CG-9335 C4ISR Project Dashboard Report Date: 12/02/2009 United States Coast Guard Total Activities Completed
Organization
C2CEN Lab Project
Percentage of Activities Completed
SV
5 of 34
15%
Deepwater Segment 2 (MSAM Compliance)
40 of 123
33%
Deepwater Segment 3
7 of 101
7%
Sentinel C4ISR
9 of 94
10%
Schedule Variance legend:
High (>20%)
Medium (10Low 20%) (<10%)
MA
Management's Detailed Assessment
11/25/2009 - 153AB IBR was held on November 16-17 in Moorestown. The contractor was given several contingencies as action items to be corrected before final approval. Cable production and configuration are currently being 11/12/2009 - NSTR 10/21/2009 - Segment 3 is on track to go to the ADE1 briefing in February and has received funding to proceed with the PORD and ORD for 2010. 11/13/2009 - Sentinel CDR is scheduled for 17 - 19 Nov 09 at PRO Lockport. There are no C4ISR CDRL's open for review. Current activities include preparing to attend CDR, preliminary C4ISR project resource requirements planning, and reviewing the Sentinel DT&E plan. Management's Assessment legend:
Completed
Medium severity High severity risks risks - tasks considerable schedule slightly behind delays schedule
On-target
C2CEN Lab Project C2CEN Lab Project Manager: Tremell Jackson
Last Updated: 11/25/2009
Summary Status:
SV
MA
Report Date: December 02, 2009
153AB IBR was held on November 16-17 in Moorestown. The contractor was given several contingencies as action items Management's Overall Assessment: to be corrected before final approval. Cable production and configuration are currently being Technical Exchange Meeting (TEM) [aka Lab Design Review] completed 1 October 2009. CGSAIL construction is in full swing with framing completed and drywall installation beginning. The racks for the C2CEN NSC maintenance and sustainment lab are in MDAC and hardware assembly begun. Integrated Design Review (IBR) completed 17 November Key Accomplishments: 2009. HQ CG Business Financial Management (BFM) is currently consolidating/analyzing IBR minutes and action items and will Issues: provide them in an IBR report to the COTR. Next Week's Objectives: Discuss Labs status and IBR action items at ITL IPT 2 December 2009.
Pri SV MA
Rigor
Status
Phase
Topic
% Comp Due Date Complete Date Responsible
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project CDRL L031 Spare Parts List Delivered
0%
12/18/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project CDRL C131 Project Management Plan Delivered
0%
12/18/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project C2CEN Equipment in MDAC Completed
0%
12/18/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project CDRL C147 Laboratory Technology Refreshment Plan Delivered
0%
12/18/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project C2CEN CNI Production Testing Completed
0%
12/18/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project C2CEN Equipment Shipped
0%
12/23/09
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project C2CEN Classification of Site Completed
0%
01/15/10
T. Jackson
2
3. Due in next 60 days
Assigned (P) C2CEN Lab Project C2CEN Installation and Integration Completed
0%
01/29/10
T. Jackson
Deepwater Segment 2 (MSAM Compliance) Segment 2 (MSAM Compliance) Project Manager: Michael Johnston Management's Overall Assessment: Key Accomplishments: Issues: Next Week's Objectives: Pr M i SV A
Rigor
Status
Last Updated: 11/12/2009
Summary Status:
SV
MA
Report Date: December 02, 2009
NSTR NSTR NSTR NSTR
Phase
Topic
% Comp
Due Date
Complete Date Responsible
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
In Progress
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
In Progress
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
In Progress
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Concurrent Clearance
20% 10/23/09
N. Morello
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Concurrent Clearance
0%
10/23/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
0%
10/28/09
S. Monteiro
2
2. Overdue
In Progress
(P Deepwater Segment 2 ) (MSAM Compliance)
11/30/2009 Jackson: Currently adjudicating concurrent clearance 20% 10/28/09 comments.
