West Irving Library Schematic Design Review
Supporting Goals #2 ‐ Nurture and Promote Vital, Vibrant Neighborhoods #7 – Promote Excellence in Irving’s Cultural, Recreational and Educational Environments #10 – Become a Successful Environmentally Sustainable Community 6.17.09
1
West Irving Library Purpose: Acquire City Council Consensus of the $8.0 Million Schematic Design for the Northwest Library ¾ ¾ ¾ ¾ ¾ ¾
Objectives Site Analysis Schematic Site Plans Schematic Floor Plan Exterior Elevation Next Steps
2 6.17.09
West Irving Library Project Objectives ¾ Enhance and expand library services in west and central Irving area. ¾ Create a State-of-the-Art destination for residents. ¾ Achieve LEED Certification resulting in reduced utilities cost. ¾ Enhance the site by using native plants and public art. ¾ Integrate the interior spaces of the building and the site enhancements through the use of glass to maximize views. ¾ House the Bookmobile for a more central service location.
3 6.17.09
West Irving Library Site Analysis
R NEW RESIDENTIAL
CONVENIENT TO NEIGHBORHOODS
32 Feet of Fall from SE to the NW corner
6.50 Acre Site
NEW FIRE STATION TO W. T. HANES
=
283,140 SF (New Library Site)
WATER TOWER NEW RESIDENTIAL
R
R
ELEMENTARY and NORTHWEST PARK RECRE. CENTER
OLD POLICE TRAINING ACADEMY
ISLAMIC CENTER of IRVING
69.09 4 6.17.09
West Irving Library Site Plan
SOLAR PANELS
SITE PLAN
“POCKET PARKS” GATEWAY ENTRY NATIVE PLANTS GATHERING AREAS
RETENTION POND SCREEN / RETAINING WALLS VISUAL IMPACTS
SCULPTURE OUTDOOR PLAZAS PEDESTRIAN PATHS
Main Entry Exterior drive-up Book Drop 5
6.17.09
West Irving Library Special Amenities
Native Stone Walls
Photovoltaic Panels Public Art
Outside Reading Areas
Retention Pond 6.17.09
Outdoor Activity Spaces
6
West Irving Library Floor Plan ADULT
CHILDREN’S
TEEN’S
MULTIPURPOSE ROOM
QUIET READING
COMPUTER LAB Main Entry Exterior drive-up Book Drop
FLOOR PLAN 25,000 SF
STAFF
Multipurpose Meeting Room Lobby / Vending Area Interior Book Drop Staff Work Area
Children’s Collec. and Storytime Craft Room / Puppet Stage TEEN Area Computer Lab
Adult Collection Quiet Reading Study Rooms Business Center 7
6.17.09
West Irving Library North Elevation
8 6.17.09
West Irving Library West Elevation
9 6.17.09
West Irving Library
Next Steps ¾ ¾ ¾ ¾ ¾
Construction Documents complete October 13th Open Bids – Early November 2009 Contract Award – Late November 2009 Begin Construction – December 2009 Grand Opening & Dedication – Early 2011
10 6.17.09