Analisis Harga Pekerjaan A.1 Pekerjaan tanah A.1.1 Pekerjaan tanah secara manual dan semi mekanis (Normatif) T.01 AHSP pembersihan dan pengupasan permukaan tanah T.01.a 1 m2 pembersihan dan striping/kosrekan No A

Uraian TENAGA Pekerja Mandor

Kode L.01 L.04

B

BAHAN

C

PERALATAN

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

Satuan

Koefisien

OH 0.0600 OH 0.0060 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

JUMLAH HARGA BAHAN

-

JUMLAH HARGA ALAT

T.01.b

T.01.c

T.06

3,960.00 480.00 4,440.00

8% -

1 m2 tebas tebang berupa memotong dan membersihkan lokasi dari tanaman/ tumbuhan ø < 15 cm Harga Satuan No Uraian Kode Satuan Koefisien (Rp.) A TENAGA Pekerja L.01 OH 0.0750 66,000 Mandor L.04 OH 0.0075 80,000 JUMLAH TENAGA KERJA B BAHAN JUMLAH HARGA BAHAN C PERALATAN JUMLAH HARGA ALAT D Jumlah (A+B+C) E Overhead & Profit 8% 8% F Harga Satuan Pekerjaan (D+E) Cabut 1 tunggul pohon tanaman keras ø > 15 cm dan membuang sisa tunggul kayu dan akar-akar nya Harga Satuan No Uraian Kode Satuan Koefisien (Rp.) A TENAGA Pekerja L.01 OH 0.2000 66,000 Mandor L.04 OH 0.0200 80,000 JUMLAH TENAGA KERJA B BAHAN JUMLAH HARGA BAHAN C PERALATAN Chainsaw E.06 Sewa-hari 0.1 300,000 JUMLAH HARGA ALAT D Jumlah (A+B+C) E Overhead & Profit 8% 8% F Harga Satuan Pekerjaan (D+E) -

4,440.00 355.20 4,795.00

Jumlah Harga (Rp.) 4,950.00 600.00 5,550.00 5,550.00 444.00 5,994.00

Jumlah Harga (Rp.) 13,200.00 1,600.00 14,800.00 30,000.00 30,000.00 44,800.00 3,584.00 48,384.00

Pelaksanaan galian tanah T.06 sampai dengan T.11 sudah termasuk - pembuangan hasil galian dengan jarak angkut L < 5 m - Perataan dan perapihan, Galian tanah biasa T.06.a Cara manual T.06.a.1) 1 m3 galian tanah biasa sedalam ≤ 1 m No A

Uraian TENAGA Pekerja Mandor

B

BAHAN

C

PERALATAN

Kode L.01 L.04

Satuan

Koefisien

OH 0.5630 OH 0.0563 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

JUMLAH HARGA BAHAN

-

JUMLAH HARGA ALAT D E F

T.06.b T.06.b.1)

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

37,158.00 4,504.00 41,662.00

8% -

41,662.00 3,332.96 44,994.00

Cara semi mekanis 1 m3 galian tanah biasa sedalam ≤ 1 m No A

B

C

D E F

Uraian

Kode

Satuan

Koefisien

TENAGA Pekerja Mandor

L.01 L.04

BAHAN BBM non subsidi

M.137.b

Liter

PERALATAN Jack hammer

E.16.a

sewa-hari 0.0500 JUMLAH HARGA ALAT

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

OH 0.2200 OH 0.0220 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

14,520.00 1,760.00 16,280.00

0.5000 9,000 JUMLAH HARGA BAHAN

4,500.00 4,500.00

250,000

8% -

12,500.00 12,500.00 33,280.00 2,662.40 35,942.00

TM.04.c. TM.04.c.1 TM.04.c.1.a

Angkutan material dan/atau hasil galian Mengangkut 1 m3 material atau hasil galian Menggunakan Dump Truck Jarak angkut < 1 Km No

Uraian

A

TENAGA

B

BAHAN

C

PERALATAN Dump Truck

Kode

Satuan

Koefisien

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

JUMLAH TENAGA KERJA

-

JUMLAH HARGA BAHAN

D E F TM.04.c.1.b

E.08 b

Sewa-Jam 0.0783 JUMLAH HARGA ALAT

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

-

600,000

8% -

Jarak angkut > 1 km untuk setiap penambahan jarak angkut 100 m No

Uraian

A

TENAGA

B

BAHAN

C

PERALATAN Dump Truck

Kode

Satuan

Koefisien

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

JUMLAH TENAGA KERJA

-

JUMLAH HARGA BAHAN E.11.b

Sewa-Jam 0.0031 JUMLAH HARGA ALAT

-

600,000

D Jumlah (A+B+C) E Overhead & Profit 8% 8% F Harga Satuan Pekerjaan (D+E) Harga Alat Sudah Termasuk BBM dan Operator (Supir,Kenek), sehingga HSD Tenaga=0 dan HSD Bahan=0