T. Jackson
2
2. Overdue
Partial Completion
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
Partial Completion
(P Deepwater Segment 2 ) (MSAM Compliance)
CMP Action Completed
0%
10/09/09
N. Cross
20% 10/09/09
N. Cross
0%
D. Dickson
CMP Signed 93 11/30/2009 Jackson: CMP has been routed back to CG93 ORD Concurrent Clearance
10/23/09
TEMP Concurrent Clearance 11/30/2009 Jackson: TEMP will be in concurrent clearance until 23 20% 10/23/09 Nov 2009.
J. Eure
TP Adjudicated Concurrent Clearance 11/30/2009 Monteiro: Resource assigned. ILSP Adjudicate Concurrent Clearance
TEMP Adjudicated Concurrent Clearance 12/01/2009 Jackson: Adjudicating Comments from Concurrent Clearance LCCE Adjudicated Concurrent Clearance 12/01/2009 Jackson: At CG-924 for ARC Waiver
50% 10/28/09
T. Jackson
50% 10/28/09
T. Jackson
Approval 2
2. Overdue
Partial Completion
(P Deepwater Segment 2 ) (MSAM Compliance)
RMP Adjudicated Concurrent Clearance
50% 10/28/09
M. Conteras
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Adjudicated Concurrent Clearance
0%
10/28/09
N. Morello
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
LCCE Signed 9335
0%
10/29/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
0%
10/29/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed 9335
0%
10/29/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed 9335
0%
10/29/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed 9335
0%
10/29/09
N. Morello
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
LCCE Signed 933
0%
10/30/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed 933
0%
10/30/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed Sponsor's Rep
0%
10/30/09
D. Dickson
0%
10/30/09
T. Jackson
TP Signed 9335 11/30/2009 Monteiro: Resource assigned
TP Signed 933
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed 933
0%
10/30/09
N. Morello
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed 933
0%
10/30/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
LCCE Signed 928
0%
11/02/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed CG-1
0%
11/03/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed 926
0%
11/03/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
LCCE Signed 9
0%
11/03/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed 93
0%
11/03/09
N. Morello
11/30/2009 Monteiro: Resource assigned.
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Signed CG-1
0%
11/03/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
LCCE Action Complete
0%
11/03/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed 928
0%
11/05/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Signed CG-4
0%
11/05/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed Test Authority
0%
11/05/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed CG-4
0%
11/05/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed Sponsor
0%
11/06/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed CG-6
0%
11/09/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Signed CG-6
0%
11/09/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed Sponsor
0%
11/09/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed 9335
0%
11/09/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed Sponsor
0%
11/09/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed 933
0%
11/10/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Signed 93
0%
11/11/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed CG-8
0%
11/11/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Signed CG-82
0%
11/11/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed 93
0%
11/11/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-4
0%
11/12/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
PMP Action Completed
0%
11/13/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed 761
0%
11/13/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2
PMP Signed 9
0%
11/13/09
T. Jackson
)
(MSAM Compliance)
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-6
0%
11/16/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed 93
0%
11/17/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-1
0%
11/18/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-93
0%
11/20/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
POP Extension - RFR
0%
11/20/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-9
0%
11/23/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
POP Extension - PR
0%
11/27/09
T. Jackson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed CG-01
0%
11/27/09
D. Dickson
2
2. Overdue
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
POP Extension - Execute Option
0%
11/30/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed VCG
0%
12/03/09
D. Dickson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ACQUISITION APPROVAL
0%
12/04/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
AP Signed DHS
0%
12/15/09
J. Kappel
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
AP Action Complete
0%
12/15/09
J. Kappel
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Signed DHS
0%
12/23/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TEMP Action Complete
0%
12/23/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Action Complete
0%
12/23/09
S. Monteiro
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
TP Signed DHS
0%
12/23/09
S. Monteiro
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Signed DHS
0%
12/29/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ILSP Action Complete
0%
12/29/09
T. Jackson
2
3. Due in next 60 days
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Action Complete
0%
01/14/10
D. Dickson
2
3. Due in next 60 days
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
2
4. Completed in last Completed 2 weeks
(P Deepwater Segment 2 ) (MSAM Compliance)
Assigned
(P Deepwater Segment 2 ) (MSAM Compliance)
ORD Signed DHS
0%
01/14/10
D. Dickson
TEMP Drafted 11/30/2009 Jackson: The TEMP has been drafted and is at concurrent clearance.
