Flats Sequencing System Update Mailer Technical Advisory Committee (MTAC) August 6, 2008 Cathy Moon FSS Project Office
Agenda
Deployment Status
Flat Mail Volume Update
Pre-Production FSS Operation
Production FSS Dulles P&DC
FSS Optimization
FSS Deployment Timeline Prototype – Indianapolis IN
Apr 2006
BOG Approval 100 Production FSS Machines
Dec 2006
Pre-production Install – Dulles P & DC
Sept 2007
First Production FSS Installation
May 2008
First Production FSS Testing
Sept 2008
Phase 1 Deployment Begin
Oct 2008
Phase 1 Deployment End
Oct 2010
Flat Volume 2006 – 2007 Comparison RPW
2006
2007
Flat Volume – 54 Billion
Flat Volume – 52 Billion
Flat Volume Trend 1995 - 2007
60.0
50.0
Billions
40.0
30.0
20.0
10.0
0.0 Volume
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
39.4
42.4
44.3
52.5
52.6
54.7
55.7
51.6
51.0
51.9
53.4
53.2
51.8
FY 2008 vs. SPLY Flat Volume Comparison Total Flat Volume Oct 2007 - June 2008 - SPLY Comparison
6,000,000
5,000,000
-14.5 -8.9 -10.7
4,000,000
-10.6
-7.8
-10.7
0 )
-16.6
-12.3 -11.6
( s c ie P
3,000,000
2,000,000
1,000,000
-
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
FY 2007
5,831,920
5,188,039
3,941,061
4,423,839
4,029,330
4,610,545
4,374,478
4,213,254
3,686,106
FY 2008
4,985,502
4,727,329
3,521,277
3,950,168
3,715,010
3,843,851
3,908,920
3,694,561
3,257,217
Diff
(846,418)
(460,710)
(419,784)
(473,671)
(314,320)
(766,694)
(465,557)
(518,693)
(428,889)
(14.5)
(8.9)
(10.7)
(10.7)
(7.8)
(16.6)
(10.6)
(12.3)
(11.6)
% Change
YTD - FY 2008 SPLY Comparison FY 2008 YTD Flat Volume vs. SPLY (Oct - June)
RPW
45,000,000
FY 2008 YTD Total Flat Volume Decline
-11.3%
40,000,000
-11.3
35,000,000
30,000,000
( s c ie P
0 )
-13.0 25,000,000
20,000,000
15,000,000
10,000,000
-2.3 5,000,000
0
-15.4 First Class
Periodicals
Standard
Total Flats
FY 2007
3,171,121
6,598,839
30,068,573
40,298,572
FY 2008
2,682,523
6,447,841
26,173,352
35,740,051
Northern VA
Dulles Pre-production Status
Installation Complete
Oct 2007
Integration / Machine Testing
Nov 2007
Live Mail Ramp-up
Dec 2007
Field Pre-Test/Test
Feb /Apr 2008
Full Machine Ramp Up
May 2008
Dulles: Pre-production FSS
Dulles Operational Ramp-up Bellview Branch Burke Branch Culpepper Post Office Engleside Branch Fairfax Post Office McLean Post Office Reston Branch Reston Annex Sterling Post Office Falls Church – Aug 6th
DPS Flats
FSS Delivery Results
FSS Delivery Results
Dulles 1st Production FSS System
Installation Complete
Jul 2008
Integration / Machine Testing
Aug 2008
Live Mail Ramp-up
Sep 2008
(Move Pre-Production Zones)
Acceptance Test
Sep 1 –Oct 10 2008
Production FSS – Dulles P&DC
Production FSS – Dulles P&DC
FSS Opti mi za tion
Flats Optimization
Incremental Improvements to Processes
Reduce Variation
Remove Activities that Have no Value to the Organization & Customers
Improve Customer Satisfaction
Standardization
Flats Optimization
Conclusion