A.2

46,980.00 46,980.00 46,980.00 3,758.40 50,738.40

1,860.00 1,860.00 1,860.00 148.80 2,008.80

Pekerjaan pasangan (Normatif) A.2.1 Koefisien untuk analisis harga satuan Pekerjaan pasangan (Normatif) P.01.c.2)

Menggunakan molen No A

Kode L.01 L.02 L.04

BAHAN Batu belah Pasir pasang Portland cement

C

PERALATAN Molen kapasitas 0,3 m3

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

B

P.01.e P.01.e.1)

Uraian TENAGA Pekerja Tukang batu Mandor

Satuan

Koefisien

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

OH 1.8000 OH 0.9000 OH 0.1800 JUMLAH TENAGA KERJA

66,000 70,000 80,000

118,800.00 63,000.00 14,400.00 196,200.00

M.06.a M.14.b M.15

m3 1.2000 m3 0.5200 kg 163.0000 JUMLAH HARGA BAHAN

130,000 130,000 1,000

156,000.00 67,600.00 163,000.00 386,600.00

E.29.b

Sewa-hari 0.0760 JUMLAH HARGA ALAT

200,000

15,200.00 15,200.00 598,000.00 47,840.00 645,840.00

8% -

Bongkar dan pemanfaatan batu bekas pasangan Bongkar 1 m3 pasangan batu dan pembersihan batu (manual) No A

Uraian TENAGA Pekerja Mandor

Kode L.01 L.04

B

BAHAN

C

PERALATAN Palu/godam (baja keras) Pahat beton (baja keras) Linggis (baja keras)

Satuan

Koefisien

OH 1.4000 OH 0.1400 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

92,400.00 11,200.00 103,600.00

250,000 125,000 300,000

2,000.00 1,500.00 6,000.00 9,500.00 113,100.00 9,048.00 122,148.00

JUMLAH HARGA BAHAN To.16 To.15 To.14

buah 0.0080 buah 0.0120 buah 0.0200 JUMLAH HARGA ALAT

D Jumlah (A+B+C) E Overhead & Profit 8% F Harga Satuan Pekerjaan (D+E) *) Jika tidak perlu menggunakan peralatan khusus (baja keras), maka HSD = 0

P.03

-

8% -

1 m2 Pekerjaan siaran dengan mortar jenis PC-PP P.03.a Siaran dengan mortar tipe M (setara campuran 1 PC:2 PP) No A

