad

Cuadrilla

Cantidad

22.86

Precio SI.

Parcial SI.

0.4444

15.14

6.73

0.4444

13.16

5.85 12.58

0202040010

Materiales ALAMBRE NEGRO N°8

kg

0.2100

4.30

0202100099

CLAVOS DE 3“

kg

0.2400

5.00

1.20

0229500091

SOLDADURA

kg

0.1000

8.00

0.80

0243000025

MADERA NACIONAL PARA ENCOFRADO

P2

3.5000

2.00

7.00

0337010001

Equipos HERRAMIENTAS MANUALES

0.90

9.90 %MO

3.0000

12.58

0.38 0.38

(W Página:

S10

12

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Subpresupuesto________ 002 MEJORAMIENTO DE PUENTE SAN LORENZO___________________________________________ Fecha presupuesto 20/08/2012

Partida

25.07.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO F'Y=4200 KG/CM2 MO 250.0000

EQ. 250.0000

Costo unitario directo por: kg Unidad

Cuadrilla

4.98

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0320

15.14

0.48

1.0000

0.0320

13.16

0.42 0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

25.08.01

Rendimiento

m3/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

0147010004

PEON

hh

0221000000

Materiales CEMENTO PORTLAND TIPO I (42.5KG)

BOL

9.0000

21.50

193.50

0238000000

HORMIGON

m3

1.3000

80.00

104.00

0239050000

AGUA

m3

0.2100

5.00

CONCRETO F'C= 210 KG/CM2. EN LOSAS MO. 20.0000

EQ. 20.0000

Costo unitario directo por: m3 Unidad

Cuadrilla

367.53

Cantidad

Precio SI.

Parcial SI.

2.0000

0.8000

15.14

12.11

1.0000

0.4000

13.16

5.26

8.0000

3.2000

11.86

37.95 55.32

1.05 298.55

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

55.32

1.66

0348010011

MEZCLADORA DE CONCRETO DE 9 -11P3

hm

1.0000

0.4000

25.00

10.00

0349070004

VIBRADOR DE CONCRETO 4 HP 2 40‘

hm

1.0000

04000

500

2.00 13.66

Partida

25.08.02

Rendimiento

m2/DIA

Código

Descripción Recurso Mano de Obra OPERARIO OFICIAL

0147010002 0147010003

ENCOFRADO Y DESENCOFRADO DE LOSA SUPERIOR (TIPO FALSO PUENTE) MO. 6.0000

EQ

6.0000

Costo unitario directo por: m2 Unidad

,

^

Cuadrilla

138.23

Cantidad

Precio SI.

Parcial SI. 40.37

hh

2.0000

2.6667

15.14

hh

2.0000

2.6667

13.16

35.09 75.46

0202040010

Materiales ALAMBRE NEGRO N°8

kg

1.0000

4.30

0202100099

CLAVOS DE 3-

kg

0.7000

5.00

3.50

0243000031

MADERA NACIONAL PARA ENCOFRADO

P2

25.6000

2.00

51.20

0337010001

Equipos HERRAMIENTAS MANUALES

i »

®

j,

4.30

59.00 \ %MO

5.0000

75.46

3.77 3.77

Página:

S10

13

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN L O R E N Z O ________________

Partida

25.08.03

Rendimiento

kg/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

0202040009

Materiales ALAMBRE NEGRO N°16

kg

0.0600

5.00

0.30

0203010007

ACERO DE REFUERZO Fy=4200 kg/cm2 GRADO 60

kg

1.0700

3.50

3.75

0337010001

Equipos HERRAMIENTAS MANUALES

ACERO DE REFUERZO FY=4200 KG/CM2 MO 250.0000

EQ. 250.0000

Costo unitario directo por: kg Unidad

Cuadrilla

4.98

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0320

15.14

0.48

1.0000

0.0320

13.16

0.42 0.90

4.05 %MO

3.0000

0.90

0.03 0.03

Partida

26.01

Rendimiento

ML/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0147010003

OFICIAL

hh

1.0000

BARANDA METALICA INC. PINTADO MO. 12.0000

EQ. 12.0000

Costo unitario directo por: ML Unidad

Cuadrilla

Cantidad

115.89

Precio SI.

Parcial SI.

0.6667

15.14

10.09

0.6667

13.16

8.77 18.86

0202850031

Materiales TUBO DE FIERRO GALVANIZADO DE 2”

ML

2.0000

22.00

44.00

0202850032

TUBO DE FIERRO GALVANIZADO DE 3'

ML

1.0000

45.00

45.00

0254020081

PINTURA ESMALTE

gln

0.0380

35.00

1.33

0254060000

PINTURA ANTICORROSIVA

gln

0.0378

35.00

1.32

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0348210066

SOLDADORA ELECTRICA

hm

91.65

0.7500

2.0000

18.86

0.38

0.5000

10.00

5.00 5.38

Parida

26.02

Rendimiento

pto/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0202850032

Materiales TUBO DE FIERRO GALVANIZADO DI

0337010001

Equipos HERRAMIENTAS MANUALES

DRENAJE EN LOSA SUPERIOR MO. 35.0000

EQ. 35.0000

Costo unitario directo por: pto Unidad

31.41

Cuadrilla

Cantidad

Precio SI.

hh

1.0000

0.2286

15.14

346

hh

1.0000

0.2286

13.16

3.01

Parcial SI.

6.47 ML

0.5500

45.00

24.75 24.75

%MO

3.0000

6.47

0.19 0.19

Parida

26.03

Rendimiento

und/DIA

Código

Descripción Recurso Materiales PLACA ACRILICA DE 0.40 X 0.60 M. INC. COLOCACION

0279560003

PLACA RECORDATORIA (INC. COLOCACION) MO. 1.0000

EQ. 1.0000

Costo unitario directo por: und Unidad und

Cuadrilla

200.00

Cantidad

Parcial SI.

1.0000

200.00

200.00

d íe a n

A m p a ro Díaz A re va lo R a p ta s e o ta n te L e g a l

( W Página:

S10

?

14

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

26.04

Rendimiento

und/DIA

Código

Descripción Recurso Materiales CARTEL DE IDENTIFICACION

0290010004

CARTEL DE IDENTIFICACION DEL PUENTE MO. 0.8000

EQ. 0.8000

Costo unitario directo por: und Unidad

Cuadrilla

GLB

1,200.00

Cantidad

Precio SI.

Parcial SI.

1.0000

1,200.00

1,200.00 1,200.00

Parida

26.05

Rendimiento

ML/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0147010004

PEON

hh

1.0000

JUNTAS DE DILATACION METALICA MO. 15.0000

EQ. 15.0000

Costo unitario directo por: ML Unidad

Cuadrilla

100.08

Precio SI.

Parcial SI.

0.5333

15.14

8.07

0.5333

11.86

Cantidad

6.32 14.39

0203030101

Materiales FIERRO CORRUGADO DE 3/8*

0229500091

SOLDADURA

0256220100

PLANCHA DE FIERRO 3/8“

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

14.39

0.43

0348210052

EQUIPO DE CORTE

hm

0.5000

0.2667

8.00

2.13

0348210066

SOLDADORA ELECTRICA

hm

1.0000

0.5333

10.00

5.33

ML

1.8000

3.00

kg m2

0.0500

8.00

0.40

0.6000

120.00

72.00

5.40

77.80

7.89 Partida

26.06

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

APOYO MOVIL DE NEOPRENE SHORE 70. MO. 5.0000

EQ. 5.0000

Costo unitario directo p o r: und Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

344.50

Precio SI.

Parcial SI.

1.6000

15.14

24.22

1.6000

11.86

18.98 43.20

0230650021

Materiales NEOPRENE SHORE DE 0.30 X 0.25 X O.i

0337010001

Equipos HERRAMIENTAS MANUALES

1.0000

pza

300.00

300.00 300.00

%MO

3.0000

43.20

1.30 1.30

Partida

26.07

APOYO FIJO DE NEOPRENE SHORE 70.

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010004

PEON

hh

0230650021

Materiales NEOPRENE SHORE DE 0.30 X 0.25 X 0.05

0337010001

Equipos HERRAMIENTAS MANUALES

MO. 3.0000

EQ. 3.0000

Costo unitario directo por: und Cuadrilla

374.16

Cantidad

Precio SI.

Parcial SI.

1.0000

2.6667

15.14

40.37

1.0000

2.6667

11.86

31.63 72.00

pza

1.0000

300.00

300.00 300.00

%MO

3.0000

72.00

2.16

Página:

S10

15

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 002 MEJORAMIENTO DE PUENTE SAN LORENZO

Partida

27

Rendimiento

MUDIA

Código

Unidad

0147010003

Descripción Recurso Mano de Obra OFICIAL

0147010004

PEON

0203030101

Materiales FIERRO CORRUGADO DE 3/8”

ML

1.8000

3.00

5.40

0229500091

SOLDADURA

kg

0.0500

8.00

0.40

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

73.76

2.21

0348210052

EQUIPO DE CORTE

hm

0.5000

1.0000

8.00

8.00

0348210066

SOLDADORA ELECTRICA

hm

1.0000

2.0000

10.00

MONTAJE DE TUBERIA MATRIZ DE 10" MO 4.0000

Costo unitario directo por: ML

EQ. 4.0000

109.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

2.0000

13.16

26.32

hh

2.0000

4.0000

11.86

47.44 73.76

5.80

20.00 30.21

Partida

28.01

Rendimiento

MUDIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

PINTURA EN BARANDAS METALICAS MO. 30.0000

EQ. 30.0000

Costo unitario directo por: ML Unidad

13.73

Cuadrilla

Cantidad

hh

1.0000

0.2667

15.14

4.04

hh

1.0000

0.2667

13.16

3.51

Precio SI.

Parcial SI.

7.55 Materiales 0253030027

THINER

0.0080

15.00

0.12

0254020042

PINTURA ESMALTE SINTETICO

0.0800

35.00

2.80

0254060000

PINTURA ANTICORROSIVA

0.0800

35.00

2.80

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

5.0000

7.55

0.38

0337010025

BROCHA DE 4*

und

0.0100

8.00

0.08

gln

5.72

0.46 Partida

28.02

Rendimiento

GLB/DIA

Código

Descripción Recurso Mano de Obra LIMPIEZA FINAL DE OBRA

0147010098

LIMPIEZA FINAL DE OBRA MO. 2,000.0000

EQ. 2,000.0000

Costo unitario directo por: GLB Unidad

Cuadrilla

GLB

200.00

Cantidad

Precio SI.

Parcial SI.

1.0000

200.00

200.00 200.00

Partida

28

Rendimiento

MUDIA

Código

Unidad

0147010003

Descripción Recurso Mano de Obra OFICIAL

0147010004

PEON

MONTAJE DE TUBERIA MATRIZ DE 16" MO. 2.0000

EQ. 2.0000

Costo unitario directo por: ML Cuadrilla

Cantidad

hh

1.0000

hh

2.0000

199.75

Precio SI.

Parcial SI.

4.0000

13.16

52.64

8.0000

11.86

94.88 147.52

0203030101

Materiales FIERRO CORRUGADO DE 3/8'

ML

1.8000

3.00

5.40

0229500091

SOLDADURA

kg

0.0500

8.00

0.40

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0348210052

EQUIPO DE CORTE

hm

0.0625

QJ2500

0348210066

SOLDADORA ELECTRICA

hm

1.0000

<^4.0000 — --------- .

5.80

-

3.0000

V

147 52

2.00

1000

40.00 46.43

\ F e m a t f^ K ija e i^ e a n ,|p

A Í n p a r t f 'f Z t S í . A r v v a l o R epresentante

4.43

8.03)

4088!

w Página:

S10

1

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - ÜCAYALI Fecha presupuesto 20/08/2012 003 OBRAS DE SANEAMIENTO_________________________________________ TRAZO, NIVELES Y REPLANTEO DE REDES

Partida

29.01.01

Rendimiento

ML/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0147010004

PEON

hh

MO. 1,000.0000

Costo unitario directo por: ML

EQ. 1,000.0000

Precio SI.

Parcial SI.

0.0080

15.14

0.12

0.0080

13.16

0.11

0.0320

11.86

0.38

Cuadrilla

Cantidad

hh

1.0000

hh

1.0000 40000

Unidad

1.08

0.61 Materiales BOL

0.0100

21.00

0.21

P2

0.0250

1.15

0.03

0230020001

YESO DE 28 Kg

0243000026

ESTACA DE MADERA

0330550014

Equipos NIVEL TOPOGRAFICO

hm

0.0080

15.00

0.12

0337010001

HERRAMIENTAS MANUALES

%MO

3.0000

0.61

0.02

0337020037

WINCHA DE 30m

und

0.0030

30.00

0.09

0.24 1.0000

0.23 Partida

29.02.01

Rendimiento

m/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349040098

RETROEXCAVADORA S/O 80-115 HP

hm

EXCAVACION DE ZANJA DE 0.6 x 1.20 M. MO. 180.0000

EQ. 180.0000

Costo unitario directo por: m Unidad hh

6.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0444

11.86

0.53 0.53

1.0000

3.0000

0.53

0.02

0.0444

140.00

6.22 6.24

Partida

29.02.02

Rendimiento

m/DIA

Código 0147010003

Descripción Recurso Mano de Obra OFICIAL

0147010004

PEON

REFINE Y NIVELACION COMPACTADO MANUAL MO. 50.0000

EQ. 50.0000

Costo unitario directo por: m Unidad

Cuadrilla

Cantidad

hh

0.3800

hh

1.0000

2.78

Precio SI.

Parcial SI.

0.0608

13.16

0.80

0.1600

11.86

1.90 2.70

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

2.70

0.08 0.08

Partida

29.02.03

Rendimiento

m/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

CAMA DE ARENA SELECTA E=0.30 MO. 280.0000

EQ

280.0000

Costo unitario directo por: m Unidad hh

11.70

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

2.0000

0.0571

11.86

0.68 0.68

Materiales 0204000000

ARENA FINA

m3

0.2160

50.00

0239050000

AGUA

m3

0.0400

5.00

10.80

0.20 11.00

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

0.68

0.02 0.02

Representante Legal

Página:

S10

2

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012

Partida

29.02.04

Rendimiento

m/DIA

Código 0147010003

Descripción Recurso Mano de Obra OFICIAL

hh

0147010004

PEON

hh

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO MO. 25.0000

Costo unitario directo por: m

EQ. 25.0000 Unidad

35.09 Parcial SI.

Cantidad

Precio SI.

1.0000

0.3200

13.16

4.21

2.0000

0.6400

11.86

7.59

Cuadrilla

11.80 Materiales 0204110023

TIERRA ROJA

m3

0.6480

25.00

0239050000

AGUA

m3

0.0200

5.00

16.20 0.10 16.30

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0383020001

COMPACTADORA TIPO SALTARIN

hm

1.0000

5.0000

11.80

0.59

0.3200

20.00

6.40 6.99

Partida

29.03.01

Rendimiento

m/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010004

PEON

hh

SUMINISTRO Y COLOCACION DE TUBERIAS PVC UF ACCESORIOS DE PVC DIAM. 110 MM S-13.3 ISO 4422 RED MATRIZ INC. ANILLO MO. 90.0000

EQ. 90.0000

Costo unitario directo por: m Unidad

Cuadrilla

20.58

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0889

15.14

1.35

1.0000

0.0889

11.86

1.05 2.40

Materiales 0213510005

LUBRICANTES

gln

0.0040

15.00

0272930002

ANILLO 110 MM- UF- KM NEGRO

und

0.1700

4.20

0.71

0272930003

TUBERIA PVC UF 0110 MM. S -13.3

m

1.0500

16.50

17.33

0337010001

Equipos HERRAMIENTAS MANUALES

0.06

18.10 %MO

3.2500

2.40

0.08 0.08

Partida

29.04.01

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010004

PEON

hh

0272940001

Materiales VALVULA LUFLEX ISO 7259 FFD 110 MM.

und

1.0000

485.00

0272940002

TAPA DE F°F° 4" X6"

und

1.0000

14.00

14.00

0272940003

TUBERIA PVC 200 MM.C-7.5

und

2.0000

45.00

90.00

0337010001

Equipos HERRAMIENTAS MANUALES

SUMINISTRO E INSTALACION DE VALVULA LUFLEX ISO 7259 FFD 110 MM. MO. 3.0000

EQ. 3.0000

Costo unitario directo por: und Unidad

Cuadrilla

663.16

Cantidad

Precio SI.

1.0000

2.6667

15.14

40.37

1.0000

2.6667

11.86

31.63

Parcial SI.

72.00 485.00

589.00 %MO

3.0000

72.00

2.16 2.16

D ía z A re v a lo Representante Legal

Página:

S10

3

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012

Partida

29.04.02

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

2.6667

15.14

40.37

0147010004

PEON

hh

1.0000

2.6667

11.86

31.63

0272950001

Materiales CODO PVC 100 MM.X 45"

0337010001

Equipos HERRAMIENTAS MANUALES

SUM. EINST. DE CODO PVC UF 0 110 mm. DE 45“ MO 3.0000

Costo unitario directo por: und

EQ. 3.0000

Cantidad

Cuadrilla

Precio SI.

224.16 Parcial SI.

72.00 1.0000

und

150.00

150.00 150.00

3.0000

%MO

72.00

2.16 2.16

Partida

29.04.03

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

0271290006

Materiales TEE F°F° 110MMX110MM ISO TIPO LUFLEX

SUMINISTRO E INSTALACION DE TEE FF TIPO LUFLEX ISO 7259110 MM. MO.

Costo unitario directo por: und

EQ. Cuadrilla

177.27

Cantidad

Precio SI.

hh

1.0000

15.14

15.14

hh

1.0000

11.86

11.86

Unidad

Parcial SI.

27.00 und

1.0000

150.00

150.00 150.00

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

1.0000

27.00

0.27 0.27

Partida

29.04.04

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0.8000

0147010004

PEON

hh

0.8000

SUMINISTRO E INSTALACION DE TAPON PVC UF DIAM. 110 MM. MO 20.0000

EQ. 20.0000

Costo unitario directo p or: und Cuadrilla

Unidad

Cantidad

34.12

Precio SI.

Parcial SI.

0.3200

15.14

4.84

0.3200

11.86

3.80 8.64

Materiales 0213510005

LUBRICANTES

gln

0272010061

TAPON PVC U/F 110 MM

und

0272930002

ANILLO 110 MM- UF- KM NEGRO

und

w íf

II 0337010001

Equipos HERRAMIENTAS MANUALES

0.0010

15.00

0.02

1.0000

21.00

21.00

10000 f- 1

4.20

ve* K

V VWESTKuf

. wwjJttOuctw» , ¡J

%MO

3.0000

4.20 25.22

8.64

0.26 0.26

Partida

29.04.05

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0.4000

15.14

6.06

0147010004

PEON

hh

1.0000

0.4000

11.86

4.74

SUMINISTRO E INSTALACION DE UNION DE REPARACION PVC UF DIAtta. 110 MM. MO. 20.0000

EQ. 20.0000

Costo unitario directo por: und Unidad

Cuadrilla

Cantidad

Precio SI.

165.60 Parcial SI.

10.80 Materiales 0213510005

LUBRICANTES

0.0050

15.00

0.08

0272130079

UNION DE REPARACION PVC U/F D= 110 MM

1.0000,.

146.00

146.00

0272930002

ANILL0110 MM- UF- KM NEGRO

4.20

8.40 154.48

0337010001

Equipos HERRAMIENTAS MANUALES

'NSyCT %MO

10.80

0.32 0.32

Á n t f ia i- t f U ia z A r e v a ia

¿Repífcscíiláiiu. U tjfá i

INGENIERO CWH.

Página:

S10

4

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO. DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012

Partida

29.04.06

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

SUMINISTRO E INSTALACION DE GRIFO CONTRA INCENDIO MO. 3.0000

Costo unitario directo por: und

EQ. 3.0000

614.16

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

2.6667

15.14

40.37

hh

1.0000

2.6667

11.86

31.63 72.00

0272960001

Materiales GRIFO CONTRA INCENDIO

0337010001

Equipos HERRAMIENTAS MANUALES

und

540.00

1.0000

540.00 540.00

%MO

3.0000

72.00

2.16 2.16

Partida

29.04.07

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0.5000

0.2222

15.14

3.36

0147010003

OFICIAL

hh

1.0000

0.4444

13.16

5.85

0147010004

PEON

hh

2.0000

0.8889

11.86

DADO DE CONCRETO MO. 18.0000

EQ. 18.0000

Costo unitario directo por: und Cuadrilla

Unidad

Cantidad

Precio SI.

42.72 Parcial SI.

10.54 19.75

0202830002

Materiales CLAVOS PROMEDIOS PARA LA CONSTRUCCION

kg

0.3300

423

1.40

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0.4600

21.50

9.89 6.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.0750

80.00

0239050000

AGUA

m3

[| 5 ESTUDIOS T QW>í V

0.0100

5.00

0.05

0243100005

MADERA CORRIENTE PARA ENCOFRADO

p2

\U

3.3600

1.50

5.04

0337010001

Equipos HERRAMIENTAS MANUALES

i f e S ‘ S3NucO r f»octífiu J

22.38 %MO

3.0000

19.75

0.59 0.59

Partida

29.04.08

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0147010004

PEON

0202830002

Materiales CLAVOS PROMEDIOS PARA LA CONSTRUCCION

0204000000

ARENA FINA

CAJA DE PROTECCION DE VALVULA MO. 15.0000

EQ. 15.0000

Costo unitario directo por: und Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

hh

1.0000

200.94

Precio SI.

Parcial SI.

0.5333

15.14

8.07

0.5333

13.16

7.02

0.5333

11.86

6.32 21.41

kg m3

0.3000

4.23

1.27

0.0500

50.00

2.50

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

3.0170

21.50

64.87

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.2000

80.00

16.00

0239050000

AGUA

m3

0.0100

5.00

0.05

0243100005

MADERA CORRIENTE PARA ENCOFRADO

P2

2.8000

1.50

4.20

0250060028

TAPA DE F°F° 6' X 8', INC. MARCO

und

1.0000

90.00

90.00 178.89

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

21.41

0.64 0.64

(KIGENtE^0 ctvH -

fójuparo D ía z A re va lo R e p re s e n ta n te L e g a l

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Subpresupuesto________ 003 OBRAS DE SANEAMIENTO___________________________________________________________Fecha presupuesto 20/08/2012

Partida

29.05.01

DOBLE PRUEBA HIDRAULICA Y DESINFECCION

Rendimiento

m/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010004

PEON

hh

Costo unitario directo por: m

EQ. 100.0000

MO. 100.0000

Cuadrilla

10.78 Parcial SI.

Cantidad

Precio S/.

1.0000

0.0800

15.14

1.21

1.0000

0.0800

11.86

0.95 2.16

0229720001

Materiales ACCESORIOS DIVERSOS

0239020079

HIPOCLORITO DE CALCIO 70%

0239050000

AGUA

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0348820008

BOMBA DE MANO

hm

6.00

und

0.5000

12.00

kg m3

0.0800

16.00

1.28

0.0160

5.00

0.08 7.36

1.0000

3.0000

2.16

0.0800

15.00

0.06 1.20 1.26

Partida

30.01.01

Rendimiento

m/DIA

Código 0147000032

Descripción Recurso Mano de Obra TOPOGRAFO

0147010004

PEON

TRAZO, NIVELES Y REPLANTEO 3 ETAPAS (PÍEXCAV, P/RELLENO,P/PAVIMENTO) MO. 800.0000

EQ. 800.0000

Costo unitario directo p o r: m

0.72

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

0.0100

15.14

0.15

hh

2.0000

0.0200

11.86

0.24

Unidad

0.39 Materiales 0229030001

YESO

kg

0.0250

1.40

0.04

0243010003

MADERA TORNILLO

/

P2

0.0020

2.50

0.01

0254020100

PINTURA ESMALTE SUPER SINTETICA i

gln

0.0005

52.00

0.03

0330550014

Equipos NIVEL TOPOGRAFICO

0337010001

HERRAMIENTAS MANUALES

0337020037

WINCHA DE 30m

//& DIVISION > 4 ^ * ffiTUOIOy'l OBRAS

II

VI"* v\

- W i HOOUCW

0.08

i , h hm

yt

0.0100

15.00

0.15

%MO

1.0000

3.0000

0.39

0.01

und

0.0030

30.00

0.09 0.25

Partida

30.02.01

Rendimiento

m/DIA

Código 0147010004

Descripción Recurso Mano de Obra PEON

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349040098

RETROEXCAVADORA S/O 80-115 HP

hm

EXCAVACION DE ZANJA DE 0.8X 1.60 - 2.60 M. MO 180.0000

EQ. 180.0000

Costo unitario directo por: m Unidad hh

6.77

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

0.0444

11.86

0.53 0.53

1.0000

3.0000

0.53

0.0444

140.00

0.02 6.22 6.24

Partida

30.02.02

Rendimiento

m/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

REFINE Y NIVELACION DE ZANJAS MO 150.0000

EQ. 150.0000

Costo unitario directo por : m Unidad hh

Cuadrilla

Cantidad

Precio SI.

2.0000

0.1067

11.86

1.31 Parcial SI. 1.27 1.27

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000 __— ----------- -127

0.04 n

(§ £ > Página:

S10

6

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYAL! 20/08/2012 Subpresupuesto________ 003 OBRAS DE SANEAMIENTO___________________________________________________________Fecha presupuesto

Partida

30.02.03

Rendimiento

m/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

CAMA DE ARENA SELECTA E= 0.20 MO. 400.0000

Costo unitario directo por: m

EQ. 400.0000 Cuadrilla

Cantidad

hh

1.0000

hh

1.0000

10.16

Precio SI.

Parcial SI.

0.0200

15.14

0.30

0.0200

11.86

0.24 0.54

Materiales 0204000000

ARENA FINA

0337010001

Equipos HERRAMIENTAS MANUALES

0.1920

m3

50.00

9.60 9.60

3.0000

%MO

0.54

0.02 0.02

Partida

30.02.04

Rendimiento

m/DIA

Código 0147010003

Descripción Recurso Mano de Obra OFICIAL

0147010004

PEON

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

0349030004

COMPACTADOR VIBR. TIPO PLANCHA 7 HP

hm

901102020501

Subpartidas TRANSP. AGUA/OBRA

RELLENO COMPACTADO ZANJA 0.80 M. X (1.60 - 2.60M) MO. 15.0000

EQ. 15.0000

Costo unitario directo por: m

57.11

Cuadrilla

Cantidad

Precio SI.

hh

0.5000

0.2667

13.16

3.51

hh

4.0000

2.1333

11.86

25.30

Unidad

Parcial SI.

28.81

2.0000

5.0000

28.81

1.44

1.0667

25.00

26.67 28.11

m3

0.1155

1.62

0.19 0.19

Partida

30.03.01

Rendimiento

m/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

SUMINISTRO Y COLOCACION DE TUBERIA PVC DIAM. 200 MM. S25 UF -KM MO. 150.0000

EQ. 150.0000

Costo unitario directo p o r: m Cuadrilla

Cantidad

hh

1.0000

hh

2.0000

Unidad

31.10

Precio SI.

Parcial SI.

0.0533

15.14

0.81

0.1067

11.86

1.27 2.08

Materiales 0213510005

LUBRICANTES

0272130082

TUBERIA PVC 200 MM S-25 UF-KM

0272930004

ANILLO 200 MM - UF - KM NEGRO

und

0337010001

Equipos HERRAMIENTAS MANUALES

% M & >. A

gln

ML

r 17™

’ /J

0.0200

15.00

0.30

1.0500

26.00

27.30

0.1700

8.00

1.36 28.96

3.0000

2.08

0.06 0.06

Partida

30.04.01

Rendimiento

m3/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

EXCAVACION DE ZANJAS - BUZONES MO. 3.0000

EQ. 3.0000

Costo unitario directo por: m3 Unidad hh

32.58

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

1.0000

2.6667

11.86

31.63 31.63

Equipos

Página:

S10

7

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYAL! 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012

Partida

30.04.02

BUZON DE CONCRETO ARMADO, H= 1.50 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0147010004

PEON

0202040010

Materiales ALAMBRE NEGRO N°8

kg

0.6000

4.30

0202100099

CLAVOS DE 3'

kg

0.4000

5.00

2.00

0203020004

ACERO CORRUGADO

23.7400

2.71

64.34

0204000000

ARENA FINA

kg m3

1.3993

50.00

69.97

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

23.5000

21.50

505.25 249.60

MO. 3.0000

Costo unitario directo p o r: und

EQ. 3.0000

1,300.54

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

2.6667

15.14

40.37

hh

1.0000

2.6667

13.16

35.09

hh

1.0000

2.6667

11.86

31.63 107.09 2.58

0238000004

HORMIGON (PUESTO EN OBRA)

m3

3.1200

80.00

0243100005

MADERA CORRIENTE PARA ENCOFRADO

31.0000

1.50

46.50

0250060029

TAPA DE CONCRETO, INC MARCO

P2 und

1.0000

250.00

250.00

0337010001

Equipos HERRAMIENTAS MANUALES

1,190.24 %MO

3.0000

107.09

3.21 3.21

Partida

30.04.03

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0147010004

PEON

BUZON DE CONCRETO ARMADO, H= 1.80 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F° MO. 3.0000

EQ. 3.0000

Costo unitario directo por: und Unidad

1,331.61

Cuadrilla

Cantidad

Precio SI.

Parcial SI.

hh

1.0000

2.6667

15.14

40.37

hh

1.0000

2.6667

13.16

35.09

hh

1.0000

2.6667

11.86

31.63 107.09

0202040010

Materiales ALAMBRE NEGRO N*8

kg

0.6000

4.30

0202100099

CLAVOS DE 3“

kg

0.3500

5.00

1.75

0203020004

ACERO CORRUGADO

24.2000

2.71

65 58

0.9800

50.00

49.00

25.0000

21.50

537.50 262 44

2.58

0204000000

ARENA FINA

kg m3

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

0238000004

HORMIGON (PUESTO EN OBRA)

m3

3.2805

80.00

0243100005

MADERA CORRIENTE PARA ENCOFRADO

34.9700

1.50

52.46

0250060029

TAPA DE CONCRETO, INC MARCO

p2 und

1.0000

250.00

250.00

0337010001

Equipos HERRAMIENTAS MANUALES

1,221.31 %MO

3.0000

107.09

3.21

Página:

8

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012 BUZON DE CONCRETO ARMADO, H= 2.20 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

Partida

30.04.04

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

0147010003

OFICIAL

hh

0147010004

PEON

hh

MO. 3.0000

Costo unitario directo por: und

EQ. 3.0000 Unidad

1,542.32 Parcial SI.

Cantidad

Precio SI.

1.0000

2.6667

15.14

40.37

1.0000

2.6667

13.16

35.09

1.0000

2.6667

11.86

Cuadrilla

31.63 107.09

0202040010

Materiales ALAMBRE NEGRO N°8

kg

0.8000

4.30

0202100099

CLAVOS DE 3'

kg

0.5000

5.00

2.50

0203020004

ACERO CORRUGADO

34.9000

2.71

94.58

0204000000

ARENA FINA

kg m3

1.2100

50.00

60.50

0221000000

CEMENTO PORTLAND TIPO i (42.5KG)

BOL

30.0000

21.50

645.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

3.8000

80.00

304.00

0243100005

MADERA CORRIENTE PARA ENCOFRADO

P2

48.0000

1.50

72.00

0250060029

TAPA DE CONCRETO, INC MARCO

und

1.0000

250.00

250.00

0337010001

Equipos HERRAMIENTAS MANUALES

3.44

1,432.02 %MO

3.0000

107.09

3.21 3.21

Partida

30.04.05

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

2.6667

15.14

40.37

0147010003

OFICIAL

hh

1.0000

2.6667

13.16

35.09

0147010004

PEON

hh

1.0000

2.6667

11.86

BUZON DE CONCRETO ARMADO, H= 2.40 M, D= 1.20 M. INC. TAPA DE C'A», MARCO F°F0 MO. 3.0000

EQ. 3.0000

Costo unitario directo por: und Cuadrilla

Cantidad

Precio SI.

1,775.07 Parcial SI.

31.63 107.09

0202040010

Materiales ALAMBRE NEGRO NT8

kg

0.9000

4.30

0202100099

CLAVOS DE 3‘

kg

0.5500

5.00

2.75

0203020004

ACERO CORRUGADO

40.0000

2.71

108.40

0204000000

ARENA FINA

kg m3

1.3890

50.00

69.45

0221000000

CEMENTO PORTLAND TIPO I (42.5KG)

BOL

34.0000

21.50

731.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

5.2100

80.00

416.80

0243100005

MADERA CORRIENTE PARA ENCOFRADO

P2

55.0000

1.50

82.50

0250060029

TAPA DE CONCRETO, INC MARCO

und

1.0000

250.00

250.00

0337010001

Equipos HERRAMIENTAS MANUALES

3.87

1,664.77 %MO

3.0000

107.09

3.21 3.21

UOGENieROCÍVIt-

Página:

S10

9

Análisis de precios unitarios Presupuesto Subpresupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Fecha presupuesto 20/08/2012 003 OBRAS DE SANEAMIENTO _____________________

Partida

30.05.01

Rendimiento

und/DIA

Código

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

1.6000

15.14

24.22

PEON

hh

2.0000

3.2000

11.86

37.95

0147010002 0147010004

PERFORACION Y EMPALME A TUBERIA MATRIZ Costo unitario directo por: und

EQ. 5.0000

MO. 5.0000

Unidad

Cuadrilla

Cantidad

Precio SI.

331.29 Parcial SI.

62.17 0221000000 0230460036

Materiales CEMENTO PORTLAND TIPO I (42.5KG) PEGAMENTO PARA PVC

BOL

0.3000

21.50

6.45

gln

0.0050

75.00

0.38 28.00

0238000004

HORMIGON (PUESTO EN OBRA)

m3

0.3500

80.00

0239050000

AGUA

m3

0.0800

5.00

0.40

0272070081

TEE PVC 200 MM.

und

1.0000

52.00

52.00

0272130082

TUBERIA PVC 200 MM S-25 UF-KM

ML

6.0000

26.00

156.00

0272930004

ANILLO 200 MM - UF - KM NEGRO

und

3.0000

8.00

24.00 267.23

0337010001

Equipos HERRAMIENTAS MANUALES

3.0400

%MO

62.17

1.89 1.89

Partida

30.06.01

Rendimiento

m/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010004

PEON

0239050000

AGUA

0337010001

Equipos HERRAMIENTAS MANUALES

PREUBA DE REDES MO. 180.0000

EQ. 180.0000

Costo unitario directo por: m Unidad

Cuadrilla

Cantidad

hh

1.0000

0.0444

hh

1.0000

0.0444

Precio S/.

1.40 Parcial S/.

Materiales m3

0.0314

0.16 0.16

3.0000

%MO

0.04 0.04

Partida

30.07.01

CONEXIONES DOMICILIARIAS CORTAS (L= 5.00 M. APROX.)

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0147010004

PEON

hh

1.0000

MO 5.0000

EQ 5.0000

Costo unitario directo por; und Cuadrilla

Cantidad

190.00

Precio SI.

Parcial SI.

1.6000

15.14

24.22

1.6000

11.86

18.98 43.20

0250520010

Materiales MARCO Y TAPA F°G° PARA MEDIDOR

und

1.0000

30.00

30.00

0272000100

TUBO PVC SAP D= 3“

pza

5.0000

10.00

50.00

0272010032

TUBERIA PVC SAP PRESION C-10 EC DE 1/2’ X5 M

ML

5.0000

1.50

7.50

0272330004

ABRAZADERA PVC 1/2* X 110 MM.

pza

1.0000

15.00

15.00

0272530066

CODO PVC SAP 1/2” X 45"

pza

2.0000

1.50

3.00

0272710006

LLAVE DE PASO

und

1.0000

10.00

10.00

0272970001

CAJA MEDIDOR DE AGUA

und

1.0000

20.00

20.00

0276210001

VALVULA CORPORATION PVC 1/2”

und

1.0000

10.00

10.00 145.50

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

3.0000

43.20

1.30 1.30

At/fparo D ía z A ru va lo Representante Legal

Página:

S10

10

Análisis de precios unitarios Presupuesto

0492001 MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI Subpresupuesto________ 003 OBRAS DE SANEAMIENTO Fecha presupuesto 20/08/2012 Partida

30.07.02

CONEXIONES DOMICILIARIAS LARGAS (L= 17.00 M. APROX.)

Rendimiento

und/DIA

Código 0147010002

Descripción Recurso Mano de Obra OPERARIO

hh

1.0000

0147010004

PEON

hh

1.0000

MO. 5.0000

EQ. 5.0000

Costo unitario directo por: und Unidad

Cuadrilla

Cantidad

300.23

Precio SI.

Parcial SI.

1.6000

15.14

24.22

1.6000

11.86

18.98 43.20

0250520010

Materiales MARCO Y TAPA F°G° PARA MEDIDOR

und

1.0000

30.00

30.00

0272000100

TUBO PVC SAP D= 3"

pza

14.0000

10.00

140.00

0272010032

TUBERIA PVC SAP PRESION C-10 EC DE 1/2" X5 M

ML

18.4860

1.50

27.73

0272140040

CODO PVC SAP 1/2' X45 °

pza

2.0000

1.50

3.00

0272330004

ABRAZADERA PVC 1/2' X 110 MM.

pza

1.0000

15.00

15.00

0272710006

LLAVE DE PASO

und

1.0000

10.00

10.00

0272970001

CAJA MEDIDOR DE AGUA

und

1.0000

20.00

20.00

0276210001

VALVULA CORPORATION PVC 1/2"

und

1.0000

10.00

10.00 255.73

0337010001

Equipos HERRAMIENTAS MANUALES

3.0000

%MO

43.20

1.30 1.30

Partida

30.08.01

CONEXIONES DOMICILIARIAS DE DESAGÜE NUEVAS (INC. TODOS LOS ACC.)

Rendimiento

und/DIA

Código

Unidad

0147010002

Descripción Recurso Mano de Obra OPERARIO

0147010003

OFICIAL

0213510005

LUBRICANTES

gln

0.0200

0230460036

PEGAMENTO PARA PVC

gln

0.2500

0231810001

DADOS DE CONCRETO f e 140KG/CM2 0.30 X 0.30 X 0.50 M.

und

2.0000

0231810002

DADOS DE CONCRETO fe 140KG/CM2 0.30 X 0.30 X 0.30 M.

und

2.0000

0250010002

1.0000

0272010063

CAJA DE REG. DE CONCRETO SIMP F C= 175 KG/CM2 HASTA 5 und CUERPOS TUBERIA PVC 160 MM S- 25 UF - KM ML

0272930005

ANILLO 160 MM - UF - KM NEGRO

und

2.0000

11.00

0272950002

CODO PVC 160 MM. X 45"

und

1.0000

55.00

0337010001

Equipos HERRAMIENTAS MANUALES

MO 4.0000

EQ. 4.0000

Costo unitario directo por. und Cuadrilla

Cantidad

hh

1.0000

2.0000

hh

2.0000

4.0000

Precio SI.

484.46 Parcial SI.

Materiales

10.0000

180.00

399.05 3.0000

%MO

82.92

2.49 2.49

Partida

30.09.01

Rendimiento

m3/DIA

Código

Descripción Recurso Mano de Obra PEON

0147010004

ELIMINACION DE MATERIAL CONTAMINANTE MO. 3.0008

EQ. 3.0008

Costo unitario directo por: m3 Unidad hh

Cuadrilla

Cantidad

Precio SI.

1.0003

2.6668

11.86

33.21 Parcial SI. 31.63 31.63

0337010001

Equipos HERRAMIENTAS MANUALES

%MO

5.0000

31.63

1.58 1.58

4089 (MSfcNieROCMt.

A m p a ro D ía z A re v a lo Representante Legal

FACTIBILIDAD DEL PROYECTO: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI”

INSUMOS FA C TIB ILID A D DEL PROYECTO:

"M E JO R A M IE N T O D E IN T E R C O N E X IO N AL C. P. SA N JOSE DESDE PUERTO CALLAO, D IS T R IT O D E YA R IN A C O C H A CORONEL P O R T IL L O - U C A Y A L I"

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

Página:

S10

1

Precios y cantidades de recursos requeridos por tipo Obra

0492001

Subpresupuesto Fecha

001

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

20/08/2012 UCAYALI - CORONEL PORTILLO - YARINACOCHA Unidad

Lugar Código

250105 Recurso

0147990025 0147990026 0198010049 0147010001 0147990023 0147990024

ACTIVIDAD DE CAPACITACION DE AIRE ACTIVIDAD DE EDUCACION AMBIENTAL CAPACITACION EN SEGURIDAD Y SALUD CAPATAZ MEDIDAS DE SEGURIDAD INICIO DEL PROYECTO MONITOREO DURANTE LA ETAPA DE CONSTRUCCION CALIDAD DE AIRE OFICIAL OPERARIO PEON PLAN DE SEGURIDAD Y SALUD TOPOGRAFO

Cantidad

Precio SI.

Parcial SI.

1.0000 1.0000 10.0000 712.7178 1.0000 1.0000

12.500.00 12.500.00 500.00 14.36 12.500.00 12.500.00

12,500.00 12,500.00 5,000.00 10,234.63 12,500.00 12,500.00

33,075.1808 39,467.8385 85,383.3200 1.0000 994.7207

13.16 15.14 11.86 5.000.04 15.14

435,269.38 597,543.07 1,012,646.18 5,000.04 15,060.07

M ANO DE O BRA

0147010003 0147010002 0147010004 0198010048 0147000032

GLB GLB GLB hh GLB GLB hh hh hh und hh

2,130,753.37 M ATERIALES 0265870004 0203010007 0239050000 0202040009 0202040010 0202000008 0239130017 0251200031 0205010003 0204000000 0213000006 0254080000 0230410041 0207010037 0212010053 0229030006 0261010002 0261010029 0221000000 0229040001 0230010030 0207900003 0229040091 0239500100 0202100099 0202830003 0202130021 0202010005 0208020003 0211910012 0229220001 0272090002 0202130031 0244010000 0253910011 0202130032 0238000000 0238000004 0230650005 0253000000 0230990019 0239020034 0239410005 0243000025 0292010006 0292010005 0292010004 0292010002 0292010009 0292010003 0292010008 0292010007 0243150008 0250020062 0265240003

ACCESORIOS DE ANCLAJE ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60 AGUA ALAMBRE NEGRO N°16 ALAMBRE NEGRO N°8 ALAMBRE NEGRO RECOCIDO # 8 ALMACEN ANGULAR 2*2*3/16" ARENA DE RIO ARENA FINA ASFALTO RC-250 BARNIZ MARINO CABLE DE ACERO DE 05/16* CABLE THW16 mm2 (color amarillo) CAJA PORTA MEDIDOR CAL CALAMINA LISA GALVANIZADA CALAMINA ONDULINE COLOR ROJO CEMENTO PORTLAND TIPO I (42.5KG) CINTA AISLANTE CINTA BANDIT 3/4’ CINTA DE SEÑALIZACION CINTA SEÑALADORA AMARILLA CINTILLO DE AMARRE CLAVOS DE 3" CLAVOS DE 4" CLAVOS PARA CALAMINA CLAVOS PARA MADERA C/C 3" CONDUCTOR ELECTRICO 2 - 1 X 6 MM2 NYY CONTROLADOR 3 FASES CORDEL CURVA PESADO PVC SAP P/INST. ELECT. 1’ ELEMENTO TERRAMESH VERDE{ 4.00 X 2.00 X 0.60 - 70°)M ESTACA DE MADERA GRASA HEBILLA DE 3/4" HORMIGON HORMIGON (PUESTO EN OBRA) JUNTA INPER WATER STOP NEOPRENE 6“ KEROSENE INDUSTRIAL LIJA LIJA DE FIERRO # 8 LIMPIEZA FINAL DE OBRA MADERA NACIONAL PARA ENCOFRADO MADERA QUINILLA DE 1 1/2’ X 1 1/2” MADERA QUINILLA DE 2” X 2 ” MADERA QUINILLA DE 2* X 4’ MADERA QUINILLA DE 3" X 11/2" i MADERA QUINILLA DE 3* X 3* MADERA QUINILLA DE 4* X1* MADERA QUINILLA DE 4" X 3" C MADERA QUINILLA DE 4"X4" MADERA SHIHUAHUACO MARCO Y TAPA P F ” PARA BUZON MARCO Y TAPA FO. GO. P/MEDIDOR 1/2*-3/4"

und kg m3 kg kg kg m2 m m3 m3 gln gln m m und kg pin pin BOL ROL cía ROL ROL und kg kg kg kg m und ML und und P2

kg und m3 m3 m gln und und GLB P2

P 2^ P 2/

p2

- r j- ^ 2

------

t w a e l Lean 1 *3 ^9 4 gpferfctvH

p2 und und

0.3330 424,712.5892 12,337.9001 21,994.7488 4,138.2656 337.7123 12.0000 198.0000 0.0900 23.2080 1,061.9447 0.3800 3.0000 15.0000 3.0000 247.6617 24.0000 28.8800 120,692.2117 0.2100 12.0000 50.0000 2.0000 9.0000 444.0720 4.5000 0.5310 2,151 4422 3.1500 3.0000 45.0000 3.0000 3,390.0000 1,173.3878 255.8050 12.0000 652.7480 23,953.9695 1,394.2950 4.0000 2.5000 4.7000 1.0000 52,570.5628 12.5000 20.0000 40.0000 11.9000 180.0000 10.9000 270.0000 420.0000 360.0000 9.0000

12.40 37.25 1,486,494.06 3.50 61,689.50 5.00 109,973.74 5.00 17,794.54 4.30 1,519.71 4.50 6.999.96 583.33 1,623.60 8.20 4.50 50.00 1,160.40 50.00 7,433.61 7.00 14.44 38.00 22.50 7.50 57.00 3.80 435.00 145.00 371.49 1.50 384.00 16.00 635.36 22.00 2,594,882.55 21.50 0.63 3.00 48.00 4.00 3,500.00 70.00 110.00 55.00 2.16 0.24 2,220.36 5.00 22.50 5.00 2.66 5.00 9,681.49 4.50 34.65 11.00 5.625.00 1.875.00 9.00 0.20 3.00 1.00 2,203,500.00 650.00 1,349.40 1.15 1,330.19 5.20 24.00 2.00 52,219.84 80.00 1,916,317.56 80.00 34,857.38 25.00 25.20 6.30 5.00 2.00 9.40 2.00 4,000.00 4.000.00 105,141.13 2.00 40.00 3.20 64.00 3.20 128.00 3.20 38.08 3.20 576.00 3.20 34.88 3.20 864.00 3.20 1,344.00 3.20 900.00 2.50 - ------- 1 5 0 .0 0 ^ v 1.350.00 Qs.ood»0A 5 /Kgasc gepQQ) ) 270.00

t v a lo narttte l-io - .i

Página:

S10

2

Precios y cantidades de recursos requeridos por tipo Obra

0492001

Subpresupuesto Fecha

001 20/08/2012

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Lugar Código

250105 Recurso

0204020002

MATERIAL DE PRESTAMO SELECCIONADA EN ZONA DE MAT. ORGANICO MEDIDOR DE ENERGIA TRIFASICO MURETE DE CONCRETO PEGAMENTO PVC PERNOS DE 0 3/8” X 41/2“ PINTURA ALTO TRAFICO PINTURA ANTICORROSIVA PINTURA ESMALTE PINTURA ESMALTE PINTURA ESMALTE ANTICORROSIVO TEKNO PLANCHA DE ACERO POSTE DE F°G° DE 0 6" X 11 MM REGLA DE MADERA SEMAFORO DE UN CUERPO X 3 LENTES DE 12" X 12" X 12“ SEÑALIZACION VERTICAL SOLDADURA SOLDADURA ELECTRICA SOPORTE DE CUATRO BRAZOS SOPORTES DE TRES BRAZOS TEKNOPORT DE 12 MM. TEKNOPORT DE 25 MM. THINER TIERRA DE CHACRA O VEGETAL TIERRA ROJA TIERRA SELECCIONADA (PUESTA EN OBRA) TIZA TORNILLO AUTOROSCANTE DE 2" TRANSPORTE DE MATERIALES EQUIPOS Y H. - PUCALLPA A OBRA TRIPLAY DE 4'x8'x 4 mm TRIPLAY DE 4'x8'x 8 mm TUB. PVC SAP P/INST. ELECT. DE 1' TUBERIA PVC SAL 2" TUBERIA PVC SAP D E 0 4OMM TUBO DE FIERRO GALVANIZADO DE 0 2" TUBO PVC SAP 1 1/4" VARILLA DE COBRE 5/8X8' WATER STOP WAYPE INDUSTRIAL YESO DE 28 Kg

0230640100 0221990042 0230460037 0202200100 0254450100 0254060000 0254020080 0254110090 0254060018 0256220020 0263010013 0243160052 0211900011 0243400033 0229500091 0229500090 0265850002 0265850003 0260000011 0260000012 0253030027 0204010003 0204110023 0204110021 0239020082 0226000080 0232010097 0244030021 0244030023 0272080011 0273010026 0229400093 0202850033 0210140079 0206700007 0237020049 0239060024 0230020001

UCAYALI - CORONEL PORTILLO - YARINACOCHA Unidad m3 und und gln pza gln qln m2 gln gln kg und p2 und und kg kg und und m2 m2 gln m3 m3 m3 BOL und GLB pin pin m m m ML ML und ML kg BOL

Cantidad

Precio SI.

Parcial SI.

18,015.6120

15.00

270,234.18

3.0000 3.0000 0.0300 0.2500 127.9200 0.9400 0.0300 77.1322 0.9400 0.4000 3.0000 60.0000

1.0000

150.00 260.00 65.00 1.50 70.00 35.00 38.00 35.00 38.00 50.00 1.550.00 2.00 1.980.00 500.00 8.00 10.00 120.00 110.00 8.00 16.00 15.00 25.00 25.00 25.00 5.00 0.50 1.200.00

0.5000 2,562.2776 15.0000 1.5000 18.0000 21.1500 511.6100 3.0000 5.9000 1.6000 302.3447

12.00 34.00 2.00 8.50 6.50 25.00 4.00 250.00 16.00 2.00 21.00

10.0000

55.0000 0.5000 11.7500 1.0000

2.0000 1,135.2250 648.7000 48.6750 4.2000 2,738.8106 57,324.8000 36.7040 94.0000

450.00 780.00 1.95 0.38 8,954.40 32.90 1.14 2,699.63 35.72 20.00 4,650.00 120.00 19,800.00 27,500 00 4.00 117.50 120.00 220.00 9,081.80 10,379.20 730.13 105.00 68,470.27 1,433,120.00^ 183.$S 47 ÓÓP 1,200.006.00 87,117.44 30.00 12.75 117.00 528.75 2,046.44 750.00 94.40 3.20 6,349.24 10,593,269.81

EQ UIPO S BOTAS DE JEBE NUEVAS BOTIQUINES CAMION CISTERNA 4x2 (AGUA) 1,500 gl CARGADOR FRONTAL CAT- 930 CARTELES DE CONSERVACION DEL AMBIENTE CARTELES DE SEGURIDAD CASCO DE SEGURIDAD CHALECOS REFLECTIVOS COCINA DE ASFALTO COMPACTAOOR V1BR. TIPO PLANCHA 4 HP COMPACTADORA TIPO SALTARIN CONOS REFLECTIVOS DEMARCADOR DE PAVIMENTO EQUIPO DE PINTURA EQUIPO DE PROTECCION COLECTIVA EQUIPO DE SOLDAR EQUIPO TOPOGRAFICO EXTINTORES GAFAS GRUA HIDRAULICA AUTOP. 127HP 18TON-9M. GUANTES DE CUERO GUANTES DE JEBE HERRAMIENTA MAN UAL HERRAMIENTAS MANUALES MEZCLADORA CONCRETO TAMBOR 18HP 11P3 MEZCLADORA DE CONCRETO DE 9 -11P3 MOTONIVELADORA DE 125 HP

PAR und hm hm und und und und hm hm hm und hm hm GLB

100.0000 20.0000 1,135.8756 790.0367 50.0000 50.0000 100.0000 30.0000 9,283.1880 1,249.1680 273.9705 50.0000 289.2800 6.2675 1.0000

28.8340 66,052.7200 20.0000

25.0000

10.0000 40.0000 30.0000

1,905.2187 5,088.6486 1,856 3228

Am

2,000.00 1,000.00 113,587.56 142,206.61 7,500.00 7,500.00 2,800.00 900.00 18,566.38 18,737.52 5,479.41 1,250.00 2,892.80 43.87 4,000.00 288.34 660,527.20 4,400.00 125.00 1,500.00 400.00 750.00 0.00 66,306.04 47,630.47 25.00 ---------127,216.22 334,138.10

20.00 50.00 100.00 180.00 150.00 150.00 28.00 30.00 2.00 15.00 20.00 25.00 10.00 7.00 4.000.00 10.00 10.00 220.00 5.00 150.00 10.00 25.00

C O\

0337990055 0348880004 0348040043 0349040093 0348880003 0348880002 0337010100 0337620037 0348080066 0349030001 0383020001 0348760055 0349110093 0337900050 0337800002 0348210003 0349880001 0348880005 0337990101 0349180010 0337600001 0337530073 0398010037 0337010001 0349100007 0348010011 0349090000

S'JLT

- v a lo

7

Precios y cantidades de recursos requeridos por tipo Obra

0492001

Subpresupuesto Fecha

001 20/08/2012

MEJORAMIENTO DE VlA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO

Lugar Código

250105 Recurso

UCAYALI - CORONEL PORTILLO -YARINACOCHA Unidad

0337620030 0337620035 0349030007 0348210004 0349040096 0349070001 0349070003 0349070004 0349070055 0349070054 0349070059

PROTECTOR DE OIDOS RESPIRADOR CONTRA POLVO RODILLO USO VIBR AUTOP 101-135HP 10-12T SOLDADORA TRACTOR A ORUGAS 140 HP VIBRADOR DE CONCRETO 4 HP 1.35" VIBRADOR DE CONCRETO 4 HP 1.50” VIBRADOR DE CONCRETO 4 HP 2.40’ VIBRADOR DE CONCRETO 4 HP 2.40” VOLQUETE VOLVO 14 M3 VOLQUETE VOLVO 15 M3

pza und hm hm hm hm hm hm hm hm hm

Cantidad

Precio SI.

Parcial SI.

25.0000 25.0000 1,301.3219 52.8000 14.7210 0.0267 4,550.4500 48.5505 48.9280 7.2988 571.6192

7.00 20.00 150.00 15.00 250.00 10.00 5.00 5.00 20.00 120.00 100.00

175.00 500.00 195,198.29 792.00 3.680.25 0.27 22,752.25 242.75 978.56 875 86 57,161.92 1,854,102.67

Total

A m p a r o D ía z A r e v a lo Representan!* Legal

SI.

14,578,125.85

S10

Precios y cantidades de recursos requeridos por tipo Obra

0492001

Subpresupuesto Fecha

002

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI MEJORAMIENTO DE PUENTE SAN LORENZO

20/08/2012

Lugar Código

250105 Recurso

0147010098 0147010003 0147010002 0147010004

LIMPIEZA FINAL DE OBRA OFICIAL OPERARIO PEON

UCAYALI - CORONEL PORTILLO - YARINACOCHA Unidad

Cantidad

Precio SI.

Parcial SI.

