Appendix-V Appendix-V-1 Combined Effluent Treatment Plant Korangi Tanneries PTA Environment, KIA, Karachi 240 51’ 16.05’’ N 670 06’ 55.35’’ E

Appendix-V-2 Combined Effluent Treatment Plant Korangi Tanneries PTA Environment, KIA, Karachi 240 51’ 16.05’’ N 670 06’ 55.35’’ E BESIDE MOHAMMAD SHAFI TANNERIES KIA

DAMMAM SEWERAGE TREATMENT PLANT Eastern Province, Saudi Arabia 260 10’ 39.06’’ N 500 12’ 35.54’’ E Inlet Structure =1 Aeration Tanks (Carousels) = 8 Clarifiers=8 Sludge Thichners =2 Screw Pump Stations = 4

Sea out-fall discharges = 250,000 m3/day



Discharge BOD Loadings: 20-25mg/l O2

Wastewater Treatment by Aeration Lagoons aborted since 1982-83 . The plant was designed and constructed by Ballast BV of Netherlands.



Advance Wastewater Treatment commissioned in late 1982

by

Activated Sludge System was

which was designed and constructed

Metcalf and Eddy Incorp, Waikfield, Mass, USA.

by

JUBAIL DESALINATION PLANT Al-Jubail, Eastern Province, Saudi Arabia

MSF Desalination/Power Generation Co-Generation Plant Largest Desalination Plant in the world

Phase-I Facility: Fresh water production=910,000m3/day Power Generation=360,000 kW =360 MW

Related Documents

Work Areas App-ii
December 2019 0
Work Areas App-iii
December 2019 5
Work Areas App-v
December 2019 3
Work Areas App-i
December 2019 2
Areas
October 2019 48
Areas
April 2020 33