B

C D E F

Uraian

Kode

TENAGA Pekerja Tukang batu Kepala Tukang Mandor

L.01 L.02 L.03 L.04

BAHAN Pasir pasang Portland cement

M.14.b M.15

Satuan

Koefisien

OH 0.3000 OH 0.1500 OH 0.0150 OH 0.0300 JUMLAH TENAGA KERJA m3 kg

0.0120 6.3400

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

19,800.00 10,500.00 1,125.00 2,400.00 33,825.00

130,000 1,000

1,560.00 6,340.00

JUMLAH HARGA BAHAN

7,900.00

JUMLAH HARGA ALAT

41,725.00 3,338.00 45,063.00

PERALATAN Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8% -

P.04.b

Plesteran tebal 1 cm, dengan mortar tipe S (setara campuran 1 PC:3 PP) No A

B

C

L.01 L.02 L.03 L.04

BAHAN Pasir pasang Portland cement

M.14.b M.15

Satuan

Koefisien

OH 0.3000 OH 0.1500 OH 0.0150 OH 0.0300 JUMLAH TENAGA KERJA m3 kg

0.0160 5.8400

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

19,800.00 10,500.00 1,125.00 2,400.00 33,825.00

130,000 1,000

2,080.00 5,840.00

JUMLAH HARGA BAHAN

7,920.00

JUMLAH HARGA ALAT

41,745.00 3,339.60 45,084.00

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8% -

1 m2 pekerjaan acian No A

B

C

Uraian

Kode

TENAGA Pekerja Tukang batu Kepala Tukang Mandor

L.01 L.02 L.03 L.04

BAHAN Portland cement

M.15

Satuan

Koefisien

OH 0.2000 OH 0.1000 OH 0.0100 OH 0.0200 JUMLAH TENAGA KERJA kg

3.2500

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

13,200.00 7,000.00 750.00 1,600.00 22,550.00

1,000

3,250.00

JUMLAH HARGA BAHAN

3,250.00

JUMLAH HARGA ALAT

25,800.00 2,064.00 27,864.00

PERALATAN

D E F

B.05.b

Kode

PERALATAN

D E F

P.04.g

Uraian TENAGA Pekerja Tukang batu Kepala Tukang Mandor

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8% -

Menggunakan molen No A

Uraian TENAGA Pekerja Tukang Batu Kepala Tukang Batu Mandor

B

Kode L.01 L.02 L.03 L.04

Satuan

Koefisien

OH 1.323 OH 0.189 OH 0.019 OH 0.132 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

87,318.00 13,230.00 1,425.00 10,560.00 112,533.00

1,000 150 275 50

326,000.00 114,000.00 282,975.00 10,750.00 733,725.00

200,000

50,000.00 50,000.00 896,258.00 71,700.64 967,958.00

BAHAN PC / Portland Cement PB / Pasir Beton Kr / Krikil Air

M.15 M.14.a.1 M.12.1 M.02

kg kg kg Liter

326 760 1029 215

Jumlah Harga

A.3.3

C

PERALATAN Molen kapasitas 0,3 M3

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

E.29.b

Sewa-hari 0.2500 JUMLAH HARGA ALAT 8%

-

Koefisien untuk analisa harga satuan pekerjaan pembesian beton B.17 Pembesian 100 kg dengan besi polos atau ulir B.17.a Untuk pembesian pelat No A

B

Uraian

Kode

TENAGA Pekerja Tukang Batu Kepala Tukang Batu Mandor

L.01 L.02 L.03 L.04

BAHAN Besi Beton (polos/ulir) Kawat Ikat

M.55.d M.67

C

PERALATAN

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

Satuan

Koefisien

OH 0.700 OH 0.700 OH 0.070 OH 0.070 JUMLAH TENAGA KERJA Kg Kg

105.000 1.500 Jumlah Harga

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

46,200.00 49,000.00 5,250.00 5,600.00 106,050.00

12,000 20,000

1,260,000.00 30,000.00 1,290,000.00

JUMLAH HARGA ALAT 8% -

1,396,050.00 111,684.00 1,507,734.00

A.3.4

Koefisien untuk analisa harga satuan pekerjaan pembuatan/penyediaan bekisting beton B.21 Bekisting lantai B.21.b

1 m² bekisting lantai beton biasa dengan multiflex 12 mm atau 18 mm (TP) No A

B

Uraian

Kode

TENAGA Pekerja Tukang Kepala Tukang Mandor

L.01 L.02 L.03 L.04

BAHAN Multiflex 12 atau 18 mm * (3 x pakai) Kaso 5/7 cm * (3 x pakai) Paku 5 cm dan 7 cm Minyak bekisting

M.39.d M.33.d M.71.b M.129

C

PERALATAN

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

Satuan

Koefisien

OH 0.200 OH 0.100 OH 0.010 OH 0.020 JUMLAH TENAGA KERJA Lembar m3 Kg Liter

0.1280 0.0050 0.2200 0.2000 Jumlah Harga

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 70,000 75,000 80,000

13,200.00 7,000.00 750.00 1,600.00 22,550.00

180,000 3,000,000 20,000 5,000

23,040.00 15,000.00 4,400.00 1,000.00 43,440.00

JUMLAH HARGA ALAT 8% -

65,990.00 5,279.20 71,269.00

CATATAN: * Bahan digunakan berulang kali, yang ke-1, koefisien 0,353 (multiflex) dan 0,014 (Kaso) yang ke-2, koefisien menjadi 0,203 (multiflex) dan 0,008 (Kaso) yang ke-3, koefisien menjadi 0,128 (multiflex) dan 0,005 (Kaso) yang ke-4, koefisien menjadi 0,091 (multiflex) dan 0,003 (Kaso)

B.27

Bongkar Bekisting B.27.a Bongkar 1m2 Bekisting secara biasa (membersihkan dan membereskan puing-puing) No A

Uraian TENAGA Pekerja Mandor

B

Kode L.01 L.04

Satuan

Koefisien

OH 0.04 OH 0.004 JUMLAH TENAGA KERJA

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

BAHAN Jumlah Harga

C

PERALATAN

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

JUMLAH HARGA ALAT

A.5

2,640.00 320.00 2,960.00

8% -

-

2,960.00 236.80 3,196.00

Pekerjaan Dewatering (Normatif) A.5.1 AHSP Pekerjaan Dewatering (Normatif) D.01 Kistdam pasir/tanah D.01.a 1 buah kistdam pasir/tanah dibungkus karung plastik bagor 43 cm x 65 cm No A