1.0000 2,153.0707 2,150.1117 2,608.1830

200.00 13.16 15.14 11.86

200.00 28,334.41 32,552.69 30,933.05

M ANO DE OBFtA GLB hh hh hh

92,020.15 M ATERIALES 0203010007 0239050000 0202040009 0202040010 0230010002 0261100002 0290010004 0290010003 0221000000 0202100099 0202830003 0229220001 0243000026 0203030101 0205000031 0238000000 0238000004 0243580005 0243000025 0243000031 0230650021 0254060000 0254020081 0254110090 0254020042 0279560003 0256220100 0229500091 0253030027 0204110023 0232010096 0244020015 0244030005 0202850031 0202850032 0237020050

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO 60 AGUA ALAMBRE NEGRO N°16 ALAMBRE NEGRO N“ 8 CAL HIDRATADA DE 25 Kg CALAMINA CORRUGADA GALVANIZADA CARTEL DE IDENTIFICACION CARTEL DE OBRA (3.00 X 5.00) BANNER und CEMENTO PORTLAND TIPO I (42.5KG) CLAVOS DE 3" CLAVOS DE 4" CORDEL ESTACA DE MADERA FIERRO CORRUGADO DE 3/8" GRAVILLA PARA FILTRO DE 1/2" DE RIO O PIEDRA CHANCADA DE 1/2“ HORMIGON HORMIGON (PUESTO EN OBRA) LISTONES DE MADERA DE 2" X 3" X 10" MADERA NACIONAL PARA ENCOFRADO MADERA NACIONAL PARA ENCOFRADO NEOPRENE SHORE DE 0.30 X 0.25 X 0.05 PINTURA ANTICORROSIVA PINTURA ESMALTE PINTURA ESMALTE PINTURA ESMALTE SINTETICO PLACA ACRILICA DE 0.40 X 0.60 M. INC. COLOCACION PLANCHA DE FIERRO 3/8” SOLDADURA THINER TIERRA ROJA TRANSPORTE DE EQUIPO Y HERRAMIENTAS TRIPLAY DE 6 mm TRIPLAY LUPUNA DE 4'x8'x 4 mm TUBO DE FIERRO GALVANIZADO DE 2“ TUBO DE FIERRO GALVANIZADO DE 3’ WAYPE INDUSTRIAL

kg m3 kg BOL pin GLB und BOL kg kg ML p2 ML m3

33,716.3741 204.2990 1,890.6378 298.3721 2.5060 13.2000 2.0000 2.0000 3,416.6525 307.8919 7.2000 158.7108 16.7064 25.9200 83.8900

3.50 5.00 5.00 4.30 7.00 13.50 1.200.00 800.00 21.50 5.00 5.00 0.20 1.15 3.00 100.00

118,007.31 1,021.50 9,453.19 1,283.00 17.54 178.20 2,400.00 1,600.00 73,458.03 1,539.46 36.00 31.74 19.21 77.76 8,389.00

m3 m3 p2 p2 p2 pza gln gln gln gln und m2 kg gln m3 GLB m2 pin ML ML ML

1,509.8625 290.8048 186.0000 3,210.5850 2,763.4440 6.0000 0.7878 0.9590 0.0020 1.6671 1.0000 8.6400 92.4500 0.1667 324.1732 1.0000 0.2000 20.7600 41.6800 24.1400 3.2000

80.00 80.00 1.80 2.00 2.00 300.00 35.00 35.00 35.00 35.00 200.00 120.00 8.00 15.00 25.00 1,000.00 22.00 14.00 22.00 45.00 4.00

120,789.00 23,264.38 334.80 6,421.17 5.526.89 1,800.00 27.57 3 3 .5 7 ^ ^ ^ 0.0f s f V*B“ 5835 \OiviStOJ

ta

2oo;.«íffey 1.036.-8Q SOcAi*»! 739.60 2 .5 0 ^ S = 3 ¿ 8,104.33 \ 1,000.00 4.40 290.64 916.96 1,086.30 12.80 389,162.07

EQ UIPO S 0337010025 0348040043 0349040093 0349040100 0348210052 0349040099 0337010001 0348010011 0349090000 0348400001 0349880002 0349110010 0348210066 0349880003 0349070004 0349070054

BROCHA DE 4" CAMION CISTERNA 4x2 (AGUA) 1,500 gl CARGADOR FRONTAL CAT- 930 CARGADOR FRONTAL CAT-950 EQUIPO DE CORTE EXCAVADORA HERRAMIENTAS MANUALES MEZCLADORA DE CONCRETO DE 9-11P3 MOTONIVELADORA DE 125 HP MOTOSIERRA NIVEL TOPOGRAFICO RODILLO LISO VIBRATORIO AUTOPROPULSADO SOLDADORA ELECTRICA TEODOLITO VIBRADOR DE CONCRETO 4 HP 2.40“ VOLQUETE VOLVO 14 M3

und hm hm hm hm hm %MO hm hm hm hm hm hm hm hm hm

0.2088 4.9873 11.5654 9.9746 3.8405 90.9840

8.00 100.00 180 00 150.00 8.00 140.00

173.9692 19.9491 2.3525 22.3030 19.9492 18.0995 22.3030 173.9692 13JQ2á___^^

25.00 180.00 10.00 15.00 130.00 10.00 20.00 5.00 120.00

____

33,780.34 c

(

/

__

\

Total

y i / Lean

s im p a ra D ía z A r e v a l o R epresen tante Legal

1.67 498.73 2,081.77 1,496.19 30.72 12,737.76 2,888.75 4,349.23 3,590.84 23.53 334.55 2,593.40 181.00 446.06 869.85 1.656.29

C IP **“ INGENIERO CIVIL

SI.

514,962.56

Página:

S10

1

Precios y cantidades de recursos requeridos por tipo Obra

0492001

Subpresupuesto Fecha

003 20/08/2012

Lugar Código

250105 Recurso

0147010003 0147010002 0147010004 0147000032

OFICIAL OPERARIO PEON TOPOGRAFO

MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI OBRAS DE SANEAMIENTO UCAYALI - CORONEL PORTILLO - YARINACOCHA Unidad

Cantidad

Precio SI.

Parcial SI.

3,528.6096 2,151.8557 14,532.2366 32.3737

13.16 15.14 11.86 15.14

46,436.50 32,579.10 172,352.33 490.14

M ANO DE O BR A hh hh hh hh

251,858.07 M ATERIALES 0272330004 0229720001 0203020004 0239050000 0202040010 0272930002 0272930005 0272930004 0204000000 0250010002 0272970001 0221000000 0202100099 0202830002 0272140040 0272950001 0272950002 0272530066 0231810002 0231810001 0243000026 0272960001 0239020079 0238000004 0272710006 0213510005 0243100005 0243010003 0250520010 0230460036 0254020100 0250060029 0272940002 0250060028 0272010061 0271290006 0272070081 0204110023 0272010032 0272010063 0272130082 0272940003 0272930003 0272000100 0272130079 0276210001 0272940001 0229030001 0230020001

ABRAZADERA PVC 1/2" X 110 MM. ACCESORIOS DIVERSOS ACERO CORRUGADO AGUA ALAMBRE NEGRO N°8 ANILLO 110 MM- UF- KM NEGRO ANILLO 160 MM - UF - KM NEGRO ANILLO 200 MM - UF - KM NEGRO ARENA FINA CAJA DE REG. DE CONCRETO SIMP F'C= 175 KG/CM2 HASTA 5 CUERPOS CAJA MEDIDOR DE AGUA CEMENTO PORTLAND TIPO I (42 5KG) CLAVOS DE 3’ CLAVOS PROMEDIOS PARA LA CONSTRUCCION CODO PVC SAP 1/2" X45 ° CODO PVC 100 MM. X 45" CODO PVC 160 MM. X 45° CODO PVC SAP 1/2" X 45" DADOS DE CONCRETO f e 140KG/CM2 0.30 X 0.30 X 0.30 M. DADOS DE CONCRETO f e 140KG/CM2 0.30 X 0.30 X 0.50 M. ESTACA DE MADERA GRIFO CONTRA INCENDIO HIPOCLORITO DE CALCIO 70% HORMIGON (PUESTO EN OBRA) LLAVE DE PASO LUBRICANTES MADERA CORRIENTE PARA ENCOFRADO MADERA TORNILLO MARCO Y TAPA F“ G° PARA MEDIDOR PEGAMENTO PARA PVC PINTURA ESMALTE SUPER SINTETICA TAPA DE CONCRETO, INC MARCO TAPA DE F°F° 4" X 6' TAPA DE F ° r 6* X 8", INC. MARCO TAPON PVC U/F110 MM TEE F°F° 110MMX110MM ISO TIPO LUFLEX TEE PVC 200 MM. TIERRA ROJA TUBERIA PVC SAP PRESION C-10 EC DE 1/2” X5 M TUBERIA PVC 160 MM S- 25 UF - KM TUBERIA PVC 200 MM S-25 UF-KM TUBERIA PVC 200 MM.C-7.5 TUBERIA PVC UF 0 110 MM. S -13.3 TUBO PVC SAP D= 3“ UNION DE REPARACION PVC U/F D= 110 MM VALVULA CORPORATION PVC 1/2" VALVULA LUFLEX ISO 7259 FFD 110 MM. YESO YESO DE 28 Kg

pza und kg m3 kg und und und m3 und

169.0000 2,388.9500 1,674.4000 481.5606 40.6000 873.2430 310.0000 553.3529 1.732.0724 155.0000

15.00 12.00 2.71 5.00 4.30 4.20 5.50 8.00 50.00 80.00

2.535.00 28,667.40 4.537.62 2,407.80 174.58 3.667.62 1.705.00 4,426.82 86,603.62 12.400.00

und BOL kg kg pza und und pza und und p2 und kg m3 und aln p2 p2 und gln gln und und und und und und m3 ML ML ML und m pza und und und kg BOL

169.0000 1,667.3600 25.6500 16.5600 164.0000 17.0000 155.0000 174.0000 310.0000 310.0000 119.4475 10.0000 382.2320 221.6375 169.0000 87.0620 2,442.0700 6.4747 169.0000 38.7550 1.6187 61.0000 12.0000 20.0000 33.0000 43.0000 1.0000 3,096.0792 1,950.8520 1,550.0000 3,405.2385 24.0000 5,016.7950 1,583.0000 14.0000 169.0000 12.0000 80.9343 47.7790

20.00 21.50 5.00 4.23 1.50 150.00 55.00 1.50 12.00 15.00 1.15 540.00 16.00 80.00 10.00 15.00 1.50 2.50 30.00 75.00 52.00 250.00 14.00 90.00 21.00 150.00 52.00 25.00 1.50 18.00 26.00 45.00 16.50 10.00 146.00 10.00 485.00 1.40 21.00

3.380.00 35,848.24 128.25 70.05 246.00 2.550.00 8.525.00 261.00 3.720.00 4.650.00 137.36 5.400.00 6,115.71 17,731 1,690 1,30: 3,66: 16 5.070.0 2.906.63 84.17 15.250.00 168.00 1.800.00 693.00 6.450.00 52.00 77,401.98 2,926.28 27.900.00 88,536.20 1.080.00 82,777.12 15.830.00 2.044.00 1.690.00 5.820.00 113.31 1,003.36 582,159.35

E Q U IP O S 0348820008 0349030004 0383020001 0337010001 0330550014 0349040098 0337020037

BOMBA DE MANO COMPACTADOR VIBR. TIPO PLANCHA 7 HP COMPACTADORATIPO SALTARIN HERRAMIENTAS MANUALES NIVEL TOPOGRAFICO RETROEXCAVADORA S/O 80-115 HP WINCHA DE 30m

382.2320 3,453.3026

15.00 25.00 20.00 15.00 140.00 30.00

5,733.48 86,332.57 30,578.56 10,614.90 1,058.95 49,822.92 721.37 184,862.75

í«G£NleROC,VH A „ . g u r o

'í J n i z A r e v a l o

Representante Legal

Total

SI.

1,018,880.17

FA C TIB ILID A D DEL PR O YEC TO : “ M E JO R AM IEN TO DE V ÍA DE IN TERCONEXIÓN A L C .P. SAN JO S É D ESDE PUERTO C A LL A O , DISTRITO DE Y AR IN AC O C H A - C O R O N EL PO R TILLO - U C A Y A L I”

METRADOS FACTIBILIDAD DEL PROYECTO:

"MEJORAMIENTO DE INTERCONEXION AL C. P. SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA CORONEL PORTILLO - UCAYALI"

DIVISION DE ESTUDIOS Y O B R A S E IN FR AESTR U C TU R A S O C IA L Y PR O D U C TIV A

Página

HOJA PE METRAPOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

de

DESCRIPCION

elem. MEJORAMIENTO DE VIA SAN JOSE

OBRAS PROVISIONALES ALQUILER DE ALMACEN SEÑALIZACION INFORMATIVA DE DESVIO - VIAS ALTERNÁS IARTEL DE IDENTIFICACIÓN DE OBRA 3 60 X 2 20 MT TRABAJOS PRELIMINARES DESMONTAJE DE ALCANTARILLA TUBULAR EXISTENTE Intersección Jr. Circunvalación Intersección Jr. Iparia

Intersección Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Prog. 3+272.82 Intersección Ca. S/N _________ Prog. 3+560 ________ Prog. 3+760 Prog. 3+854 Prog. 3+971.77 Intersección Jr. San Martin Intersección Jr. Tupac Amara Proc) 4+468 50 Intersección Jr. Mnaco Capac Intersección Jr. Eduardo del Aguila DESMONTAJE DE ALCANTARILLA DE C° A° EXISTENTE Proa

0+620

LIMPIEZA DE TERRENIO MANUAL

57.693.64

TRAZO NIVELACION Y REPLANTEO p ETAPAS EXCAV CONFORMACION LOSAS)

57,693.84

MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS PESADAS Y EQUIPOS RETIRO DE ARBOLES EXISTENTES Jr. Padre Abad y Psje. Orellana Jr. 28 de Noviembre y Jr. 13 de Abril Jr. Ucayali y Jr. arica Jr. arica y Jr. Miraflores Ca. Sn. Y Av. Guillermo Towsend Av. Belisario Panduro y Jr. Diego Zumba Jr. Diego Zumba y Jr. San Martin Jr. San Martin y Jr. Eleudora maynas Jr. Eleudora maynas y Jr. Tupac Amaru ___________ Jr. Tupac Amaru y Jr. Ucayali ___________ Jr. Ucayali y Jr. Manco Capac Jr. Manco Capac y Jr. Eduardo del Aguila Jr. Eduardo del Aguila y Orillas del lago yarina cocha

1.00 ¡4-00

10.00 26.00

REUBICACION DE POSTES DE LUZ

REUBICACION DE POSTES DE TELEFONO

20.00 SEGURIDAD Y SALUD ELABORACION, IMPLEMANTACION Y ADMINISTRACIOON DEL PLAN SEGURIDAD Y SALUD EN EL TRABAJO EQUIPOS DE PROTECCION INDIVIDUAL

50~0Ó

EQUIPOS DE PROTECCION COLECTIVA SEÑALIZACION TEMPORAL DE SEGURIDADCAPACITACION EN SEGURIDAD Y SALUD RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO MOVIMIENTO DE TIERRAS CORTE DE MATERIAL A NIVEL DE SUB RASANTE VER LÁMINA ST.01 AL ST-09

01JJ4.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO A NIVEL DE SUB RASANTE VER LAMINA ST. 01 AL ST-09

01.04.03

7,895.01

CONFORMACION DE SUB- RASANTE Intersección Jr. Circunvalación intersección Jr. Ucayali Intersección Jr. Padre Atoad Intersecciones]. Orellana

Cwereto

Leqaf

230.30 23 0.30

181.62 230.30

Página 2

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

ITEM

UND

DESCRIPCION

de elem.

Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muños Intersección Jr. La Selva Intersección Jr. Ucayali y Jr. Lima Intersección Jr. Arica Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. Sn. 01 Intersección Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. Sn. 02 Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend Intersección Jr Moyobamba Intersección Ca. Sn. 04 Intersección Jr. Diego zumba Intersección Jr. San martin Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. Manco Capac Intersección Jr. Eduardo del Aguila Jr. 03 de octubre - Jr. Circumvalacion paños iniciales paños finales Jr. Circumvalacion lado Izquierdo Jr. Circumvalacion - Jr. Ucayali palios iniciales paños finales Jr. Ucayali - Jr. Padre Abad paños finales cuadra 04 Jr. Padre Abad - Psje. Orellana paños finales Tramo San jóse 0+ 52.27 - 0+923.37 paños intermedios en alcantarilla paños intermedios en curvas paños finales Ca. 28 de Noviembre - Ca. 13 de Abril paños intermedios en alcantarilla paños finales Ca. 13 de Abril - Jr. Gavino muños paños finales Jr. Gavino muños - Jr. La Selva paños finales Jr. La Selva y psje. Victoria - prog. 1+415.33 - 1+600 prog. 1 +600 - prog. 1+800 paños iniciales paños intermedios en puente tushmo paños finales progresiva 1+800 - jr. lima paños finales Jr. Ucayali - Jr Arica paños intermedios en alcantarilla paños finales Jr. Arica - Jr. Miraflores paños finales Jr. Miraflores - Jr. Rioja paños finaies Jr. Rioja - Prog. 2+260 paños iniciales prog. 2+260 - prog. 2+741.96 paños iniciales paños intermedios en puente san lorenzo paños intermedios en curvas paños finales en curvas Ca. sn 01 - Jr. Ucayali paños finales Jr. Ucayali - Jr. miraflores paños finales Jr. miraflores Jr. yurimaguas paños finales Jr. yurimaguas - Ca. Sn 02 paños intermedios en curvas paños finales Ca. Sn 02 - Ca. Sn 03 paños intermedios en alcantarilla paños finales Ca. Sn 03 - Av. Guillermo Towsend paños intermedios en curvas paños intermedios en alcantarilla paños finaies Av. Guillermo Towsend - Jr. moyobamba paños finales Jr. moyobamba - Ca. Sn. 04 paños finafes Ca. Sn. 04 - Jr. Diego Zumba paños iniciales en curvas paños intermedios en alcantarilla paños intermedios en curvas Jr. Diego Zumba - Jr. San Martin paños intermedios en alcantarilla Jr. San Martin - Jr. Eleudora Maynas paños finales Jr. Eleudora Maynas - Jr. Tupac Amaru paños finales Jr. Tupac Amaru - Jr. Ucayali paños finales Jr. Ucayali - Jr. Manco Capac paños intermedios en alcantarilla paños finales Jr. Manco Capac - Jr. Eduardo del Aguí»

J*®'C,VIL í í e p i'a í f c m a r r t s L a c ia 1

C fP N * 4 0 8 9 4

largo m.

ancho

veces 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 100 1 1.00 1.00 1.00 1.00 1.00 1.00 ' 1.00 1.00 1.00 1.00 r 1.00 1.00 1.00 1.00 52.00 1.00 1.00 1.00 60.00 2.00 2.00 58.00 2.00 54.00 I 2.00 142.00 1.00 1.00 2.00 52.00 1.00 2.00 62.00 2.00 74.00 2.00 9200 88.00 1.00 1.00 2.00 38.00 2.00 42.00 1.00 2.00 23.00 2.00 44.00 2.00 12.00 1.00 212.00 2.00 1.00 1.00 2.00 54.00 2.00 46.00 2.00 42.00 2.00 38.00 r 1.00 2.00 38.00 1.00 2.00 112.00 1.00 1.00 2.00 38.00 2.00 6.00 2.00 18.00 1.00 1.00 1.00 50.00 1.00 48.00 2.00 46.00 2.00 48.00 2.00 42.00 1.00 2.00 46.00

Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area 4.00 Area Area Area 4.00 Area 5.21 4.00 4.74 4.00 3.81 4.00 Area Area 3.37 4.00 Area 2.69 4.00 3.23 4.00 3.14 4 00 4.00 Area Area 1.46 4.00 4,85 4.00 Area 3.78 4.00 2.48 4.00 1.55 4.00 Area 4.00 Area Area Area Area 4.00 3.75 4.00 4.29 400 3.02 4.00 Area 5.07 4.00 Area 4.07 4.00 Area Area 3.13 4.00 4.41 4.00 4.67 4.00 Area Area Area 4.00 Area 4.00 1.72 4.00 2.32 4.00 2.55 4.00 Area 4.61 4.00

242.46 219.33 481.11 310.80 265.00 257.73 257.73 206.96 162.05 221 60 221.60 323.70 231.45 211.23 249.05 21 í .60 178.27 244,05 232.77 219.42 232.00 232.77 221.60 221.60 5.40 41.65 49.81 158.26 5.40 21.53 5.40 5.40 5.40 5.40 5.40 5.40 38.83 837.67 5.40 5.40 35.61 5.40 5.40 5.40 5.40 5.40 ' 5.40 4.00 27.06 41.02 4.00 5.40 5.40 5.40 73.40 5.40 5.40 5.40 5.40 5.40 5.40 33.00 4.00 33.95 26.71 297.38 20.00 5.40 5.40 5.40 5.40 5.40 5.40 5.40 259.10 5.40 5.40 3238 5.40 5.40 432.00 81.77 5.40 5.40 5.40 5.40 5.40 5.40 310.91 56.15 258.97 5.40 70.00 5.40 5.40 5.40 5.40 5.40 5.40 5.40 64.79 5.40 5.40

de

m.

atto m.

PARCIAL

TOTAL

242.46 219.33 481.11 310.80 265.00 257.73 257.73 206.96 162.05 221 60 221.60 323.70 231.45 211.23 249.05 211.60 178.27 244.05 232.77 219.42 232.00 232.77 221.60 221.60 1,123.20 41.65 49.81 158.26 1,296.00 43.06 56.27 1,252.80 51.19 1,166.40 41.15 3,067.20 38.83 837.67 36.40 1,123.20 35.61 29.05 1,339.20 34.88 1,598.40 33.91 1,987.20 1.408.00 27.06 41.02 5r 11.68 / v v lm r « 8Í20.8Qfy_ 52 3 ^ 907 J í - r f BSTUOlOSJ' 0 73.441 yñ l 4 0 . 8 ? \* 496.80 26.78 -n f 950.40 16.74 259.20 33.00 3,392.00 67.90 26.71 297.38 s 40.00 1,166.40 40.50 993.60 46.33 907.20 32.62 820.80 259.10 54.76 820.80 32 3 8 43.96 2,419.20 432.00 81.77 33.80 820.80 47.63 129.60 50.44 388.80 310.91 56.15 258.97 1,080.00 70.00 1,036.80 18.58 993.60 25.06 1,036.80 27.54 907.20 64.79 49.79 993.60

Página 3

HOJA DE METRADOS A : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA iMENSIO *ES

» UND

DESCRIPCION

ITEM

paños finales Jr. Eduardo del Aguila - Orillas de! lago

01.04 04

M3

SOBRE EXCAVACION DE MATERIAL ORGÁNICO

de

de

largo

elem.

veces

m.

ancho m.

2.00 34.00

2.78 4.00

5.40 5.40

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - ZONA MATERIAL ORGANICO

M3

ELIMINACION DE MATERIAL EXCEDENTE

01.05

PAVIMENTOS

12.30

12.30

01.05.01

BERMAS Y LOSAS CENTRALES DE RODADURA

01.05 01.01

BASE GRANULAR e=0 15 mi (80% H + 20% T R )

020

11.538.73 11,538.73

020

11,538.73 11,538.73 26,328.25

M3

_

__

M H M HM fcstjai

26,328.25

48.475.70

M2 intersección Jr. Circunvalación intersección Jr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muños Intersección Jr. La Selva Intersección Jr. Ucayali y Jr. Lima Intersección Jr. Arica Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. Sn. 01 Intersección Jr. Ucayali Intersección Jr Miraflores Intersección Jr. Yurimaguas Intersección Ca. Sn. 02 Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend Intersección Jr Moyobamba Intersección Ca Sn 04 Intersección Jr. Diego zumba Intersección Jr. San martin Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. Manco Capac Intersección Jr. Eduardo del Aguila Jr. 03 de octubre - Jr. Circumvalacion paños iniciales paños finales Jr. Circumvalacion lado Izquierdo Jr. Circumvalacion - Jr. Ucayali paños iniciales paños finales Jr. Ucayali - Jr. Padre Abad paños finales cuadra 04 Jr. Padre Abad - Psje. Orellana paños finales Tramo San jóse 0+ 52.27 - 0+923.37 paños intermedios en alcantarilla paños intermedios en curvas paños finales Ca. 28 de Noviembre - Ca. 13 de Abril paños intermedios en alcantarilla paños finales Ca. 13 de Abril - Jr. Gavino muños paños finales Jr. Gavino muños - Jr. La Selva paños finales Jr. La Selva y psje. Victoria - prog. 1+415.33 - 1+600 prog. 1+600 - prog. 1 +800 paños iniciales paños intermedios en puente tushmo paños finales progresiva 1+800 - jr. lima paños finales Jr. Ucayali - Jr. Arica paños intermedios en alcantarilla paños finales Jr. Arica - Jr. Miraflores paños finales Jr. Miraflores - Jr. Rioja paños finales Jr. Rioja - Prog. 2+260 paños iniciales prog. 2+260 - prog. 2+741.96 paños iniciales paños intermedios en puente san lorenzo paños intermedios en curvas paños finales en curvas Ca. sn 01 - Jr. Ucayali paños finales Jr. Ucayali - Jr. miraflores paños finales Jr. miraflores - Jr. yurimaguas paños finales Jr. yurimaguas - Ca. Sn 02 paños intermedios en curvas paños finales Ca. Sn 02 - Ca. Sn 03 paños intermedios en alcantarilla pafios~í«aT§s

TOTAL

30.02 734.40

VER CUADRO DE MATERIAL ORGANICO (UC-01) 4690.54

01.04.06

PARCIAL

m.

VER CUADRO DE MATERIAL ORGANICO (UC-01) 4690.54

01.04.05

atto

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 I 1.00 1.00 1.00 1.00 1.00 1.00 1 00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 52.00 1.00 1.00 1.00 60.00 2 00 2.00 58.00 2.00 54.00 2.00 142.00 1.00 1.00 2.00 52.00 1.00 2.00 62.00 2.00 74.00 2.00 92.00 88.00 1.00 1.00 2.00 38.00 2.00 42.00 1.00 2.00 23.00 2.00 44.00 2.00 12.00 1.00 212.00 2 00 1.00 1.00 2.00 54.00 2.00 46.00 2.00 42.00 2.00 38 00 1.00 2.00 38.00 1.00 --2 .0 0

ING. ( C lf N* 40894

Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area 4.00 Area Area Area 4.00 Area 5.21 4.00 4.74 4.00 3.81 4.00 Area Area 3.37 4.00 Area 2.69 4.00 3.23 4.00 3.14 4.00 4.00 Area Area 1.46 4.00 4.85 4.00 Area 3.78 4.00 248 4.00 1.55 4.00 Area 4.00 Area Area Area Area 4.00 3.75 4.00 4.29 4.00 3.02 4.00 Area 5.07 4.00 Area 4.07

181 62 230.30 230.30 230.30 242.46 219.33 481.11 310.80 265.00 257.73 257.73 206.96 162.05 221.60 221.60 l 323.70 231.45 211.23 249.05 211.60 178 27 244.05 232.77 219.42 232.00 232.77 221.60 221.60 5.40 41.65 49.81 158.26 5.40 21.53 5.40 5.40 5.40 5.40 I 5.40 5.40 38.83 837.67 5.40 5.40 35.61 5.40 5.40 5.40 5.40 5.40 5.40 4.00 27.06 41.02 4.00 5.40 5.40 5.40 73.40 5.40 5.40 5.40 5.40 5.40 5.40 33.00 4.00 33.95 26.71 297 38 20.00 5.40 5.40 5.40 5.40 5.40 5.40 5.40 259.10 5.40 5.40 32.38 5.40

181.62 230.30 230.30 230.30 242.46 219.33 481.11 310.80 265.00 257.73 257.73 206.96 162.05 221.60 221.60 323.70 231.45 211.23 249.05 211.60 178 27 244.05 232.77 219.42 232.00 232.77 221 60 221.60 1123.20 41.65 49.81 158.26 1296.00 43 06 56.27 1252.80 51.19 1166.40 41.15 3067.20 38.83 837.67 36.40 1123.20 3561 29.05 1339.20 34.88 1598.40 33.91 1987.20 1408.00 27.06 41.02 11.68 820 80 52.38 907.20 73.40 40.82 496.80 26.78 950.40 16.74 259.20 33.00 3392.00 67.90 26.71 297.38 40.00 1166.40 40.50 993.60 46.33 907.20 32.62 820.80 259.10 54.76 820.80 32.38 43.96

//

4,

s ts ru MU

!SK>*

Página 4

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

ancho

DESCRIPCION veces Ca. Sn 03 - Av. Guillermo Towsend partos intermedios en curvasi paños intermedios en alcantarilla paños finales Av. Guillermo Towsend - Jr. moyobamba Jr. moyobamba - Ca. Sn. 04 pafios finales Ca. Sn. 04 - Jr. Diego Zumba paños iniciales en curvas partos intermedios en alcantarilla pafios intermedios en curvas Jr. Diego Zumba - Jr. San Martin pafios intermedios en alcantarilla Jr. San Martin - Jr. Eleudora Maynas pafios finales Jr. Eleudora Maynas - Jr. Tupac Amaru Jr. Tupac Amaru - Jr. Ucayali pafios finales Jr. Ucayati - Jr Manco Capac paños intermedios en alcantarilla paños finales Jr. Manco Capac - Jr. Eduardo del Aguila

ENCOFRADO Y DESENCOFRADO EN BERMAS Y LOSAS DE CONCRETO Jr. 03 de octubre - Jr. Circumvalacion ¡ Extremos de pavimento (calzada y berma Eje de pavimento (calzada y bernia __Transversales (calzada y berma); _________ Jr. Circumvalacion lado Izquierdo i Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berm a)! Transversales (calzada y berma) ___________ Jr. Circumvalacion - Jr. Ucayali Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) __ Transversales (calzada y berma) Jr. Ucayali - Jr. Padre Abac Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma _________ Transversales (calzada y berma _________ Jr. Padre Abad - Psje. OreBa Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calada y berm Progresiva 0+552.44 - Prog. 0+92C Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calzada y berma Ca. 28 de Noviembre - Ca. 13 de A Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calzada y berma Ca. 13 de Abril - Jr. Gavino mufl Extremos de pavimento (calzada y berma _ Eje de pavimento (calzada y berma _________ Transversales (calzada y berma Jr. Gavino muños - Jr. La Se Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calzada y berma)] Jr. La Selva y psje. Victoria - prog. 1+598.511 __ Extremos de pavimento (calzada y berma)j ____ Eje de pavimento (calzada y berma) j _ Transversales (calzada y berma) ¡ " " __________ Prog. 1+600 - Prog. 1+800! Extremos de pavimento (calzada y berma) i _________ Eje de pavimento (calzada y berma); Transversales (calzada y berma) ______________ progresiva 1+800 - jr. li Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calzada y berma ___________________ Jr. Ucayali - Jr. Ar Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma Transversales (calzada y berma _______ Jr. Arica - Jr. Miraflo Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma _________ Transversales (calzada y berma _________________ Jr. Miraflores - Jr. Ri Extremos de pavimento (calzada y berma Eje de pavimento (calzada y berma _________ Transversales (calzada y ber _______________Jr. Rioja - Prog. 2+259. Extremos de pavimento (calzada y berma ____lis.de pavimento (calzada y berma) Transversales (calzada y prog. 2+260 - prog. 2+7' Extremos de pavimento (calzada y berma Eje de pavimento (calzada y bernia _________ Transversales (calzada y berma _________________ Ca. sn 01 - Jr. Ucaya Extremos de pavimento (calzada y berma Eje de pavimento (calzada y ber TransversalesJfiaizSíía y berma Jr„U¿ayali - Jr. miraflo to (calzada y berma

D ía z A re v u !

Leo?

ING. CIVIt

CIP N* 40894

PARCIAL

TOTAL

Página 5

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA * DESCRIPCION

ITEM

ti 1 W

k ■ W

ACERO DE REFUERZO FY=4,200 KG/CM2 0=3/8* - BERMAS

.

«ES

de

de

largo

ancho

atto

elem.

veces

m.

m.

m.

1.00 9.00

96.30 1080

0.20 0.20

19.26 19.44

2.00 1.00 8.00

93.02 93.02 10.80

0.20 0.20 0.20

37.21 18 60 17.28

2.00 1.00 10.00

105.07 105.07 1080

0.20 0.20 0.20

42.03 21.01 21.60

2.00 1.00 7.00

83.06 83.06 10.80

0.20 0.20 0.20

33.22 16.61 15.12

2.00 1.00 24.00

274.71 274.71 10.80

0.20 0.20 0.20

109.88 54.94 51.84

2.00 1.00 800

80.41 80.41 10.80

0.20 0.20 0.20

32.16 16.08 17.28

2.00 1.00 3.00

16.46 16.46 10.80

0.20 0.20 0.20

6.58 3.29 6.48

2.00 1.00 11.00

129.03 129.03 10.80

0.20 0.20 0.20

51.61 25.81 23.76

2.00 1.00 8 00

106.48 106.48 10.80

0.20 0.20 0.20

42.59 21.30 17.28

2.00 1.00 L 9.00

97.75 97.75 10.80

0.20 0.20 0.20

39.10 19.55 19.44

2.00 1.00 9.00

94.32 94.32 10.80

0.20 0.20 0.20

2.00 1.00 9.00

98.58 98.58 10.80

0.20 0.20 0.20

39.43 19.72 19.44

2.00 1.00 9.00

94.61 94.61 10.80

0.20 0.20 0.20

37.84 18.92 19.44

2.00 1.00 9.00

94.77 94 77 10.80

0.20 0.20 0.20

37.91 18.95 19.44

2.00 1.00 7.00

68.00 72.50 10.80

0.20 0.20 0.20

27.20 14.50 15.12

Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. miraflores - Jr. yurimaguas Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. yurimaguas - Ca. Sn 02 Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Ca. Sn 02 - Ca. Sn 03 Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Ca. Sn 03 - Av. Guillermo Towsend Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Av. Guillermo Towsend - Jr. moyobamba Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. moyobamba - Ca. Sn. 04 Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Ca. Sn. 04 - Jr. Diego Zumba Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Diego Zumba - Jr. San Martin Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. San Martin - Jr. Eleudora Maynas Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Eleudora Maynas - Jr, Tupac Amaru Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Tupac Amaru - Jr. Ucayali Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Ucayali - Jr. Manco Capac Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Manco Capac - Jr. Eduardo del Aguila Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma) Jr. Eduardo del Aguila - Orillas del lago Extremos de pavimento (calzada y berma) Eje de pavimento (calzada y berma) Transversales (calzada y berma)

......

01050103

UND

PARCIAL

I

37.73 18.86 19.44

KG Jr. 03 de octubre - Jr. Circumvalacion paños iniciales paños finales Jr. Circumvalacion lado Izquierdo Jr. Circumvalacion - Jr. Ucayali paños iniciales paños finales Jr. Ucayali - Jr. Padre Abad pafios finales cuadra 04 Jr. Padre Abad - Psje. Orellana pafios finales Tramo San jóse 0+ 552.27 - 0+923.37 paños intermedios en alcantarilla paños intermedios en curvas pafios finales Ca. 28 de Noviembre - Ca. 13 de Abril paños intermedios en alcantarilla paños finales Ca. 13 de Abril - Jr. Gavino muños paños finales Jr. Gavino muños - Jr. La Selva paños finales Jr. La Selva y psje. Victoria - prog. 1+415.33 - 1+600 prog. 1+600 - prog. 1+800 paños iniciales paños intermedios en puente tushmo paños finales progresiva 1+800 - jr lima paños finales Jr. Ucayali - Jr. Arica paños intermedios en alcantarilla paños finales Jr. Arica - Jr. Miraflores paños finales Jr. Miraflores - Jr. Rioja paños finales Jr. Rioja - Prog. 2+260 pafios iniciales prog. 2+260 - prog. 2+741.96 paños iniciales panos intermedios en puente san lorenzo paños intermedios en curvas

TOTAL

66,640.67

-_____

52.00 1.00 1.00 1.00 60.00 2.00 2.00 58.00 2.00 54.00 2.00 142.00 1.00 20.00 2.00 52.00 1.00 2.00 62.00 2.00 74.00 2.00 92.00 88.00 2.00 1.00 2.00 38.00 2.00 42.00 1.00 2.00 23.00 2.00 44.00 2.00 12.00 1.00 208.00 2.00 1.00 13.00

35.58 66.50 55.87 312.00 35.58 35.59 45.26 35.58 41.05 35.58 33.69 35.58 62.19 60.30 29.62 35.58 57 99 24.43 35.58 28.97 35.58 28.55 35.58 20.82 22.00 56.00 9.95 35.58 28.00 35.58 47.00 26.00 35.58 1700 35.58 11.00 35.58 42.00 20.82 26.00 32.00 42.00

^

1,850.16 66.50 55.87 312.00 2134.80 71.18 90.52 2063.64

v

"

^ \ 7 A T 38 / í ^ 0 5 2 . ^ y s io V A vi O f t if f lr w y 1 QwfcS .......... TÍ —=1 * ’t 85?n 6

2 2 0 5 lt o “ — 57.94 2632.92 57.10 3273.36 1832.16 44.00 56.00 19.90 1352.04 56.00 1494.36 47.00 52.00 818.34 34.00 1565.52 22.00 426.96 42.00 4330.56 52.00 32.00 546.00

j •Ji / * 7 w X f

A t n p u fo S>íaz A r v v tilo í»r»S6HMHte tPas!

emando Rafael Lean INO. CIVIL CIP N* 40894

Página 7

HOJA DE METRADOS : MEJORAMIENTO OE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

ancho

de

DESCRIPCION

ITEM

elem. paños iniciales j paños intermedios en puente tushmo; progresiva 1+800 - jr. lima paños finales! paños intermedios en alcantarilla! paños finales! Jr. Arica - Jr. Miraflores paños finales i Jr. Miraflores - Jr. Rioja paños finales! Jr. Rioja - Prog. 2+260 paños iniciales! prog. 2+260 - prog. 2+741 í paños intermedios en puente san lorenzo! paños intermedios en curvas i paños finales en curvas | Ca. sn 01 - Jr. Ucayali Jr. Ucayali - Jr. miraflores paños finales j Jr. miraflores - Jr. yurimaguas j _________________ paños finales Jr. yurimaguas - Ca. Sn 02 paños intermedios en curvas I _______ paños finales] Ca. Sn 02 - Ca. Sn 03 [ paños intermedios en alcantarilla _____________________ paños finales Ca. Sn 03 - Av. Guillermo Towsend;

170.00

27.55 69 37 105.64 58.87

12.00 208.00 13.00

55.10

12,244.96

128.70 69.96 69.37

54.00 46.00

86.91 69.37

973.56 173.82

139.08 paños intermedios en alcantarilla ¡ paños finales | Av. Guillermo Towsend - Jr. moyobamba | ___________________________ paños finales] Jr. moyobamba - Ca. Sn. 0 4 i finales [ Ca. Sn. 04 - Jr. Diego Zumba paños iniciales en curvas j paños intermedios en alcantarilla paños intermedios en curvas! Jr. Diego Zumba - Jr. San Martin] paños intermedios en alcantarilla Jr. San Martin - Jr. Eleudora Maynas ¡ paños finales! Jr. Eleudora Maynas - Jr. Tupac Amaru [ paños finales Jr. Tupac Amaru - Jr. Ucayali i paños finales! Jr. Ucayali - Jr. Manco Capac | paños intermedios en alcantarilla ____________________________ paños finales ¡ Jr. Manco Capac - Jr. Eduardo del Águila I paños finales

01050105

48.00 42.00

PAVIMENTO DE CONCRETO F‘C=210KG/CM2e=0 20 mi

48,439.70 Intersección Jr. Circunvalación Buzón Intersección Jr. Ucayali ¡

- 2.00 - 12.00

Intersección Jr. Padre Abadl Buzón! Intersección Psj. Orellana Buzón Intersección Ca. 28 de Noviembre

230.30 - 2.00

-8.00 Area

Intersección Jr. Gavino Muflos i Intersección Jr. Ucayali y Jr. Lima Intersección Jr. Arica Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. Sn. 01 Intersección Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas | Intersección Ca. Sn. 1)2] Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend | Intersección Jr. Moyobamba I Intersección Ca. Sn. 0 4 1 Intersección Jr. Diego zumba Intersección Jr. Sanmartín Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru: Intersección Jr. Ucayaiil Intersección Jr. Manco Capac Intersección Jr. Eduardo del Aguila Jr. 03 de octubre - Jr. Circumvalacion! paños iniciales j Jr. Circumvalacion lado Izquierdo I Jr. Circumvalacion - Jr. Ucayalij paños iniciales [ paños finales Jr. Ucayali - Jr. Padre Abad |

257.73 206.96 162.05 221.60 221.80 323.70 231.45

257.73 206.96

221.60

249.05

232.00 232.77

1123.20 Area Area

41 65 49.81 158.26 21.53

158.26 1296.00 43.06

51.19 Jr. Padre Abad - Psje. Orettana j Tramo San jóse.

52.27 - 0+923.37

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA IMENSIONES

N° UND

DESCRIPCION

ITEM

de elem.

paños intermedios en alcantarilla paños intermedios en curvas paños finales Ca. 28 de Noviembre - Ca. 13 de Abril paños intermedios en alcantarilla paños finales Ca. 13 de Abril - Jr. Gavino muños paños finales Jr. Gavino muños - Jr. La Selva paños finales Jr. La Selva y psje. Victoria - prog. 1+415.33 - 1+600 prog. 1+600 - prog. 1+800 paños iniciales paños intermedios en puente tushmo paños finales progresiva 1+800 - jr. lima paños finales Jr. Ucayali - Jr. Arica paños intermedios en alcantarilla paños finales Jr. Arica - Jr. Miraflores paños finales Jr. Mirafiores - Jr. Rioja paños finales Jr. Rioja - Prog. 2+260 paños iniciales prog. 2+260 - prog. 2+741.98 paños iniciales P/ interm. puente san lorenzo paños intermedios en curvas paños finales en curvas Ca. sn 01 - Jr. Ucayali paños finales Jr. Ucayali - Jr. miraflores paños finales Jr. miraflores - Jr. yurimaguas paños finales Jr. yurimaguas - Ca. Sn 02 paños intermedios en curvas paños finales Ca. Sn 02 - Ca. Sn 03 paños intermedios en alcantarilla paños finales Ca. Sn 03 - Av. Guillermo Towsend paños intermedios en curvas paños intermedios en alcantarilla paños finales Av. Guillermo Towsend - Jr. moyobamba paños finales Jr. moyobamba - Ca. Sn. 04 paños finales Ca. Sn. 04 - Jr. Diego Zumba paños iniciales en curvas paños intermedios en alcantarilla paños intermedios en curvas Jr. Diego Zumba - Jr. San Martin paños intermedios en alcantarilla Jr. San Martin - Jr. Eleudora Maynas paños finales Jr. Eleudora Maynas - Jr. Tupac Amaru paños finales Jr. Tupac Amaru - Jr. Ucayali paños finales Jr. Ucayali - Jr. Manco Capac paños intermedios en alcantarilla paños finales Jr. Manco Capac - Jr. Eduardo del Aguila paños finales Jr. Eduardo del Aguila - Orillas del lago

!

b

e

r

m

a

!

de veces

largo m.

ancho m.

1.00 1.00 2.00 52.00 1.00 2.00 62.00 2.00 74.00 2.00 92.00 88.00 1.00 1.00 2.00 38.00 2.00 42.00 1.00 2.00 23.00 2.00 44.00 2.00 12.00 1.00 212.00 2.00 1.00 1.00 2.00 54.00 2.00 46.00 2.00 42.00 2.00 38.00 1.00 2.00 38.00 1.00 2.00 112.00 1.00 1.00 2.00 38.00 2.00 6.00 2.00 18.00 1.00 1.00 1.00 50.00 1.00 48.00 2.00 46.00 2.00 48.00 2.00 42.00 1.00 i 2.00 r 46.00 2.00 34.00

Area Area 3.37 4.00 Area 2.69 4.00 3.23 4.00 3.14 4.00 4.00 Area Area 1.46 4.00 4.85 4,00 Area 3.78 4.00 2.48 4.00 1.55 4.00 Area 4.00 Area Area Area Area 4.00 3.75 4,00 4.29 4.00 3.02 4.00 Area 5.07 4.00 Area 4.07 4.00 Area Area 3.13 4.00 4.41 4.00 4.67 4.00 Area Area Area 4.00 Area 4.00 1.72 4.00 2.32 4.00 2.55 4.00 Area 4.61 4.00 2.78 4.00

38.83 837.67 5.40 5.40 35.61 5.40 5.40 u 5.40 5.40 5.40 5.40 4.00 27.06 41.02 4.00 5.40 5.40 5.40 73.40 5.40 5.40 5.40 5.40 5.40 5.40 33.00 4.00 3395 26.71 297.38 20.00 5.40 5.40 5.40 5.40 5.40 5.40 5.40 259.10 5.40 5.40 32.38 5.40 5.40 432.00 81.77 5.40 5.40 5.40 5.40 5.40 5,40 310.91 56.15 258.97 5.40 70.00 5.40 5.40 5.40 5.40 5.40 5.40 5.40 64.79 5.40 5.40 5.40 5.40

alto m.

PARCIAL

TOTAL

38.83 837.67 36.40 1123.20 35.61 29.05 1339.20 34 88 1598.40 33.91 1987.20 1408.00 27.06 41.02 11.68 820.80 52.38 907.20 73.40 40.82 496.80 26.78 950.40 16.74 259.20 33.00 3392.00 67.90 26.71 297.38 40.00 1166.40 40.50 993.60 46.33 907.20 32.62 820.80 259.10 54.76 820.80 32.38 43.96 2419.20 432.00 81.77 33.80 820.80 47.63 129.60 ^ 50.44 388.80 310.91 56.15 258.97 1080.00 70.00 1036.80 18.58 993.60 i 25.06 1036.80 27.54 907.20 64.79 49.79 993.60 30.02 734.40

! S E R M L A J ¡¡

jP¡¡L

nn

S 4 0

3 .0 0

3 .6 0

a

................... .

.

'1 O O - 1 8 0 * 01050106

CURADO DE LOSAS

01.06 01.06.01

CANALETAS Y SARDINELES CANALETAS ABIERTAS TRAZO, NIVELACION Y REPLANTEO

01 06.01.01

M2

48.439.70

M3 Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo Jr. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo

5,432.24 1.00 1.00 1.00 1.00

f

A m p y / v /yi**zArevah> (W íM H M H tfc tt í g a l

:enundo Rafael Lean INO, CIVIL Ctf» N* 48894

48,439.70

111.40 118.53 125.11 94.11

0.75 0.75 0.75 0.75

|_

83.55 88 90 93.83 70.58

Página 9

HOJA DE METRAPOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

PARCLAL

DESCRIPCION

Jr. Ucayali - Jr. Padre Abad - Lado Derecho] Jr. Ucayali - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje Orellana - Lado Derecho j Jr. Padre Abad - Psje Orellana - Lado Izquierdo j Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 j Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo Ca. 13 de Abril - Jr. Gavino muflos - Lado Derecho Ca. 13 de Abril - Jr. Gavino muños - Lado Izquierdo Jr. Gavino muños - Jr. La Selva - Lado Derecho [ Jr. Gavino muños - Jr. La Selva Lado Izquierdo] Jr. La Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 Lado Derecho Jr. La Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo ___ progresiva 1+800 - jr. lima - Lado Derecho progresiva 1+800 - jr. lima - Lado Izquierdo ___ Jr. Ucayali - Jr. Arica - Lado Derecho I jr . Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. Miraflores - Lado Izquierdo Jr. Miraflores - Jr. Rioja - Lado Derecho] Jr. Miraflores - Jr. Rioja - Lado Izquierdo i Jr. Rioja - Prog. 2+260 - Lado Derecho i Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. 01 Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo a. sn 01 - Jr. Ucayali - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Derecho! Jr. Ucayali - Jr. miraflores - Lado Izquierdo Jr. miraflores - Jr. yurimaguas - Lado Derecho ¡ Jr. miraflores - Jr. yurimaguas - Lado Izquierdo ¡ Jr. yurimaguas - Ca. Sn 02 - Lado Derecho j Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo j Ca. Sn 02 - Ca. Sn 03 - Lado Derecho; Ca Sn 02 - Ca. Sn 03 - Lado izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho! Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo] Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho] Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho | Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora Maynas - Lado Derecho i Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho] Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo] Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho ___________ Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo! ___________ Jr. Ucayali - Jr. Manco Capac - Lado Derecho] __________ Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo i Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo; cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo EXCAVACION MANUAL DE ZANJA PARA CANALETA Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho] Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo] Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Padre Abad - Lado Derecho i Jr. Ucayali - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje. Orellana - Lado Derecho Jr. Padre Abad - Psje. Orellana - Lado Izquierdo] Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre ■>Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo] Ca. 13 de Abril - Jr. Gavino muños - Lado Derecho Ca. 13 de Abril - Jr. Gavino mufios Jr. Gavino muños - Jr. La Selva - Lado Derecho! Jr. Gavino mufios - Jr. La Selva Lado Izquierdo I Jr La Selva y psje Victoria - prog. 1 + 415.33 - prog 1+600 Lado Derecho! Jr. La Selva y p sje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo progresiva 1+800 - jr. lima - Lado Derecho progresiva 1 +800 - jr. lima - Lado Izquierdo] Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Arica - Jr. Miraflores - Lado Derecho Jr. Arica - Jr. Miraflores Lado Izquierdo! Jr. Miraflores - Jr. Rioja - Lado Derecho j Jr. Miraflores - Jr. Rioja - Lado Izquierdo j Jr. Rioja - Prog. 2+260 - Lado Derecho | Jr. Rioja - Prog. 2+260 - Lado Izquierdo j Prog. 2+640- Ca. Sn. 01 Lado Derecho! Prog. 2+640 -Ca. Sn. Lado Izquierdo! Ca. sn 01 - Jr. Ucayali - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Izquierdo] Jr. miraflores - Jr. yurimaguas - Lado Derecho Jr. miraflores - Jr. yurimaguas - Lado Izquierdo ] Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo] Ca. Sn 02 - Ca. Sn 03 - Lado Derecho | Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo]

Am pff/ó ¿Haz Ar«valt> * > f w > r e 8 í í r lt f ? ? * & t f c í j s i

TOTAL

Página 10

H O JA DE M ETR AD O S OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA 1MENSIONE3 UND

DESCRIPCION

ITEM

de

de

largo

ancho

atto

elem.

veces

m.

m.

m.

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

80.52 89.93 23.16 26.60 129.77 82.59 106.68 106.68 96.77 110.90 94.53 96.59 98.56 99.14 94.60 94.60 95.20 95.20 68.35 68.35

0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95

0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55

Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora Maynas - Lado Derecho Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Manco Capac - Lado Derecho Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo 01.06.01.03 01.06.01.04 01.06.01.05

ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" CANALETAS

KG.

RELLENO CON MATERIAL PROPIO - CANALETAS

M3

ENCOFRADO A s J 1 = 2 . 9 0 m i. r

\

\

\ w

X .

*7

BERMA T

i 0 .7 5

l u .s s a

0 60S ! 0 .7 0

| 1 H .

TOTAL

42.07 46.99 12.10 13.90 67.80 43.15 55.74 55.74 50.56 57.95 49.39 50.47 51.50 51.80 49.43 49.43 49.74 49.74 35.71 35.71 80,688.86 215.42

215.42 21,004.66

M2

ENCOFRADO Y DESENCOFRADO DE CANALETAS

/

PARCIAL

1

%

3 ’

Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo Jr. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr, Ucayali - Jr. Padre Abad - Lado Derecho Jr. Ucayali - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje. OreBana - Lado Derecho Jr. Padre Abad - Psje. Orellana - Lado Izquierdo Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo Ca. 13 de Abril - Jr, Gavino mullos - Lado Derecho Ca. 13 de Abril - Jr. Gavino muños - Lado Izquierdo Jr. Gavino muños - Jr. La Selva - Lado Derecho Jr. Gavino muños - Jr. La Selva Lado Izquierdo e. Victoria - prog. 1 + 415.33 - prog. 1+600 Lado Derecho Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo progresiva 1+800 - jr. lima - Lado Derecho progresiva 1+800 - jr. lima - Lado Izquierdo Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. Miraflores - Lado Derecho Jr. Arica - Jr. Miraflores - Lado Izquierdo Jr. Miraflores - Jr, Rioja - Lado Derecho Jr. Miraflores - Jr. Rioja - Lado Izquierdo Jr. Rioja - Prog. 2+260 - Lado Derecho Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. 01 Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo Ca. sn 01 - Jr. Ucayali - Lado Derecho Ca. sn 01 - Jr. Ucayal - Lado Izquierdo Jr. Ucayali - Jr. miraflores - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Izquierdo Jr. miraflores - Jr. yurimaguas - Lado Derecho Jr. miraflores - Jr. yurimaguas - Lado Izquierdo Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo Ca. Sn 02 - Ca. Sn 03 - Lado Derecho Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr San Martin - Jr. Eleudora Maynas - Lado Derecho Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Manco Capac - Lado Derecho Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo

Consorcio FRL & SG ASCONSULT A M fittr» JOfaz A re va lo te g s !

¡oR«f«l Lean •OVIL CU* N* 40894

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1 00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

111.40 118.53 125.11 94.11 140.35 122.00 130.96 112.00 368.75 335.67 131.03 87.09 141.22 126.30 172.52 151.14 197.57 183.21 80.85 184.02 95.48 95.48 94.48 94.48 98.76 89.60 33.90 29.95 102.29 108.10 111.31 116.36 96.60 96.60 87.34 L 96.00 110.30 117.40 83.28 101.98 269.76 240.99 80.52 89.93 23.16 26.60 129.77 82.59 106.68 106.68 96.77 110.90 94.53 96.59 98.56 99.14 94.60 94.60 95.20 95.20 68.35 68.35

2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90

323.06 343.74 362.82 272.92 407.02 353.80 379.78 324.80 1,069.38 973.44 379.99 252.56 409.54 366.27 500.31 438.31 572.95 531.31 234.47 533.66^? l/ fé s* 9

t V *B ° V i VISION

( j?

p86.4fc ifjf \*5fl.84ÚCl¿L \

313.49 322.80 337.44 280.14 280.14 253.29 278.40 319.87 340.46 241.51 295.74 782.30 698.86 233.51 260.80 67.16 77.14 376.33 239.51 309.37 309.37 280.63 321.61 274.14 280.11 285 82 287.51 274.34 274.34 276.08 276.08 198.22 198.22

1 J

...... \ A .

V i

HOJA DE METRADOS tA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

CONCRETO F 'O 210 KB/CM2 EN CANALETAS

0.15

BERMA

0.45',0.70

AREA=0.21M2 015

0 10 010

050

de

de

elem.

veces

largo

1,521.03 Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo Jr. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Padre Abad - Lado Derecho Jr. Ucayali - Jr. Padre Abad - Lado Izquierdo _Jr. Padre Abad - Psje. Orellana - Lado Derecho Jr. Padre Abad - Psje. Orellana - Lado Izquierdo Tramo San jóse - Lado Derecho 0-*- 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de AbrH - Lado Izquierdo Ca. 13 de Abril - Jr. Gavino muños - Lado Derecho Ca. 13 de Abril - Jr. Gavino mufios - Lado Izquierdo Jr. Gavino mufios - Jr. La Selva - Lado Derecho Jr. Gavino mufios - Jr. La Selva Lado Izquierdo Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 Lado Derecho Iva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo nrnnrp*;h/» 1+800 - ir artn n#»rprhn progresiva jr. lima - ILado Derecho progresiva 1+800 - jr. lima - Lado Izquierdo Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. Miraflores - Lado Derecho Jr. Arica - Jr. Miraflores - Lado Izquierdo Jr. Miraflores - Jr. Rioja - Lado Derecho Jr. Miraflores - Jr. Rioja - Lado Izquierdo Jr. Rioja - Prog. 2+260 - Lado Derecho Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. 01 Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo Ca. sn 01 - Jr. UcayaN - Lado Derecho Ca. sn 01 - Jr. Ucayal - Lado Izquierdo Jr. Ucayali - Jr. miraflores - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Izquierdo Jr. miraflores - Jr. yurimaguas - Lado Derecho Jr. miraflores - Jr. yurimaguas - Lado Izquierdo Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo Ca. Sn 02 - Ca. Sn 03 - Lado Derecho Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora Maynas - Lado Derecho Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Manco Capac - Lado Derecho Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29 Jr. Eduardo del Aguila - Orfflas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Agüita - Orillas del lago - Lado Izquierdo

ELIMINACION DE MATERIAL EXCEDENTE

4,639.75

CURADO DE CANALETAS ABIERTAS

14.1Z3.8Z

CURADO 1=1.95 ¡ni.

Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo Jr. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Padre Abad - Lado Derecho Jr. Ucayai - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje. Orellana - Lado Derecho Jr. Padre Abad - Psje. Orellana - Lado Izquierdo Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo Ca. 13 de Abril - Jr. Gavino mufios - Lado Derecho Ca. 13 de Abril - Jr. Gavino mufios - Lado Izquierdo Jr. Gavino mufios - Jr. La Selva - Lado Derecho Jr. Gavino mufios - Jr. La Selva Lado Izquierdo y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 Lado Derecho psje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo progresiva 1+800 - jr. lima - Lado Derecho progresiva 1 +300 - jr. lima - Lado Izquierdo Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. Miraflores - Lado Derecho Jr. Arica - Jr. Miraflores - Lado Izquierdo Jr. Miraflores - Jr. Rioja - Lado Derecho Jr. Miraflores - Jr. Rioja - Lado Izquierdo Jr. Rioja - Prog. 2+260 - Lado Derecho Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. 01 Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo Ca. sn 01 - Jr. Ucayali - Lado Derecho Ca. sn 01 - Jr. Ucayal - Lado Izquierdo Jr. Ucayai - Jr. miraflores - Lado Derecho Jr. Ucayali - Jr. miraflof—-g~tgao Izquierdo!



