Ref: APL/2x660/DPJ/Civil/08/Proposal

APPROVAL NOTE Subject: Approval for contract for the period of six months for regular maintenance of plantation in APL Premises. Ref: Approval note ref no. APL/2x660/DPJ/Civil/08/Proposal2 dated 02/02/08 In quest to develop good aesthetic of our premises, procurement of saplings of plants, compatible to grow in the saline atmosphere of Mundra, is in process of procurement. Now the need has been felt that scientific maintenance for a period of six months be carried out on regular basis for that the survival rates of plants becomes higher. The plants which are to be procured and planted are included in this estimate for their maintenance. Therefore, BOQ and special terms and conditions are drafted and attached here with appearing in separate sheets for approval. The approximate amount of the amount shall be Rs. 2,77,260.00 /The period of contract shall be six months. It is proposed to award the works to the agencies suggested by Horticulture department MPSEZ Mundra. It is also proposed to execute the work through Horticulture department MPSEZ Mundra, since they are having required manpower for such works. Encl as above. (K. P. Chakerwarti) DGM, Civil (P. Gouda) GM, Civil (B.D. De) AVP, Projects (D. P. Joshi) VP, Projects (S..K. Jain) GM, Commercial

Special Terms and Conditions: 1. The scope of work shall be maintenance of all plants and Mahendi discretely planted in APL Premises. 2. Payment shall be made limited to number of plants which have survived in the month for which the payment is asked. 3. Only 80% payment as applicable for (2) above shall be made, balance 20% shall be made in the following month along with the plants that have survived only. 4. All consumables viz fertilizer, DAP, cow-dung, pesticides and chemicals for retaining moisture in soil, etc. all as per requirements and requisite as per site conditions. All the tools and tackles required for the job shall be brought by the agency at work sites at no extra costs. 5. The rates are firm for the contract period. 6. Watering with potable water shall be done at regular intervals including arranging requisite no. of labourers. 7. Watering shall not be later than regular intervals more than 3 days. 8. Watering shall be done meticously that there is minimal wastage of water. 9. Per day minimum 3 labourers and one tanker of capacity not less than 5000 kl shall be employed.

(K. P. Chakerwarti) DGM, Civil

BILL OF QUANTITIES Name of Work: Regular maintenance for six months of plantation in APL Premises for SEZ area. Sr. Brief Description of item Quantity Rate(Rs.) no 1 Labour charges for regular 8,70,720 0.15 maintenance for six months of saplings/ Plants/ grown up trees including watering manuring etc. complete all as per detailed terms conditions and directions at site as per requirements. -Plants of any age and of any type 2 Labour charges for regular 1,46,652 1.00 maintenance for six months of saplings/ Plants/ grown up trees including watering manuring etc. complete all as per detailed terms conditions and directions at site as per requirements. - Mahendi Total

Unit

Amount(Rs.)

Nos.

1,30,608.00

Sq. mt

1,46,652.00

2,77,260.00

(K. P. Chakerwarti) DGM, Civil

Rate Analysis Item no 1 ( for 5000 plants) Potable water Three Labourers

: :

5000 lt @ Rs. 190 Rs. 150/ Labourer

Add 10% Contractor’s Profit :

= 190.00 = 450.00 = 640.00 = 64.00 = 704.00

Therefore the rate per plant comes to 704/5000 = Rs. 0.15 No. of occasions of watering shall be (6 x 30) / (14512/5000) = 60 occasions Hence the quantity shall be 14512 x 60 = 8,70,720 Item no 2 (for 800 sq mt, 9 plants are considered per sq. mt) Potable water Four Labourers

: :

5000 lt @ Rs. 190 Rs. 150/ Labourer

Add 10% Contractor’s Profit :

= 190.00 = 600.00 = 790.00 = 79.00 = 869.00

Therefore the rate per Sq. mt comes to 869/ 800 = Rs. 1.08, say Re. 1.00 No. of occasions of watering shall be (6 x 30) / [40000/(9x800)] = 32.72 occasions, say 33 occasions Hence the quantity shall be (40000/9) x 33 = 1,46,652 sq mt

(K. P. Chakerwarti) DGM, Civil