B

Uraian TENAGA Pekerja Mandor BAHAN Karung plastik /bagor/goni Tali rapia / plastik Sewa pasir *

Kode L.01 L.04

M.123.a M.140 M.14.a

Satuan

Koefisien

OH 0.04 OH 0.004 JUMLAH TENAGA KERJA buah m’ m3

1.0 2.0 0.012

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

66,000 80,000

2,640.00 320.00 2,960.00

3,000 500 130,000

3,000.00 1,000.00 1,560.00 5,560.00

Jumlah Harga C

PERALATAN

D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

JUMLAH HARGA ALAT 8%

*) Koefisien dihitung 50%, jika penggunaan kistdam selesai, pasir dimanfaatkan kembali, gunakan HSD pasir 100% **) Kode bahan dan harga agar disesuaikan dengan yang digunakan

-

8,520.00 681.60 9,201.00

D.04

Pengoperasian per-jam pompa air diesel daya 5 kW dengan suction head maks. 3 m dan discharge head maks. 20 m (kapasitas 0,5 m3/s pada suction head 1 m dan discharge head 10 m). No A

Uraian TENAGA Pekerja Operator Pompa Mandor

B

Kode L.01 L.05 L.04

Satuan

Harga Satuan (Rp.)

Koefisien

OH 0.125 OH 0.125 OH 0.013 JUMLAH TENAGA KERJA

Jumlah Harga (Rp.)

66,000 99,000 80,000

8,250.00 12,375.00 1,040.00 21,665.00

9,000

31,500.00 31,500.00

60,000

9,000.00 9,000.00 62,165.00 4,973.20 67,138.00

BAHAN Solar

M.137.b

Liter

3.50

Jumlah Harga C

PERALATAN Pompa air diesel 5 KW

E.34.b

Sewa-jam

0.15

JUMLAH HARGA ALAT D E F

LA.05.b

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8% -

1 Set foto dokumentasi menggunakan kamera digital tanpa film (jika menggunakan kamera digital, untuk dokumentasinya dengan CD dan album foto) No A

Uraian TENAGA Tukang Foto

Kode L.02

Satuan

Harga Satuan (Rp.)

Koefisien

OH

2

Jumlah Harga (Rp.)

70,000

JUMLAH TENAGA KERJA B

140,000.00

BAHAN CD copy soft file foto image Foto printing Foto album

M.117 K.02.b M.119.a

buah Lembar buah

3 300 3

5,000 2,500 25,000

15,000.00 750,000.00 75,000.00 840,000.00

200,000

400,000.00

-

400,000.00 1,380,000.00 110,400.00 1,490,400.00

Jumlah Harga C

PERALATAN Kamera SLR (Digital)

To.06

Sewa-hari

2

JUMLAH HARGA ALAT D E F LA.06 LA.07

Penggambaran LA.07.a

140,000.00

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8%

Test bahan dan pengujian mutu pekerjaan

Penggambaran dengan CAD untuk 1 buah gambar (file autocad) layout, tampak potongan dan detail untuk kondisi tidak rumit dan banyak bentuk duplikasi ukuran A1 No A

Uraian

Kode

Satuan

Koefisien

Harga Satuan (Rp.)

Jumlah Harga (Rp.)

TENAGA Drafter CAD Desain engineer

L.14 L.15

OH OH

1 0.5

75,000 132,000

75,000.00 66,000.00 141,000.00

200,000 100,000

8,000.00 3,000.00 11,000.00 152,000.00 12,160.00 164,160.00

JUMLAH TENAGA KERJA B

BAHAN

C

PERALATAN

Jumlah Harga Sewa komputer Sewa scanner ukuran A4

To.10 To.18

Sewa-Bulan Sewa-Bulan

0.04 0.03

-

JUMLAH HARGA ALAT D E F

Jumlah (A+B+C) Overhead & Profit 8% Harga Satuan Pekerjaan (D+E)

8% -

Related Documents

Analisa
October 2019 73
Analisa
May 2020 59
Analisa Air
June 2020 16
Analisa Akhir
May 2020 27
Analisa Bogowonto.pdf
November 2019 25
Analisa Dampak.docx
December 2019 27

More Documents from "sayyidah mirfat"