Página 12

HOJA DE METRAOOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE Y ARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA OiMENSIO

N* UND

DESCRIPCION

ITEM

de

de

eiem.

veces 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

Jr. miraflores - Jr. yurimaguas - Lado Derecho Jr. miraflores - Jr. yurimaguas - Lado Izquierdo Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr yurimaauas - Ca. Sn 02 - Lado Izquierdo Ca. Sn 02 - Ca. Sn 03 - Lado Derecho Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora Maynas - Lado Derecho Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amam - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Manco Capac - Lado Derecho Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo 01.06.02 01.06.02.01

CANALETAS TECHADAS TRAZO NIVELACION Y REPLANTEO

87.34 96.00 110.30 117.40 83 28 101.98 269.76 240.99 80.52 89.93 23.16 26.60 129.77 82.59 106.68 106.68 96.77 110.90 94.53 96.59 98.56 99.14 94.60 94.60 95.20 95.20 68.35 ] _ 68.35

ancho m.

....

!

alto m.

PARCIAL

TOTAL

170.31 187.20 215.09 228.93 162.40 198.86 526.03 469.92 157.01 175.36 45.16 51.87 253.05 161.05 208.03 208.03 188.70 216.26 184.33 188.35 192.19 193.32 184.47 184.47 185.64 185.64 133.28 133.28

1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95

1,214.88

M2 Canaletas techadas intersecciones Jr. Circumvalacion - Jr. Iparia - Lado Izquierdo Jr. Ucayali - Lado Izquierdo Jr. Padre Abad - Lado Izquierdo Psje. Orellana - Lado Izquierdo Ca. 28 de Noviembre - Lado Izquierdo Ca. 13 de Abril - Lado Izquierdo Jr. Gavino Munos - Lado Izquierdo Jr. La Selva y psje. Victoria - Lado Izquierdo intersección Jr. Ucayali - Jr. Lima - Lado Izq. Y Derecho Jr. Arica - Lado Izquierdo Jr. miraflores - Lado Derecho Jr. miraflores - Lado Izquierdo Jr. Rioja - Lado Izquierdo Ca. Sn 01 - Lado derecho Jr. Ucayali - Lado derecho Jr. Ucayali - Lado Izquierdo Jr. Miraflores - Lado derecho Jr. Miraflores - Lado Izquierdo Jr Yurimaguas - Lado derecho Jr. Yurimaguas - Lado Izquierdo Ca. Sn 02 - Lado derecho Ca. Sn 03 - Lado derecho Av. Guillermo Towsend - Lado derecho Av. Guillermo Towsend - Lado Izquierdo Jr. Moyobamba - Lado Derecho Ca. Sn 04 - Av. Belisario Panduro - Lado Izquierdo Jr. Diego Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. miraflores - Lado Izquierdo Jr. Eleudora Maynas - Lado Derecho Jr. Tupac Amaru Jr. Ucayali - Lado derecho Jr. Ucayali - Izquierdo Jr. Manco Capac - Lado Derecho Jr. Manco Capac - Lado Izquierdo Jr. Eduardo del Aguila - Lado Derecho Jr. eduardo del Aguila - Lado Izquierdo Terminal Orilla del lago Yarina Cocha - lado derecho Terminal Orilla del lago Yarina Cocha - lado Izquierdo Canaletas techadas en ingresos Jr Iparia - Jr. Ucayali - Lado Derecho Psje. Orellana - prog. 0+600 - Lado Derecho Prog. 0+880 - Ca. 28 de Noviembre - Lado Derecho Prog. 1+200- Prog. 1+240 Jr Eleudora Maynas - Lado Izquierdo

01.06.02.02

largo m.

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1 00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

46.48 3.50 3.50 19.20 42.06 26.70 3.50 25.80 36.15 14.00 25.60 25.60 25.71 17.05 25.60 25.60 25.60 25.60 25.60 7.00 7.00 25.60 26.20 69.87 18.60 72.32 14.00 25.60 7.00 26.20 33.20 25.60 7.00 25.60 25.60 25.60 25.60 5.20 5.20

1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20

1.00 1.00 1.00 1.00 1 00

15.00 31.56 11.00 25.00 900

1.20 1.20 1.20 1.20 1.20

^

55.78 4.20 4.20 23.04 50.47 32.04 4.20 30.96 43.38 16.80 30.72 30.72 30.85 20.46 30.72 30.72 30.72 30.72 30.72 8.40 8.40 30.72 31.44 83.84 22.32 86.78 16.80 30.72 8.40 31.44 39.84 30.72 8.40 30.72 30.72 30.72 30.72 6.24 6.24

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

46.48 3.50 3.50 19.20 42.06 26.70 3.50 25.80 36.15 14.00 25.60 25.60 25.71 17.05 25.60 25.60 25.60 25.60

1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40

0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55

35.79 2.70 2.70 14.78 32.39 20.56 2.70 19.87 27.84 10.78 19.71 19.71 19.80 13.13 19.71 19.71 19.71 19.71

Jr. Yurimaguas - Lado Izquierdo y ' Ca. Sn 02 - Lado derecho

1.00 1.00

7.00 7.00

1.40 1.40

0.55 0.55

5.39 5.39

HafMllew

I M f tU u H l fc s w il

INO, CIVIL C IP N * 40*94

V ». Í$ T t ■

*4 Co ü ;

779.55

Canaletas techadas intersecciones Jr. Circumvalacion - Jr. Iparia - Lado Izquierdo Jr. Ucayali - Lado Izquierdo Jr. Padre Abad - Lado Izquierdo Psje. Orellana - Lado Izquierdo Ca. 28 de Noviembre - Lado Izquierdo Ca. 13 de Abril - Lado Izquierdo Jr. Gavino Munos - Lado Izquierdo Jr. La Selva y psje. Victoria - Lado Izquierdo intersección Jr. Ucayali - Jr. Lima - Lado Izq. Y Derecho Jr. Arica - Lado Izquierdo Jr. miraflores - Lado Derecho Jr. miraflores - Lado Izquierdo Jr. Rioja - Lado Izquierdo Ca. Sn 01 - Lado derecho Jr. Ucayali - Lado derecho Jr. Ucayali - Lado Izquierdo Jr. Miraflores - Lado derecho Jr. Miraflores - Lado Izquierdo

t r m v a f ír

\ y \i %

18.00 37.87 13.20 30.00 1080

M3

EXCAVACION MANUAL DE ZANJA PARA CANALETA

r

HOJA DE METRAPOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA N° | UND

DESCRIPCION

ITEM

de elem.

Ca. Sn 03 - Lado derecho Av. Guillermo Towsend - Lado derecho Av. Guillermo Towsend - Lado Izquierdo Jr. Moyobamba - Lado Derecho Ca. Sn 04 - Av. Belisario Panduro - Lado Izquierdo Jr. Diego Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. miraflores - Lado Izquierdo Jr. Eleudora Maynas - Lado Derecho Jr. Tupac Amaru Jr. Ucayali - Lado derecho Jr. Ucayali - Izquierdo Jr. Manco Capac - Lado Derecho Jr. Manco Capac - Lado Izquierdo Jr. Eduardo del Aguila - Lado Derecho Jr. eduardo del Aguila - Lado Izquierdo Terminal Orilla del lago Yarina Cocha - lado derecho Terminal Orilla del lago Yarina Cocha - lado Izquierdo Canaletas techadas en ingresos Jr. Iparia - Jr. Ucayali - Lado Derecho Psje. Orellana - prog. 0+600 - Lado Derecho Prog. 0+880 - Ca. 28 de Noviembre - Lado Derecho Prog. 1+200- Prog. 1+240 Jr, Eleudora Maynas - Lado Izquierdo 01.06.02.03

ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" CANALETAS

01.06.02.04

ENCOFRADO Y DESENCOFRADO EN CANALETA

ENCOFRADO



1 —O Qñ

\

i O

Y

de

largo m.

l ancho j

alto

m.

m.

PARCIAL

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

25.60 26.20 69.87 18.60 72.32 14.00 25.60 7.00 26.20 33.20 25.60 7.00 25.60 25.60 25.60 25.60 5.20 5.20

1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40 1.40

0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55

19.71 20.17 53.80 14.32 55.69 10.78 19.71 5.39 20.17 25.56 19.71 5.39 19.71 19.71 19.71 19.71 4.00 4.00

1.00 1.00 1.00 1.00 1.00

15.00 31.56 11.00 25.00 9.00

1.40 1.40 1.40 1.40 1.40

0.55 0.55 0.55 0.55 0.55

11.55 24.30 8.47 19.25 6.93

0 »

\

Jr. miraflores - Lado Izquierdo Jr. Rioja - Lado Izquierdo Ca. Sn 01 - Lado derecho Jr. Ucayali - Lado derecho Jr. Ucayali - Lado Izquierdo Jr. Miraflores - Lado derecho Jr. Miraflores - Lado Izquierdo Jr. Yurimaguas - Lado derecho Jr. Yurimaguas - Lado Izquierdo Ca. Sn 02 - Lado derecho Ca. Sn 03 - Lado derecho Av. Guillermo Towsend - Lado derecho Av. Guillermo Towsend - Lado Izquierdo Jr. Moyobamba - Lado Derecho Ca. Sn 04 - Av. Belisario Panduro - Lado Izquierdo Jr. Diego Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. miraflores - Lado Izquierdo jr . Eleudora Maynas - Lado Derecho Jr. Tupac Amaru Jr. Ucayali - Lado derecho Jr. Ucayali - Izquierdo Jr. Manco Capac - Lado Derecho Jr. Manco Capac - Lado Izquierdo Jr. Eduardo del Aguila - Lado Derecho Jr. eduardo del Aguila - Lado Izquierdo Terminal Orilla del lago Yarina Cocha - lado derecho Terminal Orilla del lago Yarina Cocha - lado Izquierdo Canaletas techadas en ingresos Jr. Iparia - Jr. Ucayali - Lado Derecho Psje. Orellana - prog. 0+600 - Lado Derecho Prog. 0+880 - Ca. 28 de Noviembre - Lado Derecho Prog. 1+200- Prog. 1+240 Jr. Eleudora Maynas - Lado Izquierdo

TOTAL

KG.

26,696.99

M2

2,935.96

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

46.48 3.50 3.50 19.20 42.06 26.70 3.50 25.80 36.15 14.00

2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90

134.79 10.15 10.15 55.68 121.97 77.43 10.15 74.82 104.84 40.60

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

25.60 25.71 17.05 25.60 25.60 25.60 25.60 25.60 7.00 7.00 25.60 26.20 69.87 18.60 72.32 14.00 25.60 7.00 26.20 33.20 25.60 7.00 25.60 25.60 25.60 25.60 5.20 5.20

2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90 2.90

74.24 74.56 49.45 74.24 74.24 74.24 74.24 74.24 20.30 20.30 74.24 75 9 8 202.62 53.94 209.73 40.60 74.24 20.30 75.98 96.28 74.24 20.30 74.24 74.24 74.24 74.24 15.08 15.08

1.00 1.00 1.00 1.00 1.00

15.00 31.56 11.00 25.00 9.00

2.90 2.90 2.90 2.90 2.90

43.50 91.52 31.90 72.50 26.10

^ 090

------------------------

BERMA

Canaletas techadas intersecciones Jr. Circumvalacion - Jr. Iparia - Lado Izquierdo Jr. Ucayali - Lado Izquierdo Jr. Padre Abad - Lado Izquierdo Psje. Orellana - Lado Izquierdo Ca. 28 de Noviembre - Lado Izquierdo Ca. 13 de Abril - Lado Izquierdo Jr. Gavino Munos - Lado Izquierdo r. La Selva y psje. Victoria - Lado Izquierdo . Ucayali - Jr. Lima - Lado Izq. Y Derecho Jr. Arica - Lado Izquierdo

I

j veces

Página 14

HOJA DE METRADOS MEJORAMIENTO OE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

11

...>yZZ DESCRIPCION

de

de

elem.

veces

PARCIAL

TOTAL

CONCRETO F C = 210 KG/CM2 EN CANALETAS

AREA=0.39 M2

Jr. Padre Abad - Lado Izquierdo j Psje. Orellana - Lado Izquierdo Ca. 28 de Noviembre - Lado Izquierdo 1 Ca. 13 de Abril - Lado Izquierdo ] Jr. Gavino Munos - Lado Izquierdo | Jr. La Selva y psje. Victoria - Lado Izquierdo! .eccion Jr. Ucayali - Jr. Lima - Lado Izq. V Derecho! _______________________ Jr. Arica - Lado Izquierdo | Jr. miraflores - Lado Derecho! Jr. miraflores - Lado Izquierdo J r. Rioja - Lado Izquierdo j Ca. Sn 01 - Lado derecho! Jr. Ucayali - Lado derecho j Jr. Ucayali - Lado Izquierdo j Jr. Miraflores - Lado derecho j Jr. Miraflores - Lado Izquierdo j Jr. Yurimaguas - Lado derecho j Jr. Yurimaguas - Lado Izquierdo Ca. Sn 02 - Lado derecho Ca. Sn 03 - Lado derechoAv. Guillermo Towsend - Lado derecho! Av. Guillermo Towsend - Lado Izquierdo! Jr. Moyobamba - Lado Derecho Ca. Sn 04 - Av. Belisario Panduro - Lado Izquierdo ¡ Jr. Diego Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. miraflores - Lado Izquierdo; Jr. Eleudora Maynas - Lado Derecho Jr. Ucayali - Lado derecho ¡ Jr. Ucayali - Izquierdo Jr. Manco Capac - Lado Derecho Jr. Eduardo del Aguila - Lado Derecho! Jr. eduardo del Aguila - Lado Izquierdo Terminal Orüia del lago Yarina Cocha - lado derecho | Terminal Orilla del lago Yarina Cocha - lado Izquierdo: __________ Canaletas techadas en in gresos1 ______________ Jr. Iparia - Jr. Ucayali - Lado Derecho ¡ ________ Psje. Orellana - prog. 0+600 - Lado Derecho] Prog 0+880 - Ca. 28 de Noviembre - Lado Derecho ¡ ________________________ Prog. 1+200 - Prog. 1+240 j Jr. Eleudora Maynas - Lado Izquierdo |

ELIMINACION DE MATERIAL EXCEDENTE D=5 KM

BERMA

AREA3 [ÁREA: ¡AREA3 ¡AREA* AREA3 lARÉA^ AREA= AREA= AREA» AREA-

AREA= AREA: AREA3 AR£A= AREAAREA= AREA: AREA= AREA3 AREA3

AREA= AREA3 AREA3 AREA3 AREA» ÁREA: AREA3 AREA: AREA= AREA: AREA= AREA: AREA3 ÁREA3 AREA: 1,013.41

CURADO DE CANALETAS TECHADAS

L=1.20

3.50 19.20 42.06 26.70 3.50 25.80

________Canaletas techadas intersecciones j Jr. Circumvalacion - Jr. Iparia - Lado Izquierdo Jr. Ucayali - Lado Izquierdo Jr. Padre Abad - Lado Izquierdo ¡ Psje. Orellana - Lado Izquierdo i Ca. 28 de Noviembre - Lado Izquierdo! Ca. 13 de Abnl - Lado Izquierdo; Jr. Gavino Munos - Lado Izquierdo j Jr. La Selva y psje. Victoria - Lado Izquierdo I intersección Jr. Ucayali- Jr. Lima - Lado Izq. Y Derecho! Jr. Arica - Lado Izquierdo j Jr. miraflores - Lado Derecho j Jr. miraflores - Lado Izquierdo Jr. Rioja - Lado Izquierdo Ca. Sn 01 - Lado derecho! Jr. Ucayali - Lado derecho Jr. Ucayali - Lado Izquierdo Jr. Miraflores - Lado derecho | Jr. Miraflores - Lado Izquierdo Jr. Yurimaguas - Lado derecho Jr. Yurimaguas - Lado Izquierdo Ca. Sn 02 - Lado derecho} Ca. Sn 03 - Lado derecho i Av. Guillermo Towsend - Lado derecho j Av. Guillermo Towsend - Lado Izquierdo j Jr. Moyobamba - Lado Derecho! Ca. Sn 04 - Av. Belisario Panduro - Lado Izquierdo [ Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. miraflores - Lado Izquierdo! Jr. Eleudora Maynas - Lado Derecho Jr. Tupac Amaru Jr. Ucayali - Lado derecho Jr. Ucayali - Izquierdo] Jr. Manco Capac - Lado Derecho] Jr. Manco Capac - Lado Izquierdo Jr. eduardo del Aguila - Lado Izquierdo j Terminal Orilla del lago Yarina Cocha - lado derecho | Terminal Orilla del lago Yarina Cocha - lado Izquierdo |

Psje. OreBana - prog. 0+600 - Lado Derecho Prog. 0+880 - Ca. 28 de Noviembre - Lado Derecho Prog. 1+200- Prog 1+240

Página 15

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO Y ARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA DW 6N2IO 4ES



01.06.03 01.06.03.01

UND

DESCRIPCION

ITEM

SARDINELES TRAZO NIVELACION Y REPLANTEO

de

de

largo

elem.

veces

m.

ancho m.

2.00 2.00

185.00 370.00

0.15 0.15

2.00 2.00

185.00 370.00

0.15 0.15

PARCIAL

166.50

58.28

Prog. 1+600 al 1+1+800 Prog. 2+260 al 2+640 01.06.03.03

ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" SARDINEL

KG.

01.06.03.04

ENCOFRADO Y DESENCOFRADO EN SARDINEL

M2

L=1 8 0 m i

55.50 111.00

M3

EXCAVACION DE ZANJA PARA SARDINEL

TOTAL

m.

M3 Proq. 1+600 al 1+1+800 Prog. 2+260 al 2+640

01.06.03.02

alto

0.35 0.35

19.43 38.85 5,472.30

VER HOJA DE METRADO ACERO

1,998.00

Proq. 1+600 al 1+1+800 Prog. 2+260 al 2+640

2.00 2.00

185.00 370.00

2.00 2.00

185.00 370.00

1.80 1.80

666.00 1332.00

0.75 0.75

41.63 83.25

\

BERM A

\

^ 0 6 .0 3 .0 5

°

»

124.88

M3

CONCRETO F'C= 210 KG/CM2 EN SARDINELES Prog. 1+600 al 1+1+800 Proa. 2+260 al 2+640

y - lo i

0.15 0.15

BERM A

0 .7 5

( ¿ y

*

01.06.03.06

ELIMINACION DE MATERIAL EXCEDENTE

01.06.03.07

CURADO DE SARDINELES

75.76

333.00

M2 2.00 2.00

Prog. 1+600 al 1+1+800 Prog. 2+260 al 2+640 01.07

MURO DE CONTENCION

01.07.01 01.07.01.01 01.07.01.01.01

SISTEMA DE MURO DE CONTENCION (TERRAMESH VERDE) TRABAJOS PROVISIONALES LIMPIEZA DE TERRENO

■ o ? 01.01.02 w

01.07.01.02 01.07.01.02.01

M2 1.00 1.00

Tramo Puente Tushmo (Prog. 1+600 al Prog. 1+800) Tramo Puente San Lorenzo (Prog. 2+260 al Prog. 2+640)

1.00 1.00

Tramo Puente Tushmo (Prog. 1+600 al Prog. 1+800) Tramo Puente San Lorenzo (Prog. 2+260 al Prog. 2+640)

UND 1.00 1.00

SEÑALIZACION Y SEGURIDAD EN ZONA DE TRABAJO

MOVIMIENTO DE TIERRAS CORTE DE TERRENO A MAQUINA

01.07.01.02.03

01.07.01.03 01.07.01.03.01

580.00 200.00 380.00

200.00 380.00

200.00 380.00

200.00 380.00

580.00

4.00 2.00 2.00

2.00 2.00

14,117.43 1.00 1.00

Volumen Volumen

5.285.88 8,831.56

5,285.88 8,831.56 11,020.00

M2 1.00 1.00

2.00 2.00

200.00 380.00

9.50 9.50

3,800.00 7,220.00

Tramo Puente Tushmo (Prog. 1+600 al Prog. 1+800 Tramo Puente San Lorenzo (Prog. 2+260 al Prog. 2+640)

M2 1.00 1.00

2.00 2.00

200.00 380.00

9.50 9.50

3.800.00 7,220.00

1.00

3,726.00

3,726.00

1.00

24.332.00

24.332.00

1.00 1.00

Volumen Volumen

CONFORMACION DE SUB-RASANTE

SISTEMA DE MURO DE CONTENCION - SUELO REFORZADO (TERRAMESH VERDE) SUMINISTRO E INSTALACION SISTEMA TERRAMESH VERDE (2.00 X 4.00 X 0.60)

11,020.00

3,726.00

UND

M2

SUMINISTRO E INSTALACION GEOTEXTIL Ver Hoja de Metrado Terramesh

01.07.01.03.03

111.00 222.00

Tramo Puente Tushmo (Prog. 1+600 al Prog. 1+800) Tramo Puente San Lorenzo (Prog. 2+260 al Prog. 2+640)

NIVELACION Y COMPACTADO DEL TERRENO

Ver Hoja de Metrado Terramesh 01.07.01.03.02

0.30 0.30

M3 Tramo Puente Tushmo (Ver Hoja de Movimiento de Tierras) Tramo Puente San Lorenzo (Ver Hoja de Movimiento de Tierras)

01.07.01.02.02

185.00 370.00

M2

TRAZO, NiVEL Y REPLANTEO

-

01.07.01.01.03

Tramo Puente Tushmo (Prog. 1+600 al Prog. 1+800) Tramo Puente San Lorenzo (Prog. 2+260 al Prog. 2+640)

24,332.00

398.89

M3

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO Tramo Puente Tushmo (Ver Hoja de Movimiento de Tierras Tramo Puente San Lorenzo (Ver Hoia de Movimiento de Tierras

75,76

23.09 375.80

23.09 375.80

Página 16

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

PARCIAL

RELLENO CON HORMIGON. Ver Hoja de Metrado Terramesh

TRAZO, NIVEL Y REPLANTEO JR. CIRCUNVALACION L ado Izq.

EXCAVACION DE ZANJA PARA MURO DE CONTENCION JR. CIRCUNVALACION L ado Izq.

JR. CIRCUNVALACION L ado Izq.

ACERO DE REFUERZO FY=*4200 KG/CM2 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION JR. CIRCUNVALACION L ado Izq. extremos de muros

ENCOFRADO H=!35

CONCRETO Fe = 210 kg/cm2 - EN MURO DE CONTENCION JR. CIRCUNVALACION L ado Izq.

M U RO

Conaício FRL & JG ASCCHSULT

AREA=

TOTAL

Página 17

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO • UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

es

N

01.07.02.07

UND

DESCRIPCION

ITEM

de elem.

de veces

largo m.

ancho m.

atto m.

PARCIAL

1

19.70

080

080

12.61

TOTAL

M3

RELLENO COMPACTADO CON MATERIAL PROPIO

12.61

JR. CIRCUNVALACION L ado Izq. “ ““

\

BERMA C° A® FC=210 KG/CM2 >

í

t

g

i

i t i RELLENO CON M A ÍtR lA L PROPIO i

i ¡1 l¡

.................

1

SOLADO

t 01.07.02.08

ELIMINACION DE MATERIAL EXCEDENTE

M3

01.07.02.09

CURADO DE MURO DE CONTENCION

M2

15.37

EN ZAPATA EN ZAPATA Y MURO 01.08 ■1.08.01

1.00 1.00

19.70 19.70

0.60 1.50

1162 2955

PARADEROS Y MARTILLOS PARADEROS

01 08 01.01

TRAZO NIVELACION Y REPLANTEO

M2

8.00

1.00

2.30

0 49

01.08.01.02

EXCAVACION MANUAL DE ZANJA PARA PARADEROS

M3

8.00

1.00

2.30

0.75

01 08.01.03

NIVELACION Y APISONADO MANUAL

M2

8.00

1.00

2.30

0.49

01.08 01.04

RELLENO COMPACTADO CON MATERIAL PROPIO

M3

8.00

1.00

2.30

0.75

01 08.01.05

ELIMINACION E MATERIAL EXCEDENTE

M3

01.08.01.06

CONCRETO FC=140 KG/CM2 EN ZAPATA DE PARADERO

M3

8.00

1.00

2.30

01 08.01.07

CONCRETO F‘C=175 KG/CM2 EN BASE PARA BANCAS

M3

8.00

2.00

01 08.01.08

ENCOFRADO Y DESENCOFRADO EN BASE DE C°A° DE BANCAS

M2 2.00 2.00 2.00

2.00 1.00 2.00

LARERALES MENOS AREA DE ORIFICIO CANTOS 01.08 01 09

15.37 41.37

ACERO DE REFUERZO F,Y=4200 KG/CM2

902

9.02

690

..........• v.:

902

9.02

030

414

4.14

2 .7 6

35 9

3.59

0.75

020

2 76

2.76

AREA=

3.79

010

606

6.06

AREA= AREA* 1.70

0.31 0.07 0.10

050

' '

f/3 " •

KG

124 -014 068

CÍD E

/

......242.18

EN ZAPATA rv ^ 1 IO ¡ x

[

* .1 *r¡ pk

^ W

'!

.1

2 > jf

M I i % 01.08.01.10

ESTRUCTURA DE MADERA EN BANCAS

UND 8.00

1.00

8.00

1.00

N tt:

-

-

8.00

v

\

01.08.01.11 k ■ .0801.12

V

01.08.01.13

01 08 01.14

ENTRAMADO DE MADERA EN PARADEROS

UND

8 00 **- h

8.00 \

COLUMNAS DE MADERA (quinilla y/o simHar)

\

UND

V

S.OO

8.00

1.00

8.00

1.00

2.98

800 8.00

1 00 2.00

1 90 2.85

8.00

8.00

64.00

8.00

1.00

8.00

8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00

2.00 2.00 2.00 2.00 2.00 8.00 4.00 4.00

1.82 1.97 2.24 1.17 2.98 2.98 2.04 2.00

8.00

8.00

0.50

8.00

COBERTURA CON PLANCHAS DE CALAMINA ONDULINE COLOR ROJO

42 63

COLOCACION DE DE TUBOS F°G EN PARADEROS

2.04

4063

ML

01.08.01.15

PLATiNA METALICAS PARA FIJAR EN LOS PARADEROS

UND

01.08.01.16

PINTURA EN BANCAS DEL PARADERO

UND

60.80 1520 4560

64.00

01.08.01.17

PINTURA BARNIZ EN ESTRUCTURA DE MADERA

ML En columnas

Base de madera en banca (estructura de madera) Viga de madera Viguetas Sobrevigas Espaldar de madera 01.08.01.18

PINTURA ZICROMATICO EN CARPINTERIA METALICA

8.00

482.83 2912 3152 3584 18 72 47 68 19072 6528 6400

ML

' 160.98

'«mando Rafael Lean INÓ. CIVIL CIP N *40894

3200



Página 18

HOJA DE LE TR A D O S OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

N* ITEM

DESCRIPCION

01.08.02

MARTILLOS

01.08.02.01

TRAZO NIVELACION Y REPLANTEO

UND

Intersección Jr. Arica Intersección Jr. Miraflores intersección Jr. Rioja Intersección Ca. Sn. 01 InterseccionJr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. Sn. 02 Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend Intersección Jr. Moyobamba Intersección Ca. Sn. 04 Intersección Jr. Diego zumba Intersección Jr. San martin Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. Manco Capac Intersección Jr. Eduardo del Aguila Terminal orilla del lago Yarinacocha NIVELACION Y APISONADO MANUAL

.....

largo m.

ancho m.

1.00 2.00 2.00 2.00 1.00 2.00 2.00 2.00 1.00 1.00 1.00 1.00 4.00 4.00 2.00 1.00 1.00 4.00 4.00 4.00 2.00 2.00 3.00 2.00 2.00 4.00 4.00 2.00 4.00 4.00 4.00 4.00 2.00

Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area

15.90 28.27 28.27 19.28 28.27 28.27 28.27 28.27 22.29 25.65 25.54 29.72 28.27 28.27 28.27 24.95 24.11 28.27 28.27 28.27 28.27 28.27 28.27 28.27 24.92 28.27 28.27 28.27 28.27 21.89

1.00 2.00 2.00 2.00 1.00 2.00 2.00 2.00 1.00 1.00 1.00 1.00 4.00 4.00 2.00 1.00 1.00 4.00 4.00 4.00 2.00 2.00 3.00 2.00 2.00 4.00 4.00 2.00 4.00 4 00 4.00 4.00 2.00

Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area

15.90 28.27 28.27 19.28 28.27 28.27 28.27 28.27 22.29 25.65 25.54 29.72 28.27 28.27 28.27 24,95 24.11 28.27 28.27 28.27 28.27 28.27 28.27 28.27 24.92 28.27 28.27 28.27 28.27 21.89 21.89 21.89 28.27

2 4 )1 2 ^ 113'Q Í* S t i A 113 O&s 113.08' 56.54 56.54 84.81 56.54 49.84 113.08 113.08 56.54 113.08 87.56 87.56 87.56 56.54

15.90 4.80 28.27 5.79 28,27 5.79 19.28 5.74 28.27 5.74 28.27 9.44 28.27 5.79 28.27 5.74 22.29 25.65 25.54 29 72 33.36 28.27 5.79 28.27 25.60 28.27

15.90 -4.80 56.54 -5.79 56 54 -5.79 38.56 -11.48 28.27 -5.74 56.54 -18.88 56.54 -5.79 56.54 -11.48 22.29 25.65 25.54 29.72 -33.36 113.08 -17.37 113.08 -25.60 56.54

alto m.

PARCIAL

Intersección Jr. Arica Intersección Jr. Miraflores intersección Jr. Rioja Intersección Ca. Sn. 01 InterseccionJr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. Sn. 02 Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend Intersección Jr. Moyobamba Intersección Ca. Sn. 04 Intersección Jr. Diego zumba Intersección Jr. San martin Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. Manco Capac Intersección Jr. Eduardo del Aguila Terminal orilla del lago Yarinacocha BASE GRANULAR e = 10 CMS

2,158.90

21.89 21.89 28.27

2,158.90

Area Area Area Area Area Area

15.90 56.54 56.54 38.56 28.27 56.54 56.54 56.54 22.29 25.65 25.54 2 9 .7 2 y ^ . p 113 # 0 t S ? 11 a fó e r

InterseccionJr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muñoz, Jr. Contamana Intersección Jr. La Selva. Psje. Victoria Intersección Jr. Ucayali - Jr. Lima

Intersección Jr, Arica Intersección Jr. Miraflores intersección Jr. Rioja

j

249*

M2 Intersección Jr. Circunvalación

TOTAL

15.90 56.54 56.54 38.56 28.27 56.54 56.54 56.54 22.29 25.65 25.54 29.72 113.08 113.08 56.54 24.95 24.11 113.08 113.08 113.08 56.54 56.54 84.81 56.54 49.84 113.08 113.08 56.54 113.08 87.56 87 56 87.56 56.54

M2 Intersección Jr. Circunvalación InterseccionJr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muñoz, Jr. Contamana Intersección Jr. La Selva, Psje, Victoria Intersección Jr. Ucayali - Jr. Lima

01.08.02.03

JMENStO M E S

de veces

M2 Intersección Jr. Circunvalación InterseccionJr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muñoz, Jr. Contamana Intersección Jr. La Selva, Psje. Victoria Intersección Jr. Ucayali - Jr. Lima

01.08.02.02

de elem.

1,613.10 1.00 -1.00 2.00 -1.00 2.00 -1.00 2.00 -2.00 1.00 -1.00 2.00 -2.00 2.00 -1.00 2.00 -2.00 1.00 1.00 1.00 1 00 -1.00 4.00 -3.00 4.00 -1.00 2.00

Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area Area

Página 19

HOJA DE METRAPOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

de

DESCRIPCION

PARCIAL

elem. Intersección Ca. Sn. 0 1 1

InterseccionJr. Ucayali | Intersección Jr. Miraflores l Intersección Jr. Yurimaguas Intersección Ca. Sn. 02

28.27

-25.60 56.54

Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend i Intersección Jr. Moyobamba - 2.00

11.48

Intersección Ca Sn 04 ; Intersección Jr. Diego zumba -11.48 Intersección Jr. San martin j Intersección Jr. Eleudora Maynas 28.27

Intersección Jr. Tupac Amaru [ Intersección Jr. Ucayali Intersección Jr. Manco Capac

-1.00 4.00 -4.00

21.89

Intersección Jr. Eduardo del Aguila i -4 00 Terminal orilla del lago Yarinacocha I

OJO baÍ

28.27

CALZADA

gran

Wm -4 -U a

10

ENCOFRADO Y DESENCOFRADO DE MARTILLOS Intersección Jr. Circunvalación InterseccionJr. Ucayali] Intersección Jr. Padre Abad Intersección Psj. Orellana Intersección Ca. 28 de Noviembre | Intersección Ca. 13 de Abril Intersección Jr. Gavino Muñoz, Jr. Contamana Intersección Jr. La Selva, Psje. Victoria Intersección Jr. Ucayali - Jr. Lima

Intersección Jr. Arica Intersección Jr. Miraflores intersección Jr. Rioja Interseccion Ca . Sn. 01 InterseccionJr. Ucayali] Intersección Jr. Miraflores | Intersección Jr. Yurimaguas;

17.14 17.14

Intersección Ca. Sn. 03 ■ Intersección Av. Gufltermo Towsend! InterseccionJr. Moyobamba i Intersección Ca. Sn. 04; Intersección Jr. Diego zumba; Intersección Jr. San martin j Intersección Jr. Eleudora Maynas j Intersección Jr. Tupac Am aru; ____________ Intersección Jr. Ucayali] Intersección Jr. Manco Capac i Intersección Jr. Eduardo del Aguila] Terminal orilla del lago Yarinacocha ¡ 01.08.02.05

CONCRETO FC = 140 KG/CM2 EN MARTILLOS Intersección Jr. Circunvalación] InterseccionJr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana

19.28

Intersección Ca. 28 de Noviembre

28.27

Intersección Ca. 13 de Abril j Intersección Jr. Gavino Mufio¿^Jfr--epTffámána

Confeorck) FRL

ASCQmiLT C»P N 40894

TOTAL

Página 20

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UC *YALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA IMENSIO <ES

N UND

DESCRIPCION

ITEM

Intersección Jr. La Selva, Psje. Victoria En uñas Intersección Jr. Ucayali - Jr. Lima

En uñas Intersección Jr. Arica En uñas Intersección Jr. Miraflores En uñas intersección Jr. Rioja En uñas Intersección Ca. Sn. 01 En uñas InterseccionJr. Ucayali En uñas Intersección Jr. Miraflores En uñas Intersección Jr. Yurimaguas En uñas Intersección Ca. Sn. 02 En uñas Intersección Ca. Sn. 03 En uñas Intersección Av. Guillermo Towsend En uñas Intersección Jr. Moyobamba En uñas Intersección Ca. Sn. 04 En uñas Intersección Jr. Diego zumba En uñas Intersección Jr. San martin En uñas Intersección Jr. Eleudora Maynas En uñas Intersección Jr. Tupac Amaru En uñas Intersección Jr. Ucayali En uñas Intersección Jr. Manco Capac En uñas Intersección Jr. Eduardo del Aguila En uñas Terminal orilla del lago Yarinacocha En uñas

de elem.

de veces

largo m.

ancho m.

alto m.

PARCIAL

2.00 1.00 1.00 1.00 1.00 1.00 1.00 4.00 1.00 4.00 1.00 2.00 1.00 1.00 1.00 1.00 4.00 1.00 4.00 1.00 4.00 1.00 2.00 1.00 2.00 1.00 3.00 1.00 2.00 1.00 2.00 1.00 4.00 1.00 4.00 1.00 2.00 1.00 4.00 1.00 4.00 1.00 4.00 1.00 4.00 1.00 2.00 1.00

Area 4.80 Area Area Area Area 10.80 Area 7.20 Area 9.60 Area 7.20 Area Area 4.80 Area 14.40 Area 14.40 Area 9.60 Area 2.40 Area 7.20 Area 9.60 Area 4.80 Area 4.80 Area 4.80 Area 9.60 Area 7.20 Area 9.60 Area 9.60 Area 14.40 Area 14.40 Area 4.80

28.27 Area 22.29 25.65 25.54 29.72 Area 28.27 Area 28.27 .Area 28.27 Area 24.95 24.11 Area 28.27 Area 28.27 Area 28.27 Area 28.27 Area 28.27 Area 28.27 Area 28.27 Area 24.92 Area 28.27 Area 28.27 Area 28.27 Area 28.27 Area 21.89 Area 21.89 Area 21.89 Area 28.27 Area

0.10 0.04 0.10 0.10 0.10 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 004 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04 0.10 0.04

5.65 0.19 2.23 2.57 2.55 2.97 0.43 11.31 0.29 11.31 0.38 5.65 0.29 2.50 2.41 0.19 11.31 0.58 11.31 0.58 11.31 0.38 5.65 0.10 5.65 0.29 848 0.38 5.65 0.19 4 98 0.19 11.31 0.19 11.31 0.38 5.65 0.29 11.31 0.38 8 76 0.38 8.76 0.58 8.76 0.58 5.65 0.19

TOTAL

VER EDA MAITT1L JD CONCRETO F C = 1 4 0 K jG¿CM2 ü\ O 025

}

y

-

'



1/

1

* *

J ,

A »

i—

020 L

i—OlO

//



r

¿

A 01.08.02.06

CURADO EN MARTILLOS

01.09

JUNTAS

01 09.01

RELLENO DE JUNTAS ASFALTICAS DE 9 MM

i

JgTJ r //

7

M2

2,168.00

ML

k

f

____—

■”

ir v v u ío S H tü M k

Junta longitudinal tipo 1 Junta contracción tipo 2 Junta contracción tipo 2 en intersección Junta de contracción tipo 4 Jr. 03 de octubre y Jr. Circumvalacion Extremos de pavimento Jr. Circumvalacion lado Izquierdo Extremos de pavimento Jr Circumvalacion - Jr. Ucayali Extremos de pavimento Jr. Ucayali - Jr. Padre Abad Extremos de pavimento Jr. Padre Abad - Psje Orellana Extremos de pavimento Progresiva 0+552.44 - Prog. 0+923.11 Extremos de pavimento Ca. 28 de Noviembre - Ca. 13 de Abril Extremos de pavimento Ca. 13 de Abril - Jr. Gavino muños Extremos de pavimento Jr. Gavino muños - Jr. La Selva Extremos de pavimento Jr. La Selva y psje. Victoria - prog. 1+598.51 Extremos de pavimento Prog. 1+600 - Prog. 1+800 Extremos de pavimento progresiva 1+800 - jr. lima Extremos de pavimento Jr. Ucayali - Jr. Arica Extremos de pavimento Jr. Arica - Jr. Miraflores Extremos de pavimento Jr. Miraflores - Jr. Rioja Extremos de pavimento

34,691.94

•w'

1.00 690.00 33.00

5118.06 10.80 27.60

5,118 06 7.452.00 910.80

2.00

115.13

1.00

36.00

36.00

2.00

130.00

260.00

230.26

2.00

120.84

241.68

2.00

110.37

220.74

2.00

368.60

737.20

2.00

109.74

219.48

2.00

122.27

244.54

2.00

146.03

292.06

2.00

184.04

368.08

2.00

186.48

372.96

2.00

80.85

161.70

2.00

94.57

189.14

2.00

94.48

188.96

89.85

179.70

ñ ¡¿

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA N UND

DESCRIPCION

ITEM

de elem.

IMENSIONES

de veces

Jr. Rioja - Prog. 2+259.58 Extremos de pavimento prog 2+260 - prog. 2+740 Extremos de pavimento Ca. sn 01 - Jr. Ucayali Extremos de pavimento Jr. Ucayali - Jr. miraflores Extremos de pavimento Jr. miraflores - Jr. yurimaguas Extremos de pavimento Jr. yurimaguas - Ca. Sn 02 Extremos de pavimento Ca. Sn 02 - Ca. Sn 03 Extremos de pavimento Ca. Sn 03 - Av. Guillermo Towsend Extremos de pavimento Av. Guillermo Towsend - Jr. moyobamba Extremos de pavimento Jr. moyobamba - Ca. Sn. 04 Extremos de pavimento Ca. Sn. 04 - Jr. Diego Zumba Extremos de pavimento Jr. Diego Zumba - Jr. San Martin Extremos de pavimento Jr. San Martin - Jr. Eleudora Maynas Extremos de pavimento Jr. Eleudora Maynas - Jr. Tupac Amaru Extremos de pavimento Jr. Tupac Amaru - Jr. Ucayali Extremos de pavimento Jr, Ucayali - Jr. Manco Capac Extremos de pavimento Jr. Manco Capac - Jr. Eduardo del Aguila Extremos de pavimento Jr. Eduardo del Aguila - Orillas del lago Extremos de pavimento Junta de contracción tipo 4 en buzón Junta de contracción tipo 4 en Alcantarillas

RELLENO DE JUNTAS ASFALTICAS DE 20 MM

ancho m.

alto m.

TOTAL

PARCIAL

2.00

27.60

55.20

2.00

468.78

937.56

2.00

111.75

223.50

2.00

96.30

192.60

2.00

93.02

186.04

2.00

105.07

210.14

2.00

83.06

166.12

2.00

274.71

549.42 160.82

2.00

80.41

2.00

16.46

32.92

2.00

129.03

258.06

2.00

106.48

2.00

97.75

2.00

94.32

212.96 0.00 195.50 0.00 188.64

2.00

98.58

197.1/*/?”

2.00

94.61

2.00

94.77

2.00 9.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 4.00 1.00

68.00 8.00 26.12 25.88 24.68 24.60 65.60 25.60 24.60 24.60 1112.40 8223.90

j h

W *

Junta de contracción tipo 4 en canaletas techadas Junta de contracción tipo 3 Y 5 01.09.02

largo m.

/D iv is ió n S r n g s V oes i WOUCTji

136W) A 72 0 0 \ v 26.12 25.88 24.68 24.60 65.60 25.60 24.60 24.60 4,449 60 8,223.90

ML

5,862.00

Junta de dilatación tipo 3 Junta de dilatación tipo 3 en intersecciones Junta contra otras estructuras tipo 6 Junta contra otras estructuras tipo 7

307.00 32.00 56.00 56.00

10.80 27.60 10.80 18.90

3,315.60 883.20 604.80 1,058.40

01.09.03

ACERO CORRUGADO (BASTONES EN JUNTAS TIPO 1)

KG.

10,746.17

01.09 04

ACERO LISO (BASTONES EN JUNTAS TIPO 3)

KG.

16,340.18

01.09.05

JUNTAS DE DILATACION C/WATERSTOP

ML

k I

.

1,207.18

Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo Jr. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Padre Abad - Lado Derecho Jr, Ucayali - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje. Orellana - Lado Derecho Jr. Padre Abad - Psje Orellana - Lado Izquierdo Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo Ca. 13 de Abril - Jr. Gavino mufios - Lado Derecho Ca. 13 de Abril - Jr. Gavino mufios - Lado Izquierdo Jr. Gavino mufios - Jr. La Selva - Lado Derecho Jr. Gavino mufios - Jr. La Selva Lado Izquierdo Jr. La Selva y psje Victoria - prog 1 + 415.33 - prog, 1+600 Lado Derecho Jr. La Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo progresiva 1+800 - jr. lima - Lado Derecho progresiva 1+800 - jr. lima - Lado Izquierdo Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. Miraflores - Lado Derecho Jr. Arica - Jr. Miraflores - Lado Izquierdo Jr. Miraflores - Jr Rioja - Lado Derecho Jr. Miraflores - Jr. Rioja - Lado Izquierdo Jr. Rioja - Prog. 2+260 - Lado Derecho Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo Ca. sn 01 - Jr. Ucayali - Lado Derecho Ca. sn 01 - Jr. Ucayal - Lado Izquierdo Jr. Ucayali - Jr. miraflores - Lado Derecho Jr. Ucayali - Jr. miraflores - Lado Izquierdo Jr. miraflores - Jr yurimaguas - Lado Derecho Jr. miraflores - Jr. yurimaguas - Lado Izquierdo Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo Ca. Sn 02 - Ca. Sn 03 - Lado Derecho Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. Guillermo Towsend - Lado Izquierdo

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

t r ñ ü o Rafael Lean INO, CIVIL C IP N* 4 0 *9 4

5

111.50 118.53 125.11 94.11 140.35 122.00 130.96 112.00 368.75 335.67 131.03 87.09 141.22 126.30 172.52 151.14 197.57 183.21 80.85 184.02 95.48 95.48 94.48 94.48 98.76 89.60 33.90 29.95 102.29 108.10 111.31 116.36 96.60 96.60 87.34 96.00 110.30 117.40 83.28 101.98 269.76 240.99

2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00

18.58 19.76 20.85 15.69 23.39 20.33 21.83 18.67 61.46 55.95 21.84 14.52 23.54 21.05 28.75 25.19 32.93 30.54 13.48 30.67 15.91 15.91 15.75 15.75 16.46 14.93 5.65 4.99 17.05 18.02 18.55 19.39 16.10 16.10 14.56 16.00 18.38 19.57 13.88 17.00 44.96 40.16

Página 22

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA IMENSIONES

N° ITEM

DESCRIPCION

Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr moyobamba - Ca. Sn 04 - Lado Derecho Jr. moyobamba - Ca. Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora Maynas - Lado Derecho Jr. San Martin - Jr. Eleudora Maynas - Lado Izquierdo Jr. Eleudora Maynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Manco Capac - Lado Derecho Jr. Ucayali - Jr. Manco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho cuadra 29 Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo

UND

de

de

largo

ancho

alto

elem.

veces

m.

m.

m.

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

80.52 89.93 23.16 26.60 129.77 82.59 106.68 106.68 96.77 110.90 94.53 96.59 98.56 99.14 94.60 94.60 95.20 95.20 68.35 68.35

2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00

PARCIAL

13.42 14.99 3.86 4.43 21.63 13.77 17.78 17.78 16.13 18.48 15.76 16.10 16.43 16.52 15.77 15.77 15.87 15.87 11.39 11.39

TOTAL

(VV H O JA DE M ETR AD O S OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA DíMENSiO

N° UND

DESCRIPCION

ITEM

de

de

largo

ancho

alto

elem.

veces

m.

m.

m.

TOTAL

PARCIAL

01.19

INSTALACIONES ELECTRICAS

01.19.01

SEMAFORO TRIPLE TIPO LEDS 10W

UND

2.00

01.19.02

SEMAFORO CUADRUPLE TIPO LEDS 10W

UND

1.00

01.19.03

POSTE DE F°G° DE 0 6’ X 11MM

UND

3.00

3.00

01.19.04

TABLERO ELECTRICO DE CONTROL AUTOMATICO.

UND

3.00

3.00

01.19.05

MEDIDOR DE ENERGIA MONOFASICO

UND

ZOO |

1.00

3.00

3.00

3.00

20.00

60.00

01 19 06

CONDUCTOR ELECTRICO 2 - 1 X 6 MM2 NYY

ML

01.19.07

ALIMENTADOR AL MEDIDOR DE ENERGIA

ML

3.00

50.00

150.00

01.19.08

CABLE DE ACERO DE 0 5/16“

ML

3.00

50.00

150.00

01.19.09

POZO DE PUESTA ATIERRA

3.00

3.00

01.20

VARIOS

01.20.01

PINTURA ALTO TRAFICO EN PAVIMENTO

KM

01.20.02

PINTURA ALTO TRAFICO EN CRUCE PEATONAL

M2

UND

299.88 1.00 1.00 1.00

01.20.03

SEÑALIZACION VERTICAL

01.20.04

GUARDAVIAS

UND

3.00 10.80

42.00 151.20 106.68

0.50 0.50 3.81

40.00

40.00

75.00 2.00

75.00

37.50

55.00

UND

REJILLA METALICA CON MARCO 0.52 x 0.80 mt. Intersección Jr. Cincurvalacion Intersección Psje. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. La Selva - Psje. Victoria Intersección Jr. Lima - Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. S/N Intersección Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. S/N 3 Intersección Av. GUILLERMO TOWSEND Intersección Av. Moyobamba Intersección Ca. S/N 4 Intersección Jr. San Martin Intersección Jr. Eleodora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. Manco Capac Intersección Jr. Eduardo Del Aguila

I 01.20.06

28.00 28.00 28.00

ML Prog. 1+580- 1+620

01.20.05

4.69

4.69

2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 4.00 4.00 2.00 2.00 4.00 2.00 2.00 2.00 3.00 2.00 2.00 4.00 4.00 UND

TAPAS DE CONCRETO PARA INSPECCION Y LIMPIEZA

\rw

t//$J lY 'í*

tt! ir # W

i ^

J -\. tm jp w

■i l i ^

r f / f > NAO

A 1.00 1.00 1.00 2.00 1.00 2.00 1.00 2.00 3.00 3.00 3.00 2.00 2.00 4.00 4.00 3.00 1.00 2.00 3.00 2.00 2.00 2.00 3.00 2.00 3.00 3.00 4.00 4.00

..

\

66.00

, v

Intersección Jr. Cincurvalacion Intersección Jr. Ucayali Intersección Jr. Padre Abad Intersección Psje. Orellana Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Mufloz Intersección Jr. La Selva - Psje. Victoria Intersección Jr. Lima - Jr. Ucayali Intersección Jr. Arica Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. S/N Intersección Jr. Ucayali Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. S/N 2 Intersección Ca. S/N 3 Intersección Av. GUILLERMO TOWSEND Intersección Av. Moyobamba Intersección Ca. S/N 4 intersección Jr. Diego Zumba Intersección Jr. San Martin Intersección Jr. Eleodora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayal Intersección Jr. Manco Capac Intersección Jr. Eduardo Del Aguila

; . ¡J

2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 4.00 4.00 2.00 2.00 4.00 2.00 2.00 2.00 3.00 2.00 2.00 4.00 4.00

\

i

\

.......

1.00 1.00 1.00 2.00 1.00 2.00 1.00 2.00 3.00 3.00 3.00 2.00 2.00 4.00 4.00 3.00 1.00 2.00 3.00 2.00 2.00 2.00 3.00 2.00 3.00 3.00 4.00 4 00

Página 2

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA IMENSIO m . . .

N° ITEM

01.20.07 01.21

DESCRIPCION

LIMPIEZA FINAL DE OBRA

UND

GLB

de

de

largo

ancho

alto

elem.

veces

m.

m.

m.

PARCIAL

TOTAL

1.00

IMPACTO AMBIENTAL

01.21.01

COSTOS AMBIENTALES DURANTE LA PAVIMENTACION

GLB.

1.00

01.21.02

PRESUPUESTO DEL PROGRAMA DE MONITOREO AMBIENTAL

GLB.

1.00

01.21.03

PRESUPUESTO DEL PROGRAMA DE EDUCACION Y CAPACITACION AMBIENTAL

GLB.

1.00

HOJA DE METRADOS DE ACERO O B R A : MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JO S E DESDE PUERTO C A LLA O DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

DESCRIPCION

de

Total

elem .

Kg.

ACERO DE REFUERZO FY=4.200 KG/CM2 D=3/8- - BERMAS As. Transv.

4.00

As. Longit.

18.33

8 0 3 / 8 " 3 . 9 5 rn L @ .2 5

As.

4.00 5 0 Í 8 - 3.95 mt. @25

128.24

ACERO DE REFUERZO FY=4.200 KG/CM2 D=3W - LOSAS CENTRALES

3.60 37

U> 4 .0 0 8 *

1

Página 2



• HOJA DE METRADOS DE ACERO

O BR A : MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JOSE DESDE PUERTO C A LLA O DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA A cero fy=4,2Q0 Kg/cm2 DESCRIPCION

Total

CANT. P E S O /M L

As. Transv.

01.06.01.03

ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" CANALETAS

A s - lo n g itu d inal É sribos Jr. 03 de octubre - Jr. Circumvalacion - Lado Derecho Jr. 03 de octubre - Jr. Circumvalacion - Lado Izquierdo J r. Circumvalacion - Jr. Ucayali - Lado Derecho Jr. Circumvalacion - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. Padre Abad - Lado Derecho Jr. Ucayali - Jr. Padre Abad - Lado Izquierdo Jr. Padre Abad - Psje. Orellana - Lado Derecho Jr. Padre Abad - Psje. Orellana - Lado Izquierdo Tramo San jóse - Lado Derecho 0+ 552.27 - 0+923.42 Tramo San jóse - Lado Izquierdo 0+ 552.27 - 0+933.02 Ca 28 de Noviembre - Ca. 13 de Abril - Lado Derecho Ca. 28 de Noviembre - Ca. 13 de Abril - Lado Izquierdo Ca. 13 de Abril - J r Gavino muños - Lado Derecho Ca. 13 de Abril - Jr. Gavino muños - Lado Izquierdo Jr. Gavino muños - Jr. La Selva - Lado Derecho Jr. Gavino muños - Jr. La Selva Lado Izquierdo Jr. La Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 Lado Derecho Jr. La Selva y psje. Victoria - prog. 1 + 415.33 - prog. 1+600 - Lado Izquierdo progresiva 1+800 - jr. lima ■ Lado Derecho progresiva 1 +800 - jr. lima - Lado Izquierdo Jr. Ucayali - Jr. Arica - Lado Derecho Jr. Ucayali - Jr. Arica - Lado Izquierdo Jr. Arica - Jr. M iraflores - Lado Derecho Jr. Arica - Jr. M iraflores - Lado Izquierdo

r . . a : ti

i: v.’\

Jr. Miraflores - Jr. Rioja - Lado Derecho Jr. M iraflores - Jr. Rioja - Lado Izquierdo Jr. Rioja - Prog. 2+26Q - Lado Derecho Jr. Rioja - Prog. 2+260 - Lado Izquierdo Prog. 2+640 - Ca. Sn. 01 Lado Derecho Prog. 2+640 -Ca. Sn. Lado Izquierdo Ca. sn 01 - Jr. Ucayali - Lado Derecho

CfP N °40894

Página 3



• HOJA DE METRADOS DE ACERO

O BRA : MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JOSE DESDE PUERTO C A LLA O DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA A cero fy=4,2Q0 Kg/cm2 DESCRIPCION

CANT. P E S O / ML Ca. sn 01 - Jr. Ucayal - Lado Izquierdo Jr. Ucayali - Jr miraflores - Lado Derecho

Jr. Ucayali - Jr. miraflores - Lado Izquierdo Jr. miraflores - Jr. yurimaguas - Lado Derecho Jr. m iraflores - Jr. yurimaguas - Lado Izquierdo Jr. yurimaguas - Ca. Sn 02 - Lado Derecho Jr. yurimaguas - Ca. Sn 02 - Lado Izquierdo Ca. Sn 02 - Ca. Sn 03 - Lado Derecho Ca. Sn 02 - Ca. Sn 03 - Lado Izquierdo Ca. Sn 03 - Av. Guillermo Towsend - Lado Derecho Ca. Sn 03 - Av. GuiHermo Towsend - Lado Izquierdo Av. Guillermo Towsend - Jr. moyobamba - Lado Derecho Av. Guillermo Towsend - Jr. moyobamba- Lado Izquierdo Jr. moyobamba - Ca. Sn. 04 - Lado Derecho Jr. moyobamba - C a . Sn. 04- Lado Izquierdo Ca. Sn. 04 - Jr. Diego Zumba - Lado Derecho Ca. Sn. 04 - Jr. Diego Zumba - Lado Izquierdo Jr. Diego Zumba - Jr. San Martin - Lado Derecho Jr. Diego Zumba - Jr. San Martin - Lado Izquierdo Jr. San Martin - Jr. Eleudora M aynas - Lado Derecho Jr. San M artin - Jr. Eleudora M aynas - Lado Izquierdo Jr. Eleudora M aynas - Jr. Tupac Amaru - Lado Derecho Jr. Eleudora Maynas - Jr. Tupac Amaru- Lado Izquierdo Jr. Tupac Amaru - Jr. Ucayali - Lado Derecho Jr. Tupac Amaru - Jr. Ucayali - Lado Izquierdo Jr. Ucayali - Jr. M anco Capac - Lado Derecho Jr. Ucayali - Jr. M anco Capac - Lado Izquierdo Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Derecho Jr. Manco Capac - Jr. Eduardo del Aguila - Lado Izquierdo cuadra 29

Jr. Eduardo del Aguila - Orillas del lago - Lado Derecho

cuadra 29

Jr. Eduardo del Aguila - Orillas del lago - Lado Izquierdo

AS LONG. 0 3/8~® -20

BERMA

ARMADURA CANALETA ABIERTA

01.0S.02.03 ' ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" TECHADA

26,696.99

As longitudinal en losa superior

Jr. Circumvalacion - Jr. Iparia - Lado Izquierdo Jr. Ucayali - Lado Izquierdo Jr. Padre Abad - Lado Izquierdo Psje. Orellana - Lado Izquierdo Ca. 28 de Noviembre - Lado Izquierdo

Página 4

HOJA DE METRADOS DE ACERO O BRA : MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JO SE DESDE PUERTO C A LLA O DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA Acero fy=4,2Q0 Kg/cm2 T o tal

CANT.