100% 10/06/09 11/30/09
T. Jackson
11/30/2009 Jackson: The ORD has been drafted and documented. 100% 10/14/09 11/30/09 It is currently being socialized with DHS.
T. Jackson
ORD Draft - Committee
LCCE Concurrent Clearance 11/30/2009 Jackson: LCCE Concurrent Clearance complete and released for ARC approval 20 Nov 2009.
100% 10/23/09 11/30/09
T. Jackson
100% 10/23/09 11/30/09
S. Monteiro
100% 10/29/09 11/30/09
M. Conteras
100% 10/30/09 11/30/09
M. Conteras
100% 11/06/09 11/30/09
M. Conteras
100% 11/06/09 11/30/09
M. Conteras
100% 11/16/09 11/30/09
A. Johnson
100% 11/16/09 11/30/09
A. Johnson
TP Concurrent Clearance 11/30/2009 Monteiro: Resource assigned RMP Signed 9335 11/30/2009 Conteras: RMP signed by 9335. RMP Signed 933 11/30/2009 Conteras: RMP signed by 933 RMP Signed 93 11/30/2009 Jackson: RMP signed. RMP Action Completed 11/30/2009 Conteras: All RMP Actions completed. APB Signed DHS 11/30/2009 Kammel: APB signed by DHS APB Action Completed 11/30/2009 Kammel: All APB actions complete.
Deepwater Segment 3 Segement 3 Project Manager: Michael Johnston
Last Updated: 10/21/2009
Summary Status:
SV
MA
Report Date: December 02, 2009
Segment 3 is on track to go to the ADE1 briefing in February and has received funding to proceed with the PORD and Management's Overall Assessment: ORD for 2010. Completed development of the MNS, CONOPS and OMB 300 (all are in signature) Completed first draft of CDP. Affordability Assessment is waiting on funding input. First draft of the ADE1 briefing is complete. Tasking to begin Key Accomplishments: PORD/ORD is in contracts. Program funding is not available in our current budget. Without program funding, the project will be unable to produce the Issues: majority of the ADE 2 program documentation. Convene an IPT meeting to present the CDP and request review and comments from the IPT members. Begin working on Enterprise Architecture Board (EAB) briefing for ADE 1. This may not be required or may be a minor update to the Next Week's Objectives: Deepwater COP (EAB approved). Segment 3 is part of the Deepwater COP. Pr i SV MA
Rigor
Status
Phase
Topic
% Due Comp Date
Complete Date Responsible
Mission Need Statement (MNS) - Develop and Obtain Signoffs
2
1. Watchlist
Pending Completion
(P)
Deepwater Segment 3
2
1. Watchlist
Pending Completion
(P)
Deepwater Segment 3
2
2. Overdue
Partial Completion
(P)
Deepwater Segment 3
2
2. Overdue
Pending Completion
(P)
Deepwater Segment 3
2
2. Overdue
Assigned
(P)
Deepwater Segment 3
Begin Project Initiation Phase
0%
12/01/08
T. Jackson
2
2. Overdue
Pending Completion
(P)
Deepwater Segment 3
OMB Exhibit-300 Business Case - Develop and Obtain Signoffs
80% 08/14/09
T. Jackson
2
2. Overdue
Pending Completion
Deepwater (P) Segment 3
80% 09/22/09
T. Jackson
2
2. Overdue
Partial Completion
(P)
50% 11/20/09
T. Jackson
Deepwater Segment 3
12/02/2009 Baldesare: Mission Needs Statement has been routed through CG-7 and CG-5. Additional changes were required and the document is with CG-7 for approval
80% 09/04/09
T. Jackson
80% 10/23/09
T. Jackson
50% 05/23/08
T. Jackson
12/01/2009 Jackson: Comments have been received; the document is in the process of 80% 07/04/08 being revised.
