CONSTRUCTION, COMPLETION AND MAINTENANCE OF POULTRY FARM AT MADINAT ASH SHAMAL FOR BRAHAMA POULTRY FARM WLL
AREA STRUCTURAL COMPLETION CERTIFICATE Tag No.:
Project No:
RFI No:
Tag Desc.:
Record No:
Date and Time:
Drawing No:
Contractor
Project Desc:
Location:
Applicable Spec./ ITP / Procedure / Method Statement No:
Sl. No.
Description of check
Result
1
Main structural members installed in accordance with Project Specifications and Drawings, and all temporary aids / brackets removed.
2
Roof structures are installed in accordance with Project Specifications and Drawings, and all temporary aids / brackets removed.
3
All platforms and walkways are installed in accordance with Project Specifications and Drawings, and all temporary aids / brackets removed.
4
All gully gratings to drains installed and drains and sumps clean.
5
All penetrations installed, with sleeves / kick plates of specified size complete with drain holes as required.
6
All grating installed, secured and no gaps exist
7
All Packers used under uprights to be fabricated from good quality CS & to be blasted & primed as a minimum.
8
Foundations and handrails installed in accordance with Project Specifications, ladder entrances have safety bar complete with protected landing end and portable hand railings are secured.
9
All structural supports installed in accordance with drawings and all temporary aids / brackets removed.
10
All bolting installed and tightened.
11
All maintenance / scaffolding lugs are installed in accordance with drawings with the correct orientation.
12
Temporary steel work, to be removed at a later date, clearly marked and identified on relevant drawings.
13
All Welding, Stress Relief and NDT work completed and cleared.
14
Confirm that all Quality Records have been completed and accepted.
15
Confirm that all Punch List items have been completed and accepted.
Remarks:
CONTRACTOR
CONSULTANT
Signature Name Date BPF-PJT-PEB-003
Page 1 of 1
COMPANY