DESCRIPCION

Kg. Ca. 13 de Abril - Lado Izquierdo Jr. G avino Munos - Lado Izquierdo Jr. La Selva y psje. Victoria - Lado Izquierdo

_92.30

intersección Jr. Ucayali - Jr. Lima - Lado Izq. Y Derecho Jr. Arica - Lado Izquierdo Jr. m iraflores - Lado Derecho

369.18

Jr. m iraflores - Lado Izquierdo Jr. Rioja - Lado Izquierdo Ca. Sn 01 - Lado derecho

449.61

Jr. Ucayali - Lado Izquierdo Jr. M iraflores - Lado derecho

675.07 675.07 675.07

Jr. Ucayali - Lado derecho

Jr. M iraflores - Lado Izquierdo

675.07

Jr. Yurimaguas - Lado derecho

675.07

Jr. Yurimaguas - Lado Izquierdo Ca. Sn 0 2 - Lado derecho

184.59

Ca. Sn 0 3 - Lado derecho Av. GuiHermo Towsend - Lado derecho 1,842.47

Av. Guillermo Towsend - Lado Izquierdo Jr. Moyobamba - Lado Derecho C3 Sn 04 - Av. Belisario Panduro - Lado Izquierdo Jr. Diego Zumba - Lado Izquierdo Jr. San Martin - Lado Derecho Jr. m iraflores - Lado Izquierdo Jr. Eleudora M aynas - Lado Derecho Jr. Tupac Amaru Jr. Ucayali - Lado derecho Jr. Ucayali - Izquierdo Jr. Manco Capac - Lado Derecho Jr. Manco C apac - Lado Izquierdo

675.07

Jr. Edgardo del Aguila - Lado Derecho Jr. eduardo del Aguila - Lado Izquierdo Terminal Orilla del lago Yarina C ocha - lado derecho

137.12

Terminal Orilla del lago Yarina Cocha - lado Izquierdo C analetas te c h a d a s e n in g re s o s Jr. Iparia - Jr. Ucayali - Lado Derecho

395.55

Psje. Orellana - prog. 0 + 6 0 0 - Lado Derecho Prog. 0+880 - Ca. 28 de Noviembre - Lado Derecho Prog. 1 + 2 0 0 - Prog. 1+240 Jr. Bsudora M aynas - Lado Izquierdo

290.07

MALLA 0 1 £ -< U O

0.075

MALLA 03/8"®-20

ARMADURA CANALETA TECHADA •t r a

g

a

r

Página 5

HOJA DE METRADOS DE ACERO OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

DESCRIPCÍON

de etem.

CANT.

ACERO DE REFUERZO FY=4200 KG/CM2 D=3/8" SARDINEL

BERMA

HA11A0 3JB‘ Q 2b

DETALLE ARMADURA SARDINEL H=0.75 mt ACERO DE REFUERZO F'Y 4,200 KG/CM2 MURO DE CONTECION

S.10 70.69

&

1/ 2" @ 0.20

CORTE ESTRUCTURAL

Página S





Página 7

HOJA DE METRADOS DE ACERO OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JO SE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA A cero fy=4,2Q0 Kg/cm2 CANT.

DESCRIPCION

P E S O / ML

Extremos de pavimento Eje de pavimento (calzada y berma) Jr. La Selva y psje. Victoria - prog. 1+598.51 Extremos de pavimento Eje de pavimento (caízada y berma) Prog. 1 + 6 0 0 - Prog. 1+800 Extremos de pavimento Eje de pavimento (calzada y berma) progresiva 1+800 - jr. lima Extremos de pavimento Eje de pavimento (calzada y berma) Jr. Ucayali - Jr. Arica Extremos de pavimento Eje de pavimento (calzada y berma) Jr. Arica - Jr, M iraflores Extremos de pavimento Eje de pavimento (calzada y berma) Jr. M iraflores - Jr. Rioja Extremos de pavimento Eje de pavimento (calzada y berma) Extremos de pavimento Eje de pavimento (calzada y berma) prog. 2+260 - prog. 2+740 Extremos de pavimento Eje de pavimento (calzada y berma) Ca. sn 01 - Jr. Ucayali Extremos de pavimento Eje de pavimento (calzada y berma)! Jr. Ucayali - Jr. m iraflores Extremos de pavimento Eje de pavimento (calzada y berm a); J r. miraflores - Jr. yurimaguas Extremos de pavimento Eje de pavimento (calzada y berma) Jr. yurimaguas - Ca. Sn 02 Extremos de pavimento Eje de pavimento (calzada y berma) Extremos de pavimento Eje de pavim ento (calzada y berma) Ca. Sn 03 - Av. Guillermo Towsend Extremos de pavim ento Eje de pavimento (calzada y berma) Av. Guillermo Tow send - Jr. moyobamba Extremos de pavimento Eje de pavimento (calzada y berma) Jr. moyobamba - Ca. Sn. 04 Extremos de pavimento Eje de pavimento (calzada y berma)

I I I I II I I I I

Ca. Sn. 04 - Jr. Diego Zumba Extremos de pavimento Eje de pavimento (calzada y berm a): Jr. Diego Zumba - Jr. San Martin [ Extremos de pavimento Eje de pavimento (calzada y berma) Jr. San Martin - Jr. Eleudora Maynas Extremos de pavimento Eje de pavimento (c alzada y berma) Jr. Eleudora M aynas - Jr. Tupac Amaru Extremos de pavim ento Eje de pavimento (calzada y berma) | Jr. Tupac Amaru - Jr. Ucayali j Extremos de pavim ento Eje de pavimento (calzada y berma)]

w o . c n /tL

Página 8



• HOJA DE METRADOS DE ACERO

O BRA : MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JO S E DESDE PUERTO C A LLA O DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA N° Item

UND

DESCRIPCION

A cero fy=4,2Q0 Kg/cm2

de

de

elem.

v e ce s

0

CANT.

Long.

3 /8 "

|

1/2”

T o ta l

5/8"

l

r

1.58

|

4.04

PESO / ML

( M ts ) 0 .58

l

1.02

Kg-

Jr. Ucayali - Jr. Manco Capac Extremos de pavimento Eje de pavimento (calzada y berma) Jr. M anco Capac - Jr. Eduardo del Aguila

2.00 1.00

94.61

Extremos de pavimento Eje de pavimento (calzada y berma)

2.00

94.77

94.61

236.53 118.26 ' 236.93 118.46

1.00

94.77

Extremos de pavimento Eje de pavimento (calzada y berma)

2.00 1.00

68.00 72.50

170.00

intersección Jr. Circunvalación

1.00 1.00 1.00

32.83 43.80

41.04 54.75

43.80

54.75

43.80 41.40

54.75 51.75

Jr. Eduardo del Aguila - Orillas del lago

intersección Jr. Ucayali Intersección Jr. Padre Abad Intersección Psj. Orellana j

1.00 1.00 1.00

Intersección Ca. 28 de Noviembre Intersección Ca. 13 de Abril Intersección Jr. Gavino Muftos Intersección Jr. La Selva

1.00 1.00 1.00 1.00

Intersección Jr. Ucayali y Jr. Lima Intersección Jr. Arica Intersección Jr. Miraflores Intersección Jr. Rioja Intersección Ca. Sn. 01 Intersección Jr. Ucayali

1.00 1.00 1.00 1.00 1.00 1.00

Intersección Jr. Miraflores Intersección Jr. Yurimaguas Intersección Ca. Sn. 02

1.00 1.00 1.00 1.00

Intersección Ca. Sn. 03 Intersección Av. Guillermo Towsend Intersección Jr. Moyobamba Intersección Ca. Sn. 04

1.00 1.00 1.00

Intersección Jr. Diego zumba Intersección Jr. San martin

_____-

Intersección Jr. Eleudora Maynas Intersección Jr. Tupac Amaru Intersección Jr. Ucayali Intersección Jr. M anco Capac Intersección Jr. Eduardo del Aguila Intersección Terminal orilla del lago yarina cocha

-------------------------

42.60

53.25

106.80 55.80

133.50 69.75 87.13 84.00

' 69.70 67,20 64.20 55.60 64.20

.

I

1.00

64.20 65.40

1.00 1.00 1.00

64.20 64.20 63.00

1.00 1.00

63.00

81.75 80.25 80.25 78.75 78.75 5.63 17,559.10

4.50

_____

J

............. Gt* A C m / n

16,340.18

~t — r

12.00

54.54 43.63

0.45 0.45

54.54

490.86

1.00

54.54

54.54

Transversales (calzada y berma))

10.00

54.54

545.40

Jr. Ucayali - Jr. Padre Abad Transversales (calzada y berma)

9.00

54.54

490.86

8.00

54.54

436.32

\

29.00

54.54

/

7.00

54.54

10.00

54.54

11.00

54.54

599.94

I 1 P¿n “ * * 15.00 • u t V f L ) ..................

54.54

818.10

--------------

Jr. Padre Abad - Psje. Orellana Transversales (calzada y berma) Progresiva 0+552.44 - Prog. 0+923.11

y

Transversales (calzada y berma) 28 de Noviembre - Ca. 13 de Abril

---- - r

Transversales (calzada y berma) .

15.00

1" 1”

9.00

qa

¡ /

10,746.17

10,746.17

Jr. Circumvalacion lado Izquierdo | Transversales (calzada y berma) j

/

[7

0.60

KG.

Jr. Circumvalacion - Jr. Ucayali i

f b f a r O M 'H t á f ü f c ^

69.38 81.75 80.25

Jr. 03 de octubre - Jr. Circumvalacion I Transversales (calzada y berma) ?

_____ _____

2Y r

75.00 81.00 75.00

64.80 60.00 55.50 65.40

2.00 2.00

/

80.25 78.75 138.68 78.75

63.00 110.94 63.00 60.00

1/2"

ACERO LISO (BASTONES EN JUNTAS TIPO 3)

C o n s o c io /

80.25 72.54 69.50

r 58.03

SUMANADO LOS PARCIALES 01.09.05

90.63

Transversales (calzada y berma) Je Gavino muños - Jr. La Selva Transversales (calzada y berma) Jr. La Selva y psje. Victoria - prog. 1+598.51 Transversales (calzada y berma) Prog. 1 + 6 0 0 - Prog. 1+800

= = = = =

* i

f

iK ^ a r é r

Iiw /4 l^ ÍJ

1,581.66

m



cS

~P \ \

i v

s J

f J f

381.78 545.40

Página 9



• HOJA DE METRADOS DE ACERO

OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICAION: DIST. DE YARINACOCHA. CORONEL PORTILLO, DPTO, UCAYALI PROPIET : MUNICIPALIDAD DISTRITAL DE YARINACOCHA A cero fy=4,200 Kg/cm2

N° Item

DESCRIPCION

UND

de

de

etem.

veces

0

CANT.

1«"

Long. 0.58

Transversales (calzada y berma) progresiva 1 + 800- jr. lima Transversales (calzada y berma) Jr. Ucayali - Jr. Arica Transversales (calzada y berma) Jr. Arica - Jr. Miraflores Transversales (calzada y berma)

5tó"

r

1.68

4.04

1.02

Total Kg.

P E S O /M L

(M ts )

14.00

43.63

610.85

7.00

54.54

381.78

7.00

54.54

381.78

7.00

54.54

381.78

Jr. M iraflores - Jr. Rioja Transversales (calzada y berma) Jr. Rioja - Prog. 2+259.58

7.00

54.54

381.78

Transversales (calzada y berma)

2.00

54.54

109.08

prog. 2+260 - prog. 2+741.95 Transversales (calzada y berma)

38.00

43.63

1,658.02

Ca. sn 01 - Jr. Ucayali Transversales (calzada y berma)

8.00

54.54

436.32

Jr. Ucayali - Jr. miraflores Transversales (calzada y berma)

7.00

54.54

381.78

Jr. miraflores - Jr. yurimaguas Transversales (calzada y berma)

6.00

54.54

327.24

8.00

54.54

436.32

Jr. yurimaguas - Ca. Sn 02 Transversales (calzada y berma) Ca. Sn 02 - Ca. Sn 03

5.00

54.54

272.70

Transversales (calzada y berma)

22.00

54.54

1,199.88

Av. Guillermo Towsend - Jr. moyobamba Transversales (calzada y berma)

6.00

54.54

327.24

Transversales (calzada y berma)

2.00

54.54

109.08

Ca. Sn. 04 - Jr. Diego Zumba Transversales (calzada y berma)

9.00

54.54

490.86

Transversales (calzada y berma) Ca. Sn 03 - Av. Guillermo Towsend

Jr. moyobamba - Ca. Sn. 04

Jr. Diego Zumba - Jr. San Martin Transversales (calzada y berma)

6.00

54.54

327.24

Transversales (calzada y berma)

7.00

54.54

381.78

Jr. Eleudora Maynas - Jr. Tupac Amaru Transversales (calzada y berma)

7.00

54.54

381.78

7.00

54.54

381.78

7.00

54.54

381.78

Jr. San Martin - Jr. Eleudora Maynas

Jr. Tupac Amaru - Jr. Ucayali Transversales (calzada y berma) Jr. Ucayali - Jr. M anco Capac Transversales (calzada y berma) Jr. Manco C apac - Jr. Eduardo del Aguila Transversales (calzada y berma)

7.00

54.54

381.78

Jr. Eduardo del Aguila - Orillas del lago Transversales (calzada y berma)

5.00

54.54

272.70

H O JA D E M E TR A D O S OBRA : M EJORAMIE NTO DE V IA DE INTERCONEXION A L C.P. SAN JOSE DESDE PUERTO C ALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - U C AYALI UBICACIO N: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : M UNIC IP ALID AD DISTRITAL DE YARINACOCHA

03 03.01 03.01.01 03.01.01.01

largo

ancho

m.

m

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595.61 668.31 2,341 88 275.64

595.61 668.31 2,341 88 275.64

1.00 1.00 1.00 1.00

1 00 1.00 1.00 1.00

595.61 668.31 2,341.88 275.64

595.61 668.31 2,341.88 275.64

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595.61 668.31 2,341.88 275.64

595.61 668.31 2.341.88 275.64

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595.61 668.31 2.341 88 275.64

595.61 66831 2.341 88 275.64

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595.61 668 31 2,341 88 275.64

595.61 668 31 2.341 88 27564

1.00 1.00 1.00 1.00

1.30 1.30 1.30 1.30

595.61 668.31 I 2.341 88 275 64

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595 61 66831 2.341 88 275.64

595 61 668.31 2.341 88 27564

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

595.61 668.31 2,341.88 275.64

595.61 668.31 2.341.88 275.64

8.00 15.00

152.00 240 00

TOTAL

3,881.44

MOVIM IENTO DE TIERRAS

3,881.44

m Tramo 1- C.P. San Pablo de Tushmo Tramo I! - AA.HH. Interculturai La Nueva Era Tramo !!! - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Caserío San Lorenzo - C.P. San José (transversal)

03.01.01.02.02 REFINE Y NIVELACION COMPACTADO MANUAL

3,881.44

m Tramo I - C.P. San Pablo de Tushmo Tramo !l - AA.HH. Interculturai La Nueva Era Tramo IH- Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Caserío San Lorenzo - C.P. San José (transversal)

03.01.01.02.03 CAMA DE ARENA SELECTA E=0.30

3,881.44

m Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo M Caserío San Lorenzo - C.P. San José (transversal)

03.01.01.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

'

3,881.44

m Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Caserío San Lorenzo - C P. San José (transversal)

03.01.01.02.05 ^ELIMINACION DE MATERIAL EXCEDENTE

908.26

m3 Tramo I - CP. San Pablo de Tushmo Tramo II - AA.HH. Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Caserío San Lorenzo - CP. San José (transversal)

0.60 0.60 0.60 060

0.30 0.30 0.30 0.30

139.37 156.38 548 00 64 50

IN STALACIO N DE TUBERIAS

03.01.01.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS PVC UF ACCESORIOS DE PVC DIAM. 110 MM S-13.3 ISO 4422 RED MATRIZ INC. ANILLO Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Casorio San Lorenzo - C.P. San José (transversal)

3,881.44

m

PRUEBAS HID RAULIC AS

03.01.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION

3,881.44

m Tramo 1- C.P. San Pablo de Tushmo Tramo II - AA.HH. Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo «i - Caserío San Lorenzo - C.P. San José (transversal)

---------------------

03.01.01.OS

PARCIAL

m

03.01.01.02.01 EXCAVACION DE ZANJA DE 0.6 x 1.20 M.

03.01.01.04

atto m

SISTEMA DE AG UA POTABLE REDES DE AGUA TRABAJOS PRELIM IN ARES

Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José (longitudinal) Tramo III - Caserío San Lorenzo - C.P. San José (transversal)

03.01.01.03

................

........ de veces

SANEAMIENTO

03.01.01 01 01 TRAZO, NIVELES Y REPLANTEO DE REDES

03.01.01.02

HWENSiOl

de etem

w

UND

DESCRIPCION

ITEM

CONEXIONES DOMIICILIARAS

03.01.01.06.01 EXCAVACIÓN DE ZANJA C/EO. P/AGUA TUB. CONEX. DOM. TN. A=0.40CM

1,508.00

m Tramo 1- C.P. San Pablo de Tushmo Cortas Largas Tramo II - AA.HH. Interculturai Lo Nueva Era Cortas Tramo III - Caserío San Lorenzo - C.P. San José Cortas Largas

03.01.01.05.02 PERFILADO Y NIVELADO DE ZANJAS

19.00 16.00 26.00

8.00

208.00

76.00 20.00

8.00 15.00

608.00 300.00

19.00 16.00

8.00 15.00

152.00 240.00

26.00

8.00

208 00

76.00 20.00

8.00 15.00

608.00 300 00

19.00 16.00

8.00 15.00

152.00 240 00

1,508.00

ML Tramo 1- C.P. San Pablo de Tushmo Cortas Largas Tramo II - AA.HH. interculturai La Nueva Era Cortas Tramo III - Caserío San Lorenzo - C.P San José Cortas Largas

03.01.01.05.03 RELLENO DE CAMA DE FONDO CON ARENA E=0.30 M

1,508.00

ML Tramo 1- C.P. San Pablo de Tushmo Cortas Largas Tramo II - AA.HH. Interculturai La Nueva Era Cortas Tramo III - Caserío San Lorenzo - C.P. San José Cortas Largas

03 01 01 05 04 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO MANUAL

26.00

8.00

208.00

76.00 20.00

8.00 15.00

608.00 300.00

19.00 16.00

8.00 15.00

152.00 240.00

1,508.00

ML Tramo 1- C.P. San Pablo de Tushmo Cortas Largas Tramo II - AA.HH. Interculturai La Nueva Era Cortas Tramo lii - Caserío San Lorenzo - C.P. San José Cortas Largas

03.01.01.05.05 CONEXION DOMICILIARIA DE AGUA -CORTA (1/7*110 mm)

26.00

-------------

76.00 20.00

8.00

208.00

8.00 15.00

608.00 300.00

und Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. Interculturai La Nueva Era Tramo III - Caserío San Lorenzo - C.P San José

19.00 26 00 76 00

CIP N° 40894

19.00 2600 7600

| f ¡ '

121.00

Página 2

H O JA DE M ETR AD O S OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA

Tramo I - C.P. San Pablo de Tushmo Tramo III - Caserío San Lorenzo - C.P. San José

elem.

veces

ancho m.

TO .

PARCIAL

Tramo I - CP. San Pablo de Tushmo Cortas Largas Tramo II - AA.HH. intercultural La Nueva Era Cortas Tramo III - Caserio San Lorenzo - C.P. San José Cortas Largas

36.00

1,508.00 19 00 16.00

8.00 15.00

152.00 240.00

26.00

8.00

208.00

76.00 20.00

8.00 15.00

608.00 300.00

235.25

m3

03.01.01.05.08 ELIMINACION DE MATERIAL EXCEDENTE Tramo I - C.P. San Pablo de Tushmo Cortas Largas Tramo H- AA.HH. Intercultural La Nueva Era Cortas Tramo III - Caserio San Lorenzo - C.P. San José Cortas Largas 03.01.01.06 ACCESORIOS , VALVULAS SUMINISTRO E INSTALACION 03.01 01 06 01 EXCAVACION DE ZANJA MANUAL

19.00 16.00

1.30 1.30

8.00 15.00

0.40 0.40

0.30 0.30

23.71 37.44

26.00

1.30

8.00

0.40

0.30

32.45

76.00 20.00

1.30 1.30

8.00 15.00

0.40 0.40

0.30 0.30

94.85 46.80

1.10 1.10 1.10

1.10 1.10 1.10

1.40 1.40 1.40

6.78 3.39 60.98

71.15

m.3 Tramo 1- C.P. San Pablo de Tushmo Tramo II - AA.HH. Inlercuttural La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José

4.00 2.00 36.00

42.00

und

M i 01 01.06 .02 INSTALACION DE VALVULA DE COMPUERTA F<* F° 110 MM Tramo I - C.P San Pablo de Tushmo Tramo II - AA.HH Intercultural La Nueva Era Tramo III - Caserio San Lorenzo - C.P. San José 03.01.01.06.03 SUM. E INST. DE CODO PVC UF 0 110 mm. DE 45*

4.00 2.00 36.00

400 2.00 36.00

4.00 6.00

4.00 6.00

3.00 3.00 12 00

300 3.00 12.00

9.00 7.00 27.00

9.00 7.00 27.00

1.00

1.00

2.00 8.00

2.00 8.00

1.00 4.00

1.00 4.00

4.00 2.00 36.00

4.00 200 36.00

4.00 2.00 36.00

4.00 2.00 36 00

10.00

und Tramo y - AA.HH íniercuilural La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José

03.01.01.06.04 SUMINISTRO E INSTALACION DE TEE FF TIPO LUFLEX ISO 7259 110 MM.

18.00

und Tramo I - C.P. San Pablo de Tushmo Tramo H- AA.HH. Intercultural La Nueva Era Tramo III - Caserio San Lorenzo - C.P. San José

03.01.01.06.05 SUMINISTRO E INSTALACION DE TAPON PVC UF DIAM. 110 MM.

43.00

und Tramo I - C P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo ni - Caserío San Lorenzo - C.P. San José

03.01.01.06.06 SUM. E INST. DE CODO PVC UF 0 110 mm. DE 90*

1.00

und Tramo III - Caserio San Lorenzo - C.P. San José

03.01.01.06.07 SUM. E INST. DE CRUZ PVC UF 0 110 mm.

8.00

und Tramo I - C.P. San Pablo de Tushmo Tramo ¡H- Csssrio Ssn Lorenzo - C.P. San Josa

03.01.01.06.08 GRIFO CONTRA INCENDIO F T TIPO POSTE DE 2 BOCAS

5.00

und Tramo 1- C.P. San Pablo de Tushmo Tramo III - Caserio San Lorenzo - C.P. San José

03.01.01.06.09 CAJA DE C°A° FC=210 KG/CM2 PROTECCION DE VALVULA COMPUERTA

42.00

und Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. intercultural La Nueva Era Tramo III - Caserío San Lorenzo - C.P. San José

03.01.01.06.10 DADO DE CONCRETO FC=140 KG/CM2

42.00

und Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. interculturat La Nueva Era Tramo ili - Caserio San Lorenzo - C.P. San José

03.01.01.06.11 ELIMINACION DE MATERIAL EXCEDENTE

92.48

m3 Tramo I - CP. San Pablo de Tushmo Tramo II - AA.HH. ¡ntsrcuttura} La Nueva Era Tramo fíi - Caserio San Lorenzo - C.P. San José

TOTAL

16.00 20.00

16.00 20.00

ML

03.01.01.05.07 PRUEBA HIDRAULICA Y DESINFECCION

03.02 03.02.01 03.02.01.01 03.02.01.01.01

de

und

03.01 01.05 06 CONEXION DOMICILIARIA DE AGUA - LARGA (1/2*x110 mm)

r

de

-t

IMÉNSiO UNO

DESCRIPCION

ITEM

4.00 2.00 36.00

1.30 1.30 1.30

1.10 1.10 1.10

1.10 1.10 1.10

1.40 1.40 1.40

8.81 4.40 792 8

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

523.70 696.57 654.07 894.71

523.70 696.57 654.07 894.71

1.00 1.00 1.00 1.00

2.00 1.00 1.00 1.00 1.00

37.50 523.70 696.57 654.07 894.71

750 0 523.70 696.57 654.07 894.71

1.00 1.00 1.00 1.00

1 00 1.00 1.00 1.00

523.70 696.57 654.07 894.71

5237 0 696.57 654 07 894.71

SISTEMA DE ALCANTARILLADO REDES DE DESAGÜE TR ABAJO S PRELIM INARES

TRAZO. NIVELES Y REPLANTEO DE REDES

m Tramo 1- C.P. San Pabio de Tushmo Tramo H- AA.HH. Intercultural La Nueva Era Tramo ¡II - Caserio San Lorenzo Tramo Hl - C.P. San José

03.02.01.02 MOVIM IENTO DE TIERRAS 03.02.01.02.01 EXCAVACION DE ZANJA DE 0.8 X 1.60 - 2.60 M.

2.769.05

75.00 m Tramo l- CP. San Pablo de Tushmo Tramo II - AA.HH Intercultural La Nueva Era Tramo III - Caserio San Lorenzo Tramo Ili - C.P. San José

03.02.01.02.02 REFINE Y NIVELACION DE ZANJAS

2,769.05

m Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. intercultural La Nueva Era Tramo III - Caserio San Lorenzo Tramo III - C.P. San José

Página 3

H O JA DE M E TR A D O S OBRA : M EJORAMIE NTO DE V IA DE INTERCONEXION A L C.P. SAN JOSE D ESDE PUERTO C ALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - U C AYALI UBICACIO N: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : M UNIC IP ALID AD D ISTRITAL DE YARINACOCHA

V i «VJÉNSíO UND

DESCRIPCfON

ITEM

de etem.

ÜÜR® vertía

largo

ancho

m

m.

iS É I I I S «v

PARCIAL

TOTAL

' * m

03 02 01 02 03 CAMA DE ARENA SELECTA E= 0.20 Tramo ! - C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserio San Lorenzo Tramo ili - C.P. San José

1.00 1.00 1,00 1.00

523.70 696.57 654.07 894.71

.............. 523.70 696.57 654.07 894.71

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

523.70 696.57 654.07 894.71

523.70 696.57 654.07 894,71

Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserio San Lorenzo Tramo III - C.P. San José

1.00 1.00 1.00 1.00

1.30 1.30 1.30 1.30

523.70 696.57 654.07 894.71

1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00

523.70 696.57 654.07 894.71

1.00 37.00 2.00 1.00 3.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

1.00 1,00 1.00 1.00 1.00 1.00 1.00 1.00 Í . 00 1.00 1.00 1.00

Area Area Area Area Area Area Area Area Area Area Area Area

1.00

1.00

1.00

5.00 11.00 10.00 11.00

í.ó o 1.00 1,00 1.00

5.00 11.00 10.00 11.00

1.00 1.00

1.00 1.00

1.00 1.00

1.00

1.00

1.00

1.00 1.00 1.00

1.00 1.00 1.00

1.00 1.00 1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00 37.00 2 00 1.00 3.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

Area Area Area Area Area Area Area Area Area Area Area Area

1.00 1.00 1.00

1.00 1.00 1.00 00

523.70 696.57 654.07

4,607.70

m3

03.02.01.02.05 ELIMINACION DE MATERIAL EXCEDENTE Tramo I - C.P. San Pablo de Tushmc Tramo II - AA.HH. Intarcultura! La Nueva Era Trame III - Caserío San Lorenzo Tramo III- C.P. San José 03.02.01.03 IN STALACION DE TUBERIA S 03.02.01.03.01 SUMINISTRO Y COLOCACION DE TUBERIA PVC D1AM. 200 MM. S25 UF - KM

0.80 0.80 0.80 0.80

1.60 1.60 1.60 1.60

871,44 1,158.09 1.088.37 1,488.80

2,769,05

m Tramo I - C.P. San Pablo de Tushmo Tramo il - AA.HH. intercuitural La Nueva Era Tramo III - Caserio San Lorenzo Tramo ¡II - C.P. San José

03.02.01.04 BUZONES 03.02.01.04.01 EXCAVACION DE ZANJA DE BUZONES

523.70 696.57 654.07 894.71

78.S4

m3 Buzón H= 1.00 M, D= 1.20 m Buzón H= 1.20 M. D= 1.20 m Buzón H= 1.30 M, D= 1.20 m Buzón H= 1.40 M. D= 1.20 m Buzón H= 1.50 M. D= 1.20 m Buzón H= 1.60 M, D= 1.20 m Buzón H= 1.80 M, D= 1.20 m Buzón H= 2.00 M. D= 1.20 m Buzón H= 2.30 M, D= 1.20 m Buzón H= 2.40 M. D= 1.20 m Buzón H= 2.80 M,D=1.20m Buzón H= 3.00 M. D= 1.20 m

03.02.01.04.02 BUZON DE CONCRETO ARMADO. H= 1.00 M. D= 1.20 M. INC. TAPA DE C'A", MARCO F°F°

1.13 1.13 1.13 1 13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13

1.00 1.20 1.30 1.40 1.50 1.60 1.80 2.00 2.30 2.40 2.80 3.00

1.13 50.21 2.94 1.58 5.09 1.81 2.04 2.26 2.60 2.71 3.17 3.39 1.00

uncí Tramo I - C.P. San Pablo de Tushmo

03.02.01.04.03 BUZON DE CONCRETO ARMADO. H= 1.20 M. D= 1.20 M. INC. TAPA DE C°A“. MARCO F°F°

und Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. intercultural La Nueva Era Tramo III - Caserio San Lorenzo Tramo III - C.P. San José

03.02.01.04.04 BUZON DE CONCRETO ARMADO. H= 1.30 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

37.00

200

und Tramo I - C.P. San Pablo de Tushmo Tramo Id - C.P. San José

03.02.01.04.05 BUZON DE CONCRETO ARMADO. H= 1.40 M. D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

und Tramo i - C.P. San Pablo de Tushmo

03.02.01.04.06 BUZON DE CONCRETO ARMADO, H= 1.50 M. D= 1.20 M. INC. TAPA DE C°A°, MARCO F0F0

1.00

und Tramo I - CP. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - C.P. San José

03.02.01.04.07 BUZON DE CONCRETO ARMADO, H= 1.60 M, D= 1,20 M. INC, TAPA DE C°A°, MARCO F“F°

3.00

und Tramo III - Caserio San Lorenzo

03.02.01.04.08 BUZON DE CONCRETO ARMADO. H= 1.80 M. D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F3

............ 1;p0

1.00

ur.d Tramo í - C.P. San Pablo de Tushmo

03.02.01.04.09 BUZON DE CONCRETO ARMADO. H= 2.00 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

und Tramo III - CP. San José

Lfi3.02.01.04.10 BUZON DE CONCRETO ARMADO. H= 2.30 M, D= 1.20 M. INC. TAPA DE C°A\ MARCO F°F°

1.00

und Tramo 8 • AA.HH. Intercuttural La Nueva Era

BUZON DE CONCRETO ARMADO, H= 2.40 M. D= 1.20 M. INC. TAPA DE C°A°. MARCO F°F°

1.00

und Tramo III - CP. San José

03.02.01.04.12 BUZON DE CONCRETO ARMADO, H= 2.80 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO F°F°

1.00

und Tramo H- AA.HH. Intercultural La Nueva Era

03.02.01.04.13 BUZON DE CONCRETO ARMADO, H= 3.00 M. D= 1.20 M. INC. TAPA DE C°A\ MARCO F°F°

................. 1.00

und Tramo III - C.P. San José

03.02.01.04.14 ELIMINACION DE MATERIAL EXCEDENTE

1.00

m3 Buzón H*» 1.00 M, D= 1.20 m Buzón H= 1.20 M, D= 1.20 m Buzón H= 1.30 M, D= 1.20 m Buzón H= 1.40 M. D= 1.20 m Buzón H= 1.50 M,D= 1.20 m Buzón H= 1.60 M, D= 1.20 m Buzón H= 1.80 M, D= 1.20 m Buzón H= 2.00 M, D= 1.20 m Buzón H= 2.30 M. D= 1.20 m Buzón H= 2.40 M. D= 1.20 m Buzón H= 2.80 M, D= 1.20 m Buzón H= 3.00 M. D - 1.20 m

03.02.01.06 PRUEBAS HID RAULIC AS 03.02.01.06.01 PRUEBA DE REDES

78.94 1 13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13

1.00 1.20 1.30 1.40 1.50 1.60 1.80 2.00 2.30 2.40 2.80 3.00

1.13 50.21 2.94 1.58 5.09 1.81 2.04 2.26 2.60 2.71 3.17 3.39

2,769.05

m Tramo I - CP. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo 111- Caserio San Lorenzo

2,763.05

2,769.05

m

03.02.01.02.04 RELLENO COMPACTADO ZANJA 0 .80 M . X (1.60 - 2.60M)

1^3.02.01.04.11

1.00 1.00 1,00 1.00

.. ...)

523.70 696.57 654.07

Página 4

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA N* ÍTEM

DESCRIPCION

UNO

de

targo

ancho

alto

m.

m.

ro.

36.00 25.00 0.00 53 00

1.00 1.00 1.00

1 00

12.00 12.00 12.00 12.00

432.00 300.00 0.00 636.00

36.00

25.00 0.00 53.00

1.00 1.00 1.00 1.00

12.00 12.00 12.00 12.00

432.00 300.00 0.00 636.00

36.00 25.00 0.00

1.00 1.00 1.00

12.00 12.00 12.00

432.00

53.00

1.00

12.00

36.00 25.00 0.00 53.00

1.00 1.00 1.00 1.00

12.00 12.00 12.00 12.00

36.00 25.00 0.00 53.00

1.00 1.00 1.00 1.00

36.00 25.00 0.00 53.00

36 00~ 25.00 0.00 53.00

1.00 1.00 1.00 1.00

36.00 25.00 0.00 53.00

36.00 25.00 0.00 53.00

1.00 1.00 1.00 1.00

12.00 12.00 12.00 12.00

36.00 25.00 000 53.00

1.30 1.30 1.30 1.30

12.00 12.00 12.00 12.00

etem. 03.02.01.07 CONEXIONES DOMICILIARAS 03.02.01.07.01 EXCAVACIÓN DE ZANJA CON EQUIPO

PARCIAL

TOTAL

m Tramo I - C.P. San Pablo de Tushmo Tramo H- AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo lil - C.P. San José

03.02.01.07.02 PERFILADO Y NIVELADO DE ZANJAS

1,368.00

ML Tramo I - C.P. San Pablo de Tushmo Tramo 1! - AA.HH. Intercultural La Nueva Era Tramo III- Caserío San Lorenzo Tramo III - C.P. San José

03.02.01.07.03 RELLENO DE CAMA DE FONDO CON ARENA E=0.30 M

-------------------

UtMÉMSlONfcS

de veces

1,368.00

MI Tramo 1- C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo III - C.P. San José

03.02.01.07.04 RELLENO Y COMPACTADO CON MATERIAL PROPIO

1.388.00

300.00 0.00 ----------------------

636.00

m Tramo 1- C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo III - C.P. San José

03 02.01.07.05 CONEXIÓN DOMICILIARIA DE DESAGÜE TUB. PVC DN160/200 MM.

1,368.00 432.00 300.00 0.00 636.00

--------------

und Tramo l - C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Casorio San Lorenzo Tramo III - C.P San José

03.02.01.07.06 CAJAS DOMICILIARIAS SISTEMA DE DESAGÜE - LOSA •= 0.10 mt.

114.00

und Tramo I - C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo III - C.P. San José

03.02.01.07.07 PRUEBA HIDRAULICA EN CONEXIONES DE DESAGÜE

114.00

m Tramo 1- C.P. San Pablo de Tushmo Tramo II - AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo III - C.P. San José

03.02.01.07.08 ELIMINACION DE MATERIAL EXCEDENTE

---------------------

1.388.00 432.00 300.00 0.00 636.00

m3 Tramo 1- C.P. San Pablo de Tushmo Tramo H- AA.HH. Intercultural La Nueva Era Tramo III - Caserío San Lorenzo Tramo III - C.P. San José

'

320.11 0.60 0.60 060 0.60

I I

0 30 0.30 0.30 0.30

101.09 70.20 0.00 148.82

OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA IMENSIO NES

N DESCRIPCION

ITEM

01 01.01

TRABAJOS P ^ L IM IN A R E S .............. SEÑALIZACION INFORMATIVA DE DESVIO

UNO

de

de

largo

ancho

alto

elem.

veces

m.

m.

m.

PARCIAL

2.00

und 2.00

2.00 01.02

01.03

01.04

01.05

01.06

DEMOLICION DE ESTRUCTURAS DE CONCRETO En Paneles En Losa Aligerada En losa Inferior En Veredas

m3

RETIRO DE DESPERDICIOS En Puente

m2

DESVIO DE CAUCE

ML

DESBROCE DE TERRENO

LIMPIEZA DE TERRENO

01.07 H TRAZO Y REPLANTEO

01.09

01.10

02 02.01

ALAMCEN DE OBRA

CARTEL DE OBRA (3.00 X 5.00) BANNER INC. COLOCACION

TRANSPORTE DE MATERIALES EQUIPOS Y HERRAMIENTAS

MOVIMIENTO DÉ TIERRAS EXCAVACION DE ZANJA MASIVA CON MAQUINARIA

02.03

02.04

02.05

02.06

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA BAJO LECHO H 0.60M.

RELLENO CON GRAVILLA O PIEDRA CHANCADA DE 1/2“

4.50 800 4 00 8.00

7.35 4 70 4 00 0.80

1.00

10.00

9.00

1.00

50.00

1.00

70.00

20.00

1.400.00

1.00

70.00

20.00

1.400.00

1.00 1.00

20.00 10.00

19.75 8.04

395.00 80.40

1.00

10.00

6.00

60.00

04 04.01 04.01.01

50.00 50.00 1.400.00

1,400.00

475.40

m2

60.00

und

2.00 2.00

2.00

1.00

1.00

GLB

1.00

m3

402.30 2.00 400 1.00

9.86 5 28 9.86

700 3 16 8 04

1.50 1.50 1.20

207.06 100.11 95.13

1.00 1.00

10.00 4.50

8.04 3.20

0.60 0.60

48.24 8.64

2.00

22.20

7.00

1.00

310.80

2.00

Area=

16.45

22.10

727.09

2.00

20.00

12.60

0.20

100.80

522.99

522.99

I

m3

56.88

m3

m3

RELLENO CON MATERIAL DE PRESTAMO EN REPOSICION DE VIA DE INGRESO Y SALIDA. En ingreso y salida

m3

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO D= 5 KM.

m3

04.01.02

04 01.03

OBRAS DE CONCRETO ARMADO LOSA INFERIOR DE ESTRIBO CONCRETO F'C= 210 KG/CM2. EN LOSAS En losa Inferior

310.80

727.09

100.80

522.99

04.03.02

04.03.03

m2

ACERO DE REFUERZO F,Y=4200 KG/CM2

kfl

04.03 04.02.01 04.02.02

04.02.03

04.04 04.04.01

04.04.02

ACERO DE REFUERZO F'Y=4200 KG/CM2 En muro Cabezal MURO ESTRIBO CONCRETO F'C= 210 KG/CM2. En losa inferior de Muro ENCOFRADO Y DESENCOFRADO En losa inferior de Muro ACERO DE REFUERZO FT=4200 KG/CM2 En losa inferior de Muro MUROS CABEZAL CONCRETO F’C - 210 KG/CM2 EN MUROS En Aletas ENCOFRADO Y DESENCOFRADO En Aletas

2.00

10.00

7.00

0.50

70.00

2.00

10.00

7.00

1.50

210.00

4.00

17.00

1.50

102.00

m3

ENCOFRADO Y DESENCOFRADO En losa Inferior

LOSA INFERIOR EN MUROS CABEZAL CONCRETO F'C= 210 KG/CM2 EN MUROS En muro Cabezal ENCOFRADO Y DESENCOFRADO En muro Cabezal

70.00

m3

En losa Inferior 04.02 04.03.01

90.00

m2

RELLENO COMPACTADO CON MATERIAL MEJORADO 80% HOR. + 20% TR. En Estribos

OBRAS DE CONCRETO SIMPLE SOLADO DE CONCRETO F'C= 100 KG/CM2 E=0.50 M solado en estribos E * 0.50 m

33.08 26.32 480 1.28 90.00

1.00 03 03.01

0.50 0.70 0 30 0.10

m2

Para estribos Para estribos (Aletas) En Losa de Cimentación 02.02

65.48 2.00 1.00 1.00 2.00

m2

En Losa superior 01.08

TOTAL

210.00

102 00

14,711.70

4.00

12.50

4.00

Area=

24.23

8.00 4.00

Area= Area=

26.23 4.25

14,711.70

m3

145.38 1.50

t“

145.38

m2

¿2b,#4 209.84 17.00 i'á

kfl 1.00

9,334.70

m3

245.56 2.00

Area=

14.00

8.77

245.56

4.00

12.00

1.40

8.77

589.34

m2

589.34

12,780.37

kg 2.00

12,780.37

m3

' 4.00

3.61

8.00 4.00

3.81 6.07

1.50

9.10

197.11

9.10 1.50

262.81 36.42

m2

197.11

299.23

.■

Página 2

HOJA DE METRADOS OBRA : MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - CORONEL PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : MUNICIPALIDAD DISTRITAL DE YARINACOCHA O FENSIONES

N° DESCRIPCION

ITEM

04.04.03

ACERO DE REFUERZO F-Y=4200 KG/CM2

04.05 04.05.01

VIGA LONGITUDINAL CONCRETO F'C= 210 KG/CM2 EN VIGA TENSOR En viga Longitudinal

UND

de

de

largo

ancho

alto

elem.

veces

m.

m.

m.

9.833.93 6.00

m3

ENCOFRADO Y DESENCOFRADO En lateral de viga longitudinal En inferior de viga longitudinal

m2

04.05.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kq

04.06 04.06.01

VIGA DIAFRAGMA CONCRETO F'C= 210 KG/CM2 VIGA En viga Diafragma

3.00

10.00

0.40

6.00 6.00

10.00 1000

040

0.50

6.00

0.50

30.00 24.00

R oo

3,303.95 1.00

04.06.02

04.06.03 04.07 04.07.01

-----

m2

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

LOSA SUPERIOR Y VEREDAS CONCRETO F’C= 210 KG/CM2. EN LOSAS

m3

En Veredas m2

04.07.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

04.08 04 08.01

LOSA EN CAUCE CONCRETO FC = 210 KG/CM2 EN LOSA DE CAUCE En losa En uñas

m3 m3 m3

04 08.02

04.08.03

3.11 10.00 2.00

2.55 8.00

0.25 0.25

20.00 20.00 4.00

2.55 2.55 8.04

0.25

ENCOFRADO Y DESENCOFRADO DE LOSA DE CAUCE

m2

En losa

m2

ACERO DE REFUERZO F Y *4200 KG/CM2

kg

05.02

VARIOS BARANDA METALICA INC. PINTADO tubo F°G de 0 3" tubo F°G de 0 2* DRENAJE EN LOSA SUPERIOR

JUNTAS DE DILATACION METALICA

05.05

05.06

----

— ñc '

APOYO MOVIL DE NEOPRENE SHORE 70.

APOYO FIJO DE NEOPRENE SHORE 70.

PINTURA EN BARANDAS METALICAS

15.30 12.75 16.08

0.50

___ __ ___ ___ 2.00

Area=

0.32

1.00 1.00 2.00 4.00

10.00 10.00 10.00 10.00

665

143.54 394.88 24.40 10.00 10 00

6^40 106.50

0.20 1.20 0.35

66.50 2.00 24.00 14.00 4,999.68

10 80 10.80

8.00 0.50

1.00

37.60

0.75

0.75 1.00

64 80 10.80 28.20 28.20 898.27 898.27

ML

54.72 18.00 2.00

0.90 19.26

16.20 38 52

pto

------- 6.Ó0 ~ 6 0Í T

ML

20.88 10.44

20.88

und

3.00 3.00

3.00

3.00

3.00

und

3.00

ML

__

4,999.68

75.60 1.00 2.00

2.00 05 04

0.30

538.42

6.00

05.03

1.91 1.20 44.13

1.00 05 05.01

0.30 0.30

1.00 1.00

ENCOFRADO Y DESENCOFRADO DE LOSA SUPERIOR (TIPO FALSO PUENTE) En losa infer. Lateral de Losa En vereda Inferior Lateral de Vereda

04.07.02

3,303.95

m3

ENCOFRADO Y DESENCOFRADO En viga lateral Diafragma En viga inferior Diafragma

TOTAL

9,833.93

kq 1 00

04.05.02

PARCIAL

5Í.12 2.00 2.00

6.80 19.26

13.60 38.52





HOJA DE METRADO ACERO DE PUENTE (LOSA) OBRA : M EJORAM IENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO DISTRITO YARINACOCHA - C O R O N E L PORTILLO - UCAYALI UBICACION: CP SAN JOSE DISTRITO DE YARINACOCHA PROPIETARIO : M UNICIPALIDAD DISTRITAL DE YARINACOCHA

DESCRIPCION

ELEMENTO

LOSA SUPERIOR As+ Long superior(arriba)

11.42

As+TRANSVERSAL superior(arriba) As+ Long inferior(abajo) As+TRANSVERSAL inferior(abajo)

DIAMETRO

1" 4.04 kg/ml

LONGITUD POR METRO LINEAL 3/4" 1/2" 3/8" 2.26 kg/ml 1.02 kg/ml 0.58 kg/ml

5/8" 1.56 kg/ml

38.00

11.92

452.96

3/4

1

41.00

9.93

407.13

3/4

1

38.00

11.92

452.96

34

1

41.00

9.93

407.13

1.50

i 2

6

6

1.50

54.00

0.75

:/

4

6

0.75

18.00

5/8

2

5

11.62

116.20

5'8

2

40

1.80

144.00

58

2

40

1.35

108.00

I

| 25 9 43

|

11.42 I .25

As+TRANSVERSAL ¡nferior(abajo)

N° DE LONGITUD DE ELEMENTOS ELEMENTO

1

1.25

125

CANT DE VECES

I 943

|

VEREDA As Long temperatura+contracc

1,15

As transv temperatura+contracc

As Transv temperatura+contracc

1142

,

1.80

I 1,10

L 1 35

,

O O

O

As Transv temperatura+contracc

5.3

2

40

1.00

80.00

5/3

2

5

11.62

116.20

5 '

2

4

11.62

92.96

l_

As Long temperatura+contracc

1.15 11 42

|

As Long temperatura+contracc

1.15 1142

I

4.04

PESO EN KILOS POR METRO LINEAL LONGITUD TOTAL POR DIAMETRO EN METROS LINEALES TOTAL EN KILOS POR METRO LINEAL

0 .0 0

2.26 1720.18 3,887.61

1.02 72.00 73.44

0.58

0.00 4,999.68

TOTAL

LOSA CAUSE As+long

115

1142

|

As+transversal

,15 I

682 " ...... ........I

As+long

115

1142

I

8.24

As+transversal / ,70

\

3/8

1

32

11.72

375.04

38

1

51

7.12

363.12

33

1

32

11.72

375.04

3/8

1

51

8.54

435.54

1.58 657.36 1,038.63

Kg

FACTIBILIDAD DEL PROYECTO: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI”

ESTUDIO SOCIOECONOMICO FACTIBILIDAD DEL PROYECTO:

"M EJO RAM IENTO DE IN T E R C O N E X IO N AL C. P. SAN JOSE DESDE PUERTO CALLAO> , D IS T R IT O DE YARINACOCHA CORONEL PO R TILLO - U C A Y A LI"

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCiAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

ESTUDIO SOCIOECONOMICO

FACTIBILIDAD DELPROYECTO: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA- CORONEL PORTILLO - UCAYALI

2012

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

CONTENIDO FICHA TECNICA METODOLOGIA I.

ESTRUCTURA POBLACIONAL Estructura de la Población.

II.

PERFIL SOCIOECONOMICO Aspectos Demográficos Características de las Viviendas Servicios de Saneamiento Básico. Actividades Económicas. Efectos en el desarrollo de las familias

III.

SERVICIOS DE TRANSPORTE Condiciones de la Vía. Destino en la Salida de la Población. Tiempo de Transporte. Toma del Servicio de Transporte Disponibilidad de Vehículo. Tipo de Vehículo. Medio de Transporte Público. Costo de Transporte Percepción de la Población Sobre el Transporte Público. Factores por la que No Utilizaría el Transporte Público.

IV.

IMPACTOS DEL SERVICIO DE INFRAESTRUCTURA VIAL Lean ^ é lP 40 894 in g e n ie r o c iv il

Principales Problemas Identificados en la Zona. Efectos de los Problemas en la Población Peligrosidad de la Vía A m p y t'o 'r iuz

Eventos de peligrosidad ocurridos en la Zona. Beneficios esperados de la Mejora de la Vía. V.

CONCLUSIONES

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

presentante Legal

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

1.

FICHA TECNICA Objetivos. 1.

Identificar el perfil socio demográfico y económico de la población que vive en el área de influencia del proyecto.

2.

Identificar

las

características

delapoblación

que

circula

por

la

vía

de

interconexión del C. P. San José desde Puerto Callao en el Distrito de Yarinacocha. 3.

Determinar los hábitos y preferencias de actividades de transporte de la población acerca de la demanda de servicios de transporte.

4.

Indagar acerca de la percepción que tiene la población por la infraestructura vial a intervenir.

5.

Determinar el flujo de transporte que circula por dicha vía diario, semanal y anual.

6.

Determinar la problemática de la población beneficiaría, así como los efectos e impacto que tendrá la vía una vez intervenida.

2.

METODOLOGÍA. El

presente

estudio

fue

realizado

mediante

una

investigación

de

carácter

cuantitativo, teniendo en cuenta lassiguientes consideraciones metodológicas: •

Técnica: Entrevista personal directa a las familias que se encuentran asentadas en dichas vías.



Instrumento: Cuestionario estructurado y estandarizado con preguntas abiertas y cerradas.



Universo

a

investigar:

Está

conformado

por

hombres

y

mujeres

d'

nacionalidad peruana de 15 a 80 años de edad, residentes en las vías d estudio. •

Ámbito geográfico: Zonas urbana del Distrito de Yarinacocha.



Tamaño de muestra: Para el estudio se tuvo 242 casos (cuya unidad de medida está determinado por el N° de viviendas ocupadas por las familias) con un margen de error de ± 5%, utilizando la siguiente fórmula:



Para determinar la muestra se ha utilizado la técnica de muestreo probabilística~con universo población conocido, para lo cual se usado la forn

Donde: n

= tamaño de la muestra necesaria

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Z „ / 2 = 1.96 (tabla)



P

= probabilidad de que el evento ocurra 0.50

Q

= probabilidad de que el evento no ocurra 0.50

e

= 0.05 ó 5%

N

= tamaño de la población: 636 Lotes Habitados

Se ha tomado en cuenta el número de familias existentes en la zona de influencia del proyecto, dado por 120familias.



Aplicando la fórmula de la muestra se ha determinado, una muestra de 120 familias a entrevistarse, pero con la finalidad de tener mayor consistencia en el desarrollo del estudio socioeconómico, se ha tomado en cuenta a 120 familias a entrevistarse,

Localidad

Muestra

Margen de error

120

±5%

Yarinacocha •

Consistencia y Procesamiento La consistencia comprende un análisis de la coherencia del resultado de las preguntas, por medio del cual se identifican encuestas no veraces, las cuales son separadas de este modo no distorsionar la información. El procesamiento se ha realizado con el uso del aplicativo informático Excel para obtener el valor de

las

variables

analizadas,

en

función

a

los

objetivos

del

estudio

socioeconómico.



Fecha de Trabajo: El trabajo de campo se realizó del 16 al 20 de Mayo del

2012

Consorcio FRL & SG ASCON SULT A m p a r o D íu z A r e v u lo Representante Legat

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Capítulo I: Estructura Poblacional

r e vulo presentante Legal

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

(N G £ N tE R O C *V H -

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

I.

POBLACION

1.1

Estructura Poblacional. De acuerdo al área de influencia del Proyecto, se determina el número de población existente en la zona. Para la cual se ha desarrollado la siguiente metodología. •

De la estructura poblacional existente del Distrito Yarinacocha(resultados de CPV 2007 INEI) se ha determinado, la proporción según estructura poblacional de la zona del proyecto (Interconexión C. P. San José desde Puerto Callao)



Con la determinación de la estructura porcentual de la población de la zona del proyecto se estructurado la población según grandes grupos de edad. Tal como se muestra en el cuadro N° 1.2



Se ha tomado para la determinación de la población de la Carretera desde Puerto Callao hasta el C. P. San José según el N° de viviendas existentes en dichas vía (en total suman 120 viviendas. Tal como se muestra en el cuadro N° 1.1 Cuadro N° 1.1: N° de Viviendas Existentes en la Zona del Proyecto Vias

Localidad

N? de Viviendas

Zona

Jr. San A le ja n d ro

P u e rto C allao

18 D is trito d e Yarinacocha

Jr. Lima

C. P. San P a b lo d e T u s h m o

10 D is trito de Yarinacocha

A v. San Lorenzo

C aserío San Lorenzo

4 0 D is trito d e Yarinacocha

A v. B e lis a rio P a n d u ro

C aserío San Lorenzo

A v. San Jóse

C. P .S a n José

42 D is trito de Yarinacocha

A v. Los C edros

C. P. San José

7 D is trito de Y arinacocha

TOTAL

3 D is trito d e Yarinacocha

120

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

De la encuesta socioeconómica se obtenido la densidad poblacional, que viene a ser 5.3 habitantes/familia, este indicador se encuentra en los ratios p ro m e ^ ® ^ 1 . de densidad familiar de la región Ucayali, que ha venido disminuyendo e n jo ^ o v ^ últimos años. En toda la zona de influencia se cuenta con 636 personas a p ro x im a d a m e n te ^ *,NAC° la actualidad, estimada mediante el número de viviendas ocupadas en la zona con la densidad de habitantes por familia. Dichos resultados se reflejan en el siguiente cuadro.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro N° 1.2: Población Según Estructura de Edad Est. Edad (Grupo Edad)

% Según Est. Edad

Fbb. Zona del R-oyecto

< 1 año

17

2.70%

1 a 4 años

69

10.85% 10.98%

4 a 9 años

70

10 a 14 años

87

13.70%

15 a 19 años

73

11.50%

20a 49 años

254

39.92%

50 a 54 años

20

3.10%

55 a 59 años

15

2.33%

60 a 64 años

9

1.42%

65 a 69 años

10

1.55% 0.78%

70 a 74 años

5

75 a 79 años

4

0.65%

> 80 años

3

0.52%

636

100.00%

Total

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

P o b la c io n s e g ú n Est. E d a d > 8 0 años

0.5 2%

7 5 a 79 años

0.6 5%

7 0 a 74 años

0.7 8%

6 5 a 69 años

1.5 5%

6 0 a 64 años

1.4 2%

55 a 59 años

2.33%

5 0 a 54 años

3.10%

20a 49 años

39 .9 2 % La 11.50%

15 a 19 años 10 a 14 años

13.70%

4 a 9 años

10.98% j |

1 a 4 años

10.85%

< 1 añ o

2 .7 0%

0.0 0%

10.00%

2 0 .0 0 %

30 .00%

4 0 .0 0 %

50 .00%

Como se puede apreciar en el gráfico anterior, el 39.92% de la población se encuentra en el rango de edad de 20 a 49 años, el 13.70% de la población se encuentra en el rango de edad de 10 a 14 años. Mientras la menor proporción de la población se encuentra en el rango de edad de mayor a 80 años con solo 0.52% Predominantemente la población es joven en la zona del proyecto. Ubicación de la zona influencia. Lean rssentantfc Ley¿¡

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

894 CfVH.

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO P O B L A D W A N JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHR^CORONEL PORTILLO - UCAYALI

Mapa: Zona de intervención del Proyecto.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

II.

PERFIL SOCIOECONOMICO.

2.1

ASPECTOS DEMOGRAFICOS. •

Población según Sexo. En el desarrollo del estudio se ha encontrado que la población según sexo, está conformada en el área de influencia del proyecto del 51% de varones y el 49% de mujeres. Gráfico 2.1: Población Según Sexo

Poblacion de la zona de estudio según sexo

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.