T. Jackson
Concept of Operations Document (CONOPS) - Develop and Obtain Signoffs 12/02/2009 Baldesare: Edits required by CG-761 have been made and document is back in routing Project Management Plan (PMP) - PM Prepare Capability Development Document - Develop and Obtain Signoffs
Affordability Assessment (AA) - PM/CG-821 prepare - Develop and Obtain Signoffs 10/27/2009 Jackson: Affordability Assessment is currently on CDR Johnston's desk going through internal review. Draft ADE1 Brief
(P)
Deepwater Segment 3
Schedule Milestone 1 Briefing
0%
11/24/09
T. Jackson
3. Due in next In Progress 60 days
(P)
Deepwater Segment 3
Schedule and conduct review sessions
20% 01/01/10
T. Jackson
3. Due in next Assigned 60 days
(P)
Deepwater Segment 3
EAB Review
0%
T. Jackson
2
2. Overdue
2 2
Assigned
01/04/10
Sentinel C4ISR Sentinel C4ISR Project Manager: Michael Johnston
Management's Overall Assessment: Key Accomplishments:
Issues: Next Week's Objectives: Pr M i SV A
Rigor
Status
Last Updated: 11/13/2009
Summary Status:
SV
MA
Report Date: December 02, 2009
Sentinel CDR is scheduled for 17 - 19 Nov 09 at PRO Lockport. There are no C4ISR CDRL's open for review. Current activities include preparing to attend CDR, preliminary C4ISR project resource requirements planning, and reviewing the Sentinel DT&E plan. Reviewed the Sentinel DT&E plan V0.1. Comments submitted on 13 November 2009. Submitted Sentinel C4ISR schedule V1.01 for uploading into Primavera P6. a. Seawatch-Sentinel PM assessment of behind schedule or problematic for the C2CEN Seawatch-Sentinel development schedule (as of 10 November 2009). b. INS contract award under protest (01 Oct 09) and is awaiting adjudication. INS is the Navigation software for Seawatch-Sentinel. c. Awaiting decision from DHS for whether there is a DHS EAB review requirement for Sentinel. A DHS EAB review is a MSAM Obtain Phase activity. Sentinel DHS ADE-2B ARB is scheduled for 04 December 2009. The Sentinel LRIP option expires 15 December 2009. d. Changes to the recommended Seawatch-Sentinel equipment suite are expected to meet TEMPEST Level II compliance requirements and to resolve issues identified during system development and testing at C2CEN. The Seawatch-Sentinel equipment will be CFE and purchased by Bollinger. Seawatch-Sentinel is GFI. Attend the Sentinel CDR at PRO Lockport
Phase
Topic
% Due Comp Date
Complete Date Responsible
Critical Design Review (CDR) In (P Sentinel Progress ) C4ISR
2
2. Overdue
2
3. Due in next (P Sentinel Assigned 60 days ) C4ISR
2 2
11/16/2009 Jackson: Sentinel CDR is November 17-19 with a November 16 government only meeting in which Jermaine Mays will be attending. Other personnel attending the CDR are Burton Owlett, Mir Ali, and Shawn Ali.
20% 11/17/09
T. Jackson
Certification and Accreditation (C&A) Activity Period
0%
12/16/09
A. Johnson
3. Due in next (P Sentinel Assigned 60 days ) C4ISR
EOA on Legacy Cutter
0%
01/29/10
B. Owlett
3. Due in next (P Sentinel Assigned 60 days ) C4ISR
Complete Network Design
0%
01/29/10
B. Owlett