Nivel de Educación del Jefe de Familia. El nivel de educación del jefe de familia, está considerado como una variable que determina la estructura del desarrollo social de la población, con la finalidad de avizorar las condiciones educativas de las familias y de los cambios, que estas sufren en el seno familiar. En ese sentido, el nivel de educación de los jefes de familia en la zona de influencia del proyecto, está dado por: Cuentan con primaria incompleta el8% de los jefes de familia, que se convierte en una limitación estructural en el desarrollo de sus propias familias. Tienen primaria completa el 18%, de los jefes de familia de la zona de influencia del proyecto, lo que representa que cada uno de los jefes de famili^_ti©nen-una mejor predisposición para el desa dentro de la familia.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuentan con secundaria incompleta la que tienen el 23% de los jefes de familia, que tienen este nivel educativo, razón por la cual existe una predisposición de mejora en cuanto al desarrollo económico, educativo y social de sus familias. Cuentan con secundaria completa la que tienen el 34% de los jefes de familia, que tienen este nivel educativo, razón por la cual existe una predisposición de mejora en cuanto al desarrollo económico, educativo y social de sus familias. Con un nivel educativo de superior técnico No Universitario se tiene al 9% de los jefes de familia, dicha población estámayor predispuesta a tener mejores oportunidades de superación y crecimiento familiar dentro de su entorno social y cultural. Con superior universitaria se tiene al 8% de los jefes de familia, lo que es una población relativamente baja, esta población tiene mejores condiciones de superación de su entorno familiar y cuenta con mayores oportunidades de crecimiento y desarrollo. Dicha apreciación se refleja en el siguiente cuadro. Cuadro 2.1.1: Nivel de Educativo de los Jefes de Familia

D esc rip ció n

P rim aria

P rim aria

In c o m p le ta

C o m p le ta

S e c u n d a ría In c o m p le ta

S ecu nd aria C o m p le ta

S up erior T é c n i c o No U n iv .

Sup erior

No tie n e

U n i v e r s i t a ria

e s tu d ios

Frec. A b s o l u t a

10

21

28

41

11

9

0

Frec. R e l a t i v a

8%

18%

23 %

34 %

9%

8%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Nivel de instrucción del jefe de Familia Superior

Primaria Universitari |ncomp(eta

3

8% Superior Técnico No

8% ^

Primaria ^Completa 18%

Secundaria Completa

Secundaria

34%

Incompleta 23%

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

CIP

*MG£ HIERO CH/H.

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

2.2

CARACTERÍSTICAS DE LAS VIVIENDAS •

Piso. El piso de las viviendas en la zona de influencia del proyecto, está dado por cemento 45%, tierra 24% y madera 31%. Como se aprecia el piso de la vivienda en más de la mitad, que el piso es de cemento, lo cual hace presumir las condiciones favorables en las que viven la población. Cuadro: 2.2.1: Piso en las Viviendas. D esc rip ció n

M a te r ia l p r e d o m in a n te piso de V iv ie n d a M adera

Frec . A b s o l u t a Frec . R e l a t i v a

C em ento

Ti e rra

Otro

37

54

29

0

31%

45%

24%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Tipo de material de Construcción de Piso de Viviendas

Tierra 24%

Pared y Cobertura. En cuanto al sistema constructivo de las viviendas en el área de influencia del proyecto, se tiene, el 83% estáconstruido de pared de madera + techo de madera con cobertura de calamina, y 12% son pared de ladrillo + tacho de madera con calamina, 5% pared de madera + techo de hoja. Como se aprecia los resultados se tiene que la predominancia en la zona las viviendas son de madera y cobertura de calamina en más de la mitad, también se constituye en un indicador que determina las condiciones de la población de la zona de influencia del p ro ye cta Cuadro N°: 2.2.2: Material de

e Viviendas. ^ A -^ F m tá o K W tlL m $

'

C lP

N» 4 0 8 9 4

lN G E i-«fef
DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

Ampapó uiiaz .-i revi Spresen íante Lega l

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Pared de

Pared de

P aresd de

Pared de

m ade ra + T e c h o

la d rillo + T e c h

la d rillo + T e c h

m adera y

d e m a d e r a con

o d e lo z a

o de m adera

techo de

ca la m in a

alig e ra d a

con ca la mi na

h o ja

Frec . A b s o l u t a

100

0

14

6

0

Frec . R e l a t i v a

83%

0%

12%

5%

0

D esc rip ció n

Otr o

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Tipo de material de construcción de Viviendas P a re d d e m a d e ra y te c h o d e h o ja

P a re s d d e la d r iilo + T e cho de m a d e ra con c a la m in a 12%

2.3

P a re d d e m a d e r a -*■ Techo de m a d e ra con c a la m in a 83%

SERVICIO DE SANEAMIENTO BÁSICO. •

Agua Potable. La disponibilidad de agua potable en el área de influencia del proyecto, cuentan con dicho servicio, el 4% de la zona, mientras que 96% de las familias sostienen que no cuentan con disponibilidad del servicio de agua potable. Cuadro N°: 2.3.1: Disponibilidad del Servicio de Agua Potable. D esc rip ció n

D is p o n ib ilid a d de agua p o ta b le Si

Frec. A b s o l u t a Frec. R e l a t i v a

No 5

115

4%

96 %

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

A m

p ü r u

<sK e p re s e n ta m t Ley¿>i

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Disponibilidad de agua potable

Abastecimiento de Agua Las familias se aprovisionan del servicio de agua mediante pozo artesiano el 30% a través de la dotación de un vecino el 48% y las demás familias compran el agua 15% así como las que se aprovisionan de pozo tubular, que representan el 7%. Este tipo de agua no garantiza la calidad necesaria para su consumo. Cuadro N°: 2.3.2: Abastecimiento de Agua. Provision de agua

Descripción

Pozo artesiano Atraves de un vecino Triciclo Pozo tubular Frec. Absoluta Frec. Relativa

5

0

0

115

4%

0%

0%

96%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Sistema de Dotacion de agua para consumo Pozo artesiarío 4%

Pozo tubular 96%

s 4 r tn fr íti o 'D í if c n A S f r r u l!

^-•''Representante Ley,

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

C*VH.

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI



Servicio de Desagüe El servicio de desagüe que tiene la población está dado por, red pública2%, y los que no cuentan con sistema de desagüe de red pública, representa el 98% es importante considerar que la dotación de este servicio se da, en casiel 100% no cuenta con este servicio, lo cual es favorable para la mejora de la calidad de vida de la población. Cuadro N° 2.3.3: Provisión del Servicio de Desagüe. D i s p o n i b i l i d a d de Desagüe

D esc ri pc io n Si Frec. A b s o l u t a Frec. R e l a t i v a

No 2

98

2%

98 %

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Disponibilidad de desagüe Si

2%

Descarga de Aguas Servidas Del 98% de las familias que no cuentan con sistema de desagüe, el 1% afirma que descargan sus aguas servidas a Canaletas de las vía, y el 88% de la población afirma que cuenta con letrina para la descarga de las aguas servidas y el 11% de las familias sostienen que cuentan con pozo séptico donde descargan sus aguas servidas.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro N° 2.3.4: Descarga de Aguas Servidas. S iste m a de d e s a g ü e u tilizza d o D esc rip ció n

Frec. A b s o l u t a Frec . R e l a t i v a

Caño

C a n a le ta s

C u e n t a con

Pozo

n a tural

d e la via

le trin a

s é ptic o

Otr o

0

1

105

14

0

0%

1%

88 %

11%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Sistema de disponibilidad de desagüe 1%

Principalmente la población se dedica a ser trabajador independiente73%, por estar en la estructura poblacional joven son estudiantes en 18%, luego se encuentran los que desarrollan actividades de empleados públicos (8%), el 1% se dedica

a la actividad

empresarial,

como se

puede

apreciar de las

características de la población, 3 de cada 4 personas desarrollan actividades en forma independiente, donde están ocupadas y sub ocupadas. Dicha característica se aprecian en el siguiente cuadro. Cuadro: 2.4.1: Actividad económica de la Población. Tipo de actividad a la que se dedica Descripción

Frec. Absoluta Frec. Relativa

Trabajador

Empleado

in dep en diente

publico

FF. AA. (Fuerza

Estudiante

Empresario

22

1

87

10

0

0

0

18%

1%

73%

8%

0%

0%

0%

Fuente: Encuesta Socioeconómica del Proyecto

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

Obrero

Otros

Aerea)

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Tipo de actividad que realiza las Familias Empleado publico

8%



Nivel de Ingreso Promedio Familiar Es una variable determinante para medir las condiciones en las que se encuentra la población, se determina los niveles de ingreso promedio familiar de la población promedio por mes, en el momento que se lleva a cabo el estudio. Así tenemos que 51% de ellos tienen sus niveles de ingreso en el rango de 300 a 600 nuevos soles, hasta 300 nuevos soles el 37% al igual que las familias que tienen sus niveles de ingreso de 600 a 900 nuevos soles que constituyen el 8%, también se tiene una población del 4% que tienen ingresos promedio mensuales de 900 a 1200 nuevos soles. Con dichos niveles de ingresos se tiene que la población ha venido mejorando sus condiciones de pobreza en los últimos años, aunque sigue manteniéndose la pobreza en el área del proyecto dado que la mitad de la población se encuentra en situación de pobreza.

Cuadro: 2.4.2: Niveles de Ingreso Promedio Familiar. Nivel de ingreso promedio promedio mensualFamilia

Descripción Hasta 300

De 3 01 a 600

44

61

10

5

0

0

37%

51%

8%

4%

0%

0%

Frec. Absoluta Frec. Relativa

De 60 1 a 9 0 0 De 901 a 1 2 0 0

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

A m

p fr fo

/y /ílZ ^ tr Z tu la

^■Representante Legal

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

De 12 01 a 1 5 0 0 De 15 01 a mas

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Nivel de ingreso promedio familiar

De 601a 900



De 901a 1200 4%

Desarrollo de Actividad Comercial El 18% de las familias de la zona del proyecto, sostienen que desarrollan alguna actividad comercial, con la finalidad de mejorar sus condiciones económicas y niveles de ingreso. Mientras que el 82% de las familias manifiestan que no desarrollan actividades comerciales en la zona.

Cuadro: 2.4.3: Actividad Comercial de las Familias. A c tiv id a d C o m e rc ia l de la F a m ilia D e s c rip c ió n Si

No

Frec. A b s o lu ta

22

98

Frec. R e la tiv a

18%

82%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

í ^ v'v *r

¡s?<

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Del 18% de las familias que sostienen que desarrollan actividades comerciales para mejorar sus niveles de ingreso promedio, se tiene que el 86% cuenta con bodegas, mientras que existe un 1% que se dedican a la industria. Como se puede apreciar en los resultados, 3 de cuatro familias tienen pequeñas bodegas, lo que permite que el desarrollo de las actividades comerciales no sea significativo de alto valor agregado.

Cuadro: 2.4.4: Tipo de Actividad Comercial de las Familias. Tip o de a c tiv id a d C o m e rc ia l de la F a m ilia D e s c rip c ió n Bodega Frec. A b s o lu ta Frec. R e la tiv a

Fuente de Soda

H osp e d a je

O tro (in d u s t.)

19

0

0

3

86%

0%

0%

14%

Fuente: Encuesta Socioeconómica del Proyecto. Elaboración: Consultor.

Tipo de actividad Comercial de las Familias Otro

2.5

EFECTOS DE LA CONDICION DE LA VIA EN LAS FAMILIAS DE LA ZONA DE INFLUENCIA. Dado que las capacidades de la población, son las de mejorar de una situación negativa a otra favorable, se considera los efectos que viene teniendo las condiciones de la vía en el desarrollo normal de las familias. Los efectos-senniden por los siguientes aspectos:



Efectos de Enfermedades Respiratorias

^nscrchéu^Asem^LT / n i«&á&¿vula

/ ¿ • p re s e n ta n t t Ceg¿<

La presencia de enfermedades respiratorias como consecuencia del polvo en la vía, debido al alto flujo de vehículos por la zona, afectan a la población que se encuentra en la zona del proyecto. Entonces se tiene que la población que sufre de enfermedades respiratorias en la zona del proyecto suman a 75% es decir casi las tres cuartas partes de la población sufre de infecciones respiratorias,

la cual perjudica el normal

desenvolvimiento de la población en cada una de sus actividades que se dedica.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 2.5.1: Población que Sufre de Enf. Respiratorias. S ufre de E n fre m e d a d e s R e s p ira to ria s D e s c rip c ió n No

Si Frec. A b s o lu ta Frec. R e la tiva

90

30

75%

25%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Poblacion que sufre de en ferem edad es respiratorias en la zona

Como consecuencia se tiene los gastos en las que incurre la población para tratarse la prevalencia de infecciones respiratorias asociadas a las condiciones de la vía. Sufre de e n fe rm e d a d e s re s p ira to ria s G a sto p ro m e d io Si

90

Na de veces que se e n fe rm a 4 .7 0

p o r v e z q u e se

G asto

G asto p o r

to ta l

e n fe rm a 7.9 0

fa m ilia

3 ,3 4 0 .0 0

3 7 .11

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

En promedio del 75% de las familias que sufren de infecciones respiratorias tienen un gasto de 37.11 nuevos soles al año.

Enfermedades Oculares Los males de la vista que sufren la población se dan como consecuencia del polvo existente en la vía en estudio, a raíz de ello la población se ve perjudicada en cuanto sufren principalmente de conjuntivitis. Tal es así, que el 25% de la población ha sufj

de enfermedades oculares;

perjudica su accionar diario y le resta Consor/

milias. ¡ULT, '

im puro DíOTTArevula Representanlfc Leyai DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

INGfc

IVH_

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 2.5.2: Población que Sufre de Enf. Oculares. Sufre de E n fre m e d a d e s O culares D e s c rip c ió n Si Frec. A b s o lu ta Frec. R e la tiva

No 30

90

25%

75%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Poblacion que sufre de enfermedades oculares

Como consecuencia se tiene los gastos en las que incurre la población para tratarse la prevalencia de enfermedades oculares asociadas a las condiciones de la vía. Sufre de e n fe rm e d a d e s O culares G asto Si

N§ de veces que

p ro m e d io p o r

Gasto

G asto p o r

se e n fe rm a

v e z q u e se

to ta l

fa m ilia

-L

e n fe rm a 30

3.0 0

11 .50

1 ,0 3 5 .0 0

3 4 .5 0

En promedio del 25% de las familias que sufren de infecciones respiratorias tienen un gasto de 34.50 nuevos soles al año.

Enfermedades Vectoriales Las enfermedades vectoriales se presentan principalmente en los lugares que sufren de anegamientos, donde se da la proliferación de vectores (zancudos y mosquitos) que disminuyen las capacidades de desenvolvimientojX)r-mal de la población en sus quehaceres diarios, adejyvá^qu&%je representan costos de curación.

C onsorcio F X L & S é 'A S C O W S tiL T

íe n m á n f r iP

N ° 40894

INGIERO CtVH-

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Así tenemos que el 22% de la población manifiesta que ha sufrido, por lo menos una vez al año enfermedades vectoriales.

Cuadro: 2.5.2: Población que Sufre de Enf. Vectoriales. S ufre de E n fre m e d a d e s V e c to ria le s D e s c rip c ió n No

Si Frec. A b s o lu ta Frec. R e la tiv a

26

94

22%

78%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Poblacion que sufre de enfermedades Vectoriales en la zona

Como consecuencia se tiene los gastos en las que incurre la población para tratarse la prevalencia de enfermedades vectoriales asociadas a las condiciones de la vía. Sufre de e n fe rm e d a d e s V e c to ria le s G asto Ns de veces Si

p ro m e d io p o r

Gasto

G a sto por

vez que se

to t a l

fa m ilia

qu e se e n fe rm a

26

e n fe rm a

2.8 0

9 .7 0

7 0 6 .0 0

21 .15

En promedio del 22% de las familias que sufren de enfermedades vectoriales^ tienen un gasto de 21.15 nuevos soles al año.

Enfermedades Diarreicas En épocas de lluvias,

1Hr^ EROavN

la zona del proyecto sufre anegamiento y como

consecuencia el lodo y barro afecta a la población en cuanto, si no tienen el cuidado debido en sus hábitos de higiene. En ese sentido se tiene que la población que sufre de enfermedades diarreicas agudas representa solo 8% de la población que se ubica en dicha zoxy

Cuadro: 2.5.3: Población que Sufre de Enf. Diarreicas. Tiufíhirc-vZlT ✓•''Representantfc Len¿' DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Sufre de E nfre m ed ade s D ia rre ic a s D e s c rip c ió n No

Si Frec. A b s o lu ta

10

110

Frec. R e la tiva

8%

92%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Poblacion que sufre de enfermedades Diarreicas en la zona

Como consecuencia se tiene los gastos en las que incurre la población para tratarse la prevalencia de enfermedades diarreicas asociadas a las condiciones de la vía. Sufre de e n fe rm e d a d e s D ia rre ca s G asto de vece s que Si

se e n fe rm a d a d e s

10

2.3 0

p ro m e d io po r

G asto

G asto p o r

vez que se

to ta l

fa m ilia

■%r>8* OMISION -í» P fstutiiosi T■=\WS1»XTUM SOCHI IWOWCII»

e n fe rm a 11.52

2 6 5 .0 0

2 6 .5 0

En promedio del 8% de las familias que sufren de enfermedades vectoriales tienen un gasto de 26.50 nuevos soles al año.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Capítulo III: Servicios de Transporte

m Femó? N
DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

III.

DE LOS SERVICIOS DE TRANSPORTE •

Condiciones de la Vía La percepción que tiene acerca de las condiciones de la vía, están dados por 51% considera que las actuales condiciones de la vía son malas, el 33% de la población considera que dicha vía es regular, y solo el 12.5% de la población considera que la vía en estudio es muy mala. De acuerdo a la apreciación de la población se tiene que la vía en estudio se encuentra en

pésimas condiciones,

razón

por la cual es necesaria

su

intervención.

Las condiciones de la vía en estudios se presentan en la toma. Se encuentra a nivel de afirmado (malo). Lo que genera alta incidencia de polvo.

Vista del Puente y la via en inadecuadas condiciones por el encala minado y producto de la inundación de la vía.

Consorcii

INGfcUlERO C(VW_

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 3.1: Percepción de la Población Acerca de la Vía. C o n d ic io n e s de la Via

D e s c rip c ió n

M u y bu ena Buena

R egular M a lo

M u y M a lo No o p in a

Frec. A b s o lu ta

2

1

40

61

15

1

Frec. R e la tiv a

1.67%

1%

33%

51%

12.50%

1%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Condiciones de la via según la poblacion No opina

M uY buena

1/0 Buena 1%

Al realizar sus actividades económicas, sociales, educativas y culturales, la población realiza una ruta de transitabilidad para llegar a sus destinos. En ese sentido la población principalmente se dirigen al centro del Pucallpa en promedio 29 minutos, van a sus instituciones educativas el 30 minutos, se dirigen al mercado el 20 minutos, van hacia su trabajo se demoran en promedio 22 minutos, se dirigen al universidad se demoran 23 minutos y se van a Yarina se demoran en 24 minutos. Como se aprecia de los resultados de la encuesta la población, generalmente se dirige y toma la vía para llegar al centro, el mercado y su trabajo, dichas actividades son las que desarrolla en forma periódica.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 3.2: Destino de la Población. D e s tin o de v ia je Lugar de d e s tin o

T ie m p o (m in u to ) Ida

R eto rno

P u c allpa

29

30

C olegio

17

16

M e rc a d o

20

22

C e n tro d e T ra b a jo

25

26

U n iv e rs id a d

23

24

Ya riña

18

19

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Tiem pos de vfiaje según destino en m inutos

La población de acuerdo a su necesidad de demanda para transporte público, manifiesta que camina para tom ar un servicio de transporte el 11%. Lo que implica pérdida de tiempo para las actividades que va desarrollar al lugar donde se dirigen.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 3.3: Disponibilidad de Unidad de Transporte D e s c rip c in

C am ina para to m a r u n id a d d e T ra n s p o rte Si

Frec. A b s o lu ta Frec. R e la tiva

No 13

107

11%

89%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Camina para tomar su unidad de transporte

Del 11% de la población que manifiesta que camina para disponer una unidad de transporte para llegar a su destino, el 77% camina una cuadra, 23% camina dos cuadras, lo que refleja las condiciones inaccesibles de la población tomar una unidad de transporte y dirigirse a sus destinos. Esta población está asentada básicamente en el área de influencia de la vía.

Cuadro: 3.5: N° de Cuadras que Transita la Población D e s c rip c ió n

Frec. A b s o lu ta Frec. R e la tiv a

N3 de c u a d ra s que ca m in a Una c ua dra

Dos c u a d ra s

> a dos cu a d ra s

10

3

0

77%

23%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

N2 de cuadras que camina Dos cuadras

77%



Disponibilidad de Vehículo De acuerdo a los resultados de la encuesta desarrollada en la vía en estudio se tiene que el 27% de las familias cuentan con vehículo propio para desarrollar sus desplazamientos a sus lugares de destino. Mientras que el 73% manifiesta que no cuenta unidad de transporte propio. Se puede concluir que una familia de tres cuenta con unidad de transporte.

Cuadro: 3.6: Disponibilidad de Vehículo Propio de la Población D e s c rip c in

T ie ne v e h íc u lo p ro p io Si

Frec. A b s o lu ta Frec. R e la tiva

No 32

88

27%

73%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Disponibilidad de vehículo propio

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI



Tipo de Vehículo. Del 27% de las familias que manifiestan que cuentan con unidad de transporte, tienen motokar el 53% de las familias, el 47% sostiene que cuentan con una moto lineal. Es decir más de la mitad de las familias que cuentan con unidad de transporte cuentan con vehículo trimovil, que a la vez les sirve para desarrollar sus actividades diarias de transporte público.

Cuadro: 3.7: Tipo Vehículo Propio de la Población T ip o de V e h ic u lo p ro p io

D e s c rip c ió n M o to Line al Frec. A b s o lu ta Frec. R e la tiva

M o to c a rro A u to m o v il

C a m io n e ta

C am ión

V olvo

17

15

0

0

0

0

53%

47%

0%

0%

0%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

^ tenptMdíTMftrf L w r ' cn P

40S9

(NfifeM1EROCW.L Es importante determinar cuál es el medio de transporte público que utiliza la población en el transporte de origen y destino, con la finalidad de medir los tiempos y los recursos que son asignados en ella. El 96% de la población utiliza como medio de transporte para dirigirse a su destino el Motokar, el 3% de la población sostiene que toma un colectivo, se entiende que diferencia (1% utiliza moto lineal). Como se aprecia de los resultados se tienen que el principal medio de transporte utilizado es el Motocar, la que se refleja por sus condiciones adecuadas para esta zona.

Cuadro: 3.8: Medio de Transporte que Utiliza

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

Consorcio

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

T ip o de V e h íc u lo q u e u tiliz a pa ra su tra n s p o rte p u b lic o D e s c rip c ió n

M o to k a r

C o le c tiv o

R e to rn o

Ida

Ida

R eto rno

Frec. A b s o lu ta

115

113

4

4

Frec. R e la tiv a

96%

94%

3%

3%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Tipo de transporte publico mas utilizado 140 120

96%

94%

100

80 60 40 20

3%

3% Ida

Retorno

Ida

Motokar

Retorno Colectivo

Mientras que para su retorno, la población utiliza el 94% motokar, 3% utilizan colectivo, al igual que la ida, en esta situación también se ve que el Motokarel es la unidad de transporte mayoritariamente utilizado por la población.

Costo de Transporte Este indicador nos determinará los costos en que incurre la población en su quehacer diario. Como se puede apreciar en los resultados de la encuesta la población, gasta en promedio por día mayor a 3 nuevos soles el 53%, el 12% sostiene que gasta en su transporte diario 4 nuevos soles, el 10% manifiesta que gasta en su servicio de transporte público 2 nuevos soles, El 9% de la población manifiesta que gasta en su transporte diario > 8 nuevos soles. Es necesario indicar que con la intervención en la vía los costos de transí de la población tendrán una ligera disminución.

Cuadro: 3.10: Costo de Transporte/día Gasto diario por fam ilia en tra nspo rte

Descruipcion 2 Frec. Absoluta Frec. Relativa

IN G E N IE R O C íV Il.

3

4

5

7

6

> a S/. 8 N.S.

12

63

14

5

8

6

10%

53%

12%

4%

7%

5%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

11 /

------- -

Consorú

Representóme. Le; DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

No sabe/ no opina 1 1%

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Gasto diario de las familias según su destino > a S/. 8 No sabe/ N .S. no opina 9%

1%

2 10%

Percepción de la Población Sobre el Transporte Público. Esta variable determina la calidad con la que presta los servicios de transporte público, en ella se determinan cual son las condiciones de oferta del servicio, que no necesariamente satisfacen la demanda del servicio. Con respecto al Motokar la población considera que es rápido (82%), es es confortable (10%) y es caro (8%) y no sabe no opina (0%)

Cuadro: 3.10: Percepción de la Población Transporte Público: Motokar Como percibe el tra nspo rte publico en la zona Descripción

M o tokar Es confortable

Frec. Absoluta Frec. Relativa

Es rápido

Es caro

O tro

NS/NO

12

98

10

0

0

10%

82%

8%

0%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Percepción de la poblacion acerca del Motokar

120

82»

100 80 60 40

■ Es confortable

M m Es rápido

Es taro

'■~' ~ ....... ” ..... 0% 0% Otro

NS/NO

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Con respecto al colectivo, la población considera que otro (77%), es confortable (8%) y es rápido (8%) y no sabe no opina el 7% de las familias.

Como percibe el tra nspo rte publico en la zona Descripción

Colectivo Es confortable

Es rápido

Es caro

O tro

NS/NO

Frec. Absoluta

10

10

0

92

8

Frec. Relativa

8%

8%

0%

77%

7%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Percepción de la poblacion acerca det colectivo 300

m

90 80 70 60 50 40

30 20

8%

10

8%



0

7%



Es confortable

Es rápido

Es caro

Otro

NS/NO

Con respecto al combi bus, la población considera que caro (0%), es confortable (0%) y es rápido (1%) y no sabe no opina el 99% de las familias. Como percibe el tra nspo rte publico en la zona Descripción

Combi/Bus Es confortable

Frec. Absoluta Frec. Relativa

Es rápido

Es caro

O tro

NS/NO

0

1

0

0

119

0%

1%

0%

0%

99%

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Título del gráfico 140 99%

120 100 80 60 40

20 0%

1%

0%

0%

0 Es confortable

Es rápido

Escaro

Otro

NS/NO

Como se aprecia en los resultados las preferencias de la población respecto al servicio de transporte público están dadas básicamente por el servicio del Motokar, a pesar que consideran que no es confortable y encima caro.



Factores por la que No Utilizaría el Transporte Público. La población manifiesta que no utilizaría el transporte público por las siguientes razones: Principalmente no utilizarían el Motokar por inseguridad (62%), por la frecuencia de accidentes (22%), por los altos costos de transporte 3% y y los que no saben no opina el 0%

Cuadro: 3.11: Factores por la Que No Utilizaría el Servicio de Transporte Público. Porque razones no utilizaría el tra nspo rte publico M o to ka r

Descripción Inseguridad Frec. Absoluta Frec. Relativa

A ltos costos de

Accidentes

tra nspo rte

O tro

NS/NO

74

4

26

0

0

62%

3%

22%

0%

0%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Consorcii

¿y¿az A.re\*ulo ^ é p re se n ta m c L e u ¿ i

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Razones por lo cual no utulizaria el M otokar para su transporte

bm -

22%

-3%-

0%

1 Inseguridad

Altos costos de transporte

Accidentes

0%

Otro

NS/NO

Principalmente no utilizarían el colectivo por inseguridad (1%), por los altos costos de transporte 0% y por la frecuencia de accidentes (0%) y los que no saben no opina el 92% Porque razones no utilizaría el tra nspo rte publico Colectivo

Descripción

Altos costos de

inseguridad Frec. Absoluta Frec. Relativa

Accidentes

tra nspo rte

O tro

NS/NO

1

0

0

0

110

1%

0%

0%

0%

92%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor. Razones por el cual no utulizaria el colectivo para su transporte

120

-92%-

100

80 60 40 20 1%

0

0%

Inseguridad Altos costos de transporte

0%

0% Accidentes

Otro

NS/NO

Lean /¿ ÍP \ p ía z A r e v <

Spieséniantfc Legal

V " 40894


DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Principalmente no utilizarían el combi/bus por inseguridad (41%), por los altos costos de transporte 1% y por la frecuencia de accidentes (21%) y los que no saben no opina el 30% Porque razones no utilizaría el tra nspo rte publico Combí/Bus

Descripción Inseguridad Frec. Absoluta Frec. Relativa

Altos costos de

Accidentes

tra nspo rte

O tro

NS/NO

15

1

2

0

102

12%

1%

2%

0%

85%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Razones por la cual no utilizaría el Combi/Bus para su transporte 120

85% 100

80 60 40 20

0

12%



Inseguridad

1% Altos costos de transporte

2% Accidentes

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

o% Otro

NS/NO

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Capítulo IV: Impactos del de la Infraestructura Vial

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

IV.

IMPACTOS DE LA INFRAESTRUCTURA VIAL. A continuación se detallan los principales impactos que se determinan cuando se realiza la intervención en la vía de estudio:

4.1

Principales Problemas Identificados en la Zona. De acuerdo a los resultados obtenidos de la encuesta, se ha determinado que los principales problemas se constituyen en: existencia de polvo en la zona como consecuencia del flujo de transporte vehicular el 99%, en segundo lugar se encuentra a que la vía se encuentra con baches (huecos) para el 68% de las familias, además el 26% de las familias sostienen que en la vía ocurren frecuentes accidentes. Y otros problemas que se tiene en la zona de estudio en menor medida como: asaltos, anegamiento, barros, ruidos y otros.

Cuadro: 4.1.1: Principales Problemas de la Zona Problemas en la zona Problemas

Frec. Abs.

Frec. Relativa

Accidentes

31

26%

Baches

54

45%

81

68%

Huecos Polvo

119

99%

Transito

50

42%

Otros

30

25%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Principales p ro b le m a s id e n tific a d o s en la zona

Transito

Otros

Accidentes

8%

8%

Baches

14%

4.2

Efectos de dichos Problemas en la Población De acuerdo a los principales problemas identificados por la población, esta no lleva a determinar los p rin c ip ie s efectos qu£)generan cáda una d e ,e llo s / .

A m n á r d tT íá z A r e v a l o íe p re s e n ta n te Legal

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

FefímtioRíif^Leii n

5 ’

C IP

40894'

(MGENtERC

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Para el 3% de la población se genera enfermedades respiratorias por efectos de la alta incidencia del polvo en la zona, así como otras enfermedades que sufren la población (alergias en 1%), además de que sus viviendas paran sucias y se deterioran los artefactos con las que cuentan las familias (10%) en general afectan a su salud en 92% lo cual lógicamente influye en el deterioro de su economía (73%) de las familias en la zona. Inseguridad en el transporte 42%, demora en el tiempo de llega 49%, Y otros efectos que ocasiona a las familias en la zona de estudio

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 4.1.2: Efectos de los Problemas en la Población Como afecta a las Familias dichos problem as Efectos

Frec. Absoluta

Salud

Frec. Relativa

110

92%

Economía

88

73%

Inseguridad en el tra nspo rte

50

42%

Demora en el tie m p o de llegada

59

49%

Polvo

4

3%

Otros

2

2%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Efectos de los problemas identificados Otros Demora Polvo 2% en el

3°/

Insegurida d en el tra n sp o rte

42'

4.3

Peligrosidad de la Vía La percepción de la población acerca de la peligrosidad del área de influencia de la vía, considera en 57% si es peligrosa en el área de influencia del proyecto, mientras que solo para el 43% de la población la zona de la vía en estudio no es peligrosa.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Cuadro: 4.1.3: Peligrosidad de la Vía Descripción

La via en estudio es peligrosa Si

No

Frec. Absoluta Frec. Relativa

68

52

57%

43%

Fuente; Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Es peligroso la via en estudio

4.4

Eventos de peligrosidad ocurridos en la Zona. Del 99% de la población que afirma que la zona de influencia de la vía es peligrosa, manifiestan que los principales eventos peligrosos que ocurren en la zona se detallan a continuación: El robo es principal evento peligroso que ocurre en la zona, según lo afirma el 91% de las familias, ocurre maltrato como consecuencias de los asaltos en la zona 3%, ocurre violación como consecuencias de los asaltos en la zona 3% y otros tipos de peligros que ocurre para el 3% de las familias.

Cuadro: 4.1.4: Eventos Ocurridos de Peligrosidad Tipo de eventos peligrosos que ocurre

Descripción Robo

Violacion

M a ltra to

O tro

Frec. Absoluta

109

3

4

Frec. Relativa

91%

3%

3%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

4 3%

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Tipos de eventos peligrosos

4.5

M a ltra to

0 tro

3%

3%

Beneficios esperados de la Mejora de la Vía. La población afirma que, con la mejora de la vía se tendrán los siguientes beneficios esperados: El 100% de la población cree que se produjeran la disminución de la incidencia de enfermedades oculares y disminución de las enfermedades respiratorias. Además, se produjera la disminución de enfermedades respiratorias, según la percepción de la población en 99%, ahorro en el lavado de la ropa y el uso del agua 100%.

Cuadro: 4.1.5: Beneficios Esperados de la Mejora de la Vía Disminución de enfermedades oculares

Disminución de enfermedades respiratorias

Disminución del polvo en el ambiente

Beneficios de la vía una vez pavimentada Ahorro en el Seguridad en el lavado de ropa y Seguridad en la zona transporte uso de agua

Disminución de de Mayor rapidez en Dstos de llegada a su transporte destino

Otro

120

119

119

120

119

120

119

86

8

100%

99%

99%

100%

99%

100%

99%

72%

7%

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

Consorcio

A m pjtfo D íaz Ur'evulo ^ R e p r e s e n ta n te L e g a l

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

1(* g e w ‘Er O C ‘ v " -

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Beneficios sociales de la via una vez pavimentada Disminución de

Disminución de de

Mayor rapidez en

enfermedades

llegada a su destino

oculares

9%

13% Disminución de

Dstos de transporte

enfermedades

13%

respiratorias

12%

Ahorro en el lavado de ropa y uso de agua 13%

De acuerdo a la encuesta realizada también se ha determinado los beneficios de la población en términos monetarios en forma indirecta del proyecto (una vez mejorada la vía), tal como se aprecia en el siguiente cuadro:

Cuadro: 4.1.6: Beneficios en Términos Monetarios Beneficios de la via una vez pavim entada en S/. Disminución de

Dism inución de

A horro en el

enferm edades

enferm edades

lavado de ropa y

oculares

respiratorias

uso de agua

11.50

7.90

18.25

Fuente: Encuesta Socioeconómica del Proyecto Elaboración: Consultor.

C»V|l-

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

Beneficios de la poblacion una vez m ejorada la via en S /.

Ahorro en el lavado de ropa y uso de agua

18.25

Disminución de enfermedades respiratorias

Disminución de enfermedades oculares

11.50

0.00

5.00

10.00 15,00 20.00

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

MEJORAMIENTO DE VIA DE INTERCONEXION AL CENTRO POBLADO SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI

V. •

CONCLUSIONES La población de la zona de estudio está constituida por 49% mujeres y 51% de varones, esta proporción tiene relación con los datos obtenidos en el último censo realizado por el INEI en el año 2007 donde se da una tendencia del 51% varones y 49% mujeres



Los niveles educativos de los jefes de familia (tanto mujeres como varones) se tiene principalmente el 34% cuenta con secundaria completa, lo que determina que para las siguientes generaciones los niveles educativos se desarrollaran mejor en cuanto a los estudios de nivel superior de la población.



En cuanto a las características de sus viviendas, en la zona predomina el piso de cemento (45%), la construcción de la vivienda predomina pared de madera con techo de calamina, y que su techo es de cobertura liviana, así es del 31% de las viviendas en la zona.



La dotación del servicio de saneamiento básico, cuentan con el servicio de agua el 4%, las familias que no cuentan con servicio de agua potable de red pública (96%), cabe precisar que el aprovisionamiento del agua de los que no cuentan con el servicio se da a través de la compra de triciclos o vecinos que tienen conectadas el servicio.



Principalmente la población se dedica ser trabajador independiente (73%), es decir sus actividades están dedicadas al comercio, y otras actividades de sub empleo, el 18% de la población viene a ser estudiante.



Los efectos que genera las condiciones actuales de la vía en estudio, se tiene que sufren de enfermedades de respiratorias el 75%, de enfermedades oculares el 25%, enfermedades vectoriales el 22% y de enfermedades diarreicas agudas 8%.



La población percibe que las condiciones actuales la vía en estudio se encuentra en malas condiciones el 53%, lo que determina la intervención de la vía, con la finalidad de mejorar las condiciones de la población que vive y transita en la z o n a ^ ^ . OIVI



El principal medio de transporte utilizado en el servicio de transporte, por parte ralfalS:*'’ población estada dado por moto lineal (53%) y motokar (47%) en menor mecida por el colectivo y su propia unidad de transporte (principalmente moto lineal).



Para el 53% de la población los costos de transporte diario en que incurren representan aproximadamente mayor a S/. 3.00 nuevos soles, lo que ocurre por la frecuencia de viajes que realiza a sus lugares de destino.



Los principales beneficios esperados de la mejora de la vía, determinados por la población vienen a ser disminución de las enfermedades respiratorias y oculares, disminución del polvo en el ambiente, lo g y e ilfiiía ra al ahorro el consumo del a g u í y el lavado de la ropa, disminución de>t6s costos de transporte y mayor ra p ^ e z en la llegada sus destinos. R tffcie sfcn ta n te L e g a l

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

*

¡ Ñ S 6 N 16P O O V l t

FACTIBILIDAD DEL PROYECTO: “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA - CORONEL PORTILLO - UCAYALI”

^53& n

? 7 3

ESTUDIO DE IMPACTO AM BIENTAL FACTIBILIDAD DEL PROYECTO:

"M EJO RAM IENTO DE IN T E R C O N E X IO N AL C. P. SAN JOSE DESDE PUERTO CALLAO, D IS T R IT O DE YARINACOCHA CORONEL PO R TILLO - U C A YA LI"

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

M ejoram iento de Vías de Intersección al C entro Poblado San José desde Puerto Callao, d is trito de Yarinacocha Coronel P o rtillo - Ucayali”

^UCAD£*. ■».

——

¡-

V

/o ouo*«»ir'5ii7iv A /or UK9E0CTUMCK1W 4'VLA

iiH ü J i®

m a n i m

í»

ESTUDIO AMBIENTAL - DIA

FACTIBILIDAD DEL PROYECTO: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA- CORONEL PORTILLO - UCAYALI”

2012

DIVISION DE ESTUDIOS Y OBRAS E INFRAESTRUCTURA SOCIAL Y PRODUCTIVA

FtCA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

INDICE

1.

DATOS GENERALES.

2.

DESCRIPCION DEL PROYECTO

3.

4.

2.1.

Datos generales del proyecto.

2.2.

Características del proyecto.

2.3.

Actividades asociadas o generadas por el proyecto

MARCO INSTITUCIONAL Y LEGAL. 3.1.

Marco institucional.

3.2.

Marco legal.

ASPECTOS

DEL MEDIO

FISiCO,

BIOTICO,

SOCIAL,

CULTURAL Y

ECONOMICO (LINEA BASE). 5.

PLAN DE PARTICiPACíON CIUDADANA.

6.

DESCRIPCION DE LOS POSIBLES IMPACTOS AMBIENTALES.

7.

MEDIDAS

DE

PREVENCION,

MITIGACION,

REMEDIACION

Y

COMPENSACION. 8.

PROGRAMA DE MANEJO DE RESIDUOS SOLIDOS Y LIQUIDOS.

9.

PROGRAMA DE SEGUIMIENTO Y CONTROL.

10. PLAN DE CONTINGENCIA. 11. PROGRAMA DE CIERRE DE EJECUCION DE OBRA DEL PROYECTO Y PROGRAMA DE ABANDONO. 12. CRONOGRAMA DE EJECUCION. 13. PRESUPUESTO DE IMPLEMENTACION. 14. CLASIFICACION AMBIENTAL. ANEXOS

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL - FtCA

(13 FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

FIC H A IN FO R M A T IV A DE C LA S IF IC A C IO N A M B IE N T A L (FIC A ) P A R A PRO YEC TO S DE S A N E A M IE N TO 1.

DATOS GENERALES. 1.1.

Titular del proyecto.

Mencionar la Razón social de la 1.1.1. empresa o nombre de la entidad pública, otros.

MUNICIPALIDAD DISTRITAL DE YARINACOCHA

1.1.2. Numero de RUC de ser el caso.

20154435965

1.1.3.

Dirección legal (mencionar distrito, provincia, departamento/región).

Jr. 2 de Mayo N° 277- Yarinacocha

Nombres completos del representante legal (deberá acreditar mediante 1.1.4. documentos legalizados) y mencionar su numero de DN/.

ALCALDE EDWIN DIAZ PAREDES DNI N° 00071628

1.1.5. Teléfono y/o fax.

Teléfono: 061 590407

1.1.6. Correo electrónico.

1.2.

mun¡varinacocha(3>speedv.com.pe ; yarinacocha@ yarinacocha. puca. md. gob. pe

Proponente (de ser el caso).

1.2.1.

Mencionar la Razón social de la empresa o nombre de la entidad pública, otros.

Fernando Rafael Lean. Ingeniero Civil

1.2.2.

Numero de RUC de ser el caso.

10182053321

Nombres completos del representante legal (deberá acreditar mediante 1.2.3. documentos legalizados) y mencionar su numero de DNI.

Fernando Rafael Lean. DNI N° 18205332

1.2.4.

Domicilio legal (mencionar distrito, provincia, departamento/región).

Jr. Arlfonso Ugarte 244 - Calleria - coronel portillo

1.2.5.

Teléfono y/o fax.

061 570190

1.2.6. Correo electrónico. 1.2.7.

Adjuntar copia legalizada del contrato suscrito por el titu la r del proyecto.

[email protected] Documento en anexos

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

1.3.

Empresa y/o entidad autorizada

para la elaboración del presente

docum ento (llenar solo el que corresponda). Mencionar la razón social de la empresa o entidad inscrita en el registro de empresa 1.3.1. autorizada para elaborar EIA en el Sector VIVIENDA.

SERVICIOS GENERAL ASCONSULT S.R.L

1.3.2.

20393230879

Numero de RUC.

Nombres completos del representante legal (deberá acreditar mediante 1.3.3. documentos legalizados) y mencionar su numero de DNI.

Edwin Rafael Lean

Número de registro inscrito en el sector

1.3.4. VIVIENDA, (adjuntar copia de Resolución

145

Directoral vigente) Profesionales registrados que participan en la elaboración del presente documento 1.3.5. (indicar numero de colegiatura y copia del certificado de habilidad del colegio profesional respectivo)

1.3.6.

Domicilio legal (mencionar distrito, provincia, departamento/región).

1.3.7. Teléfono y /o fax.

Quím ico Edwin Rafael Lean Colegiatura N° 75406

Calle Las GardiniasMz.“C” - Lt. “04 ”, Distrito de Yarinacocha, Provincia de Coronel Portillo, Región Ucayali 061 -570190 frlean27(a>hotmail.com Jucamacaía>hotmail.com

1.3.8. Correo electrónico. Adjuntar copia legalizada del contrato

1.3.9. suscrito con el titu la r del proyecto o el

Documento en anexos

ponente.

2.

DESCRIPCION DEL PROYECTO 2.1.

Datos generales del proyecto. 2.1.1. Nombre: “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN

JOSÉ

DESDE

PUERTO

CALLAO,

DISTRITO

DE

YARINACOCHA, CORONEL PORTILLO - UCAYALI” . Código SNiP 149054. El proyecto se encuentra en la fase de

PRE - INVERSION

(Factibilidad) y NO pertenece a un programa de inversión.

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL • FICA CONSORCIO Gffl 4 SG A! CIP. N* 75406 ESPECIALISTA EN GESTION AMBIENTAL

A rn n jrfij D ihz -Afet>a lo • ¡P R E S E N T A N T E

leg a l

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

2.1.2. La

Unidad

Formuladora

YARINACOCHA,

la

es

MUNICIPALIDAD

Unidad

Ejecutora

DISTRITAL DE YARINACOCHA,

es

DISTRITAL

DE

MUNICIPALIDAD

la Evaluadora es OPI de la

MUNICIPALIDAD DISTRITAL DE YARINACOCHA y la Fuente de Financiamiento son el canon y sobre canon, regalías, renta de aduanas y participaciones 2.1.3. Actualmente

la

zona

presenta

una

deficiente

plataforma

de

transitabilidad afirmado, mal nivelado. Por la cual el proyecto viene interviniendo la zona, por ello podemos decir que la situación actual de la vía está en mal estado, siendo ésta la que permite la interconexión vial entre la zona rural y urbana del Distrito de Yarinacocha, contribuyendo al turismo en el centro Poblado San José, Yarinacocha y a la venta de artesanías. El número de beneficiarios directos a lo largo de la vía asciende a 587 personas que viven al margen del proyecto. Y los beneficiarios indirectos son los pobladores que tienen influencia a la vía y son 2860 personas. 2.1.4. La ejecución del proyecto reducirá accidentes de tránsito, así como también los costos en el trasporte de productos agrícolas y las tasas de contaminación de aire. 2.1.5. Costo de ¡a ejecución del proyecto: COSTO DE EJECUCION

S/. 16'123,133.36

2.1.6. El costo de operación y mantenimiento: COSTO DE OPE y MAN ORDINARIO

S/.

111,521.09

COSTO DE OPE y MAN EXTRAORDINARIO:

S/.

245,224.44

2.1.7. El tipo de zonificación donde se ejecuta el proyecto es Urbano Marginal _Rural. 2.1.8. Localización. a) Región / departamento : UCAYALI b) Provincia

: CORONEL PORTILLO

c) Distrito

: YARINACOCHA

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIEN TAL - FICA

(J J P FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

d) Localidad

:SAN PABLO DE TUSHMO, PUERTO CALLAO, C.P. SAN JOSE

2.1.9. Ubicación de! proyecto: Geográficamente el área a intervenir se encuentra ubicada a 770 Km de la ciudad de Lima y a 5.00 Km aproximadamente de la ciudad de Pucallpa, al margen izquierdo del rio Ucayali y a orillas de la laguna Yarinacocha por el centro poblado de San José.

Nota: Se adjunta el plano de ubicación y localización del proyecto a escala visible con coordenadas UTM (a colores), y se adjunta fotos. 2.1.10. Tiempo de vida útil deí proyecto según eí estudio a nivel de pre inversión es de 10 años, 2.1.11. El proyecto por ser una vía de acceso y de comunicación, ya tiene su delimitación vial definida por la Municipalidad Distrital de Yarinacocha, la cual dentro de su plano catastral esta definida el límite del proyecto. Nota: se adjunta el plano brindada por la Municipalidad Distrital de Yarinacocha, para su verificación. 2.1.12. Antecedentes o aspectos que es necesario conocer sobre el provecto. Los beneficiarios directos son los habitantes residentes en la avenida, la cual actualmente representa 587 habitantes, los niveles de vida de la población es baja, por lo mismo se ubican en situación de pobreza, las viviendas por lo general son de pared de madera, con techo de madera y calamina, la mayoría cuenta con servicio de agua de red pública, electricidad, se aprecia déficit en servicios de desagüe, bajos niveles de ingreso, siendo la principal actividad económicas los trabajos independientes. La Sostenibilidad del proyecto se refiere a la posibilidad que el proyecto genere los beneficios esperados a lo largo de su vida y están referidos a los arreglos institucionales (logística) previstos para las fases de operación y mantenimiento del proyecto. Por un lado se t i e ^ el compromiso del financiamiento del proyecto por parte de Municipalidad, mientras que la operación y mantenimiento est

FICHA INFORM ATIVA DE C LA S ipQ A C IO N AM BIENTAL - FICA

y

O d- —

____

In c jS d w ta RaíafiÍDean 7 C IP .N * 75406 EC IALK TAEN GESTION AMBIENTAL

C 0 N S 0 H M F W

.» » K C 0 N S U L T 5 J 1

C ^X / _______ I

,

\^ a r o W

/

h

' - l 3 ¿ —

* * Z J & e V b ,n

9 PRESENTANTE LEGAL

i

. . . y

'

^

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI”.

financiado por canon, sobre canon, regalías, renta de aduanas y participaciones que recibe la misma Municipalidad

Distrital de

Yarinacocha. 2.2.

C aracterísticas del proyecto. 2.2.1. Etapa de Planificación. A. Dentro de la etapa de planificación se tendrá en cuenta actividades previas como: .

Obras Preliminares, dentro de ello se considerará el alquiler de almacén y oficina.

.

Trabajos

Prelim inares

como:

Alquiler

de

almacén,

Desmontaje de alcantarillas existentes, Retiro de arboles existentes, Limpieza de terreno manual, Trazo, niveles y replanteo, Cartel de identificación De la obra 1.80 x 3.60 m, Transporte de equipos y herramientas, Mejoramiento de vías de acceso. B. La población beneficiaría directa con la ejecución del proyecto es de 587 hab., a su vez la población beneficiaria indirecta es de 2860 habitantes 2.2.2. Etapa de ejecución. A.- Instalaciones Las Instalaciones que se habilitaran para la ejecución del proyecto son los siguientes: •

Oficina /Almacén. El almacén será un local cercano a la obra, que servirá como resguardo a los materiales, equipos y herramientas que serán utilizados en la obra, brindando protección //^

seguridad. •

I

O ficinas y SS.HH. La Oficina será habilitada dentro del local del almacén para poder facilitar la adecuada administración y uso de los

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL ¿ fe

'

£

CONSORCOTfL iy m m tíip .R .1

CIPc N« c w ¡ 5 i u a i f ü T i i

rpip p iíro ú ro U td ^ A í^ u a lo A p ""^ P R E S E N T A N T E LEG AL

ESPECIALISTA EN GESTION AMBIENTAL

REPRESENTANTE LEG AL

\

'

...

iw f t f c M t f c fW O V Í L

FtCA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

diferentes insumos, los servicios higiénicos serán ubicados en un espacio donde puedan hacer uso el personal que labora en el proyecto, cabe indicar que en la longitud de la vía a construir se pueden ubicar casetas transportables en el uso de los SS.HH. •

Servicios. Para el desarrollo del proyecto se requerirán: Agua. -

Consumo Total: 13, 023 m3

-

Fuente. Privada

-

Red de Agua Potable: de EMAPACOP S.A

-

Superficial: NO

-

Subsuelo:

SI

(Sector

1B

del

Plan

Maestro

de

EMAPACOP S.A.) Electricidad: -

Consumo : Mínimo / Variable

-

Potencia requerida : N/D

-

Fuente: Privada

-

Red de Distribución: ELECTROUCAYALI S.A.

-

Fuente Propia : No

B.- Detalle de los componentes del proyecto y sus metrados' •

EXPEDIENTE TECNICO. Consiste en la elaboración de un estudio definitivo que esta en la etapa de ejecución.



SUPERVISION E INSPECCION Se desarrolla en la etapa de ejecución del proyecto, son los encargados de hacer cumplir la ejecución del proyecto teniendo como base el expediente técnico.

FICHA INFORM ATIVA DE

SIFICACION AM BIENTAL - FICA ^

CIP. N " 75406 ESPECIALISTA Eál GESTION AMBIENTAL

CONSTO FRl i S O ^O N S W flll.

Apijía n>U iTnr-Afv ualo PRESEN TAN TE

le g a l

FtCA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYAU".



OBRAS CIVILES La vía abarca una longitud de 4.690 Kmy se tiene registrado a ambos lados de la vía los siguientes centros poblados



LUGAR

POBLACION

1 Intersección Jr. 3 de Octubre 2

75

Jr. San Alejandro.

135

3 A.H.Intercultural Nueva Era. 4

100

Caserío San Pablo de Tushmo

2,000

5 C. P.M. San Lorenzo 6

350

C. P.M. San José

EN EL MEJORAMIENTO DE

200 2,860.00

VÍA DE INTERCONEXIÓN

TENEMOS: 01 Obras Preliminares. Se refiere al alquiler del almacén, reubicación de postes de teléfono, templadores de postes, también la tala de árboles y la señalización informativa de desvío- vías alternas. Item

Descripción

Unid.

Metrado

01.01

ALQUILER DE ALMACEN

MES

10.00

01.02

REUBICACION DE POSTES DE TELEFONO

unid

20.00

01.03

REUBICACION DE TEMPLADORES DE POSTES

unid

10.00

01.04

TALA DE ARBOLES

unid

149.00

01.05

SEÑALIZACION INFORMATIVA DE DESVIO - VIAS ALTERNAS

UND

1.00

02 Trabajos preliminares Es el trazo, nivelación y replanteo del área del proyecto^ trasporte de equipos y herramientas, colocación del cartel de identificación de la obra, posteriormente la limpieza del terreno manualmente.

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Item

Descripción

Unid.

Metrado

02.01

TRAZO, NIVELACION Y REPLANTEO

02.02

TRANSPORTE DE EQUIPOS Y HERRAMIENTAS

GLB

1.00

02.03

CARTEL DE IDENTIFICACION DE LA OBRA 3.60 x 2.20M

unid

4.00

02.04

LIMPIEZA DE TERRENO MANUAL

m2

57,742.35

m2

57,742.35

03 Seguridad y salud 03.1 Elaboración, implementación y administración de! pian de seguridad y salud en el trabajo Se

refiere

a

la

elaboración,

implementación

y

administración del plan de seguridad y salud en el trabajo, compra de equipos de protección individual y colectiva, señalización temporal de seguridad y a la capacitación Item

Descripción

Unid.

Metrado

03.01.02

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD YSALUD EN EL TRABAJO EQUIPOS DE PROTECCION INDIVIDUAL

unid

100.00

03.01.03

EQUIPOS DE PROTECCION COLECTIVA

GLB

1.00

03.01.04

SENAUZACION TEMPORAL DE SEGURIDAD

GLB

1.00

03.01.05

CAPACITACION EN SEGURIDAD Y SALUD

GLB

1.00

03.01.01

03.2

Recursos

para

respuestas

ante

GLB

1.00

emergencias

en

seguridad y salud durante el trabajo. Consiste en contar con recursos para respuestas ante emergencias en seguridad y salud durante el trabajo. - Item 03.02.01

Descripción RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO

Und. Metrado GLB

1.00

04 Movimiento de tierras Es la parte principal de la ejecución, ya que implica los trabajos en el terreno con la finalidad de habilitarlo para la ejecución de los trabajos de pavimentación y drenaje, tiene las

(16)> FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Descripción

Item

Unid.

Metrado

04.01

CORTE DE MATERIAL A NIVEL DE SUB-RASANTE

m3

04 02

RELLENO CON MATERIAL PROPIO PARA NIVELAR SUB RASANTE

m3

171.63

04.03

COMPACTACION Y CONFORMACION DE SUB-RASANTE

m2

48,579.70

m3

11,548.47

M3

15,013.01

04.04

CORTE DE TERRENO CON EQUIPO EN ZONA DE MATERIAL ORGANICO RELLENO CON MATERIAL DE PRESTAMO EN ZONA DE MATERIAL ORGANICO RELLENO COMPACTADO CON MATERIAL PROPIO - MARTILLO

04.05 04.06

736.05

m3

1,640.58

04.07

EXCAVACION MANUAL SARDINEL

m3

69 30

04.08

RELLENO Y COMP.MATERIAL PROPIO SARDINEL

m3

17.16

04.09

EXCAVACION MANUAL PARA CANALETAS

M3

3,396.30

04.10

RELLENO COMPACTADO CON MATERIAL PROPIO - CANALETAS

m3

179.92

04.11

ELIMINACION DE MATERIAL EXCEDENTE

m3

17,863.10

05 Pavimentos Consiste en la ejecución de las siguientes actividades y metrados. Item

Descripción

Und.

Metrado

05.01

SUB BASE GRANULAR

m2

05.02

ENCOFRADO Y DESENCOFRADO LOSA DE CONCRETO

m2

3,243.50

05.03

PAVIMENTO DE CONCRETO F'C= 210 KG/CM2 E=0.20 M

m2

48,574.70

05.04

ACERO DE REFUERZO EN BERMAS F'Y=4200 KG/CM2

kg

66,640.67

05.05

ACERO DE REFUERZO EN CALZADA F'Y=4200 KG/CM2

169,380.69 5,116.10

05.06

ACERO CORRUGADO (BASTONES EN JUNTAS TIPO 1)

kg KG

05.07

ACERO CORRUGADO (BASTONES EN JUNTAS TIPO 3)

kg

48,551.70

31,922.44

06 Juntas Consiste en el relleno de juntas asfálticas. Item

Descripción

Und.

Metrado

06.01

RELLENO DE JUNTAS ASFALTICAS DE 9 mm

m

34,691.94

06.02

RELLENO DE JUNTAS ASFALTICAS DE E= 20 mm

m

5,862.00

07 Obras de drenaje Consiste en trabajos preliminares, armado de canaletas concreto y sardineles. Item 07.01 07.01.01 07.02

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES TRAZO, NIVELACION Y REPLANTEO

ML

8,255.39

CONCRETO ARMADO - CANALETAS

07.02.01

CONCRETO CANALETAS (losa de fondo y paredes fe = 210 kg/cm2)

m3

1,521.03

07.02.02

CONCRETO CANALETAS (TECHO fe = 210 kg/cm2)

m3

440.39

07.02.03

CONCRETO F'C= 175 KG/CM2- LOSA/FONDO Y PAREDES

M3

1.00

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL - FICA

CIP. N* 75406 c S P E C U U S W E li GESTION A M H V M L

répíésentante legal

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

07.02.04 07.02.05 07.02.06 07.02.07 07.02.08 07.03

07.03.01 07.03.02 07.03.03 07.03.04

CONCRETO F'C= 210 KG/CM2 EN TECHOS / TAPAS ENCOFRADO Y DESENCOFRADO DE CANALETAS ACERO DE REFUERZO F'Y=4200 KG/CM2 CANALETAS ACERO DE REFUERZO PY=4200 KG/CM2 WATER STOP NEOPRENE 6" EN CANALETAS

M3 M2 kg kg M

1.00 13,512.34 111,149.16 1.00 1,327.90

SARDINELES

CONCRETO F'C= 175 KG/CM2 EN SARDINELES ENCOFRADO Y DESENCOFRADO DE SARDINEL ACERO DE REFUERZO F'Y=4200 KG/CM2 SARDINELES ACERO DE REFUERZO F'Y=4200 KG/CM2

m3 m2 kg kg

117.00 1,559.88 5,105.26 1.00

08 Concreto en martillos y rampas Tienes las siguientes acciones y metrados. Item

Descripción

Und.

Metrado

08.01

ENCOFRADO Y DESENCOFRADO DE MARTILLOS Y INTERSECCIONES

m2

578.96

08.02

CONCRETO F’C=140 KG/CM2 PARA MARTILLOS

m3

2,381.49

09 Sistema De Muro De Contención (Terramesh Verde) Tienes las siguientes acciones con sus respectivos metrados. Item 09.01

Descripción

Und.

Metrado

TRABAJOS PROVISIONALES

09.01.01

LIMPIEZA DE TERRENO

m2

300.00

09.01.02

TRAZO, NIVEL Y REPLANTEO

m2

300.00

09.01.03

SEÑALIZACION Y SEGURIDAD EN ZONA DE TRABAJO

und

2.00 1,048.95

09.02

MOVIMIENTO DE TIERRAS

09.02.01

CORTE DE TERRENO A MAQUINA

m3

09.02.02

NIVELACION Y COMPACTADO DEL TERRENO

m2

300.00

m2

250.00

und

3,390.00

m3

44,096.00

09.02.03 09.03 09.03.01 09.03.02

CONFORMACION DE LA SUB RASANTE SISTEMA DE MURO DE CONTENCION - SUELO REFORZADOíTERRAMESH VERDE) SUNMNiSTRO E INSTALACION SISTEMA TERRAMESH VERDE (2.00 X 4.00 X 0.60) RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

10 Construcción de alcantarilla n° 1 (1.60m x 1.00mm x 32.50) - progresiva: 0+126.95 Tienes las siguientes acciones con sus respectivos metrados. Item 10.01

Descripción

Und.

10.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

10.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

10.02 10.02.01 10.02.02

Metrado

TRABAJOS PRELIMINARES

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL DE MATERIAL ORGANICO RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

FICHA INFORM ATIVA DE

■ICACION AM BIENTAL ■ FICA

rv el

Lean

¿SPECIAUSTA E li GESTION AMBIENTAL

Á in jy ir o O iT T T ^ f^ a lo íjrp R E S E N T S U T E l e g a l '■'írPRÍ

138.00 , 0

y

m3

is í m

i

m3

V

FICA proyecto: "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

10.02.03 10.03 10.03.01 10.04 10 04.01

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

97.18

SOLADO 1:10 E= 4"

m2

74.75

OBRAS DE CONCRETO ARMADO LOSA INFERIOR

10.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

10.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

10.04.02

m3

OBRAS DE CONCRETO SIMPLE

m3

15.20

kg

768.38

MUROS REFORZADOS

10.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

13 96

10.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

139.60

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

877.63

10.04.02.03 10.04.03

LOSA SUPERIOR

10.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

13.00

10.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

65.80

ACERO DE REFUERZO FY=4200 KG/CM2

kg

686.43

ML

5.90

10.04.03.03 10.04.04 10.04.04.01

JUNTA DE DILATACION JUNTAS DE DILATACION CON WATER STOP

11 Construcción de alcantarilla n° 2 (2.00m x 2.00m x 13.00) progresiva: 0+620 Se considera las siguientes actividades con sus metrados Item 11.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

11.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

66.00

11.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

31.20

11 02

MOVIMIENTO DE TIERRAS

11.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

35.10

11.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

35.10

11.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

45.63

m2

35.10

11.03 11.03.01 11.04 11 04.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR

11.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

11.04.01.02

ACERO DE REFUERZO FY=4200 KG/CM2

11.04.02

m3

7.31

kg

654.02

MUROS REFORZADOS

11.04.02.01

CONCRETO F’C=210 KG/CM2 EN MUROS REFORZADOS

m3

10.35

11.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

103.52

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

989.32

11.04.02.03 11.04.03

LOSA SUPERIOR

11.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

6.24

11.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

32.16

11.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

579.69

(& FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

12 Construcción de alcantarilla n° 3 (1.00m x 1.50m x 12.95) progresiva: 1+028.60 Se considera las siguientes actividades y metrados ítem 12.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

12.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

50.83

12.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

18.13

12.02

MOVIMIENTO DE TIERRAS

12.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

22.02

12.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

22.02

12.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

28.62

m2

22.02

12.03 12.03.01 12.04 12.04.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10 E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR

12.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

4.59

12.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

287.39

12.04.02

MUROS REFORZADOS

12.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

12.10

12.04.02.02 12.04.02.03

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

120.96

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

585.71

12.04.03

LOSA SUPERIOR

12.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

2.59

12.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

13.35

12.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

246.79

13 Construcción de alcantarilla n° 4 (1.00m x 1.50m x 12.35) progresiva: 1+928.40 Se considera las siguientes actividades con sus respectivos metrados. Item 13.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

13.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

48.79

13.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

17.29 21.00

13.02

MOVIMIENTO DE TIERRAS

13.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

13.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

21.00

13.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

27.29

m2

21.00

13.03

OBRAS DE CONCRETO SIMPLE

13.03.01 13.04

OBRAS DE CONCRETO ARMADO

13.04.01

SOLADO 1:10 E= 4" LOSA INFERIOR

13.04.01.01

CONCRETO F’C= 210 KG/CM2. EN LOSA INFERIOR

m3

4.36

13.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

281.13

13.04.02

MUROS REFORZADOS

13.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

12.10

13.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

120.96

FICA p ro y e c to : “MEJORAM IENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JO SÉ DESDE PUERTO CALLAO , DISTRITO DE YARINACOCHA, CORONEL PO RTILLO - U C A Y A LI".

13.04.02.03 13.04.03

13.04.03.01 13.04.03.02 13.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

574.57

m3 m2

3.46 15.38 246.79

LOSA SUPERIOR

CONCRETO F’C= 210 KG/CM2. EN LOSA SUPERIOR ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR ACERO DE REFUERZO FY=4200 KG/CM2

kg

14 Construcción de alcantarilla n° 5 (0.80m x 1.00m x 12.30) progresiva: 3+273.50 Se considera las siguientes actividades y metrados Item 14,01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

14.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

45.76

14.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

14.76

14.02

MOVIMIENTO DE TIERRAS

14.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

18.45

14.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

18.45

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

23.99

m2

18.45

14.02.03 14.03 14.03.01 14.04 14.04.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10 E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR

14.04.01.01

CONCRETO FC= 210 KG/CM2. EN LOSA INFERIOR

m3

3.85

14.04.01.02

ACERO DE REFUERZO FY=4200 KG/CM2

kg

194.74

14 04.02

MUROS REFORZADOS

14.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

5.60

14.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

56.00

ACERO DE REFUERZO FY=4200 KG/CM2

kg

327.05

14.04.02.03 14.04.03

LOSA SUPERIOR

14.04.03.01

CONCRETO FC= 210 KG/CM2 EN LOSA SUPERIOR

m3

2.95

14.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

12.70

14.04.03.03

ACERO DE REFUERZO FY=4200 KG/CM2

kg

171.33

15 Construcción de alcantarilla n° 6 (1.20m x 1.60m x 32 progresiva: 3+563.45 Se considera las siguientes actividades y metrados Item 15.01

Descripción

Und.

TRABAJOS PRELIMINARES

15.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

125.28

15.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

52.48 106.07

15.02

MOVIMIENTO DE TIERRAS

15.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

15.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

62.32

15.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

137.89

m2

62.32

m3

12.67

15.03 15.03.01 15.04 15.04.01 15.04.01.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10 E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

FICHA INFORM ATIVA Q S -fLA S IFIC A C IO N AM BIENTAL - FICA CONSORCI CIP. N* 75406

i S ftC IA U S T A EN GESTION M M iE N U L

A m p a p t 'lN a z W

& h i/ o

^ ESFNTANTE le g a l

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

15.04.01.02 15.04.02

ACERO DE REFUERZO FY=4200 KG/CM2

kg

775.05

MUROS REFORZADOS

15.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

28.10

15.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

281.04

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

1,458.63

15.04.02.03 15.04.03

LOSA SUPERIOR

15.04.03.01

CONCRETO FC= 210 KG/CM2. EN LOSA SUPERIOR

m3

12.46

15.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

52.88

15.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

493.08

16 Construcción de alcantarilla n° 7 (1.20m x 1.70m x 12.80) progresiva: 3+852.90 Se considera las siguientes actividades y metrados Item 16.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

16.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

50.32

16.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

20.48 24.32

16.02

MOVIMIENTO DE TIERRAS

16.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

16.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

24.32

16.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

31.62

m2

24.32

16 03 16.03.01

OBRAS DE CONCRETO SIMPLE

16.04

OBRAS DE CONCRETO ARMADO

16.04.01

SOLADO 1:10 E= 4" LOSA INFERIOR

16.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

5.07

16.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

424.91

16.04.02

MUROS REFORZADOS

16.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

8.87

16.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

88.70

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

747.76

16.04.02.03 16.04.03

LOSA SUPERIOR

16.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

4.10

16.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

21.08

16.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

376.31

17 Construcción de alcantarilla n° 8 (1.20m x 1.70m x 12 progresiva: 3+951.80 Se considera las siguientes actividades y metrados Item 17.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

17.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

42.90

17.01.02

TRAZO, NIVELACION Y REPLANTEO DE ALCANTARILLADO

m2

17.22

m3

20.91

17 02 17.02.01

MOVIMIENTO DE TIERRAS EXCAVACION MANUAL DE MATERIAL ORGANICO

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL - FICA

U /\

F r i w i n R a f a n l\ | c a n

ESPECIALISTA

EN GESTIONA lU fU U t

ro (ljT 7 T T -A ftria lo ^ « E S E N T A N T E LEG AL

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

17.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

20.91

17.02.03

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

27.18

m2

20.91

17.03 17.03.01

17.04 17.04.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR

17.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

17.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

17.04.02

m3

4.37

kg

233.25

MUROS REFORZADOS

17.04.02.01

CONCRETO F'C=210 KG/CM2 EN MUROS REFORZADOS

m3

6.59

17.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

65.86

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

349.32

17.04.02.03 17.04.03

LOSA SUPERIOR

17.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

3.45

17.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

17.62

17.04.03.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

192.93

18 Construcción de alcantarilla n° 9 (1.60m x 1.50m x 12.30) progresiva: 4+491.50 Se considera las siguientes actividades y metrados Item 18.01

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES

18.01.01

LIMPIEZA DE TERRENO MANUAL (Con pico, Lampa y carretilla)

m2

42.90

18.01.02

TRAZO, NIVELACION Y R E P U N T E O DE ALCANTARILLADO

m2

24.60

18.02

MOVIMIENTO DE TIERRAS

18.02.01

EXCAVACION MANUAL DE MATERIAL ORGANICO

m3

28.29

18.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO - TIERRA ROJA

m3

28.29

ELIMINACION DE MATERIAL EXCEDENTE C/ EQUIPO

m3

36.78

m2

24.60

18.02.03

18.03 18.03.01

18.04 18.04.01

OBRAS DE CONCRETO SIMPLE SOLADO 1:10 E= 4" OBRAS DE CONCRETO ARMADO LOSA INFERIOR

18.04.01.01

CONCRETO F'C= 210 KG/CM2. EN LOSA INFERIOR

m3

5.91

18.04.01.02

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

500.52

18.04.02

MUROS REFORZADOS

18.04.02.01

CONCRETO F’C=210 KG/CM2 EN MUROS REFORZADOS

m3

11.58

18.04.02.02

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

115.58

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

453.43

18.04.02.03 18.04.03

LOSA SUPERIOR

18.04.03.01

CONCRETO F'C= 210 KG/CM2. EN LOSA SUPERIOR

m3

4.92

18.04.03.02

ENCOFRADO Y DESENCOFRADO EN LOSA SUPERIOR

m2

25.40

18.04.03.03

ACERO DE REFUERZO FY=4200 KG/CM2

kg

404.79

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

19 Instalaciones eléctricas Se considera las siguientes actividades y metrados Item 19.01

Descripción

Und.

Metrado

SEMAFORO

19.01.01

SEMAFORO TRIPLE TIPO LEDS 10W

und

19.01.02

SEMAFORO CUADRUPLE TIPO LEDS 10W

und

2.00 1.00

19.01.03

POSTE DE FaG DE 0 6" X 11 MM

und

3.00

19.01.04

TABLERO ELECTRICO DE CONTROL AUTOMATICO

und

3.00

19.01.05

MEDIDOR DE ENERGIA MONOFASICA

und

3.00

19.01.06

CONDUCTOR ELECTRICO 2 - 1 X 6 MM2 NYY

m

3.00

19.01.07

ALIMENTADOR AL MEDIDOR DE ENERGIA

m

3.00

19.01.08

CABLE DE ACERO DE 0 5/16"

m

3.00

19.01.09

POZO DE PUESTA DE TIERRA

und

3.00

20 Varios Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 20.01 20.02 20.03

Descripción

Und.

REJILLA METALICA CON MARCO 0.52x0.80 TAPAS DE CONCRETO PARA INSPECCION Y LIMPIEZA 0.60X0.53 F'C=210 KG/CM2 PINTURA ALTO TRAFICO EN PAVIMENTO

Metrado

und

66.00

und

132.00

KM

4.69

m2

870.00

SEÑALIZACION VERTICAL

und

55.00

LIMPIEZA FINAL DE OBRA

GLB

1.00

20.04

PINTURA ALTO TRAFICO EN CRUCE PEATONAL

20.05 20.06 20.07

BUZONES

20.07.01

ENCOFRADO Y DESENCOFRADO EN LOSA DE BUZON

m2

2.25

20.07.02

CONCRETO F’C= 210 KG/CM2. EN LOSA DE BUZONES

m3

5.82

20.07.03

ACERO DE REFUERZO F'Y=4200 KG/CM2 MARCO Y TAPA DE BUZON

kg und

248.90

20.07.04

m2

11.50 4.31

20.08 20.08.01 20.08.01.01 20.08.02

9.00

PARADEROS TRABAJOS PRELIMINARES TRAZO, NIVELACION Y REPLANTEO MOVIMIENTO DE TIERRAS

20.08.02.01

EXCAVACION DE ZANJA MANUAL

m3

20.08.02.02

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

m3

1.17

20.08.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

5.61

20.08.03

OBRAS DE CONCRETO ARMADO

20.08.03.01

CONCRETO F'C=140 KG/CM2 EN CIMIENTO DE PARADERO

m3

3.23

20.08.03.02

CONCRETO F'C=175 KG/CM2 EN BASE PARA BANCAS

m3

0.06

20.08.03.03

ENCOFRADO Y DESENCOFRADO EN BASE DE C°A DE BANCAS

m2

1.21

20.08.03.04

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

171.42

20.08.04

ESTRUCTURAS Y COBERTURAS DE MADERA

20.08.04.01

ESTRUCTURA DE MADERA EN BANCAS

und

5.00

20.08.04.02

ENTRAMADO DE MADERA EN PARADEROS

und

5.00

20.08.04.03

COLUMNAS DE MADERA (quinllla y/o similar)

und

3 0 ^

20.08.04.04

COBERTURA CON PLANCHAS DE CALAMINA ONDULINE COLOR ROJO

m2

A m ,

20.08.05

ACCESORIOS METALICOS

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL - FICA CONSORCIO Fl

Lean ECIAUSTA EN GESTION A M B E t lA L

Am paro U ía z U rítm io ■¿^P R E S E N TA N TE LEG AL

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

20.08.05.01

COLOCACION DE DE TUBOS F°G EN PARADEROS

mil

23.50

20.08.05.02

PLATINA METALICAS PARA FIJAR EN LOS PARADEROS

und

20.00

20.08.06

PINTURA und

5.00

20.08.06.01

PINTURA EN BANCAS DEL PARADERO

20.08.06.02

PINTURA BARNIZ EN ESTRUCTURA DE MADERA

m

47.50

20.08.06.03

PINTURA ZICROMATICO EN CARPINTERIA METALICA

m

23.50

21 Impacto Ambiental Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 21.01 21.02 21.03

Descripción

Und.

COSTOS AMBIENTALES DURANTE LA PAVIMENTACION PRESUPUESTO DEL PROGRAMA DE MONITOREO AMBIENTAL PRESUPUESTO DEL PROGRAMA DE EDUCACION Y CAPACITACION AMBIENTAL

EN

EL MEJORAMIENTO

DE

PUENTE

Metrado

GLB

1.00

GLB

1.00

GLB

1.00

SAN

LORENZO

sus

respectivos

TENEMOS: 01 Trabajos preliminares Tienes

las

siguientes

actividades

con

metrados. Item

Descripción

Und.

Metrado

01.01

SEÑALIZACION INFORMATIVA DE DESVIO

und

2.00

01.02

DEMOLICION DE ESTRUCTURAS DE CONCRETO

m3

48.35

01.03

RETIRO DE DESPERDICIOS

m2

81.60

01.04

DESVIO DE CAUCE

ML

23.00

01.05

DESBROCE DE TERRENO

m2

147.03

01.06

LIMPIEZA DE TERRENO

m2

273.00

01.07

TRAZO Y REPLANTEO

m2

835.32

01.08

ALAMCEN DE OBRA

m2

60.00

01.09

CARTEL DE OBRA (3.00 X 5.00) BANNER INC. COLOCACION

und

2.00

01.10

TRANSPORTE DE MATERIALES EQUIPOS Y HERRAMIENTAS

GLB

1.00

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI

______________ ________________

02 Movimiento de tierras Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 02.01 02.02 02.03 02.04

Descripción

Und.

EXCAVACION DE ZANJA MASIVA CON MAQUINARIA EXCAVACION DE ZANJA MASIVA CON MAQUINARIA BAJO LECHO H 0.60M. RELLENO CON GRAVILLA O PIEDRA CHANCADA DE 1/2" RELLENO COMPACTADO CON MATERIAL MEJORADO 80% HOR. + 20% TR. RELLENO CON MATERIAL DE PRESTAMO EN REPOSICION DE VIA DE INGRESO Y SALIDA. ELIMINACION DE MATERIAL EXCEDENTE C! EQUIPO D= 5 KM.

02.05 02.06

Metrado

m3 m3 m3 m3

1,520.09 249.08 83.89 279.62

m3

967.20

m3

722.84

03 Obras de concreto simple Se refiere solado de concreto. Item 03.01

Descripción

Und.

SOLADO DE CONCRETO F C= 100 KG/CM2 E=0.10 M

m2

Metrado 245.75

04 Obras de concreto armado Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 04.01 04.01.01 04.01.02 04.01.03 04.02 04.02.01 04.02.02 04.03 04.03.01 04.03.02 04.03.03 04 04 04.04.01 04.04.02 04.04.03 04.04.04 04.05 04.05.01 04.05.02 04.05.03 04.06 04.06.01

Descripción

Und.

Metrado

LOSA INFERIOR DE ESTRIBO

CONCRETO F'C= 210 KG/CM2. EN LOSAS ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO F'Y=4200 KG/CM2

m3 m2 kg

52.72 35.14 3,644.93

LOSA INFERIOR DE MURO CABEZAL

CONCRETO F'C= 210 KG/CM2. EN LOSAS ENCOFRADO Y DESENCOFRADO

m3 m2

52.72 35.14

m3 m2

114.26 406.61 7,966.47

MUROS CABEZAL

CONCRETO F'C= 210 KG/CM2 EN MUROS ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

MUROS DE ENCAUSAMIENTO

CONCRETO F'C= 210 KG/CM2 EN MUROS ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO F'Y=4200 KG/CM2 ACERO DE REFUERZO F'Y=4200 KG/CM2

m3 m2 kg kg

124.20 362.43 5,785.26 9,975.84

m3 m2 kg

2.64 43.09 1,202.99

m3

2.64

VIGA LONGITUDINAL

CONCRETO F'C= 210 KG/CM2 EN VIGA TENSOR ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO F'Y=4200 KG/CM2 VIGA TRANSVERSAL

CONCRETO F'C= 210 KG/CM2 VIGA

FICHA INFORM ATIVA DE CLASIFICACIO N AM BIENTAL - FICA

j/b • to w ifiK a ta e i'L e a n " E S rtC lA ü S T A EN GESTION AMBIENTAL

\ r Ijjlfe u c íw J l W

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

04.06.02

ENCOFRADO Y DESENCOFRADO

m2

21.81

04.06.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

273.34

VIGA DIAFRAGMA

04.07 04.07.01

CONCRETO F'C= 210 KG/CM2 VIGA

m3

2.54

04.07.02

ENCOFRADO Y DESENCOFRADO

m2

13.09

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

152.74

04.07.03 04.08 04.08.01

LOSA SUPERIOR Y VEREDAS CONCRETO F'C= 210 KG/CM2. EN LOSAS

m3

22.72

04.08.02

ENCOFRADO Y DESENCOFRADO DE LOSA SUPERIOR (TIPO FALSO PUENTE)

m2

105.74

04.08.03

ACERO DE REFUERZO F'Y=4200 KG/CM2

kg

2,509.06

05 Varios Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item

Descripción

Und.

Metrado

05.01

BARANDA METALICA INC. PINTADO

ML

20.84

05.02

DRENAJE EN LOSA SUPERIOR

pto

6.00

05.03

PLACA RECORDATORIA (INC. COLOCACION)

und

1.00

05.04

CARTEL DE IDENTIFICACION DEL PUENTE

und

2.00

05.05

JUNTAS DE DILATACION METALICA

ML

14.40

05.06

APOYO MOVIL DE NEOPRENE SHORE 70.

und

3.00

05.07

APOYO FIJO DE NEOPRENE SHORE 70.

und

05.08

MONTAJE DE TUBERIA MATRIZ DE 10“

ML

3.00 24.00

05.09

MONTAJE DE TUBERIA MATRIZ DE 16"

ML

24.00

05.10

PINTURA EN BARANDAS METALICAS

ML

20.84

05.11

LIMPIEZA FINAL DE OBRA

GLB

1.00

PARA LAS OBRAS DE SANEAMIENTO TENEMOS 01.1 Agua potable: Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 01.01.01 01.01.01.01

01.01.02

Descripción TRAZO, NIVELES Y REPLANTEO DE REDES MOVIMIENTO DE TIERRAS

01.01.02.01

EXCAVACION DE ZANJA DE 0.6 x 1.20 M.

01.01.02.02

REFINE Y NIVELACION COMPACTADO MANUAL

01.01.02.03

CAMA DE ARENA SELECTA E=0.30

01.01.02.04

RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

01.01.03 01.01.03.01 01.01.04 01.01.04.01

Und. Metrado

TRABAJOS PRELIMINARES

INSTALACION DE TUBERIAS

//ti

((§ \

L / ci<\r \ V . £,\

\

'

ML

4,777.90

jj -T / m

4,777.90

r* i /

\

m

4,777.90

m m

4,777.90

m

4,777.90

4,777.90

J

SUMINISTRO Y COLOCACION DE TUBERIAS PVC UF ACCESORIOS DE PVC DIAM. 110 MM S-13.3 ISO 4422 RED MATRIZ INC. ANILLO INSTALACION DE ACCESORIOS Y VALVULAS SUMINISTRO E INSTALACION DE VALVULA LUFLEX ISO 7259 FFD 110 MM.

und

12.00

FICA proyecto: "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

01.01.04.02

SUM. E INST. DE CODO PVC UF 0 110 mm. DE 45"

und

17.00

01.01.04.03

SUMINISTRO E INSTALACION DE TEE FF TIPO LUFLEX ISO 7259 110 MM.

und

43.00

01.01.04.04

SUMINISTRO E INSTALACION DE TAPON PVC UF DIAM. 110 MM. SUMINISTRO E INSTALACION DE UNION DE REPARACION PVC UF DIAM. 110 MM. SUMINISTRO E INSTALACION DE GRIFO CONTRA INCENDIO

und

33.00

und

14.00

01.01.04.05 01.01.04.06 01.01.04.07 01.01.04.08 01.01.05 01.01.05.01

und

10.00

DADO DE CONCRETO

und

32.00

CAJA DE PROTECCION DE VALVULA

und

20.00

PRUEBA HIDRAULICA DOBLE PRUEBA HIDRAULICA Y DESINFECCION

m

4,777.90

01.2 Alcantarillado (4.50 KM). Tienes

las

siguientes

actividades

con

sus

respectivos

metrados. Item 01.02.01 01.02.01.01 01.02.02

Descripción

Und.

Metrado

TRABAJOS PRELIMINARES TRAZO, NIVELES Y REPLANTEO 3 ETAPAS (P/EXCAV, P/RELLENO.P/PAVIMENTO)

m

3,237.37

MOVIMIENTO DE TIERRAS

01.02.02.01

EXCAVACION DE ZANJA DE 0.8 X 1.60 - 2.60 M.

m

3,237.37

01.02.02.02

REFINE Y NIVELACION DE ZANJAS

m

3,237.37

01.02.02.03

CAMA DE ARENA SELECTA E= 0.20

m

3,237.37

01.02.02.04

RELLENO COMPACTADO ZANJA 0.80 M. X (1.60 - 2.60M)

m

3,237.37

m

3,237.37

01.02.03

INSTALACION DE TUBERIAS

01.02.03.01 01.02.04

SUMINISTRO Y COLOCACION DE TUBERIA PVC DIAM. 200 MM. S25 UF - KM BUZONES

01.02.04.01 01.02.04.02 01.02.04.03 01.02.04.04 01.02.04.05 01.02.05 01.02.05.01 01.02.06 01.02.06.01 01.02 07

EXCAVACION DE ZANJAS - BUZONES BUZON DE CONCRETO ARMADO, H= 1.50 F°F° BUZON DE CONCRETO ARMADO, H= 1.80 F°F° BUZON DE CONCRETO ARMADO, H= 2.20 F°F° BUZON DE CONCRETO ARMADO, H= 2.40 F°F° EMPALMES

m3 M, D= 1.20 M. INC. TAPA DE C°A°, MARCO M, D= 1.20 M. INC. TAPA DE C°A°, MARCO M, D= 1.20 M. INC. TAPA DE C'A*’, MARCO M, D= 1.20 M. INC. TAPA DE C°A°, MARCO

PERFORACION Y EMPALME A TUBERIA MATRIZ

123.05

und

30.00

und

15.00

und

8.00

und

8.00

und

1.00

PRUEBAS PREUBA DE REDES

m

3,237.37

CONEXIONES DOMICILIARAS

01.02.07.01

CONEXIONES D O M IC ILIA R IA S CORTAS (L= 5.00 M. APROX.)

und

87.00

01.02.07.02

CONEXIONES DOMICILIARIAS LARGAS (L= 17.00 M. APROX.)

und

82.00

und

155.00

m3

90.58

01.02.08 01.02.08.01 01.02.09 01.02.09.01

RED DE DESAGÜE CONEXIONES DOMICILIARIAS DE DESAGÜE NUEVAS (INC. TODOS LOS ACC.) VARIOS ELIMINACION DE MATERIAL CONTAMINANTE

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI

C. En la etapa de construcción se tendrá partidas para obtener metas como: •

Pavimento flexible bicapaMAC2 de 4 cm. y MACB de 3.5 cm de espesor, colocada sobre una base granular de e=0.20 m, subbase granular compactada e=0.15 m., subrasante estabilizada con cal de e=0.30m con una longitud de 4,690.51 m.anchosde calzada en diferentes tramos de 8.00m y 10.80m



Construcción de 6,101.02 mi de canaletas laterales de concreto fc=175 Kg/cm2, ancho variable (0.50 m. a 1.00 m.) y espesor de 0.10 m. ambos lados.



Construcción de 3,214.00 mi de sardineles ambos lados sumergidos de concreto f’c=175 Kg/cm2.



Construcción de alcantarillas y martillos, a los largo del asfaltado.



Obras de saneamiento.



Ampliación del puente San Lorenzo.



Señalizaciones de seguridad Vial. Las

partidas

involucradas

directamente

construcción son las siguientes:

con

la

etapa

de

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI

PROGRESIVA

LUGAR JNSTJTUTO PEDAGOGICO BILINGÜE DE YARINACOCHA

0+940

UNIVERSIDAD NACIONAL INTERCULTURAL DE LA AMAZONIA

1+220

C.P. SAN PABLO DE TUSHMO

1+880

CASERIO SAN LORENZO

3+000

C.P. SAN JOSE

3+840



Obras de Mitigación Ambiental.

-

Limpieza de maleza y arbustos, Acondicionamiento de botaderos Recuperación de áreas verdes.

D.- La construcción de la vía, obstaculizará el pase peatonal y de medios de transporte,

de forma temporal, siendo necesaria la

apertura de vías alternas, para el acceso de las mismas. E.-Las actividades que involucran el proceso constructivo son: •

PARA DEL MEJORAMIENTO VIAL SISTEMA DE INTERCONEXIÓN VIAL

Item 01

Descripción OBRAS PRELIMINARES

Item 02

Descripción TRABAJOS PRELIMINARES

Item 03

Descripción SEGURIDAD Y SALUD

Item 04

Descripción MOVIMIENTO DE TIERRAS

Item 05

Descripción PAVIMENTOS

Item 06

Descripción JUNTAS

Item 07

Descripción OBRAS DE DRENAJE

,

07.01

TRABAJOS PRELIMINARES

{■

07.02

CONCRETO ARMADO - CANALETAS

f •

07.03

SARDINELES

Item 08

\

Descripción CONCRETO EN MARTILLOS y RAMPAS

Item 09

FICHA INFORM ATIVA

Descripción SISTEMA DE MURO DE CONTENCION (TERRAMESH VERDE)

CLASIFICACIO N AM BIENTAL - FICA CONSORCIO FRL & aafSbcONSULT 8ÍR.L

D m ttrtv a ío ESPíCtdUSUElt

• ^ pr e se n ta n te l e g a l

Q p FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI

09.01

TRABAJOS PROVISIONALES

09.02

MOVIMIENTO DE TIERRAS SISTEMA DE MURO DE CONTENCION - SUELO REFORZADOfTERRAMESH VERDE)

09.03

Ítem

Descripción CONSTRUCCION DE ALCANTARILLA N° 1 (1,60m x 1 .OOMrn x 32.50) PROGRESIVA: 0+126.95 TRABAJOS PRELIMINARES

10 10.01 10.02

MOVIMIENTO DE TIERRAS

10.03

OBRAS DE CONCRETO SIMPLE

10.04

OBRAS DE CONCRETO ARMADO

10.04.01

LOSA INFERIOR

10.04.02

MUROS REFORZADOS

10.04.03

LOSA SUPERIOR

10.04.04

JUNTA DE DILATACION

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 2 (2.00m x 2.00m x 13.00 ) PROGRESIVA: 0+620 TRABAJOS PRELIMINARES

11 11.01 11.02

MOVIMIENTO DE TIERRAS

11.03

OBRAS DE CONCRETO SIMPLE

11.04

OBRAS DE CONCRETO ARMADO

11.04.01

LOSA INFERIOR

11.04.02

MUROS REFORZADOS

11.04.03

LOSA SUPERIOR

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 3 (1 00m x 1,50m x 12.95) PROGRESIVA: 1+028.60

12 12.01

TRABAJOS PRELIMINARES

12.02

MOVIMIENTO DE TIERRAS

12.03

OBRAS DE CONCRETO SIMPLE

12.04

OBRAS DE CONCRETO ARMADO

12.04 01

LOSA INFERIOR

12.04.02

MUROS REFORZADOS

12.04.03

LOSA SUPERIOR

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 4 (1,00m x 1 50m x 12.35) PROGRESIVA: 1+928.40 TRABAJOS PRELIMINARES

13 13.01 13.02

MOVIMIENTO DE TIERRAS

13.03

OBRAS DE CONCRETO SIMPLE

13.04

OBRAS DE CONCRETO ARMADO

13.04.01

LOSA INFERIOR

13.04.02

MUROS REFORZADOS

13.04.03

LOSA SUPERIOR

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 5 (0 80m x 1 OOm x 12.30) PROGRESIVA: 3+273.50

14 14.01

TRABAJOS PRELIMINARES

14.02

MOVIMIENTO DE TIERRAS

14.03

OBRAS DE CONCRETO SIMPLE

14.04

OBRAS DE CONCRETO ARMADO

14.04.01

LOSA INFERIOR

14.04.02

MUROS REFORZADOS

14 04.03

LOSA SUPERIOR

Item

FICHA INFORM ATIVA DE

Descripción

■IFICACION AM BIENTAL - FICA CONSOL

:o w in Rata el Lean CIP. N ' 75406 ' E S P E C U U S r* EN GESTION AMBIENTAL LEG AL

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

CONSTRUCCION DE ALCANTARILLA N° 6 (1,20m x 1,60m x 32.80) PROGRESIVA: 3+563.45 TRABAJOS PRELIMINARES

15 15.01 15.02

MOVIMIENTO DE TIERRAS

15 03

OBRAS DE CONCRETO SIMPLE

15.04

OBRAS DE CONCRETO ARMADO

15.04.01

LOSA INFERIOR

15.04 02

MUROS REFORZADOS

15.04.03

LOSA SUPERIOR

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 7 (1,20m x 1,70m x 12.80) PROGRESIVA: 3+852.90 TRABAJOS PRELIMINARES

16 16.01 16.02

MOVIMIENTO DE TIERRAS

16.03

OBRAS DE CONCRETO SIMPLE

16.04

OBRAS DE CONCRETO ARMADO

16.04.01

LOSA INFERIOR

16.04.02

MUROS REFORZADOS

16.04.03

LOSA SUPERIOR

Descripción CONSTRUCCION DE ALCANTARILLA N° 8 (1 20m x 1 70m x 12.30) PROGRESIVA: 3+951.80 TRABAJOS PRELIMINARES

17 17.01 17.02

MOVIMIENTO DE TIERRAS

17.03

OBRAS DE CONCRETO SIMPLE

17.04

OBRAS DE CONCRETO ARMADO

17.04.01

LOSA INFERIOR

17.04.02

MUROS REFORZADOS

17.04.03

LOSA SUPERIOR

Item

Descripción CONSTRUCCION DE ALCANTARILLA N° 9 (1 60m x 1 50m x 12.30) PROGRESIVA: 4+491.50 TRABAJOS PRELIMINARES

18 18.01 18.02

MOVIMIENTO DE TIERRAS

18.03

OBRAS DE CONCRETO SIMPLE

18.04

OBRAS DE CONCRETO ARMADO

18.04.01

LOSA INFERIOR

18.04.02

MUROS REFORZADOS

18.04.03

Item 19

LOSA SUPERIOR

Descripción

I

INSTALACIONES ELECTRICAS

19.01

SEMAFORO

Item

Descripción

20

VARIOS

20.01

REJILLA METALICA CON MARCO 0.52x0.80 TAPAS DE CONCRETO PARA INSPECCION Y LIMPIEZA 0.60X0.53 F'C=210 KG/CM2 PINTURA ALTO TRAFICO EN PAVIMENTO

20.02 20.03 20.04

PINTURA ALTO TRAFICO EN CRUCE PEATONAL

20.05

SEÑALIZACION VERTICAL

20.06

LIMPIEZA FINAL DE OBRA

20.07

BUZONES

20.08

PARADEROS

20.08 01 20.08.02

TRABAJOS PRELIMINARES MOVIMIENTO DE TIERRAS

20.08.03

OBRAS DE CONCRETO ARMADO

w FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI”.

20.08.04

ESTRUCTURAS Y COBERTURAS DE MADERA

20.08.05

ACCESORIOS METALICOS

20.08.06

PINTURA

Descripción

Item 21

IMPACTO AMBIENTAL COSTOS AMBIENTALES DURANTE LA PAVIMENTACION

21.01 21.02

PRESUPUESTO DEL PROGRAMA DE MONITOREO AMBIENTAL PRESUPUESTO DEL PROGRAMA DE EDUCACION Y CAPACITACION AMBIENTAL

21.03



Las actividades que involucran el proceso constructivo del mejoramiento del PUENTE DE SAN LORENZO es como sigue:

MEJORAMIENTO DE PUENTE SAN LORENZO Item 01

Descripción TRABAJOS PRELIMINARES

Item 02

Descripción MOVIMIENTO DE TIERRAS

Item 03

Descripción OBRAS DE CONCRETO SIMPLE

Item 04

Descripción OBRAS DE CONCRETO ARMADO

04.01

LOSA INFERIOR DE ESTRIBO

04.02

LOSA INFERIOR DE MURO CABEZAL

04.03

MUROS CABEZAL

04.04

MUROS DE ENCAUSAMIENTO

04.05

VIGA LONGITUDINAL

04.06

VIGA TRANSVERSAL

04.07

VIGA DIAFRAGMA

04.08

LOSA SUPERIOR Y VEREDAS

Descripción 05

VARIOS



Las actividades que involucran el proceso constructivo de OBRAS DE SANEAMIENTO es como sigue:

Item 01.01

OBRAS DE SANEAMIENTO Descripción AGUA POTABLE

01.01.01

TRABAJOS PRELIMINARES

01.01.02

MOVIMIENTO DE TIERRAS

01.01.03

INSTALACION DE TUBERIAS

01.01.04

INSTALACION DE ACCESORIOS Y VALVULAS

01.01.05 01.02 01.02.01

PRUEBA HIDRAULICA ALCANTARILLADO (4.50 KM). TRABAJOS PRELIMINARES

01,02.02

MOVIMIENTO DE TIERRAS

01.02.03

INSTALACION DE TUBERIAS

FICA proyecto: "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

01.02.04

BUZONES

01.02.05

EMPALMES

01.02.06

PRUEBAS

01.02 07

CONEXIONES DOMICILIARAS

01.02.08

RED DE DESAGÜE

01.02.09

VARIOS

F.- El tiempo de ejecución del proyecto es de 365 días calendarios que es equivalente a 12 meses (se anexa el programa de ejecución). G.-Se Adjunta en anexos planos generales del sistema vial del proyecto, a escala visible. H.- La cantidad de personal necesario que se encargará de la etapa de ejecución del proyecto entre personal de MOC y MONC son 750 personas aproximadamente. 2.2.3. Etapa de operación y mantenimiento. A.- Por el tipo de proyecto se harán dos tipos de análisis para la operación y mantenimiento: la operación y mantenimiento ordinario y la operación y mantenimiento extraordinario B.-

Para

la

alternativa

recomendada

se

ejecutaran

como

mantenimiento ordinario las siguientes partidas: ITEM 1 .0 0

1.01 1.02 1 .0 3 1.0 4 1 .0 5 2 .0 0

2.01 3 .0 0 3.01 3 .0 2 3 .0 3 4 .0 0 4.01 4 .0 2 5 .0 0 5.01 6 .0 0

6.01 6.02

D E S C R IP C IO N L IM P IE Z A L im p ie z a g e n e ra l L im p ie z a d e c a n a le ta s a b ie rta s y te c h a d a s L im p ie z a d e a lc a n ta r illa d e c o n c re to a rm a d o L im p ie z a d e c a u c e a g u a s a rrib a y a g u a s a b a jo d e p u e n te s E lim in a c ió n d e m a te ria l p ro v e n ie n te d e lim p ie z a P A V IM E N T O R e lle n o d e ju n ta s e n L o s a s y B e r m a s (5 % ) PARADEROS P in tu ra e n B a n c a s d e l P a ra d e ro P in tu ra B a rn iz e n E s tru c tu ra d e M a d e ra P in tu ra Z ín c ro m á tic o e n C a rp in te ría M e ta lic a S E Ñ A L IZ A C IO N P in tu ra a lto tra fic o e n p a v im e n to /¿ X VR° ^y*\\ P in tu ra a lto tra fic o e n c ru c e p e a to n a l / jp PtyjélQN \ B A R A N D A PUENTE ............................................................................................... II |.p t lltf*¿ pjctTo,ri.Jr .rr H P in tu ra d e B a ra n d a M é ta lic a S0C¡ ( ' n S IS T E M A D E D E S A G Ü E V w 177 y L im p ie z a d e R e d e s d e D e s a g ü e L im p ie z a d e B u z o n e s

FICA proyecto: “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Para

la

alternativa

recomendada

se

ejecutaran

como

mantenimiento extraordinario las siguientes partidas: ITEM 1.00 1 .01 1 .02 1.03 1 .04 1.06 2.00 2.01 2.02 2.03 2.04 3.00 3.01 3.02 4.00 4.01 4.02 4.03 5.00 5.01 5.02 6.00 6.01 7.00 7.01 7.02

DESCRIPCION OBRAS PRELIMINARES Movilización y Demovilización de Equipo Señalización y Seguridad en zona de trabajo Mantenimiento de tránsito Trazo, Nivelación y Replanteo Cartel de Obra LIMPIEZA Limpieza de canaletas abiertas ytechadas Limpieza de alcantarilla de concreto arm ado Limpieza de cauce aguas arriba yag u as abajo de puentes Eliminación de material proveniente de limpieza PAVIMENTO R e sa n e de filos yoíros (5% ) Relleno de juntas en Losas y Berm as (35% ) PARADEROS Pintura en Bancas del Paradero Pintura Barniz en Estructura de Madera Pintura Zincromatico en Carpintería Metalica SEÑALIZACION Pintura alto trafico en pavimento Pintura alto trafico en cruce peatonal BARANDA PUENTE Pintura de Baranda Métalica SISTEMA DE DESAGÜE Limpieza de Redes de D esagü e Limpieza de Buzones

D. Para la etapa de operación se contara con los servicios de 3 personas que se dedicaran a la administración y control de todo el sistema vial teniendo a su cargo la correctasupervisión de la vía. Para mantenimiento ordinario se tendrá en cuenta 10 personas que será por administración directa, y para el mantenimiento extraordinario se dar por contrata a terceros. 2.3.

A ctividades asociadas o generadas por e! proyecto 2.3.1. Material de préstamo o extracción. Durante la ejecución del proyecto se utilizara material agregado, el cual será extraído de 3 canteras como se detalla la ubicación de cada una a continuación: •

La Cantera Nuevo Piura: que se encuentra ubicada en la carretera Nueva Requena km 11+00 margen izquierda se penetra se penetra por una trocha carrozable en regular estado a una distancia de 19.00 km para llegar a orillas del Río Aguaytía.

FICHA INFORMATIVA DE CLASIFICACIO N AM BIENTAL - FICA

2 ___ /W /

Edw irt Rafaéi Lean —

n íin rrw o r

ESPECIALISTAEH GESTION M tB E H T A l

n J n ru b u 'T X r e v ú lO REPRESENTANTE l e g a l

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".



Cantera Cambio 90 - Curimana: Se encuentra ubicada en la carretera de Curimana. Se accede a dicho banco de material tomando el desvio a la derecha a la altura del Km 32+000 hasta una distancia aproximada de 2.50 km, de longitud el acceso se encuentra en regular condiciones.



Cantera Bandeja Pozo: La cantera Manco Capác se encuentra ubicada

cerca

de

la

localidad

de

San

Alejandro

a

aproximadamente 2.50 Km de esta, a dicho banco de materiales se accede por la carretera Federico Basadre km 108+500 por el lado izquierdo, por donde se ingresa hasta una distancia aproximada de 3.00 km llegando a las inmediaciones del Río San Alejandro, la que se encuentra en regulares condiciones.

La extracción se efectuara del siguiente modo: MATERIALES DE PRESTAMO O EXTRACCIÓN M EJORAM IENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO

MATERIALES

Unidad

ARENA DE RÍO

m3

0.0900

Ejecución

ARENA FINA

m3

23.2080

Ejecución

HORMIGON

m3

176.4500

Ejecución

HORMIGON (PUESTO EN OBRA)

m3

24,430.2675

Ejecución

MATERIAL DE PRESTAMO SELECCIONADA EN ZONA DE MAT. ORGANICO

m3

18,015.6120

Ejecución

TIERRA DE CHACRA O VEGETAL

m3

4.2000

Ejecución

TIERRA ROJA

m3

2,738.8106

Ejecución

TIERRA SELECCIONADA (PUESTA EN OBRA)

m3

57,324.8000

Ejecución

AGUA

m3

12,337.9001

Ejecución

Cantidad

Etapa

MEJORAMIENTO DE PUENTE SAN LORENZO MATERIALES

Unidad

AGUA

m3

204.2990

Ejecución

GRAVILLA PARA FILTRO DE 1/2" DE RIO O PIEDRA CHANCADA DE 1/2”

m3

83.8900

Ejecución

HORMIGON

m3

1,800.6673

Ejecución

TIERRA ROJA

m3

324.1732

Ejecución

Cantidad

Etapa

OBRAS DE SANEAMIENTO MATERIALES

Unidad

ARENA FINA

m3

FICHA INFORMATIVA DE CLASIFICACION AM BIENTAL - FICA

Cantidad 1,732.0724

Etapa Ejecución

m FICA p ro y e c to : "MEJORAMIENTO D E VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U CAYALI".

HORMIGON (PUESTO EN OBRA)

m3

221.6375

Ejecución

TIERRA ROJA

m3

3,096.0792

Ejecución

AGUA

m3

481.5606

Ejecución

Durante la operación

no se requieren material de préstamo pero

durante el mantenimiento ordinario y extraordinario si requerirán de material de préstamo o extracción que se encuentran en el área de influencia del proyecto me menor cantidad. 2.3.2. Insumos. A.-EI proyecto utilizara algunos insumos químicos de poca relevancia las cuales también se deberán de tener cuidado con su uso, el uso de estos insumos químicos se dará durante la ejecución de la obra. En la operación no se da uso de estos insumos químicos porque la etapa de operación es netamente administrativa. El la etapa de mantenimiento se hará uso de algunos insumos químicos que se mencionan en la etapa de ejecución como por ejemplo las pinturas de señalización. A continuación describimos los insumos químicos. INSUMOS DEL MEJORAMIENTO DE LA INTERCONEXION VIAL Producto Químico

Nombre Comercial

Unid.

Criterio de Peligrosidad

Cantidad Inflamable

ASFALTO RC-250

gln

BARNIZ MARINO

No menciona

gln

No menciona

kg

X

Ejecución

247.6617

X

120,692.2117

X

Ejecución

BOL

GRASA

No menciona

kg

No menciona

gln

4.0000

PEGAMENTO PVC

No menciona

gln

0.0300

X

PINTURA ALTO TRAFICO

No menciona

gln

127.9200

X

PINTURA ANTICORROSIVA

No menciona

gln

PINTURA ESMALTE

Etapa del Proyecto

Ejecución 0.3800

No menciona

INDUSTRIAL

Tóxico X

CEMENTO PORTLAND TIPO I (42.5KG)

KEROSENE

Reactivo Explosivo

1,061.9447

ASFALTO DE PETROLEO RC-250

CAL

Corrosivo

Ejecución

No menciona

m2

255.8050

0.9400 0.0300

X

Ejecución

X

X

X X

x ^ \C A 0 XD^lSiC n m ^ EST30IOSYOBRAS S il ElOTAülfc ClijFtO tí I aok\iwo! _ /

X

Ejecución Ejecución Ejecución Ejecución Ejecución

77.1322 PINTURA ESMALTE

No menciona

gln

X Ejecución

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

0.9400

X

gln

48.6750

X

No menciona

BOL

36.7040

X

No menciona

BOL

302.3447

X

PINTURA ESMALTE ANTICORROSIVO TEKNO

No menciona

gln

THINER

No menciona

TIZA YESO DE 28 Kg

Ejecución Ejecución Ejecución Ejecución

irvSUMOS DEL MEJORAMIENTO DE PUENTE SAN LORENZO Producto Químico

HIPOCLORITO DE CALCIO

Criterio de Peligrosidad

Nombre Comercial

Unid.

CAL HIDRATADA DE 25 Kg

BOL

Cantidad Inflamable

Corrosivo

Reactivo Explosivo

No menciona

X

PINTURA ESMALTE

No menciona

PINTURA ESMALTE

No menciona

PINTURA ESMALTE SINTETICO

No menciona

THINER

No menciona

Ejecución

3,416 6525 BOL

No menciona

Etapa del Irritable Proyecto

2.5060

CEMENTO PORTLAND TIPO 1(42.5KG) PINTURA ANTICORROSIVA

Tóxico

X

Ejecución

2.4549 gln gln

0.9590

gln

0.0020

X

Ejecución

X

Ejecución

X

Ejecución

X

Ejecución

X

Ejecución

1.6672 gln gln

0.1667

1NISUIVOS DE OBRAS DE SANEAMIENTO Criterio de Peligrosidad Producto Químico

Nombre Comercial

Unid.

Cantidad

Inflamable

Corrosivo

Reactivo

Explosivo

Etapa Tóxico

del Proyecto

Irritable

CEMENTO PORTLAND TIPO 1(42.5KG)

No menciona

BOL

HIPOCLORITO DE CALCIO 70%

CAL HIDRATADA

'■
382.2320

LUBRICANTES

No menciona

gln

87.0620

PEGAMENTO PARA PVC PINTURA ESMALTE SUPER SINTETICA

No menciona

gln

38.7550

No menciona

gln

1.6187

YESO

No menciona

k9......

80.9343

X

Ejecución

YESO DE 28 Kg

No menciona

BOL

47.7790

X

Ejecución

X

Ejecución

1,667.3600 Ejecución

X

Ejecución

X

Ejecución Ejecución

X

FICHA INFORMA TIVA DE CLASIFICACION AMBIENTAL ■ FICA

*.

CONSO1

4 Lean el Lean ESrtCUUST» ENGESTIONAMBIENTAL

A m ta rtí U ia i z re v a lo iW sEN TA N TÉ t-EGAL

r iP

*

Q3? FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

____________________________________________________________

B.- Son insumos químicos de poca peligrosidad y serán transportados vía terrestre, envasados en sus empaquetaduras originales de fabrica, serán almacenados en un ambiente preparados a la apertura de la obra, debidamente acondicionado y techado, se abrirá el envase exclusivamente cuando se le dará uso inmediato, volviendo a sellarlo si tiene algún sobrante. En cuanto a la transportación de los productos químicos como el Asfalto estará acargo del contratista, lo cual en su mayoría de veces trasladan los insumos desde la ciudad de Lima y la forma de almacenamiento será sobre estantes de madera o en los envases

que

la

planta

proveedora

los

venda,

para

el

almacenamiento de la Calserá sobre depósitos que garanticen que no contamine el medio de los trabajadores o el medio ambiente,para los cuales se tendrán en cuenta todas las consideraciones en las hojas MSDS. 2.3.3. Efluentes. A.-Caudal de efluente: Los caudales del que se han considerado para las obras de arte son: •

Para la progresiva 0+126.95 es de: 0.95 m3/seg.



Para la progresiva 0+626es de: 1.19 m3/seg



Para la progresiva 1+028.65 es de: 0.79 m3/seg



Para la progresiva 1+928.40 es de: 0.16 m3/seg



Para la progresiva 3+273.40 es de: 1.87 m3/seg



Para la progresiva 3+563.53 es de: 1.22 m3/seg



Para la progresiva 3+852.92 es de: 0.96 m3/seg



Para la progresiva 3+971.78 es de: 0.72 m3/seg



Para la progresiva 4+468.45 es de: 1.70 m3/seg

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

________________________________________________

B.- Características del efluente: Las características dei efluente en cuanto a parámetros como: •

Características químicas: No son de significancia para el proyecto dado que es una intervención a nivel de mejoramiento de vías urbanas.



Características físicas: No son de significancia para el proyecto dado que es una intervención a nivel de mejoramiento de vías urbanas.



Características microbiológicas: No son de significancia para el proyecto dado que es una intervención a nivel de mejoramiento de vías urbanas.

C.- Cuerpo receptor de efluentes y normativa vigente. Según la normativa vigente en la Ley de Recursos Hídricos: Ley N°29338 y su reglamento indica los lineamientos de vertimientos de aguas residuales en el cuerpo receptor. Por lo que para evacuar y/o verter aguas pluviales en un cauce o cuerpo receptor natural deber hacerse previa opinión y/o permiso ante la Autoridad Local del Agua - Pucallpa. En cuanto a los efluentes que existen en el área del proyecto son aguas que discurren

por las alcantarillas ubicadas en

las

progresivas: 0+126.95, 0+626, 1+028.65, 1+928.40, 3+273.40, 3+563.53, 3+852.92, 3+971.78, 4+468.45, aguas que confluyen hacia el drenaje aguas abajo con dirección a laguna de Yarinacocha.

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, _______________________________ DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI

2.3.4. Residuos sólidos y Líquidos A.- Residuos Sólidos •

Tipo de residuo

TIPO DE RESIDUO

PARTIDA

Envases de Pinturas, Envases de asfalto, Envases de Lubricantes, envases de thinec

DESCRIPCION

Pintura en Sardineles, Pintura en Cruces

Se generara Residuos solidos cuando se desocupen los envases de las

Peatonales

pinturas a emplearse.

En partidas de Encofrados de Losas, Encofrados Se Generara Residuos de clavos cuando estos sean mal empleados y no

Clavos

en Bermas, Etc.

sirvan para volver a clavar

En partidas de Encofrados de Losas, Encofrados Se generaran residuos de alambres cuando se ejecuten partidas de

Alambres

en Bermas, Acero de Refuerzo Etc.

Acero

ACERO DE REFUERZO F'y=4200 kg/cm2 GRADO

Se generaran residuos de acero al ejecutar la partida de aceros de

60

refuerzo en los enmallados de las parrillas de losas y bermas

Base Granular e=0.20m; Concreto E'c =210

Hormigon

Kg/cm2

Arena

Relleno de Cama de Arena de Fondo

Tierra

Corte de Material, Relleno Compactado

Madera



encofradoo amarre o empalme de aceros de refuerzo

Conformación de Base, Cama de arena el zanjas de tuberías

Se generara resiuos de arena al ejecutar partidas donde se coloque suministros de tuberías y conexiones Se generará residuos de Tierra en la partida movimiento de tierras (cortes, rellenos)

Encofrados de Losas, Encofrados en Bermas,

Se generará residuos de Madera cuando se ejecute partidas de

Etc.

Encofrados y Desencofrados.

Cantidades y/o Volúmenes estimados de residuos sólidos (ejecución, operación y mantenimiento). CANTIDAD

TIPO DE RESIDUO

EJECUCION

Envases de Pinturas, Envases de Lubricantes, envases de Thiner

1451 Blds

Clavos

2957.84 Kg

Alambres

RESIDUO DE EJECUCION

1451

Blds

29.57

Kg

26511.32 Kg

265

Kg

Acero

460,103.36 Kg

460

Kg

Hormigón

26,629.02 m3

26.62

m3

Arena

1,755.37 m3

1.75

m3

Tierra

63,488.0630 m3

63.48

m3

Madera

63,973.97 p2

63.87

P2

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UC AYALI” .

Residuos Líquidos Los residuos líquidos producidos por la ejecución son mínimos y no significativos,

pero

en la etapa de operación y

mantenimiento, estos si están vinculados a la descarga de las aguas pluviales a los drenajes naturales que discurren en el área de influencia del proyecto. Asimismo los líquidos residuales que puedan existir durante la ejecución del proyecto son en mínimas cantidades y serán provenientes

de

los

combustibles

o

insumos

para

el

funcionamiento temporal de la maquinaría que se utilizará para el movimiento de tierras o para el vaciado de las ¡osas de concreto en la construcción de la pavimentación. EQUIPOS MAQUINARIA

HM REQUERIDA

LUBRICANTE P O R HM (gln)

DESECHO LIQUIDO

CAMION CISTERNA 4x2 (AGUA) 1,500 gl

hm

1,135.8756

0.005

5.68

gln

CARGADOR FRONTAL CAT-930

hm

800.1113

0.010

8.00

gln

COCINA DE ASFALTO

hm

9,283.1880

0.001

9.28

gln

COMPACTADOR VIBR. TIPO PLANCHA 4 HP

hm

1,249.1680

0.001

1.25

gln

COMPACTADOR VIBR. TIPO PLANCHA 7 HP

hm

3,453.3026

0.001

3.45

gln

COMPACTADORA TIPO SALTARIN

hm

1,802.8985

0.001

1.80

gln

GRUA HIDRAULICA AUTOP. 127HP 18TON-9M.

hm

10.0000

0.010

0.10

gln

MEZCLADORA CONCRETO TAMBOR 18HP 11P3

hm

0.0267

0.003

0.00

gln

MEZCLADORA DE CONCRETO DE 9-11P3

hm

7,167.8098

0.003

21.50

gln

MOTONIVELADORA DE 125 HP

hm

1,876.2719

0.020

37.53

gln

SOLDADORA

hm

52.8000

0.001

0.05

gln

TRACTOR A ORUGAS 140 HP

hm

14.7210

0.010

0.15

gln

VIBRADOR DE C 0N C R E T 0 4 HP 1.35"

hm

0.0267

0.001

0.00

gln

VIBRADOR DE CONCRETO 4 HP 1.50"

hm

4,550.4500

0.001

4.55

gln

VIBRADOR DE CONCRETO 4 HP 2.40''

hm

271.4477

0.001

0.27

gln

VOLQUETE VOLVO 14 M3

hm

21.1012

0.010

0.21

gln

VOLQUETE VOLVO 15 M3

hm

571.6192

0.010

5.72

gln

EXCAVADORA

hm

90.9840

0.003

0.27

gln

RETROEXCAVADORA S/O 80-115 HP

hm

355.8780

0.015

5.34

gln

MOTOSIERRA

hm

2.3525

0.001

0.00

gln

RODILLO LISO VIBRATORIO AUTOPROPULSADO

hm

19.9492

0.015

0.30

9'1Í

BOMBA DE MANO

hm

382.2320

0.0010

0.38

glr)|

TOTAL DE DESECHOS LIQUIDOS EN gln TOTAL DE DESECHOS LIQUIDOS EN m3

FICHA INFORMATIVA DE CLASIFICACION AM BIENTAL ■ FICA

_

¿ILean

CONSüw

ESPECIALISTAENGESTO* AtlSHML REPRESENTANTE

LEGAL

105.84

gln

0.4

m3

FICA p ro y e c to : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UC AYAU ".

B.-Sistemas de almacenamiento y tratamiento dentro de las instalaciones. Según el Reglamento para la gestión de Residuos Solidos de la Construcción

y Demolición

indica en el: Capítulo

III.- Del

Almacenamiento y Prohibición de Abandono de Residuos Sólidos de la construcción y demolición. Artículo 26°.- Almacenamiento inicial de residuos de obras mayores y de gran envergadura: El proceso de almacenamiento inicial de residuos en obras mayores y de gran envergadura, se realizará en la misma obra, teniendo en cuenta el lugar o áreas donde los residuos se generan; una vez acumulado, y de acuerdo a su Plan de Manejo el generador podrá disponer el traslado según corresponda, ya sea a un centro de acopio, planta de transferencia, planta de tratamiento y disposición final en una escombrera o relleno de seguridad autorizados por la municipalidad correspondiente para su disposición final. El plazo de almacenamiento en obra estará previsto en el Plan de Manejo y sólo podrá ampliarse de manera excepcional, por razones debidamente justificadas y deberá ser puesto en conocimiento y autorizado por la autorídadmunicipal competente. C.- El transporte de los residuos solidos a sus disposiciones finales serán en envases y bolsas adecuadas para evitar su derrame a lo largo de su traslado. D.- La incidencia de desechos de la construcción de obras civiles se estima en la eliminación de material excedente, el cual será tierra que excede de la nivelación de la superficie para la futura pavimentación, por la calidad de este material puede ser reutilizado como material de relleno. En cuanto al material proveniente de la limpieza final de obra por su mala calidad, será totalmente eliminado

(í^ FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYALI”.



Ei trabajo se desarrollara enmarcado dentro del de las Normas Técnicas Peruanas referidas al tema: -

NTP 400.050.199 Generalidades sobre el manejo de residuos de construcción

-

NTP 400.051.1999 reciclaje de mezclas asfálticas NTP 400.052.1999 reutilización y reciclaje de materiales de base y sub base proveniente de la demolición de carreteras y plataformas NTP 400 053 1999 reciclaje de concreto de demolición NTP 400 054 1999 reciclaje de materiales de demolición no clasificados.

E.- Residuos Peligrosos TIPO DE RESIDUO

PARTIDA

DESCRIPCION

Movimiento de Tierras

Donde se utilizaran maquinarias como : Camiones Cisterna, Compactador, Rodillo Liso Vibratorio, Cargador Forntal, Retroexcavadoras

Almaceno Campamento de Maquinarias

Donde se guardaran y/o repararan maquinarias como : Camiones Cisterna, Compactador, Rodillo Liso Vibratorio, Cargador Fomtal, Retroexcavadoras

Juntas Longitudinales, Juntas de Dilatación, Juntas de Expansión, Juntas de Articulación, Juntas Transversales

En la partida de Jmtas, se hace la utilización del insumo de Asfalto para que cumpla el trabajo de material flexible cuando ocurra tos fenomenos de expansión (altas temperaturas) y fenomenos de contracción (bajas temperaturas)

Obras de Saneamiento Agua Potable y Alcantarillado

Intalacion de suministros de tuberías y conexiones de Agua y Alcantarillado

Lubricantes, combustibles

Asfalto

Lubricantes para uniones, pegamentos

F.-Cantidades y/o Volúmenes estimados de residuos líquidos (ejecución, operación y mantenimiento).

TIPO DE RESIDUO

EJECUCIÓN

CANTIDAD RESIDUO DE EJECUCIÓN

Lubricantes, com bustibles

Am 3

AX 0.01 m3

Asfalto

1061.94 GIn

10.6194 GIn

Lubricantes para uniones

87 GIn

0.87 GIn

FICHA INFORMA TlVt

/

'CLASIFICACION AMBIENTAL - FICA

ael Lean CIP. N* 7S40C ESPECIALISTAEMGESTIONAMBIENTAL

Am ñftfí) D íaz /•"REPRESENTANTE LEGAL

6WfL

(J V P FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YA RIÑA COCHA, CORONEL PORTILLO - U C AYAU ".

2.3.5.

Emisiones atmosféricas. •

Los equipos y maquinarias que generaran emisiones gaseosas, de fuentes fijas y fuentes móviles durante la etapa de ejecución son: MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO CARGADOR FRONTAL CAT- 930 COCINA DE ASFALTO COMPACTADOR VIBR. TIPO PLANCHA 4 HP COMPACTADORA TIPO SALTARIN GRUA HIDRAULICA AUTOP. 127HP 18TON-9M. MEZCLADORA CONCRETO TAMBOR 18HP 11P3 MEZCLADORA DE CONCRETO DE 9-11P 3 MOTO NIVELADORA DE 125 HP RODILLO LISO VIBR AUTOP 101-135HP 10-12T SOLDADORA TRACTOR A ORUGAS 140 HP VIBRADOR DE CONCRETO 4 HP 1.35" VIBRADOR DE CONCRETO 4 HP 1.50" VIBRADOR DE CONCRETO 4 HP 2.40" VIBRADOR DE CONCRETO 4 HP 2.40" VOLQUETE VOLVO 14 M3 VOLQUETE VOLVO 15 M3

FICHA INFORMATIVA

r

E CLASIFICACION AM BIENTAL - FICA ? CO NSO RC

C1P. N‘ 754#€

Aptffaro D ía z ^ r^ u a lo X

REPRESENTANTE legal

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UC AYAU

OBRAS DE SANEAMIENTO BOMBA DE MANO COMPACTADOR VIBR. TIPO PLANCHA 7 HP COMPACTADORA TIPO SALTARIN RETROEXCAVADORA S10 80-115 HP



La circulación de vehículos pertenecientes al proyecto si generar emisiones gaseosas a la atmosfera pero estas emisiones serán mínima.

2.3.6. Generación de ruido Las obras en construcción son sitios regularme ruidosa. La exposición prolongada al ruido fuerte puede causar daños permanentes de audición. El ruido en el trabajo puede causar tensión nerviosa y dificultad en conciliar el sueño. Los niveles muy elevados de ruido, como los que producen

las

herramientas

de

potencia,

pueden

provocar daños

instantáneos en el sistema auditivo. Los niveles de ruido generados por operaciones tales como la perforación de estructuras, operaciones de limpieza pueden ser tales que las personas sin protección rebasan su dosis diaria de resistencia en cuestión de segundos. Varios minutos de exposición diaria a una máquina muy ruidosa son suficientes para causar daño permanente al oído. El ruido fuerte puede provocar pérdida parcial del oído durante un tiempo, con períodos de recuperación que oscilan entre 15 minutos y varios días, según el nivel de ruido. También se da un «campanilleo» auditivo que debe tomarse como advertencia, ya que la pérdida provisoria puede volverse permanente con exposiciones reiteradas. La sordera se desarrolla muy gradualmente pero una vez declarada no se cura. El ruido también dificulta escuchar los sonidos que es preciso oír, como las señas de trabajo y los gritos de advertencia.

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL - FICA

CIR N* 75406 especialista oí gísto *

LEGAL

FICA p ro ye cto : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYALI”.

A continuación se presenta los Limites Permisibles para Ruidos de la Actividad de la Construcción: Periodo

dB (decibeles)

8 horas

75

Doméstico

-

45

Dormitorio

Noche

35

EIA

55

Noche

45

T ipo de A m biente

Laboral

Exterior diurno Exterior nocturno

Fuente : Organización M undial de la Salud (OMS)



...., i_ ’VUPIP 'Wrr*)

m M ÍÉ i CoM kKdM y S— twwhiB

ANEXO V 01 LIMITES MAXIMOS PERMISIBLES PARA RITPOS DE LA ACTHIPAD DE LA CONSTRI CCION Cuadro V 02: Limita Máximo; Pet inisibles para luidos de la actividad de la LMP para l uidos de las acmida des de constmcción en LA J .el cual esta construcción. t i p n sado en dB (A) Horano Diurno Horano Nocturno1 Actividades de la Construcción en Para nudos producidos (Despues de las 19 Areas de Sensibilidad Acústica 1 entre las 7:00 y 19 00 horas y antes de las horas 7 horas del día siguiente) 1 Zona de protección especial zona residencial oficinas centros de 75 No se podra realizar investigación (duración de nudo no obras mavor a 8 horas en este nivel) 2 Zona comercial campos deportivos, estacionamientos ceñiros de recreación 80 70 (duración de ruido no mayor a 10 horas en este nivel) 3 Zona índustnal. autopistas, lineas férreas, y aeropuertos (duración de 85 75 ruido no mavor a 12 horas en este mvel)

FICA p ro ye cto : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Niveles Límite de Ruido Establecidos por la Organización Mundial de la Salud (OMS) • Señalar los medios que se utilizaran para minimizar o reducir los ruidos. El nivel de ruido serán temporales en la fase de ejecución del proyecto lo cual durara del inicio hasta su culminación de las obras civiles, las consideraciones para minimizar podrían ser: - Cerrar las tapas de los motores de las compresoras cuando estén en marcha - Verificar que los amortiguadores de rompe pavimentos y dispositivos similares estén bien ajustados. - Ver que los tableros de las distintas máquinas estén bien ajustados y no vibren. En la fase de operación del Proyecto es decir cuando este operativa la vía el tránsito que se generará emitirá una serie de ruidos que solo podrá ser evaluada dentro de los parámetros permisibles. 2.3.7. Generación de vibraciones. Muchas máquinas ruidosas o herramientas de mano también transmiten vibraciones al cuerpo - las perforadoras neumáticas es el mas común. Pueden así causar lesiones en músculos y articulaciones y afectar la circulación de la sangre, particularmente en los dedos de la mano. Al usar estas herramientas es preciso protegerse con guantes, que amortiguan las vibraciones. Las maquinarias que generan ruido y vibraciones son las siguientes: Descripción de Equipos

En el Proyecto

Martillos hidráulicos/neumáticos

-

Vibradores de Concreto

X

Rodillo Liso Vibratorio Autopropulsado

X

Compactadores Pesados

X

FICHA INFORMATIVA j

CLASIFICACION AMBIENTAL - FICA COÑSURCí

[>ia irá'«n>Raía«í /

CIP. N* 75406 ESPEOM.ÍSTA en GESTIOHMMWIttL

1

FICA p ro ye cto : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

3.

MARCO INSTITUCIONAL Y LEGAL. 3.1.

Marco institucional. •

Ministerio de Vivienda,

Construcción v Saneamiento. Sera ei ente

encargado de monitorear la adecuada panificación del proyecto, hasta su aprobación. •

Gobiernos Locales. Los gobiernos locales, constituyen el nivel de gobierno de mayor cercanía a la población y de allí la importancia de su rol en la gestión del proyecto y en la gestión ambiental, el mismo que representara a la comunidad y promoverá la adecuada prestación de los servicios públicos locales y el desarrollo integral, sostenible y armónico de su circunscripción; en armonía con las políticas y planes nacionales y regionales de desarrollo.

3.2.

Marco legal. El Presente Proyecto se encuentra dentro de los siguientes lineamientos: •

El Perfil de Inversión Pública corresponde a la primera acción para identificar y proponer la solución al problema, de acuerdo a la Ley 27293, Sistema Nacional de Inversión Pública. El Proyecto se enmarca en la: Función

15

Transporte.

División Funcional

036

Transporte Terrestre.

Grupo Funcional

074

Vías Urbanas.

Sector Responsable

Vivienda, Construcción y Saneamiento.

OPI Responsable : •

OPI de la Municipalidad Distrital de Yarinacocha

Dentro de los lineamientos de la Municipalidad Distrital de Yarinacocha es fomentar el desarrollo, dentro del proceso de descentralización mediante la concertación de los gobiernos locales, sociedad civil y población

FICHA INFC

FICA p ro ye cto : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

de transporte, con la finalidad de elevar los estándares de vida de la población. •

Dentro del Programa multianual de Inversión Pública en el objetivo general dos (2) dice: Mejorar la calidad de vida de la población, promoviendo y ejecutando obras de infraestructura económica y social, incentivando la inversión privada. Teniendo como inciso el N° 25, 26, 27, 28, 29 la cual menciona: 25. Construcción y mejoramiento de carreteras en las zonas rurales y urbano marginal. 26.

Garantizar el

mantenimiento

de

la

infraestructura

vial

conservando la naturaleza y características de la misma. 27. Construir, mantener y rehabilitar los caminos rurales destinados a establecer nexos entre centros poblados y de estos con la red principal. 28. Incrementar el servicio de transporte terrestre, fluvial y aéreo, controlándola y fiscalizándola. Requerimientos legales: El proyecto se enmarca dentro de las siguientes normas legales: • Constitución Política del Perú (1993). •

Ley General del Ambiente Ley N° 28611 El proyecto busca mejorar la calidad del Ambiente de acuerdo al Capitulo 3 art. 113 De la Calidad Ambiental (Preservar, conservar, mejorar y restaurar, según corresponda, la calidad del aire, el agua y los suelos y demás componentes del ambiente identificando y controlando los factores de riesgo que la afecten).

• Ley del Sistema Nacional de Evaluación de Impacto 27446 Cuyo objetivo es determinar la CATEGORIZACIÓN DE ACUERDO AL RIESGO AMBIENTAL en concordancií dicha LEY.

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYAU ".

Art. 4.1 Toda acción comprendida en el listado de inclusión que establezca el Reglamento,según lo previsto en el Artículo 2 de la presente Ley, respecto de la cual se solicite su certificación ambiental, deberá ser clasificada en una de las siguientes categorías: a) Categoría I.- Declaración de Impacto Ambiental b) Categoría II.- Estudio de Impacto Ambiental Semidetallado c) Categoría I I I E s t u d i o de Impacto Ambiental Detallado •

Ley de los Recursos Hídricos N° 29338 Con la Ejecución del Proyecto se pretende cumplir con el Título II capitulo I De la Conservación y Preservación de los recursos Hídricos, que existe en el caño natural que es afluente de la Laguna de Yarinacocha. (Alcantarillas proyectadas)



Reglamento de Estándares de Calidad Ambiental de Aire



Reglamento de Estándares de Calidad Ambiental de Ruido



Reglamento de Acondicionamiento Territorial y Desarrollo Urbano D.S. N° 027-2003-VIVIENDA -

Acta de Compromiso de Mantenimiento Vial anexado en el estudio del Factibilidad:

-

Certificación del tipo de vía y la sección que le corresponde adjunto en el estudio de factibilidad.



Tipo de Vía según el Plan Vial de la Ciudad de Pucallpa Ley General de Residuos Sólidos.

Artículo 8o de la Ley N° 27314, Ley General de Residuos Sólidos, y el artículo 6o del Decreto Legislativo N°1065, que modifica la Ley N° 27314, para asegurar una gestión y manejo de los residuos sólidos de la construcción y demolición, sanitaria y ambientalmente adecuada, con sujeción

a los principios de minimización,

prevención

ambientales y protección de la salud y el bien

FICHA INFORMATIVA DE CLA SIFICA CION AM BIENTAL - FICA CONSORCIO FRL i SG ASCONSUIT S.R.L Ing. Ed w in Rafael Lean CIP. N* 75*Oí

ESPECIALISTAen GESTIONAMBIENTAL

A m p a ro D ía z Ar'évalo REPRESENTANTE

le g a l

de riesgos

FICA p ro ye cto : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

ASPECTOS DEL MEDIO FISICO, BIOTICO, SOCIAL, CULTURAL Y ECONOMICO (LINEA BASE). A. Caracterización del medio físico, biótico, social, cultural y económico del ámbito de influencia del proyecto. ASPECTOS DEL MEDIO FÍSICO. Características ambiéntales del entorno: • Clima.El clima predominante es cálido y húmedo con abundantes precipitaciones, existe muy poca variación de temperatura y humedad entre el día y la noche, las lluvias son abundantes (2,344mm anuales en promedio); pero, no supera la precipitación al de la selva alta en donde alcanza los 4,000mm al año.

• Humedad relativa La Humedad relativa anual media es de 84.24%, la que es favorecida por la evaporación que se produce en los numerosos cursos de aguas. • Vientos Los vientos tienen una dirección predominante de norte a sur, con una velocidad promedio de1.4 metros por segundo. •

Hidrología: De acuerdo al mapa de peligros de la Municipalidad de Coronel Portillo, la zona donde se realiza el proyecto existe un escurrimiento de aguas superficiales donde se puede diagnosticar que existe una cuenca formada por la depresión en la zona 4, Actualmente, el servicio de desagüe es irregular, pero lo que se aprecia con mayor incidencia es el escurrimiento o estancamiento de aguas pluviales en las cunetas de las vías y estas a los caños naturales, generando un impacto ambiental negativo en el entorno. En contradicción a la Ley de Los Recursos Hídricos en su Titulo v de la Protección del Agua, articulo 83, que a la letra dice “Está prohibido verter sustancias contaminantes y residuos de cualquier tipo en el aguav^fijfAL,^ v°b° ^ bienes asociados a ésta, que representen riesgos significatiwjÉ^ I r 8

e

itif S A ñ r íY c r *

loscriterios de toxicidad, persistencia o bioacumulación”. Con lasVotfrásí;d’e i mejoramiento de saneamiento se paleara este problema.

FICHA INFORMATIVA

LA SIFICA CION AMBIENTAL - FICA

ftLean ESPECIALISTAEHGESTIONAMBWTAl

Ampúro D íaz fir w a lo " ¿^PRESENTANTE LEGAL

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Mediante el estudio hidrológico se determinara los niveles de máximas avenidas para calcular el nivel de la rasante de la superficie de rodadura y el caudal de escorrentía para el diseño de las respectivas alcantarillas de concreto armado para poder dar continuidad a la proyección de la vía. La ejecución de estas obras civiles se realizara en la etapa de Inversión. •

Principales componentes paisajísticos: El distrito cuenta con paisajes naturales y los recursos turísticos másimportantes son: Laguna Yarinacocha, en Puerto Callao: Se encuentra a 7 km alnoreste de Pucallpa (15 minutos en auto). Sus aguas tibias ytranquilas, es un antiguo meandro del río Ucayali, creado por elcambio de su curso. En temporada de lluvias la laguna se une conei río Ucayali a través de canales o "caños", dinámica que le da una gran riqueza ictiológica, permitiendo que sus aguas se renueven periódicamente. En la laguna se puede pescar, hacer esquí acuático, nadar, remar y observar delfines deagua dulce. En Puerto Callao, embarcadero artesanal de (a laguna, se pueden contratar botes para dirigirse a diferentescomunidades mestizas y nativas de la etnia Shipibo-Conibo. Destacan las comunidades nativas de San Francisco yNuevo Destino y el Caserío 11 de Agosto o "Caserío de Cesteros", llamado así porque muchas mujeres de dedican a laartesanía elaborada con fibras vegetales que son recolectadas en los bosques naturales. Con el cogollo de caña brava, bombonaje y corteza de plátano tejen a mano canastos, carteras, abanicos, sombreros, paneras y una gran variedad deartículos utilitarios. -

Laguna Cashibococha, en Cashibococha Ubicada al margen izquierda del Lago Yarinacocha Tiempo Aprox. 2horas. Navegable por botes típicos en cualquier época de! año.

-

Isla del Amor:

Ubicada al margen izquierda del Lago de

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYAU ".

ASPECTO DEL MEDIO BIOLÓGICO: •

Zonas de vida El Área de Yarinacocha interés del presente estudio, comprende la siguiente zona de vida, siguiendo la clasificación de Leslie Holdridge, tal como se presenta:

Zona de vida natural

Simbología

Altitud (m.s.n.m)

Clima

Características principales

Biotemperatura media anual Bosque Húmedo -Tropical Transicional o Bosque Húmedo - Premontado Tropical

bh-PT

Menor a 350

Húmedo y cálido

máxima de 25 °C y media anual mínima de 17° C; promedio máximo de precipitación total/año de 1968 mm y promedio mínimo de 936 mm. Relieve topográfico varía, entre terrenos ondulados y empinados a una configuración colinosa dominante.

Fuente: Mapa ecológico del Perú (INRENA 1995).

ASPECTOS SOCIOECONÓMICOS • Población El distrito de Yarinacocha tiene una población estimada para el año 2012 supera los 91 100 habitantes, de los cuales el 88.7% habitan en la capital del distrito de Yarinacocha denominada Puerto Callao; así mismo, el 90.87% residen en la zona urbana y el restante en la zona rural. •

Economía y Principales Recursos -

Producción agropecuaria: escasa, aunque abunda la yuca, elarroz, plátano, papayas, tabaco.

-

Producción forestal: fundamentalmente a base de la madera. Hay aserraderos que utilizan la caoba, el cedro, la moena, e lishpingo y

FICA p ro y e c to : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

-

Muchas mujeres de la etnia shipibo se dedican a la textilería manual y a la artesanía de collares y brazaletes, ellasvenden sus productos por las calles de Pucallpa.



Principales Instituciones y Empresas que operan en el distrito de Yarinacocha En la jurisdicción del distrito de Yarinacocha, operan diversas instituciones del estado, empresas privadas y sector comercio; entre ellas se pueden mencionar los siguientes: -

Hospital de Yarinacocha

-

Empresa de Electricidad - Electro Ucayali S.A.

-

Banco de la Nación

-

Universidad Nacional de Ucayali Universidad Alas Peruanas Institutos Superiores Tecnológicos

-

Universidad Nacional Intercultural de la Amazonia Restaurant Turísticos - Orillas de la Laguna Yarinacocha Mercado del distrito de Yarinacocha

-

Colegios Nacionales y Particulares

-

Centros Educativos Inicial y Primaria

-

Aeropuerto

-

Grifos (Líquidos y Gas) Hostales y Comercio (Pollerías, Farmacias, Restaurants, etc) Empresas Molineras

-

Aserraderos Empresas secadoras de madera

-

Cervecería San Juan Planta de Fraccionamiento de Maple Gas

B. Descripción del área de influencia ÁREA DE INFLUENCIA INDIRECTA • Geografía Limita al norte, sur y este con el distrito de Callería y al oeste con eldistrito de Nueva Requena y el distrito de Campo Verde. En estedistrito se encuentra en

REPRESENTANTE LEGAL

FICA p ro y e c to : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYAU

Aeropuerto Internacional Capitán FAP David Abensur Rengifo y el Aeropuerto de OFASA ubicado en el InstitutoLingüístico de Verano. • Superficie La superficie total del distrito es 596.2 km2, representando 0.58% del territorio del departamento de Ucayali (102,410.55 km2). Su capital es Puerto Callao, situada

a

154

m.s.n.m,

tiene

una

densidad

poblacional

de

143.6

habitantes/km2. ÁREA DE INFLUENCIA DIRECTA • Población La población beneficiaría directa será de 587 personas. •

Educación En cuanto al nivel de educación en la zona del proyecto se tiene que la población que tiene estudios con secundaria completa es de 35%, estudios Superior Técnico un 13%, Estudio Superior Universitaria en un 5% y con estudios incompletos un 26% y un 21% con primaria completa. N IVEL DE IN S TR U C C IÓ N DEL JEFE DE FAM ILIA

Primaria Incompleta

Secundaria Incompleta

Primaria Completa

Secundaria Completa

Superior Técnico No Univ.

Superior Universitaria

5%

21%

21%

35%

13%

5%

100%

NIVEL DE INSTRUCCIÓN DEL JEFE DE FAMILIA

35%

m5% 21%

1 Primaría

Incompleta

I Secundaría Incompleta O Primaria Completa n Secundaria Completa 1Superior



FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL - FICA

□ 21%

Técnico No Univ.

3Superior Unjwsitaria

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

• Salud En cuanto a las características del sistema de salud en el área de influencia del proyecto se consigna que hay un 2% de personas que sufren enfermedades respiratorias lo que ocasionan un gasto en los recursos de la canasta familiar.

SUFRE DE ENFERM EDADES R E S P IR A T O R IA S SI

C u a n ta s V e c e s se e n fe rm a /A ñ o )

G a s to P r o m e d io / p o r cad a v e z q u e se e n f e r m a (s / .)

2%

0%

NO

98%

100%

SUFRE DE ENFERM EDADES RESPIRATORIAS

2%0%

B SI Cuantas Veces se enferma/Año) ■ SI Gasto Promedio/porcada vez que se enferma (sJ.) O NO

Servicios públicos -

Agua Potable y Desagüe

El sistema de saneamiento básico es deficiente, ya que no cuenta con el servicio de desagüe por parte de EMAPACOPSA teniendo un sistema provisional, pero la mayoría de la población si cuenta con el servicio de agua con sistema de conexión domiciliaria, pero lo que no cuenta es una adecuado sistema de excretas, para lo cual se estima que proyecto de

Agua y Desagüe del Sector 10 se considera los pará

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL ■ FICA CO n SORCI

____ (

'" J Edw jiLBa/ael Lean CIP. N* 7J40* ; SPSCUUSTAENGESTIONAMBIENTAL

AtXfXÍrt ^REPRESENTANTE LEGAL

lis

ESTUDIOS

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYAU ".

técnicos - sanitarios en el área que se esta ejecutando en la vía, salvaguardando la duplicidad de costos de inversión. Energía Eléctrica

En el tramo de vía a intervenir se aprecia que cuenta con energía eléctrica a lo largo de la vía asimismo en los centros poblados, dicho suministro es impartido por ELECTRO UCAYALI S.A. Telecomunicación

La zona del proyecto también cuenta con servicios de telefonía •

Economía Local Actividades Económicas de la Población

-

En cuanto al tipo de actividad que se realiza en la zona del proyecto se consigna que el 37% con trabajadores independientes,

30% son

estudiantes, 15% son familiares de la FF.AA, el 13% son empresarios y el 4% son obreros TIPO DE ACTIVIDAD A QUE SE DEDICA LOS MIEMBROS DE FAMILIA > A 14 AÑOS

Estudiante

Em presario

T rabajador Independiente

Em pleado Público

O brero

F F -A A (Fuerzas Arm adas)

OTROS: (especificar)

30%

13%

37%

4%

1%

15%

0%

100%

TIPO DE ACTIVIDAD A QUE SE DEDICA LOS MIEMBROS DE FAMILIA > A 14 AÑOS

m Estudiante ■ Empresario □ Trabajador Independiente □ Empleado Público m Obrero a FF- AA (Fuerzas Armadas) m OTROS: (especificar)

Se adjunta el plano que visualiza el AID y AH

FICHA

DE CLASIFICACION AMBIENTAL - FICA

CIP. N ‘ 7 5 4 » S i* C W I iSTA E li G ESÍI0K M IB IE IT M .

^ REPRESEN TAN TE LEGAL

© FICA p ro y e c to : '‘MEJORAMIENTO DE VIA DE INTERCONEXION AL C.P. SAN JOSE DESDE PUERTO CALLAO, __________________________________________________________________ DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

C.- El proyecto no se ubica dentro de los límites o zona de amortiguamiento de un Área Natural Protegida, sin embargo, existe dentro del Área de influencia Indirecta el Lago de Yarinacocha, sitio turístico, comúnmente visitada por turistas y población en general, actualmente el lago es dedicado a múltiples usos incluyendo la recreación y el turismo, de ella dependen numerosas poblaciones asentadas en sus áreas adyacentes. D.- No existe conflicto con la población con respecto a la ubicación del proyecto, la aprobación de la ejecución de la vía es de un 100% aceptada por la población, por un mejoramiento de la vía, eficiente sistema de drenaje pluvial, adecuado sistema de saneamiento básico y una adecuada señalización de tránsito, que conlleva una mejor calidad de vida. E.- Por ser un componente principal, la vía de acceso, las casas se encuentran en el margen derecho e izquierdo de las vivienda lo largo de la obra. F.- Los fenómenos naturales comunes que podrían ocurrir en la zona de emplazamiento del proyecto son: •

Inundación: Se puede tener en cuenta por las frecuentes lluvias en épocas de invierno ya que según la topografía plana están inmersos al desborde de la laguna que está cerca a la vía en estudio por la cual se deberá tomar en cuenta en la construcción o diseño del asfaltado.



Lluvias Intensas Las lluvias Intensas pueden ser consideradas como peligros en la situación sin proyecto debido a que los sistemas de drenaje y las obras de arte existentes son insuficientes, lo cual estarían expuestas las viviendas de los centros poblados aledaños a la vía.



Erosión Fluvial/De Laderas La erosión es la desintegración, desgaste o pérdida de suelo y/o rocas como resultado de la acción del agua y fenómenos de intemperismo. La erosión fluvial es el desgaste que producen las fuerzas hidráulicas de un río en sus márgenes y en el fondo de su cauce, con variados ef§ colaterales.

FICHA INFORMATIVA,0S¡ CLASIFICACION AMBIENTAL - FICA CONSORCIO Fj

Tnvftaííal Lean opa FTSHV

iSPECIAltSTAENGESTO* U B H ttl

—-----A n t f r n r t j^ ü ia z A ré v a ib ^ ^ PRESENTANTE

LEGAL

,

ñ g & fé H O OM L

FICA p ro y e c to : “ MEJORAMIENTO DE VIA DE INTERCONEXION A L C.P. SAN JOSE DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYALI” .

Mientras que por erosión de laderas, se entiende a todos los procesos que ocasionan el desgate y traslado de los materiales de superficie (suelo o roca), por el continuo ataque de agentes erosivos, tales como agua de lluvias, escurrimiento superficial y vientos, que tiende a degradar la superficie del terreno. 5.

PLAN DE PARTICIPACION CIUDADANA. El proponente deberá elaborar el Plan de Participación Ciudadana tomando en consideración las disposiciones establecidas en las normas sectoriales y el título IV del DS N° 002-2009-MINAM, según corresponda. INFORMACIÓN Y COMUNICACIÓN A LA COMUNIDAD. El objetivo es efectuar reuniones entre los representantes del proyecto y los de la comunidad con el fin de presentar la información respecto a las actividades planeadas del proyecto, beneficios, consecuencias de las mismas y sus medidas de mitigación.

Medidas de Manejo para la Participación Ciudadana.

-

Se deben realizar reuniones o talleres con los trabajadores al inicio de la construcción de la obra y reforzar con charlas breves al inicio de jornada en cada uno de los frentes de trabajo acerca de buenas prácticas ambientales. Los mismos que deben comprender la importancia de la conservación de los recursos agua, aire, suelo, vegetación y fauna, con especial énfasis en la conservación de la biodiversidad y las especies protegidas.

Se deberán establecer comunicación con la comunidad antes, durante y después del proyecto. El ejecutor puede designar a un trabajador como relacionista comunitario, quien se encargará de establecer contacto con la comunidad, con el fin de dar toda la información acerca del proyecto, respondiendo las inquietudes de ellos. Buscando ponerse de acuerdo para actividades conjuntas si el caso lo requiere. 6.

DESCRIPCION DE LOS POSIBLES IMPACTOS AMBIENTALES. En base a la información desarrollada en los ítems anteriores, señalamos los principales impactos ambientales y sociales que se estima generara el proyecto.

FICHA INFORMATIVA DB^BLASIFICACION AMBIENTAL - FICA

______ _

s

p

s

a

n

u

s

w

A

ü

i

e

í

s

w

)

»

m

P

p ^

r ^

U

i a i ^

r e v a l o

re s e nt ant e l e g a l

FICA p ro ye cto : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C A Y A U ".

PRINCIPALES IMPACTOS AMBIENTALES

CONSTRUCCION

OPERACIÓN

MANTENIMIENTO

Eliminación de arboles ornamentales por la tala Emanación de gases por tubos de escape de Desechos de materiales ocasionados de tos mismos para construcción de veredas vehículos que transitan en la zona por cocina de asfalto - Juntas

Acondicionamiento de patio de maquinas

Incremento de ruidos por transito de vehículos

Residuos de pinturas

Ruidos de maquinaria durante ejecución de trabajos

--------------

--------------

Emanación de gases por tubos de escape de maquinaria pesada durante la ejecución del proyecto. (C02,C0)

--------------

--------------

Generación de residuos sólidos ( material de demolición de alcantarillas, materia orgánica, botellas, clavos, madera, etc.)

--------------

Incremento de enfermedades respiratorias por generación de polvo

---------------

Contaminación del suelo por derrame de lubricantes y aceites

--------------

--------------

Principales Impactos Sociales. CONSTRUCCION

OPERACIÓN

MANTENIMIENTO

Incremento de puesto de trabajos en la zona

Trafico mas fluido con seguridad y comodidad

Aparición de puestos de trabajo para actividades de mantenimiento

Disminución de accidentes de transito

an> FICA p ro ye cto : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - U C AYAU ".

7.

MEDIDAS DE PREVENCION, MITIGACION, REMEDIACION Y COMPENSACION. MEDIDAS DE PREVENCION, MITIGACION 0 CORRECCION DE IMPACTOS AMBIENTALES

CONSTRUCCION

OPERACIÓN

MANTENIMIENTO

Es inevitable durante la construcción, la taia de árboles una Se aplicara mediante la Oficina de Transito del Gob. vez finalizada ia obra, se acopiaran en un punto para su Local el control de Emanación de gases por tubos de eliminación, se limpiará y dejará el centro de acopio, al escape de vehículos que transitan en la zona igual que como se encontraban al inicio de las obras.

Se aplicara mediante la Oficina de Transito del Gob. Local el control de Incremento de ruidos por transito de vehículos

El área de patio de maquinas será restaurado con reemplazo de material en la superficie de rodadura

Se restaurará el área donde se utilizó la cocina de asfalto - Juntas

Se eliminará todo residuos de pinturas en el área de la via mantenida

Se revisará las maquinaria que emita ruidos por encima de lo permitido Se revisara los tubos de escape de maquinaria pesada con la finalidad que no emane gases mas de permitido

---------------

El material de demolición será utilizado en otras obras como relleno. El material a desmontaren su mayoría serán calaminas y madera deteriorada, en el menor plazo posible debe ser dispuesto a un relleno sanitario autorizado, otra alternativa sería para los residuos de madera, como algunos pobladores de esa zona utilizan la leña para cocinar podría ser dispuesta en un lugar para que los que necesitan puedan llevarse.Q Materia orgánica deberá, ser colocada en un lugar adecuado para ser entregado a los carros recolectores.

Al terminar la partida de movimiento de tierras disminuirán el incremento de enfermares respiratorias Exigir el uso de protectores de las vías respiratorias a los trabajadores que estén expuestos a estas partículas.

MEDIDAS DE PREVENCION, MITIGACION O CORRECCION DE IMPACTOS SOCIALES

CONSTRUCCION

OPERACIÓN

MANTENIMIENTO

Aumento de posibilidades de comercio Trafico y transito seguro en la zona

Priorizar la contratación de pobladores locales, que residan en la zona de influencia del proyecto durante la respectiva e t a g ^ f ^ .

FICHA INFORMATIVA DEJSLASIFICACION AMBIENTAL - FICA

C0NS0RCI0M&SG'ASCONSira.R.L

'apioMi»

A rn piíro D ía z A ré v iU ii^ ‘• ' r e p r e s e n ta n te

le g a l

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, __________________________ DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

8.

PROGRAMA DE MANEJO DE RESIDUOS SOLIDOS Y LIQUIDOS. Al finalizar los trabajos, quedara residuos como es costumbre, finalmente para el fraguado del pavimento de concreto se utilizaran las arroceras que serán habilitadas de tierra, que deberán ser retiradas en su totalidad, paño por paño, sin dejar sobrantes, para evitar la contaminación por la difusión del polvo al abrir el tránsito en la zona. En cuanto a los desechos humanos se adiestrará al personal para que sepan tratar adecuadamente los desechos, tratando de evacuarlos o generando servicios higiénicos temporales o portátiles. Unas vez concluidas las obras de arte como las alcantarillas , la población tiene la voluntad y la tarea periódica de realizar el mantenimiento, debido a que los cauces de aguas superficiales atraviesan por debajo de sus viviendas, lo cual es típico en la zona del proyecto para luego ser vertidas estas agua a la laguna de Yarinacocha. La forma del manejo del insumo cemento es de la siguiente manera: Para el Personal Obrero, deberá usar EPP: -

El empleo de guantes.

-

Ropa de Protección (overoles, mangas largas, pantalones largos, calzado de protección, protección para ojos etc.)

-

Contar con lavabos grandes y suficientes para la adecuada limpieza del personal que maniobra el cemento.

-

El personal obrero debe usar rodilleras cuando se arrodille sobre el cemento mojado. En cuanto a la disposición final de residuos de cemento ya sea en polvo o en forma de concreto serán conducidos al Botadero Municipal.

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO ■ UCAYALI".

9.

PROGRAMA DE SEGUIMIENTO Y CONTROL. Plan de seguimiento y control para las medidas de mitigación establecidas

IMPACTO / PARÁMETRO A MONITOREAR

FASE

PUNTO DE CONTROL

MÉTODO

AUTORIDAD FISCALIZADORA E INFORMES

PERIODICIDAD

COMPONENTE : RUIDO

Generación de ruido.

Construcción y Cierre

Inspección visual

Mensual durante el periodo de obras civiles, en los puntos de medición Gerencia de Medio sensibles. Informe Ambiente semestral consolidado durante las fases de construcción y cierre

COMPONENTE : FLORA Y VEGETACION

Corta de vegetación y arboíes Construcción en zonas aledañas a vias

Puntos de control según Inspección visual, plano de tala de delimitación de zona arboles

Se controlará atravez de ios Gerencia de Medio supervisores ambientales Ambiente

COMPONENTE : PATRIMONIO ARQUEOLOGICO Y CULTURAL No se registra antecedentes de existencia de restos arquelogicos en la zona del proyecto

----

----

Frentes de Trabajo

Inspección visual y registro de actividades de humedicimiento de caminos de tierra

COMPONENTE : AIRE

Construcción y Emisión de material particulado Cierre

Informe mensual de supervisión ambiental

Gerencia de Medio Ambiente

COMPONENTE: FAUNA En la zona del proyecto no se registra intervención en habitat de fauna

-----

COMPONENTE.SUELO Pérdida o degradación de suelo por excavaciones de zanjas

Construcción

Frentes de Trabajo

Inspección visual y contraste de registro fotográfico inicial

Entrega de 1 informe a los Gerencia de Medio 30 dias de finalizada la Ambiente construcción de las obras ^;í\D A D V“B° e- \ DIVISION/ \

í

e STÜDI0S>C8RAS \ il^PpíStRuCTURA ^ « I mproductiva

.... FICHA INFORMATIVA DE CLASIFICACION AM BIENTAL - FICA

CONSORC Eflwin Rafael] /

CIP. N" 75406 espECUUSW EN 5ESTK* MIBIEtfTAL

A m paro D ia 2~Xr'évalo representante legal

li , ¡¡

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO ■ U C AYALI” .

10.

PLAN DE CONTINGENCIA. Tal como se ha determinado anteriormente los impactos potenciales del proyecto, en

esta parte se describe como se planea mitigar las futuras acciones dentro de

la etapa de ejecución del proyecto: •

Trabajos Preliminares: Las obras preliminares tales como la construcción de los almacenes se deben ubicar en lugares adecuados sobre la base de que los materiales insumos utilizados deben ser confinados en lugares que eviten su derramamiento y/o fuga. Se deberá de contar con maquinarias y equipos en perfecto estado de operación, con operadores idóneos, evitando la fuga de combustibles y aditivos o lubricantes, con motores de perfecta combustión interna.



Movimiento de Tierras: Los efectos negativos por los gases de combustión, fugas y derrames de combustible

y

lubricantes,

en

las

propias

maquinarias

y

zonas

de

almacenamiento de hidrocarburos, se evitara con la presencia de maquinarias en perfecto estado de funcionamiento,

así como destinando personal

especializado tanto para su operación como para el almacenamiento de los mismos. Esto significa que las maquinarias deben encontrarse en buen estado mecánico y de carburación, de tal manera que se queme el mínimo necesario de combustible, minimizando las emisiones atmosféricas. Así mismo, el estado de los silenciadores de los motores deben ser buenos, para evitar el exceso de los ruidos. Estos equipos deben de operarse de tal manera que caus^n-el mínimo deterioro posible a los suelos, vegetación y cursos de agu^fs^jj tramo de la vía en estudio. •

Obras de Concreto La manera de mitigar la acción negativa de los hidrocarburos de la zona proyecto es utilizando los mismos que se encuentren en una condición óptima operativa en todos sus sistemas, así como el personal responsable de ellas sean expertos en su operación y mantenimiento. En lo que respecta a la

FICHA INFORMA 77J¿A,DE CLASIFICACION AMBIENTAL - FICA CONSOfiC

l Lean O ****» ™ «

«

FICA p ro y e c to : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UC AYAU ".

contaminación con concreto, esta debe ser mitigado con la ejecución de encofrados perfectos, manipuleo adecuado, tanto en la zona de preparación como en la zona de ubicación de la misma. Aparte de lo anteriormente indicado, no deberá existir ninguna interrupción del sistema de drenaje, así como los desmontes, depresiones, etc. •

Almacenamiento de materiales. Las instalaciones de almacenaje de productos inflamables o peligrosos, como combustibles, lubricantes, etc., deberán estar adecuadamente protegidas y ubicadas, a fin de evitar cualquier eventualidad que pueda devenir en prejuicio de los trabajadores, debiendo preverlas ventilaciones, señales de escape y accesorios de mitigación de este tipo de desastres, como extintores, arena, agua, entre otros.

11.

PROGRAMA DE CIERRE DE EJECUCION DE OBRA DEL PROYECTO Y PROGRAMA DE ABANDONO. Plan de cierre o abandono al terminar el proyecto tendrá los siguientes procedimientos: •

Trabajos de Cierre.Determinar cuales son los equipos e instalaciones que quedaran en la zona. Realizar una evaluación de los elementos o partes de los equipos e instalaciones que se quedaran en la zona para prevenir que no contengan sustancias contaminantes;

en el caso de encontrarse deberán ser

evacuados, tratados adecuadamente y colocados en zonas predeterminadas para evitar que afecten al medio ambiente. De igual manera se procederá con los materiales o insumos contaminantes que se tengan en stock en la zona a abandonar En cuanto a los contaminantes de alta peligrosidad, como son residuos iubrícantes, es recomendable para zonas con Napas Freáticas profu (mayores de 15m.) el enterrado, previa impermeabilización de la zo mezclado con arena cubriendo la superficie con una capa de tierra limpia por lo menos 1m. de espesor, siendo conveniente la colocación de hitos de limitación y letreros que indiquen la existencia de dichos contaminantes. En

FICHA INFORMA TIVfy&ÉCLASIFICAC IO N AM BIENTAL - FICA COk Í w

ng T E d w in iw w i l Le an

ctp. n* 75*06

ESPECIM.STf.tNGESTIONAMBKKTM.

"

*

...

^ ím p a r u D ía z A réva lo REPRESENTANTE LEGAL

FICA p ro y e c to : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

el caso de las zonas con Napas no profundas es recomendable utilizar como alternativa el proceso de relleno sanitario (Landfilling) o el método de compostaje biológico -

Todos los desechos contaminantes no peligrosos deberán ser tratados adecuadamente de acuerdo al manual de procedimientos de manipulación, almacenamiento

y

disposición

de

desechos

contaminantes,

siendo

recomendable para estos casos el tratamiento de degradación biológica.



Trabajos de Desmantelamiento.El

alcance

de

los

trabajos

de

desmantelamiento

o

desmontaje

de

equipamientose refiere básicamente a los equipos electromecánicos. Los trabajos aquí especificados no son limitantes ni restrictivos de otros que sean necesarios para el desmontaje total de los equipos. El listado final de equipos a desmantelar será presentado por el contratista antes dei inicio de las obras. El trabajo de desmontaje y desmantelamiento comprende las provisiones de toda la mano de obra, equipos, materiales y todo el trabajo necesario para el retiro de los siguientes elementos: Bombas i anques de combustibles Grúas. Todos los materiales a ser utilizados durante el desmontaje deberán estar conformes para su utilización bajo responsabilidad del contratista. Los materiales que así lo requieran deberán almacenarse, separarse, manipularse y protegerse de forma adecuada durante los procedimientos de desmontaje para mantent aptitud de uso.



Trabajos de Demolición.El presente numeral establece los requisitos para la ejecución de los trabajo demolición de estructuras. Antes del inicio de la obra de demolición, deberá estudiarse como punto inicial de! programa de ejecución, el comportamiento estructural de la infraestructura y

FICHA INFO

OSIFICACION AMBIENTAL ■

SSPÍCIAUST» H GESTION M W W U l.

A m p Q p rfu ia z A té rra lo ¿jfífPRESENTANT6

leg al

FICA p ro y e c to : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

edificaciones a demoler y se recomienda que de acuerdo a este estudio sean marcados con signos visibles el orden de desmantelamiento y demolición de los elementos. Los trabajos de demolición conllevan necesariamente a la generación de material particulado proveniente del material pulverizado, que en gran cantidad y concentración puede ser muy perjudicial para la salud. Todo el personal deberá estar debidamente protegido por máscaras como complemento del trabajo de rociado de agua para sedimentar dichos polvos. No deberá detenerse el proceso de demolición de una estructura, cualquiera sea su tipo, debido a que sus capacidades auto portantes ya se encontrarían comprometidas. Por lo que se recomienda una vez iniciadas las obras de demolición, no se paralicen hasta el retiro total del material de desmonte. Los escombros originados en la demolición deberán ser retirados totalmente, para

ello

se

deberán

clasificar:

Las

tierras

removidas

deberán

ser

adecuadamente dispersas, y los restos de material de construcción deberán ser trasladados hacia botaderos debidamente acondicionados para su posterior enterramiento.

Medidas de Mitigación.Los trabajos para la protección y restauración comprenden: -

Estabilización física de las obras de las obras en abandono.

-

La demolición, de ser necesario, de las estructuras, lo cual requerirá martillos neumáticos o taladros neumáticos.

-

Los escombros originados en la demolición deberán ser retirados totalmente, para

ello

se

deberán

clasificar

las

tierras

removidas

deberán

ser

adecuadamente dispersas, y los restos de material de construcción deberán ser trasladados hacia botaderos debidamente acondicionados para su posterior enterramiento. -

Descontaminación del suelo y arreglo de la superficie. La tierra y suelos contaminados

con aceites

y productos

químicos

ocasionados

por la

maquinaría empleada, deberán ser retirados y traslados a los botaderos para su posterior enterramiento.

FICA p ro ye cto : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Para la utilización del material de préstamo se tendrá que seleccionar zonas

-

de aprovisionamiento luego de un análisis de alternativas, lo que se tendrá que

preparar

revegetación

un el

Plan

de

Explotación,

que tendrá

que

recuperación

ser debidamente

morfológica

aprobado

y

por los

especialistas. -

Revegetación. Una vez finalizadas las obras, se realizará en la brevedad posible

la

recuperación

de

las

zonas

afectadas

con

la

siembra

preferentemente con especies nativas del lugar, tratando de armonizar con las áreas adyacentes.



Medidas de Restauración.En las medidas de restauración se tendrá que restaurar: -

Restauración de áreas donde se almacenará el cemento. Restauración de áreas donde se acopiará agregado fino / grueso.

-

Preservación de vegetación.



Sobre los Campamentos (almacén) Durante las operaciones del Plan de Cierre se prevé la instalación de campamentos para lo cual se propone adoptar las medidas mitigadoras.



Depósitos de Materiales Excedentes (Botaderos) En la determinación de la ubicación de las áreas destinadas para los botaderos

se

tendrá

que

pedir

necesariamente

la

participación

de

especialistas ambientales e Ingeniero Sanitario para que el impacto al ambiente sea mínimo. Luego que el material ha sido excavado será transportado a los lugares de desmonte, previamente aprobados por la supervisión. Se ha considerado que en el proyecto los posibles botadores se encuentran a una distancia máxima de 3 km. En cuanto a la exacta ubicación de los botaderos, este se determinará en la época en que se llevará a cabo el Programa de Cierre, pues pasados los años de vida útil de las instalaciones se p r^ v ^ ^ ^ o c u rra n cambios significativos sobre todo en la expansión urbana y

FICHA INFORMATIVA D&GLASIFICACION AMBIENTAL - FICA

CÜffSÜKCiOFR^Sy------ y

,

y

---------------------- ------------—

n :n r -

- A m p a f^ a ^ v S ÍÓ « ffis iK M M w e n M .

----------

e iú t d d J ^ iL a u « P

resen tan te l e g a l

*

'

Q O ? FICA p ro ye cto : “ MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, _______________________________________________________________ DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

12.

CRONOGRAMA DE EJECUCION. Cronograma de ejecución del plan de seguimiento y control adjunto en anexos

13.

PRESUPUESTO DE IMPLEMENTACION. PRESUPUESTO PARA LAS OBRAS DE MANEJO A M BIEN TAL U t f n A o r L M n l U t IV IM n / tJU A lV lD lb n l I A L

UND

PRESUPUESTO | METRADO P.UNT.

TOTAL

Costos am bientales durante la pavim entación

GLB

1

12,500.00

12,500.

presupuesto de programa de m on itoreo am biental

GLB

1

12,500.00

12,500.

GLB

1

25,000.00

25,000.

TOTAL

50,000.

presupuesto programa de educación y capacitación am biental

DESAGREGADO DEL PRESUPUESTO PARA OBRA DE M ANEJO AM BIEN TAL POR 6 MESES PRESUPUESTO UND

| M E TR A D O |

P .U N T.

TOTAL

Costos am bientales durante la pavimentación P r o te c c ió n a l p e r s o n a l o b re ro -. I m p le m e n t o s d e s e g u n d a d

g lb

B o tiq u ín y p r im e r o s a u x ilio s e n o b ra

g lb

C o n o s p lá s tic o s

und

C erco d e m a lla HDP

mi

C e rc o c o n c in ta s d e S e g u rid a d H a b ilita c ió n d e B o td e r o s

1.00

2 ,5 5 0 .0 0

2,5 50.

1.00

1 ,5 0 0 .0 0

1 ,5 0 0 j

32 .0 0

2 5 .0 0

800.1

1 0 0 .0 0

1 .5 0

1 50 J

r o ll

6 .0 0

2 5 0 .0 0

1,500J

und

2 .0 0

3 ,0 0 0 .0 0

6 ,0 00.

12,500.< Presupuesto de programa de m onitoreo am biental C o n tr o l d e c a lid a d d e a ir e ( p o lv o s . 2 m u e s tr a s p o r m e s x 2 m eses) C o n tr o l d e r u id o s 2 m u e s tr a s p o r m e s x 2 m e s e s )

und

2 2 .0 0

2 8 4 .0 9 2

6,250.1

und

2 2 .0 0

2 8 4 .0 9 0

6,249.!

12,500.< Presupuesto Programa de educación y capacitación am biental c h a rla s d e c a p a c ita c ió n a l p e r s o n a l d e o b r a - C o n s e rv a c ió n d e r e c u r d o d n a tu r a le s y m e d io a m b ie n t e a c tiv id a d e s d e e d u c a c ió n a m b ie n t a l e d ic ió n d e c a r tilla s , f o lle t o s , d o c u m e n t o s , c u a d e r n illo s

und

4 .0 0

5 ,0 0 0 .0 0

20,000.1

g lb

5 .0 0

1 ,0 0 0 .0 0

5,000.1

2 5,0 00 .(

FICA p ro ye cto : “MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

14.

CLASIFICACION AMBIENTAL. 14.1 Clasificación ambiental que propone la empresa 14.2 clasificación otorgada por la autoridad y/o entidad que desarrolla e l presente documento competente (marcar con un aspa) Declaración de Impacto ambiental

Declaración de Impacto ambiental

X

Estudio de Impacto Ambiental semidetallado

Estudio de Impacto Ambiental semidetallado

Estudio de Impacto Ambiental detallado

Estudio de Impacto Ambiental detallado

SELLO Y FIRMA DEL RESPONSABLE DEL DESARROLLO

SELLO V FIRMA DEL PROFESIONAL DE LA AUTORIDAD

DEL PRESENTE DOCUMENTO

COMPETENTE

Nom bre del profesional responsable N úm ero de colegiatura DNI Dirección T elefono/ce lular E-mail

Edwin Rafael Lean 75406 17931325 AA.HH. VILLA ORIENTE MZ"A" - LT"4" 57 0190- PUCALLPA frlean27@ hotm ail.com - [email protected]

ANEXOS >

Copia de la FICA elaborados en el estudio de Pre factibilidadto

>

Plano de ubicación y localización del proyecto a escala visible con coordenadas UTM.

>

Panel fotográfico.

>

Plano brindada por la Municipalidad Distrital de Yarinacocha.

>

Cronograma de ejecución.

>

Planos generales del sistema vial del proyecto a escala visible.

>

Plano que visualiza el Area de influencia directa y Area de influencia indirecta.

FICA p ro ye cto : " MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

ANEXOS

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL - FICA

FICA p ro ye cto : "MEJORAMIENTO DE VÍA DE INTERCONEXIÓN A L C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UCAYALI".

Panel fotográfico.

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL - FICA

Foto 01: Toma del punto de inicio de la futura obra

Foto 02: Lugar donde estara hubicada una de las alcantarillas que cruza la vía.

C . Edwin Rafael Lean

CIP. N' 7Í40Í fCUUSTAENGESTIONAMBIENTAL

WKfsexrr/siNTf

©

F”

Foto 03: Otro punto donde estara una alcantarilla nueva. Se nota el polvo existente

Foto 04: Parque de Thusmo, punto por donde pasa la vía

(9

Foto 05: Se muestra el puente existente en buen estado por donde pasara la via

Foto 06: Se visualiza uno de las alcantarillas existentes artificial

C P. N* 75406

F." r.ESUCti R f? R íS ít
Lean ESȣC liliS U E* GESTO* U IBW IAL

FICA p ro ye cto : ‘‘MEJORAMIENTO DE VÍA DE INTERCONEXIÓN AL C.P. SAN JOSÉ DESDE PUERTO CALLAO, DISTRITO DE YARINACOCHA, CORONEL PORTILLO - UC AYALI” .

Piano de ubicación y localización del proyecto a escala visible con coordenadas UTM.

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL - FICA

Prefactibilidad SNIP: 149054

MUNICIPALIDAD DISTRITAL YARINACOCHA U illM K im K IIIU

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL DE PROYECTOS

“Mejoramiento de vía de interconexión al C.P. San José desde Puerto Callao, Distrito de Yarinacocha, Coronel Portillo - Ucayali” (SNIP: 149054) NIVEL DE ESTUDIO: PRE FACTIBILIDAD

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad SNIP: 149054

FICHA INFORMATIVA DE CLASIFICACION AMBIENTAL DE PROYECTOS GENERALIDADES Proyecto:

‘Mejoramiento de vía de interconexión al C.P. San José desde Puerto Callao, Distrito de Yarinacocha, Coronel Portillo - Ucayali” (SNIP: 149054) NIVEL DE ESTUDIO:PRE FACTIBILIDAD

Responsable(s) o Titular(es) (propietario(s)): ■

Unidad Formuladora MUNICIPALIDAD DISTRITAL DE YARINACOCHA



Unidad Ejecutora

:

MUNICIPALIDAD DISTRITAL DE YARINACOCHA ■

Unidad Evaluadora MUNICIPALIDAD DISTRITAL DE YARINACOCHA

Fecha: 24/01/2011

DEL PROYECTO.

1 . Antecedentes del Proyecto: •

Se aprueba el perfil del proyecto después de haber cumplido con el contenido mínimo del formato snip 5B , el evaluador recomienda su aprobación Con Informe Técnico N° 003-2010MDY-SGPP-DPI-EV-EGRP de fecha 15 de julio del 2010,para pasar al siguiente nivel de estudio se deriva ala unidad formuladora

Prefactibilidad SNIP: 149054



Mejoramiento de la infraestructura vial, consistente Pavimento flexible con tratamiento Bicapa de 4 y 3.5 cm de espesor, colocada sobre una base granular de e=0.10 m., subbase granular de e=0.15 m. y subrasante estabilizada con cal de e=30 cm. con anchos de calzada en diferentes tramos de 8.00m y 12.00 m



Construcción de 6,101.02ml de canaletas laterales de concreto armado fc=140 Kg/cm2, ancho variable (1.00 m. a 1.20 m.) y espesor de 0.15 m. ambos lados.



Construcción de 4690.51 mi de sardineles ambos lados sumergidos de concreto f’c=140 Kg/cm2.



Construcción de alcantarillas y martillos, a lo largo del asfaltado.

Según el Plan Vial de la ciudad de Pucallpa se desarrolla vías que conectan los distritos de Callería y Yarinacocha, siendo clasificada como vía colectora. El crecimiento paulatino del distrito de Yarinacocha y el incremento poblacional del distrito de Callería han ocasionado que sus vías sean transitadas de manera constante e interrumpida en los meses de épocas lluviosas (zona selva baja), ocasionando molestias con enfermedades respiratorias a los pobladores que viven en su área de influencia; por lo que se han gestionado a través de sus dirigentes y la iniciativa del MUNICIPALIDA DISTRITAL DE YARINACOCHA:él Mejoramiento de vía de interconexión al C.P. San José desde Puerto Callao, Distrito de Yarinacocha, Coronel Portillo - Ucayali.

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad SNIP: 149054

A continuación detallamos un Diagnostico detallado por tramos a lo largo de la vía: TRAMO PROGRESIVA KM 0+00 O HASTA

KM 1+693 PUENTE SAN PABLO

DE TUSHMO. Este tramo se inicia entre: ■ El Jr 03 de octubre y el Jr San Alejandro en la progresiva 0+00 y 0+130 cuenta con un ancho de vía de 12mt y una capa de rodadura de afirmado con un espesor e=0.15mt. ■ En la progresiva 0+130 y 0+580 cuenta con un ancho de vía de 13mt y una capa de rodadura de afirmado con un espesor e=0.15mt. ■ En la progresiva 0+580 y 1+694 cuenta con un ancho de vía de 9.4mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt respecto al sistema de agua y desagüe solo existe en la progresiva 0+00 hasta el Jr Circunvalación. ■ Existe instalaciones de Energía Eléctrica y de telefónica las cuales no interfieren en la ejecución del proyecto. ■ Existe una alcantarilla en la progresiva 0+618.18 la cual se va demoler, otra alcantarilla existente en la progresiva 1+ 033.61 la cual se va demoler. ■ El puente SAN PABLO DE TUSHMO se inicia en la progresiva 1+693 y termina en la progresiva 1+708. ■ Todo este tramo pasa por las siguientes instituciones ELECTROUCAYALI, BASE DE LA FUERZA AREA DEL PERU , INSTITUTO SUPERIOR PEDAGOGICO PUBLICO BILINGÜE YARINACOCHA y UNIVERSIDAD NACIONAL INTERCULTURAL DE LA AMAZONIA. TRAMO PROGRESIVA KM 1+708 HASTA KM 2+840 CPM SAN LORENZO ■ En la progresiva 1+708 y 1+800 cuenta con un ancho de vía de 9.4mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt. ■ En la progresiva 1+800 hasta la 2+220 cuenta con un ancho de vía de 12mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt, recorriendo este tramo en la progresiva 1+928 hay una alcantarilla la cual se va demoler. ■ En la progresiva 2+220 hasta la 2+306 cuenta con un ancho de vía de 9.4mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt. ■ El puente San Lorenzo se inicia en la progresiva 2+306 y termina en la progresiva 2+314. ■En la progresiva 2+314 hasta la 2+840 cuenta con un ancho de vía de 9.4mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt.

Prefactibilidad SNIP: 149054

■ Respecto al sistema de agua y desagüe no existen en este tramo, solo cuenta con instalaciones de Energía eléctrica y de telefonía las cuales no interfieren en la ejecución del proyecto.

TRAMO PROGRESIVA KM 2+840 HASTA KM 4+690.5 ( LAGUNA SAN JOSE) ■ En la progresiva 2+840 hasta la 3+240 cuenta con un ancho de vía de 13mt y una capa de rodadura de afirmado con un espesor e= 0.1 Omt ■ Existe una alcantarilla en la progresiva 3+837.20 la cual se va demoler. ■ En la progresiva 3+240 hasta la 3+760 cuenta con un ancho de vía de 9.4mt y una capa de rodadura de afirmado con un espesor e= 0.15mt ■ En la progresiva 3+760 hasta la 4+690.5 tramo final de la carretera (Laguna de San José) cuenta con un ancho de vía de 13mt y una capa de rodadura de afirmado con un espesor e=0.10mt ■ En la progresiva 4+140, se encuentra ubicado, la Institución Educativa CARLOS CUETO FERNANDINI SAN JOSE YARINACOCHA ■ Existe una alcantarilla en la progresiva 4+040 la cual se va demoler. ■ Existe dos alcantarillas en la progresiva 4+488.5 la cual se va demoler. ■ Existe dos alcantarillas en la progresiva 4+605 la cual se va demoler. ■ Respecto al sistema de agua y desagüe no existen en este tramo, solo cuentan con instalaciones de Energía Eléctrica y de telefonía las cuales no interfieren en la ejecución del proyecto. ■ Se han coordinado con personal de EMAPACOPSA sobre las obras de saneamiento proyectadas las cuales se envió el Oficio N° 032-2009-MDYSGIDIU por parte la entidad y las cartas CARTA N° 2 3 -ING-RCVG-2010 y CARTA N° 28-ING-RCVG-2010 por parte del consultor.

RodolfoCarlosvilaizan goyaí INGENIERO CIVIL Reg.CIP 63414

Municipalidad Distrital de Yarinacocha - Sub Gerencia de infraestructura.

Prefactibilidad SNIP: 149054

Item

Descripción

01

TRABAJOS PROVICIONALES

01.01

ALMACEN Y CASETA DE GUARDIANIA

01.02

CARTEL DE IDENTIFICACION DE OBRA

02

OBRAS PRELIMINARES

02.01

MOVILIZACION Y DESMOVILIZACION DE EQUIPOS

02.02

MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL

02.03

TOPOGRAFIA Y GEOREFRENCIACION

02.04

DESBROCE Y LIMPIEZA DE MALEZAS

03

MOVIMIENTO DE TIERRAS

03.01

DEMOLICION DE ESTRUCTURAS

03.02

CORTE DE TERRENO A NIVEL DE SUB RASANTE

03.03

CONFORMACION DE LA SUB RASANTE

03.04

RELLENO CON MATERIAL PROPIO

03.05

SUB RASANTE ESTABILIZADA (SUELO - YESO)

03.06

ELIMINACION DE MATERIAL EXCEDENTE

03.07

YESO

04

SUB BASES Y BASES

04.01

SUB BASE GRANULAR

04.02

BASE GRANULAR

05

PAVIMENTO DE ASFALTO

05.01

IMPRIMACION ASFALTICA

05.02

RIEGO DE LIGA

05.03

PAVIMENTO DE CONCRETO ASFALTICO EN CALIENTE MACK B

05.04

PAVIMENTO DE CONCRETO ASFALTICO EN CALIENTE MACK 2

05.05

CEMENTO ASFALTICO DE PENETRACION 60 - 70

05.06

ASFALTO DILUIDO TIPO MC - 30

06

OBRAS DE ARTE Y DRENAJE,PUENTE Y OTRAS OBRAS CIVILES

06.01

CANALETAS LATERALES DE C°A°

06.01.01

EXCAVACION DE ZANJA

06.01.02

ELIMINACION DE MATERIAL EXCEDENTE

06.01.03

PERFILADO Y COMPACTACION

06.01.04

CONCRETO fe = 175 KG/CM2, EN LOSA INFERIOR

06.01.05

ENCOFRADO Y DESENCOFRADO, EN CANALETAS

06.01.06

ACERO DE REFUERZO FY=4,200 KG/CM2

06.01.07

JUNTA WATER STOP

06.02

ALIVIADEROS DE MANPOSTERIA

06.02.01

EXCAVACION DE TALUD PARA ALIVIADERO

06.02.02

ELIMINACION DE MATERIAL EXCEDENTE

06.02.03

CONCRETO CICLOPEO fe = 175 KG/CM2

06.02.04

ENCOFRADO Y DESENCOFRADO DE ALIVIADEROS

06.03

SARDINELES DE C°A°

06.03.01

EXCAVACION DE ZANJA

06.03.02

CONCRETO fe = 175 KG/CM2, EN SARDINEL

06.03.03

ENCOFRADO Y DESENCOFRADO, EN SARDINELES

06.03.04

ACERO DE REFUERZO FY=4,200 KG/CM2

06.03.05

JUNTA WATER STOP

06.04

ALCANTARILLAS TMC

06.04.01

EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS

06.04.02

RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO

06.04.03

ELIMINACION DE MATERIAL EXCEDENTE

06.04.04

RELLENO PARA FILTROS

06.04.05

CONCRETO fe = 210 KG/CM2 PARA ESTRUCTURAS

06.04.06

ENCOFRADO Y DESENCOFRADO NORMAL

06.04.07

ACERO DE REFUERZO FY=4,200 KG/CM2

06.04.08

ALCANTARILLA TMC D = 48"

06.04.09 07

ALCANTARILLA TMC D = 24REFUERZO DE TALUD

07.01

PERFILADO Y COMPACTACION

07.02

SUMINISTRO Y COLOCACION DE BIOMAC10X12

08

MARTILLOS

08.01

EXCAVACION DE ZANJAS PARA SARDINEL

RODOLF® CARLOS V1LLA1ZAN G0 YAS INGENIERO CIVIL Reg. CIP 63414

Utt.02

I I I I I I I

PERFILADO Y COMPACTACION

08.03

! i i i I !

|1 I I I I I

I I I I I

CONCRETO fe = 175 KG/CM2, EN MARTILLOS

08.04

ENCOFRADO Y-DESENCOFRADO NORMAL

08.05

ACERO DE REFUERZO FY=4,200 KG/CM2

09

SEÑALIZACION Y SEGURIDAD VIAL

09.01

SEÑAL PREVENTIVA

09.02

SEÑAL REGLAMENTARIA

09.03

SEÑAL INFORMATIVA

09.04

POSTE SOPORTE DE SEÑALES CO.

09.05

ESTRUCTURA DE SOPORTE TIPO E1

09.06

ESTRUCTURA DE SOPORTE DE SEÑALES TIPO E2

09.07

POSTE DELINEADOR

09.08

TACHAS RETROREFLECTIVAS

09.09 09.10

'

PINTADO DE LINEAS PINTADO DE SIMBOLOS Y LETRAS

09.11

PINTURA PARAPETO DE MUROS, PONTONES Y ALCANTARILLAS

09.12

POSTE KILOMETRICO DE CONCRETO

09.13

BARANDAS METALICAS

09.14

CONSTRUCCION DE PARADEROS DE CONCRETO

Prefactibilidad SNIP: 149054

linar

terií

2.1 Localización: Región Departamento: Provincia: Distrito: Localidad: Área:

Ucayali Ucayali Coronel Portillo Callería - Yarinacocha. Ciudad de Pucallpa Zona Urbana

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura o s v itL n z a n g ó w s

Prefactibilidad SNIP: 149054

2.2 Componentes, instalaciones, procesos constructivos y operativos del proyecto, materiales, equipos y maquinarias a utilizar: > Componentes Los componentes del proyecto son los siguientes: Mejoramiento de la infraestructura vial, consistente Pavimento flexible con tratamiento Bicapa de 4 y 3.5 cm de espesor, colocada sobre una base granular de e=0.10 m., sub base granular de e=0.15 m. y subrasante estabilizada con cal de e=30 cm. con anchos de calzada en diferentes tramos de 8.00m y 12.00 m construcción de alcantarillas, canaletas, sardineles de confinamiento incluyendo mejoramiento de obras de saneamiento (agua potable y alcantarillado), reubicación de instalaciones eléctricas y telefónicas, señalización horizontal y vertical y actividades de mantenimiento rutinario y periódico.

> Instalaciones Las Instalaciones que se habilitaran para la ejecución del proyecto son los siguientes: Almacén. El almacén será un local cercano a la obra, que servirá como resguardo a los materiales, equipos y herramientas que serán utilizados en la obra, brindando protección y seguridad. Guardianía. La guardianía será ubicada en un espacio cercano al almacén, donde se pueda vigilar y brindar protección a los diferentes insumos, estará a cargo del personal responsable y que cumpla las condiciones mínimas requeridas para este puesto de trabajo. Oficinas y SS.HH. La Oficina será habilitada dentro del local del almacén para poder facilitar la adecuada administración y uso de los diferentes insumos, los servicios higiénicos serán ubicados en un espacio donde puedan hacer uso el personal que labora en el proyecto, cabe indicar que en la longitud de la vía a construir se pueden ubicar casetas transportables en el uso de los SS.HH.

Municipalidad Distrital de Yarinacocha

-

Sub Gerencia de Infraestructura 'IGENIERO CIVIL Reg. CIP 63414

Prefactibiiidad SNIP: 149054

>

Procesos Constructivos y Operativos del Proyecto. “Mejoramiento de vía de interconexión al C.P. San José desde Puerto Callao, Distrito de Yarinacocha, Coronel Portillo - Ucayali”. LONGITUD TOTAL : 4.690 Km TIPO DE PAVIMENTO : PAVIMENTO ASFALTICO Los Procesos constructivos y operativos del Proyecto están enmarcados por las actividades a realizarse en la ejecución del proyecto, “Mejoramiento de vía de interconexión al C.P. San José desde Puerto Callao, Distrito de Yarinacocha, Coronel Portillo - Ucayali”, consiste en realizar las siguientes etapas:

1.

PAVIMENTO FLEXIBLE CONTRATAMIENTO BICAPA Trabajos preliminares. En los trabajos preliminares consiste en realizar los preparativos para el inicio de las obras civiles a proyectarse movilizando y desmovilizando los equipos y herramientas que se requerirán también se realizaran la señalización indicando la clausura temporal del transito e indicando las rutas alternas a emplearse, en cuanto a la seguridad en la zona de trabajo se tomaran las medidas de cuidado pertinentes como el evitar accidentes ocasionados por maquinarias o por procesos constructivos como : atropellos .choques y golpes, para lo cual se dotará de protección con cascos , botas de seguridad y guantes. Para el almacenamiento de los materiales que han sido transportados a la obra se contará con el espacio adecuado y propicio para la conservación de estos, la custodia de los insumos y herramientas importantes estará a cargo de la guardianía que se ubicara al lado de la oficina. Los trabajos preliminares se iniciará con la colocación del cartel de obra para luego realizar la limpieza del terreno y la eliminación de malezas, para luego realizar el trazo y replanteo y finalmente eliminar el material proveniente de limpieza. Movimientos de Tierras. En los trabajos de movimientos de tierras se realizarán cortes de material con equipos, rellenos con material propio más la compactación y mejoramiento de la sub-rasante, en esta partida se eliminará el material sobrante inservible a un botadero fuera de obra. Pavimento. La construcción del Pavimento consistirá en Pavimento flexible con tratamiento Bicapa de 4 y 3.5 cm de espesor, colocada sobre una base granular de e=0.10 m., conjuntamente las bermas laterales, y esto de acuerdo a la sección de vía que ha sido proporcionada por la Dirección de Desarrollo urbano de la Municipalidad Distrital de Yarinacocha , la pavimentación contará con obras de arte y drenaje ( cunetas y alcantarillas) para la adecuada evacuación de las aguas que provienen de las precitaciones pluviales y de los caños naturales que existen en la zona.

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad SNIP: 149054

Tachos de Basura. Los tachos de basura se colocaran en los espacios comprendidos entre la vereda y el Jardín, con la finalidad de contribuir con el ornato y limpieza en el área del proyecto.

2.

OBRAS DE ARTE Y DRENAJE EN PAVIMENTOS Canaletas de Drenaje Pluvial Abierta y Techadas. Las canaletas de drenaje pluvial están diseñadas para recolectar el agua proveniente de la calzada en épocas de lluvias.

3.

Alcantarillas de Concreto Armado Aparte de las cunetas se construirá alcantarillas de Concreto Armado de sección, Tipo Cajón, espesor 0.20m, para el control de las aguas que provienen de los escorrentías de agua naturales (conocidos en la zona como caños). Trabajos que implican: movimiento de tierras, obras de Concreto simple, Obras de Concreto Armado en total se identifico las siguientes alcantarillas que se encuentran en las siguientes progresivas Existe una alcantarilla en la progresiva 0+618.18 la cual se va demoler, otra alcantarilla existente en la progresiva 1+ 033.61 la cual se va demoler. Existe dos alcantarillas en la progresiva 4+488.5 la cual se va demoler. Existe dos alcantarillas en la progresiva 4+605 la cual se va demoler. Todas estas estas alcantarillas se van a construir nuevamente

4.

Obras de Saneamiento. (Sistema de Desagüe y Agua Potable) En cuanto a las obras de Saneamiento se ha tomado como referencia la información brindada por la empresa prestadora de servicios EMAPACOP S.A. mediante Carta N° 00552010.-GG.EMAPACOP S.A , donde SE OTORGA LA FACTIBILDAD DE SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO AN adjuntando los planos de catastro de campo visados de las redes de agua potable, colectores de desagüe, c o n e x io n e s ............... de agua y desagüe existentes y proyectadas.

RODOLF 1 TO O S VIlLAlZAN GOVAS Municipalidad Distrital de Yarinacocha

-

Sub Gerencia de Infraestructura

INGENIERO CIVIL Reg.C IP 63414

Prefactibiiidad SNIP: 149054

Redes de Agua Potable. En el tramo en estudio la empresa prestadora de servicio recomienda el cambio de Tubería de Asbesto Cemento a PVC/UF - ISO 4422, S-20 y algunos accesorios, también recomienda ejecutar las cajas de protección de válvulas Se adjunta un cuadro de las conexiones y redes de agua potable

CONEXIONES DOMICILIARIAS AGUA POTABLE

0+540

SECTOR ELECTROUCAYALI

PROGRESIVA

0+000

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 0 16 16

PROGRESIVA

0+900

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 1 25 26

PROGRESIVA

1+820

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 16 16 32

1+540

2+240

SECTOR

SECTOR LORENZ

PROGRESIVA

2+740

CONEXIÓN EXISTENTE

LARGA CORTA TOTAL 0 0 0 27 37 10

PROYECTADA

3+340

SECTOR

PROGRESIVA

3+640

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 0 15 15

PROGRESIVA

3+960

Municipalidad Distrital de Yarinacocha

3+960

SECTOR JOSE

4+690

-

SECTOR

Sub Gerencia de Infraestructura

I< INGENIERO CIVIL Reg.C IP 63414

Prefactibiiidad SNIP: 149054

JOSE CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 17 30 47

TOTAL CONEXIONES

173

INGENIERO CIVIL Reg. CIP 63414

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad SNIP: 149054

Redes de Alcantarillado. Se adjunta un cuadro de las conexiones y redes de deague

CONEXIONES DOMICILIARIAS DESAGÜE

SECTOR ELECTROUCAYALI

PROGRESIVA

0+000

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 16 0 16 0 0 0

PROGRESIVA

0+900

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 11 15 26

PROGRESIVA

1+820

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 32 4 36

PROGRESIVA

2+740

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 30 5 35

0+540

1+540

2+240

3+340

SECTOR UNIA

SECTOR TUSHMO

SECTOR SAN LORENZO

A

á .'EsnfwiSi

4K* 30CMI MOUCTNA

SECTOR SAN JOSE

PROGRESIVA

3+640

CONEXIÓN EXISTENTE PROYECTADA

LARGA CORTA TOTAL 0 0 0 13 0 13

3+960

SECTOR SAN JOSE

PROGRESIVA

3+960

CONEXIÓN EXISTENTE

LARGA CORTA TOTAL 0 0 0

Municipalidad Distrital de Yarinacocha

4+690

-

Sub Gerencia de Infraestructura

^

FOCARLOSVUAIZANGOYAS INGENIERO CIVIL Reg. CIP 63414

Prefactibiiidad SNIP: 149054

PROYECTADA

15

28

TO TAL CONEXIONES

43

153

Instalaciones Eléctricas Las Obras complementarias se contemplaran en la inversión del mejoramiento del pavimento, como el mejorar las instalaciones y tendidos de redes eléctricas para que la futura vía, brinde una adecuada iluminación en los horarios nocturnos y pueda dar un buen servicio. A continuación se detalla los postes de baja tensión a reubicar PROGRESIVA CANTIDAD 0+039 1 0+079 1 0+108 1 0+189 1 0+220 1 0+253 1 0+290 1 0+328 1 0+432 1 0+470 1 0+520 1 0+539 0+680 1 0+859 1 1+178 1 1+240 1+418 1 1+589 1 1+830 1 1+880 1 1+216 1 2+671 1 3+228 1 3+242 1 3+472 1 3+570 1 26 RODOLFO G&L0SVILW2AN GOYAb INGENIERO CIVIL Reg. CIP 63414

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

A continuación se presenta la estructura de las partidas del Proyecto 0Materiales. Los materiales a utilizarse para la ejecución del proyecto serán abastecidos del mercado local o nacional según sea el tipo de modalidad de contrato que asuma el Gobierno Regional de Ucayali para la ejecución del proyecto

Código

Recurso

Unidad

0147010002 0147010003 0147010004 0147000050

OPERARIO OFICIAL PEON TOPOGRAFO

H.H H.H H.H hh

Cantidad

Precio SI.

Parcial SI. esupuc

MANO DE OBRA 15,334.0121 6,624.9790 64,252.8722 46.9051

14.32 12.58 11.35 14.32

219,583.05 83,342.24 729,270.10 671.68

219,297.99 82,811.25 729,002.52 656.67

1,032,867.07

1,031,768.43

MATERIALES 0201010001 0229830008 0221010001 0249990001 0213030021 0213030022 0220010004 0253100004 0253900002 0254010008 0254010009 0254010010 0254110090 0254220009 0254470004 0201070002 0202040009 0202040010 0202040011 0202130021 0202130022 0203120003 0217030002 0230010015 0230010038 0229550094 0256220068 0213030026 0229830003 0265020008 0265020009 0229830007 0230010042 0230710007 0231310013 0204010002 0205400002 0221010004 0209010018 0209010021 0243010001 0243010022 0243010023 0245010004 0202510061 0202510062

COMBUSTIBLE, LUBRICANTES Y OTROS CAL (EN BOLSA) CEMENTO PORT.TIPO I EN BOLSAS 42.5 KGS. MOVILIZACION Y DESMOVILIZACION DE EQUIPOS ASFALTO LIQUIDO TIPO RC-250 ASFALTO LIQUIDO MC - 30 CEMENTO ASFALTICO DE PENETRACION 6070 PETROLEO KEROSENE INDUSTRIAL PINTURA ESMALTE PARA TRAFICO BLANCO NEGRO PINTURA DE TRAFICO BLANCO PINTURA DE TRAFICO COLORES PINTURA ESMALTE PINTURA ANTICORROSIVA EPOXICA TINTA SERIGRAFICA NEGRA O ROJA LUBRICANTES, FILTROS Y GRASAS ALAMBRE NEGRO N° 08 PERFIL ACERO LAC ALAMBRE NEGRO N° 16 CLAVOS CLAVOS PROMEDIOS PARA LA CONSTRUCCION FIERRO CORRUGADO FY = 4200 KG/CM2 G-60 YESO MICROESFERAS DE VIDRIO DROP ON CEMENTO EPOXICO SOLDADURA CELLOCORD PLANCHA DE ACERO LAC (3/8') ASFALTO DILUIDO TIPO MC - 30 WATER STOP DE 6* TUBO ACERO A-53 SCH-40 D=3’ TUBO FOGO D = 75 MM. ALMACEN Y CASETA DE GUARDIANIA MALLA BIOMAC 10X12 LAMINA REFLECTIVA ALTA INTENSIDAD AMARILLA/BLANCA FIBRA DE VIDRIO AGUA HORMIGON (Puesto en Obra) FILLER TUBERIA TMC D = 1.20 M. TUBERIA TMC D = 0.60 M. MADERA TORNILLO MADERA CORRIENTE PARA ENCOFRADO MADERA CORRIENTE PARA topografía TRIPLAY LUPUNA 19 MM. X 4' X 8' PERNO DE ANCLAJE A-36 3/4" X 18" R/100 MM CON TUERCA Y ARAN PERNO DE ANCLAJE 3/8” X 1 1/4’ CON

%EQ bis BOL GLB

150.0963 13,131.4080 1.0000

18.00 22.50 20,000.00

258.72 2,701.73 295,456.68 20,000.00

258.72 2,720.50 295,456.68 20,000.00

gln gln gln

42,646.7904 8.4813 192,847.6200

6.10 6.98 6.01

260,145.42 59.20 1,159,014.20

259,878.88 59.11 1,158,922.36

gln gln gln

21,556.8132 7,996.2732 27.0505

6.00 10.00 60.00

129,340.88 79,962.73 1,623.03

129,341.63 79,962.74 1,623.03

gln gln gln gln gln kg kg kg kg kg kg

318.4080 379.7000 21.6596 7.4263 0.6948 249.8835 4,505.6627 284.0900 2,879.5276 5,820.3166 8.3800

50.00 50.00 30.00 35.00 70.00 15.00 5.00 6.00 5.00 5.00 5.00

15,920.40 18,985.00 649.79 259.92 48.64 3,748.25 22,528.31 1,704.54 14,397.64 29,101.58 41.90

15,944.10 18,985.00 668.55 259.87 48.63 3,748.26 22,528.33 1,704.54 14,807.46 29,179.94 41.90

kg

86,288.7165

3.20

276,123.89

276,123.88

kg kg kg

1,679,217.3720 1,422.0000 0.3200 2.2850 83.1000 59,822.1225 933.2800 62.4000 34.0000

0.50 12.09 161.91 12.00 6.00 6.98» 20.00 58.65 43.10 31.53 15.00 137.61

839,608.69 17,191.98 51.81 27.42 498.60 417,558.42 18,665.60 3,659.76 1,465.40 3,783.60 253,102.50 2,683.40

847,604.96 17,206.20 51.20 27.42 498.60 417,615.39 18,665.60 3,659.78 1,465.40 co 3,783.60 r §253,102.50 / \% J , 683.54

20.1500 30.6835 2,137.6660 226.5610 31.8150 63.6300 230.4500 22,441.4250 447.0056 2.5140 32.0000

159.45 5.00 80.00 400.00 353.46 105.00 2.50 1.50 1.15 95.00 12.00

3,212.92 153.42 171,013.28 90,624.40 11,245.33 6,681.15 576.13 33,662.14 514.06 238.83 384.00

19.6000

4.00

78.40

120.0000 873.5000 19.5000

und

Ü W Ir 'I '

1 § |l3 .0 3 « £ 461.80 3lS .W 3.2 8 S ,§*4.40 § Í , 245.24 § 6,681.15 § 576.13 33,751.90 515.96 238.83 384.00 78.40

0229550095 0229830006 0230010016 0230010045 0230020033 0230020034 0251280002 0251280003

TUERCA Y ARANDELA SOLDADURA CADLWELL CARTE DE IDENTIFICACION EN BANNER DE 2.50X3.50 (INC. COLO) TACHAS REFLECTORIZANTES B.D. PARADERO DE CONCRETO BARRENO DE 7/8" X 5 PIES BARRENO DE 1 1/8" X 5 PIES LIJA PARA MADERA LIJA PARA FIERRO

und und

5.0000 4.0000

12.00 700.00

60.00 2,800.00

60.00 2,800.00

und und und und und und

320.0000 9.0000 0.0582 0.3271 7.7500 64.2527

6.79 2,500.00 366.12 370.00 1.20 1.20

2,172.80 22,500.00 21.31 121.03 9.30 77.10

2,172.80 22,500.00 21.30 120.99 9.30 77.10

4,236,515.23

4,244,873.91

EQUIPOS 0337010001 0348010001

%MO H.M

15.7749

25.00

31,439.44 394.37

31,439.44 394.37

H.M

910.8604

25.00

22,771.51

22,767.24

H.M H.M H.M H.M H.M

30.2201 0.5686 36.2500 6.6665 1.9400

10.00 10.00 10.00 10.00 58.84

302.20 5.69 362.50 66.67 114.15

301.74 5.69 362.50 66.65 114.15

H.M H.M H.M H.M H.M

206.5704 3.8800 49.7088 1,246.0935 45.2189

35.00 12.00 180.00 180.00 160.00

7,229.96 46.56 8,947.58 224,296.83 7,235.02

7,329.92 46.56 8.947.63 224,316.03 7.224.63

H.M H.M

1,120.3609 382.4958

180.00 160.00

201,664.96 61,199.33

201.723.58 61,199.33

H.M H.M ■

8.7204 379.7214

140.00 140.00

1,220.86 53,161.00

1 ,220.86 53,160.92

H.M H.M H.M H.M H.M

346.7499 209.7072 30.7289 839.2754 199.9068

150.00 25.00 25.00 150.00 150.00

52,012.49 5,242.68 768.22 125,891.31 29,986.02

52,100.08 5,242.68 768.05 125,941.30 29.986.02

H.M

199.9068

150.00

29,986.02

29.986.02

H.M

48.6587

150.00

7,298.81

7,321.97

159.9254

160.00

25,588.06

25,588.07

0349130006

RODILLO PATA DE CABRA VIBRATORIO H.M AUTOPROPULSADO 100-135 HP CHANCADORA PRIM-SECUND ME 75 46-70 T/H H.M

1,371.6152

60.00

82,296.91

82,236.19

0349130007 0349140002 0349160003 0349160005 0349240003 0349240004 0349260005 0349270005 0349270006 0349280002 0349280003 0349310003 0349320001 0349320006 0349520004 0349520005 0349900022 0330020030 0330020096

FAJA TRANSPORTADORA 18x5 3KW ZARANDA VIBRATORIA 4’ X 6" X 14 ME 15 MOTONIVELADORA DE 125 HP MOTONIVELADORA DE 145-150 HP PAVIMENTADORA S/ORUGA 69 HP 10-16" SECADOR DE ARIDOS 70HP 60-115 Tn PLANTA DE ASFALTO CALIENTE 30-60 TON/H GRUPO ELECTROGENO DE 75 KW. GRUPO ELECTROGENO DE 150 KW. VOLQUETE 6X4 DE 12 M3 VOLQUETE 6X4 DE 10 M3 CAMION IMPRIMADOR DE 1800 GLS. CAMION CISTERNA 2,000 GLN CAMION VOLQUETE 15 M3 VIBRADOR DE CONC. 4 HP = 1.25" VIBRADOR DE CONCRETO 1.50" 4HP EQUIPO DE PINTURA TEODOLITO NIVEL TOPOGRAFICO

226.0946 1,369.4563 64.6587 999.2009 199.9068 199.9068 199.9068 1.0501 1,629.0361 99.8507 1,272.0552 206.5704 2,690.1753 6,927.6439 901.8854 24.7499 317.6809 46.9051 23.4526

80.00 80.00 200.00 200.00 180.00 100.00 130.00 45.00 52.53 120.00 120.00 110.00 130.00 130.00 25.00 25.00 16.00 10.00 5.00

18,087.57 109,556.50 12,931.74 199,840.18 35,983.22 19,990.68 25,987.88 47.25 85,573.27 11,982.08 152,646.62 22,722.74 349,722.79 900,593.71 22,547.13 618.75 5,082.89 469.05 117.26

18,087.57 109.677.58 12,931.74 199.840.17 35,983.22 19,990.68 25,987.88 47.23 85.737.17 11,972.80 152,646.69 ^ 2 J ,322.46 3$,745.98 §900,898.78 c? y 542.94 u ró618.67 § ffl,084.51 469.05 140.72

2,954,030.46

2,955,517.46

8,223,412.76

8.232.159.80

0348010003 0348120053 0348120054 0348210056 0348210057 0349010002 0349010093 0349020006 0349040052 0349040055 0349040056 0349040057 0349040060 0349060060 0349060061 0349080005 0349100001 0349100003 0349110002 0349110050 0349110051 0349110065 0349110066

HERRAMIENTAS MANUALES MEZCLADORA DE CONCRETO DE 11 P3 /TOLVA MEZCLADORA DE CONCRETO DE 9 P3 (TROMPO) MOTOBOMBA 12 HP D=4* MOTOBOMBA (DIESEL) 12 HP D=4" EQUIPO DE SOLDADURA EQUIPO DE SOLDADURA A GASOLINA COMPRESORA NEUMATICA 250-330 PCM, 87 HP BARREDORA MECANICA 10-20HP MARTILLO NEUMATICO DE 25 - 29 KG CARGADOR S/LLANTAS 125-155 HP.3.0 Y3 CARGADOR S/LLANTA 160-195 HP, 3.5 Y3 CARGADOR S/LLANTAS 100-115 HP,2.0-2.35 Y3 CARGADOR S/LLANTA 200-250 HP, 4.0-4.1 Y3 CARGADOR S/LLANTAS 100-115 HP,2.0-2.35 YD3 RETROEXCAVADORA S/LL 58HP 1YD3 RETROEXCAVADORA S/0 170-250 HP.1.1-2.7 Y3 TRACTOR SOBRE ORUGA DE 190-240 HP COMPACTADORA VIB. TIPO PLANCHA 4 HP COMPACTADORA VIB. TIPO PLANCHA 7 HP RODILLO V.A.L. 101-135 HP, 10-12 TN RODILLO NEUMATICO AUTOP 81-100 HP 5.520Tn RODILLO TANDEM ESTAT. AUTOM. 58-70 HP 810 Tn RODILLO VIBRATORIO LISO AUTOPR. 7-9 TON

H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M H.M hm hm

Total

SI.

SI. La columna parcial es el producto del precio por la cantidad requerida; y en la última columna se muestra el Monto Real que se está utilizando

8.232.159.80



Prefactibilidad S N IP : 149054

1.1 Recurso humano: Los recursos humanos que elaboraran en el proyecto son los siguientes: ❖

Numero de Trabajadores por áreas de trabajo:

Los Trabajos por áreas de trabajo estarán a cargo de por lo memos: (01) ING. RESIDENTE. (01) ASISTENTE DEL ING. RESIDENTE.

Los Trabajos por áreas, serán verificados y controlados por: (01) INGENIERO SUPERVISOR (01) ASISTENTE DE SUPERVISOR. En las metas de las obras civiles son: A.- Pavimento de Concreto

1.

Trabajos preliminares.______ DESCRIPCION

N° DE TRABAJADORES

OPERARIO

0

OFICIAL

1 4

PEON

2.

Movimientos de Tierras. DESCRIPCION

N° DE TRABAJADORES

OPERARIO OFICIAL

2 1 8

PEON

3.

Pavimento.(Inc. Obras de Arte) DESCRIPCION

N° DE TRABAJADORES

OPERARIO

3

OFICIAL

2

PEON

4.

26

Veredas y Martillos DESCRIPCION OPERARIO

N° DE TRABAJADORES 2

OFICIAL

1

PEON

5

RODOLF^WÍOSVlLLAlZía'J GO¡ INGENIERO CIVIL Reg. CIP63-S1'1

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad S N IP : 149054

B.- Obras de Arte y Drenaje.

5.

Alcantarillas de Concreto Armado DESCRIPCION

N° DE TRABAJADORES

OPERARIO

3

OFICIAL

2

PEON

10

B.- Obras de Saneamiento.

6.

Obras de Saneamiento. DESCRIPCION

N" DE TRABAJADORES

OPERARIO OFICIAL PEON

2 0 4

C.- Obras de Instalaciones Eléctricas.

7.

Instalaciones Eléctricas. DESCRIPCION

N* DE TRABAJADORES

OPERARIO OFICIAL PEON

2 0 4

El número de trabajadores es un promedio que se utilizara a lo largo de toda la ejecución de la obra (ref. obras similares en la región), según el tipo de cada actividad y según el avance que se quiera dar en obra ❖

Numero de Trabajadores en la etapa Operativa : EL número de trabajadores en la etapa operativa, es decir cuando se requiera hacer el mantenimiento correspondiente:

Duración del proyecto. El tiempo de ejecución de las obras civiles es de 330 días calendario. Tiempo por etapas: 1 2 3 4 5 6 7 8 9

Trabajos provisionales 10dias Obras preliminares. (250 días) Movimientos de Tierras. (159 días) Sub base y base (35 dias) Pavimento.asfaltico( ( 210 días) Obras de arte, drenaje, puente (322 dias) Señalización y seguridad vial (122 días) Mejoramiento de puente San Lorenzo(95 días) Obras de Saneamiento. (70 días)

...CJ R0D1 ^

PLOSVIOA^00^ ' enieR° ciy'L Reg.ClP «3414

*Nota: Las partidas de Trabajos Preliminares, Movimiento de Tierras, Obras de saneamiento y Obras complementarias se ejecutaran según los frentes a trabajar y según lo programado, estando estos trabajos inmersos en la partida de Pavimentos, por lo que el tiempo total de ejecución de las obras serán 330 días naturales. Municipalidad Distrital de Yarinacocha

-

Su b Gerej

\fraestructura

Prefactibilidad S N IP : 149054

1.3 Análisis de alternativas del proyecto: Para el planteamiento de alternativas se ha tomado como la única ruta de vía, la existente debido a que esta ha sido aperturaza desde unos 20 años atrás aproximadamente cuando la expansión urbana creció y se definieron las principales avenidas y Jirones. En cuanto al planteamiento de las posibles alternativas a ejecutarse en el futuro proyecto se evaluaron los aspectos de inversión y el mantenimiento que se brindaría a cada alternativa planteada A continuación se describen las alternativas planteadas: A L T E R N A T IV A N ° 1

Las características se presentan en el cuadro siguiente •

Pavimento flexible con tratamiento Bicapa de 4 y 3.5 cm de espesor, colocada sobre una base granular de e=0.10 m., subbase granular de e=0.15 m. y subrasante estabilizada con cal de e=30 cm. con anchos de calzada en diferentes tramos de 8.00m y 12.00 m



Construcción de 6,101.02ml de canaletas laterales de concreto armado f'c=140 Kg/cm2, ancho variable (1.00 m. a 1.20 m.) y espesor de 0.15 m. ambos lados.



Construcción de 4690.51 mi de sardineles ambos lados sumergidos de concreto f’c=140 Kg/cm2.



Construcción de alcantarillasy martillos, a lo largo del asfaltado.

N° DE A LC AN TAR ILLAS DIMENSIONES

íp

TIPO DE MATERIAL

TIPO

REFERENCIA

OBSERV.

LO NG ITUD

SECCION

1

7.00

1.50x2.40

RECTANGULAR

CONCRETO ARMADO

AMPLIACION

0*033

2

25.00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*010

3

25.00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*020

4

25.00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*080

5

20.00

1.25X1.15

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1+325



Obras de saneamiento.



Ampliación del puente San Lorenzo



Señalizaciones de seguridad Vial.

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Reg. CIP 63414

Prefactibilidad S N IP : 149054

ALTERNATIVA N° 2



Pavimento rígido con carpeta de concreto fc=210 Kg/cm2, Ancho calzada de 8.40 m y e=0.20m. (39,400.28 m2 — 4,690.51 mi.)



Construcción de 6,101.02m de canaletas laterales de concreto armado fe=140 Kg/cm2, ancho variable (1.00 m. a 1.20 m.) y espesor de 0.15 m. ambos lados.



Construcción de 4690.51 mi de sardineles ambos lados sumergidos de concreto f’c=140 Kg/cm2.



Construcción de alcantarillas y martillos, a los largo del asfaltado. N° DE ALCAN TAR ILLAS DIMENSIONES

N-

TIPO DE MATERIAL

TIPO

OBSERV.

REFERENCIA

LONGITUD

SECCION

1

7,00

1.50x2.40

RECTANGULAR

CONCRETO ARMADO

AMPLIACION

0*033

2

25,00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*010

3

25,00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*020

4

25,00

1.00X1.00

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1*080

5

20,00

1.25X1.15

RECTANGULAR

CONCRETO ARMADO

CONSTRUCCION NUEVA

1+325



Obras de saneamiento.



Ampliación del puente San Lorenzo.



Señalizaciones de seguridad Vial.

DESCRIPCION DE ALTERNATIVA RECOIV

DESCRIPCION TECNICA La alternativa seleccionada es la alternativa N° 1, teniendo las siguientes características de diseño. El planteamiento técnico es mediante el Método AASHTO-1996 cuyo

diseño esta basado en los

resultados obtenidos de campo mediante métodos destructivos; es decir caracterización físico-mecánica de los materiales del terreno de fundación.El método AASHTO - 1993 incluye en la metodología

Municipalidad Distrital de Yarinacocha

-

Sub G erencia de Infraestructura

Prefactibilidad S N IP : 149054

parámetros que no han sido consideradas en las versiones anteriores, las que son basadas principalmente en resientes investigaciones. A continuación se presentan dichos parámetros.

El numero de repeticiones de ejes equivalentes para este caso fue de : Tipo de trafico T 1 T1 50,000 a 150,000 EE El CBR obtenido de las calicatas es el siguiente C1 = 2.42 C5 = 2.54 C9 = 3.43 C7 = 3.69 C11= 2.89 El periodo de diseño es para 10 años por lo que se tiene para el diseño de espesor de asfalto los siguientes parámetros para estas características CLASE DE TRAFICO Numero de repiticiones EE Periodo de diseño tipo de subrasante CBR confiabilidad Numero Estructural Sub rasante Superficie de rodadura Base garnular Sub base granular

T1 50000 10 años muy pobre < 3% 60% 2,89 Tratamiento Supercial Bicapa 20 cm 15 cm

I

Una vez mejorada la sub rasante y compactada al 95 % de la máxima densidad seca, se colocara la capa de sub base granular de espesor 15 cm y luego la capa de base granular de espesor de espesor 20 cm El Espesor de la capa de rodadura Tratamiento Supercial Bicapa consta de lo siguiente: Mezcla de asfalto calienta B con un espesor de 3.5 cm Mezcla de asfalto calienta 2 con un espesor de 4.0 cm



Pavimento flexible bicapaMAC2 de 4 cm. y MACB de 3.5 cm de espesor, colocada sobre una base granular de e=0.20 m, sub-base granular compactada e=0.15 m., subrasante estabilizada con cal de e=0.30m con una longitud de 4,690.51 m.anchosde calzada en diferentes tramos de 8.00m y 12.00 m



Construcción de 6,101.02 mi de canaletas laterales de concreto fc=175 Kg/cm2, ancho variable (0.50 m. a 1.00 m.) y espesor de 0.10 m. ambos lados.



Construcción de 3,214.00 mi de sardineles ambos lados sumergidos de concreto fc=175 Kg/cm2.

Municipalidad Distrital de Yarínacocha

-

Sub Gerencia de Infraestructura

\|L INGENIERO CIVIL

Prefactibilidad S N IP : 149054



Construcción de alcantarillas y martillos, a los largo del asfaltado.



Obras de saneamiento.



Ampliación del puente San Lorenzo.



Señalizaciones de seguridad Vial.

Conocido al detalle de los estudios Básicos se han analizado ambas alternativas considerando las siguientes características: Trabajos Provisionales. Consiste en los trabajos previos a la ejecución de las obras, con la finalidad de lograr un ambiente de trabajo adecuado y dar inicio a las obras. Entre las principales partidas, tenemos: construcción provisional de un almacén y una caseta de guardianía; transporte de materiales, equipos y herramientas; instalación de carteles de obra en lugar visible; trazo, nivelación

y

replanteo de la obra. Movimiento de Tierras. Implica los trabajos en el terreno con la finalidad de habilitarlo para la ejecución de los trabajos de pavimentación y drenaje. Los principales trabajos a ejecutar son: corte y relleno con material propio, mediante el uso de maquinaria; compactación y mejoramiento de la sub rasante y la respectiva eliminación del material excedente de las excavaciones. Pavimentos y Obras de Concreto. Comprende la ejecución de la estructura de pavimento a nivel superior. •

Pavimento Superior. (Pavimento Rígido y Pavimento Flexible)



Juntas.

Veredas en Martillos.

Á

Los martillos se construirán de concreto fc=175 kg/cm2, con un acabado semi pulido las cuales deberán de ser bruñadas y con juntas de dilatación. Obras de Arte v Drenaje Se construirán obras de drenaje pluvial, mediante canaletas de concreto armado y sardineles, con la finalidad de evacuar las aguas de lluvias, las cuales son perjudiciales al pavimento.

Prefactibilidad S N IP : 149054

La obra considera la instalación de redes de agua y alcantarillado, con sus respectivas obras de conexiones domiciliarias, para abastecer de agua potable a las viviendas carentes de éste vital servicio; comprende: excavación, instalación de conexiones domiciliarias, relleno con material propio y las pruebas hidráulicas respectivas. Señalización. Consiste en la marcación del pavimento con señales horizontales y la colocación de señales verticales en el trayecto de la vía. Las marcas en el pavimento (señalización horizontal) debe de darse en los siguientes lugares:

LUGAR

PROGRESIVA

IN STITU TO PEDAGOGICO BILINGÜE DE YARINACOCHA

0+940

UNIVERSIDAD NACIONAL INTERCULTURAL DE LA AM AZONIA

1+220

C.P. M SAN PABLO DE TU SH M O

1+880

CASERIO SAN LORENZO

3+000

C.P.M SAN JOSE

3+840

Obras de Mitigación Ambiental. Consiste en la limpieza de maleza y arbustos, acondicionamiento de botaderos y recuperación de áreas verdes

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Prefactibilidad S N IP : 149054

DESCRIPCION ECONOMICA La Inversión que se consigna para la alternativa recomendada (nivel PRE factibilidad) es la siguiente:

RESUMEN DE PRESUPUESTO ETAPA PRE O PER ATIVA

ALTERN ATIVA N» 1

DESCRIPCION

CO STOS

P.PRIVADOS

P.SO CIALES

•.* * - -

.

r;:

TANGIBLES

COSTOS

OBRAS CIVILES + IMPACTO AMBIENTA

11,171,132.79

7,989.52

SUB TO TAL

11,171,132.79

7,989.52

IGV (1 9 % )

2,122,515.23

TO TAL

13,293,648.02

INTANGIBLES inc (IGV)

719,611.34

609,990.43

400,554.00

336,600.00

4,000.00

3,636.36

315,057.00

264,754.07

SUB T O TAL

14,013,259.36

8,594,510.43

TO TA L

14,013,259.37

8,594,510.43

ESTUDIOS CONVOCATORIA Y DIFUSION DE OBRA SUPERVISION Y LIQUIDACION

Reg. CIP 63414

Municipalidad Distrital de Yarinacocha

-

Sub G erencia de Infraestructura

Prefactibilidad S N IP : 149054

DESCRIPCION AMBIENTAL La Descripción del medio ambiente en la Región Ucayali predomina el clima tropical: calidohúmedo - lluvioso. En la Región Ucayali tiene extensas área de bosques maderables, lo cual tiene la vigilancia del INRENA y la existencia de aserraderos hace que sea la principal actividad de la Región. El Ambiente v el Provecto: Si bien es cierto el apertura una nueva vía o ruta de camino en una zona inexplorada daña de manera severa al medio ambiente entonces se tendría que tomar medidas que mitiguen aquellos impactos negativos que se produciría, pero al ser este proyecto el mejoramiento de una vía que existe y que la ruta está aperturada hace mas de 20 años atrás y la población que reside en el área pertenece al casco urbano entonces generará mayores impactos positivos en bien del progreso y el avance de sus actividades socio-económicas y por consiguiente mejorará el nivel de vida de los pobladores de la Región Ucayali.

IMPACTO AMBIENTAL. Por sus características,

la puesta en marcha

del proyecto generará impactos positivos y

negativos en la zona de influencia del proyecto. Entre dichos impactos tenemos: Impactos negativos: (Temporales). •

Congestión temporal de vehículos, durante la ejecución del proyecto.



Ruidos de maquinaria durante la ejecución de trabajos.



Emanación de gases por tubos de escape de maquinaria pesada durante la ejecución del proyecto.



Acumulación de materiales (tierra, agregados y otros)



Desestabilización de riberas (canteras de río).

Impactos positivos: •

Desaparición del polvo en el ambiente, una vez culminadas las obras,



Tráfico más fluido con seguridad y comodidad



Disminución de accidentes de tránsito

Mitigación del Impacto ambiental propuestas (1) y (2) Se proponen las siguientes acciones de protección ambiental: Señalización adecuada de desvío en la vía, maquinaria a emplear debe contar con certificación de emisión de ruidos dentro de lo permisible. Recuperación am biental del área ocupada por maquinaria: El Reacondicionamiento del área intervenida, será efectuada teniendo en consideración: eliminación de suelos contaminados y su traslado a depósitos de desecho, limpieza de basuras, almacenar los desechos de aceite en bidones y trasladarlos a lugares seleccionados en las localidades cercanas para su disposición final. Debe tenerse presente que por ningún motivo estos desechos de aceites deben ser vertidos en el suelo o en cuerpos de agua.

Municipalidad Distrital de Yarinacocha

-

Sub Gerencia de Infraestructu

© Prefactibilidad S N IP : 149054

Depósitos de desechos: Los materiales excedentes que se obtengan de la construcción de la vía serán retirados en forma inmediata de las áreas de trabajo y colocados en las zonas localizadas como botaderos de la localidad, lugar que será precisado en la ejecución. La disposición de los materiales de desechos será efectuada cuidadosamente y gradualmente compactada por tanda de vaciado, de manera que el material articulado originado sea mínimo. El depósito de desechos será rellenado paulatinamente con los materiales excedentes, en el espesor de capa dispuesto por el proyecto o por el Supervisor, extendida y nivelada sin permitir que existan zonas en que se acumule agua y proporcionando inclinaciones según el desagüe natural del terreno. Manejo y acondicionam iento de botadero utilizando zona apropiada mínimo a 3.5 Km de la zona del trabajo.

El presupuesto del plan de manejo ambiental esta dentro del presupuesto general la cual mencionaremos a continuación: HKfcSUHUEST0 (jfc N tK A L DE M IIIÜ A U O N A M BIENTAL

1--------Und. Metrado Precio SI. Parcial SI.

CARRETERA PUERTO CALLAO • CPM SAN JOSE L o n g * 4+690. 51 KM I.. i »it o .W[»íl 1 I i |; í l l T ' V r l l T i r T T I l i l l W l i l i W H f f l I l l l H i W i T K th U K tS I AUIUN U t A K tA IN I hKVtNIUA UUN PLAN 1AS 1IHIUA un ! tLlMINAUIUN Ub MAI bKIAL DON 1AMINAN 1t rw CUImS i KÜCUIUN U t StKVICIOS HIUIbNICUS und

¡p H IS l ■ yij nr> tí.UU

-

' ÍÍU " , "■ "11 «0 4bü.íT' ' 3,'60210

MEJORAMIENTO DEL PUENTE SAN LORENZO | MITIGACION IMPACTO AMBIENTAL

|

|

K th U K tS I AUIUN U t A K tA INI tKV tN IU A UUN KLANIAS 1IKIUA und tLlMINAUIUN U t M A ItK IA L CON 1AMINAN 11 ma UUNSI KUUUIUN U t StkVIUIUS HIUItNlCUS und LIMFIbZA Ub C A U C ty AUUAS AKKIdA Y AUUAÜ AbA JU

4U.UU 4b.UU Ü.UU 1UU.0U

1/.UB

1.2B

602740 i.a u .y u 9Ü0 o¿ liííí.UU

OBRASDESANEAMIENTO ¡M

IT IG A C IO N IM P A C T O A M B I E N T A L

tLlMINAUIUN U t MAI tKIAL UUN 1AMINAN 11 UUNSI kUUUIUN U t ¡jtKVIUIUS HIUItNIUUS

2.181-52 m3 und



20 00

y uu

7 'í " " 4Í)U.J1

i, wu.au auu.B^

C O S T O D IR ECTo|

13,024.72

■ Cabe indicar según la Ley del Sistema Nacional de Evaluación de Impacto Ambiental Ley N° 27446. Artículo 2.- Ámbito de la ley Quedan comprendidos en el ámbito de aplicación de la presente Ley, los proyectos de inversión públicos y privados que impliquen actividades, construcciones u obras que puedan causar impactos ambientales negativos, según disponga el Reglamento de la presente Ley.

"Artículo 3.- Obligatoriedad de la certificación ambiental No podrá iniciarse la ejecución de proyectos ni actividades de servicios y comercio referidos en el artículo 2 y ninguna autoridad nacional, sectorial, regional o local podrá aprobarlas, autorizarlas, permitirlas, concederlas o habilitarlas si no cuentan previamente

Prefactibilidad S N IP : 149054

con la certificación ambiental contenida en la Resolución expedida por la respectiva autoridad competente." El Objetivo de la Ley N° 27446 es determinar la CATEGORIZACIÓN DE PROYECTOS DE ACUERDO AL RIESGO AMBIENTAL en concordancia con el Articulo. 4 de dicha LEY. Articulo. 4.1 Toda acción comprendida en el listado de inclusión que establezca el Reglamento, según lo previsto en el Artículo 2 de la presente Ley, respecto de la cual se solicite su certificación ambiental, deberá ser clasificada en una de las siguientes categorías: a) Categoría I.- Declaración de Impacto Ambiental b) Categoría II.- Estudio de Impacto Ambiental Semidetallado c) Categoría III .- Estudio de Impacto Ambiental Detallado Por lo que para efectos del desarrollo del rubro de Impacto Ambiental en la fase de Inversión se Clasifica en la Categoría I .- Declaración Ambiental.

INGENIERO CIVIL Reg. CIP 63414

Municipalidad Distrital de Yarinacocha - S u b Gerencia de Infraestructura

Prefactibilidad S N IP : 149054

Percepción de la población circundante respecto al provecto. Para dar sustento al nivel de aprobación que tiene el proyecto se puede estimar un 95 % debido a las encuestas de campo que se han realizado y a la voluntad de poder cooperar en la recopilación de información socio-económica lo cual fue emitida por la población. El responsable del proyecto es directamente el Gobierno Regional de Ucayali y según el tipo de gestión que se realiza la población tiene grandes expectativas

5. Clasificación ambiental que propone el Responsable del Proyecto (marcar con un aspa)1 Declaración Ambiental X Estudio de Impacto Ambiental Semidetallado Estudio de Impacto Ambiental Detallado

Clasificación otorgada por la Dirección Nacional competente (usos del Ministerio)2

6.

Declaración Ambiental Estudio de Impacto Semidetallado Estudio de Impacto Detallado

ANEXOS



Anexo :Fichas SN IP

Numero de colegiatura: 63414 DNI : 09372583 Dirección: Jr. GUEPI 163 - Pucallpa Teléfono: 961092953 E-m ail: c9villaizan@ vahoo.com

Municipalidad Distrital de Yarinacocha - Sub Gerencia de Infraestructura

Ambiental Ambiental

Related Documents


More Documents from "Marycruz Flores"

Se Acerca La Web 3
October 2019 29
Datos Curiosos.docx
June 2020 13
Formacion Del Profesorado
October 2019 37
Mercadillo9
November 2019 27