Volorizaciones Edzon.xlsx

  • Uploaded by: jackon
  • 0
  • 0
  • April 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Volorizaciones Edzon.xlsx as PDF for free.

More details

  • Words: 1,735
  • Pages: 26
Pb= 61,696.39 Fpb= Jan-18 Fr= Po/Pb 0.ABCDE Po= PRESUPUESTO OFERTADO Po= 58,905.86 UBICACIÓN: Cusco ÁREA GEOGRÁFICA: 6 DURACIÓN: 3 MESES INICIO: MAYO

0.95477

15813.81 15494.5292

ANTERIOR DESCRIPCIÒNUND. CANT. P.UNIT. PARCIAL TOTAL CANTIDAD IMPORTE 1.00 CONCRETO ARMADO 1.01 COLUMNA 15,947.92 1.01.01 CONCRETO F'M3. 15.00 463.08 6,946.20 1.01.02 ENCOF. -DES M2. 68.00 46.79 3,181.72 1.01.03 ACERO CORRU KG. 1,200.00 4.85 5,820.00 1.02 VIGAS 11,316.00 1.02.01 CONCRETO F'M3. 10.00 443.58 4,435.80 1.02.02 ENCOF. -DES M2. 48.00 52.40 2,515.20 1.02.03 ACERO CORRU KG. 900.00 4.85 4,365.00 1.03 LOSA ALIGERADA 15,908.98 1.03.01 CONCRETO F'M3. 9.00 400.42 3,603.78 1.03.02 ENCOF. -DES M2. 120.00 36.96 4,435.20 1.03.03 ACERO CORRU KG. 1,000.00 4.85 4,850.00 1.03.04 LADRILLO 0.1UND. 1,000.00 3.02 3,020.00 2.00 MUROS 7,815.85 2.01 DE LAD. KK M2. 35.00 64.25 2,248.75 2.02 DE LAD. KK 1 M2. 55.00 101.22 5,567.10 COSTO DIRECTO 50,988.75 GASTOS GENERALES 12% 6,118.65 UTILIDAD 9% 4,588.99 SUBTOTAL 61,696.39 IGV 11,105.35 TOTAL 72,801.74 %AVANCE 100 ITEM

VR=

ACTUAL CANTIDAD IMPORTE

ACUMULADO CANTIDAD

39.85 984.65

1,864.58 4,775.55

39.85 984.65

24.85 40.55

1,596.61 4,104.47 12,341.22 1,480.95 1,110.71 14,932.88

24.85 40.55

24.20% 14,257.47

ACUMULADO IMPORTE

1,864.58 4,775.55

SALDO CANTIDAD IMPORTE

15.00 28.15 215.35 10.00 48.00 900.00 9.00 120.00 1000.00 1000.00

1,596.61 4,104.47 12,341.22 1,480.95 1,110.71 14,932.87

24.20%

10.15 14.45

6,946.20 1,317.14 1,044.45 0.00 4,435.80 2,515.20 4,365.00 0.00 3,603.78 4,435.20 4,850.00 3,020.00 0.00 652.14 1,462.63 38,647.53 4,637.70 3,478.28 46,763.51

75.80%

% AVANCE

0% 59% 82%

71% 74% 50,988.75

61,696.39

100.00%

ITEM

DESCRIPCIÒNUND. CANT. P.UNIT. PARCIAL TOTAL 1.00 CONCRETO ARMADO 1.01 COLUMNA 15,947.92 1.01.01 CONCRETO F'M3. 15.00 463.08 6,946.20 1.01.02 ENCOF. -DES M2. 68.00 46.79 3,181.72 1.01.03 ACERO CORRU KG. 1,200.00 4.85 5,820.00 1.02 VIGAS 11,316.00 1.02.01 CONCRETO F'M3. 10.00 443.58 4,435.80 1.02.02 ENCOF. -DES M2. 48.00 52.40 2,515.20 1.02.03 ACERO CORRU KG. 900.00 4.85 4,365.00 1.03 LOSA ALIGERADA 15,908.98 1.03.01 CONCRETO F'M3. 9.00 400.42 3,603.78 1.03.02 ENCOF. -DES M2. 120.00 36.96 4,435.20 1.03.03 ACERO CORRU KG. 1,000.00 4.85 4,850.00 1.03.04 LADRILLO 0.1UND. 1,000.00 3.02 3,020.00 2.00 MUROS 7,815.85 2.01 DE LAD. KK M2. 35.00 64.25 2,248.75 2.02 DE LAD. KK 1 M2. 55.00 101.22 5,567.10 COSTO DIRECTO 50,988.75 GASTOS GENERALES 12% 6,118.65 UTILIDAD 9% 4,588.99 SUBTOTAL 61,696.39 IGV 11,105.35 TOTAL 72,801.74 %AVANCE 100

v2 ANTERIOR CANTIDAD IMPORTE

39.85 984.65

ACTUAL CANTIDAD IMPORTE

10.00 28.15 215.35

1,864.58 4,775.55

24.96

39.60

24.85 40.55

1,596.61 4,104.47

10.15 14.45

4,630.80 1,317.14 1,044.45 0.00 0.00 1,307.90 0.00 0.00 0.00 1,463.62 0.00 0.00 0.00 652.14 1,462.63 11,878.67 1,425.44 1,069.08 14,373.19

23.30% V2R=

13,723.09

ACUMULADO CANTIDAD IMPORTE

10.00 68.00 1200.00 0.00 0.00 24.96 0.00 0.00 0.00 39.60 0.00 0.00 0.00 35.00 55.00

4,630.80 3,181.72 5,820.00 0.00 0.00 1,307.90 0.00 0.00 0.00 1,463.62 0.00 0.00 0.00 2,248.75 5,567.10 24,219.89 2,906.39 2,179.79 29,306.07

47.50%

SALDO CANTIDAD IMPORTE

5.00 0.00 0.00 0.00 10.00 23.04 900.00 0.00 9.00 80.40 1000.00 1000.00 0.00 0.00 0.00

2,315.40 0.00 0.00 0.00 4,435.80 1,207.30 4,365.00 0.00 3,603.78 2,971.58 4,850.00 3,020.00 0.00 0.00 0.00 38,647.53 4,637.70 3,478.28 46,763.51

75.80%

% AVANCE

67% 100% 100%

52%

33%

100% 100% 50,988.75

61,696.39

100.00%

ITEM

DESCRIPCIÒN 1.00 CONCRETO ARMADO 1.01 COLUMNA 1.01.01 CONCRETO F' 1.01.02 ENCOF. -DES 1.01.03 ACERO CORRU 1.02 VIGAS 1.02.01 CONCRETO F' 1.02.02 ENCOF. -DES 1.02.03 ACERO CORRU 1.03 LOSA ALIGERADA 1.03.01 CONCRETO F' 1.03.02 ENCOF. -DES 1.03.03 ACERO CORRU 1.03.04 LADRILLO 0.1 2.00 MUROS 2.01 DE LAD. KK 2.02 DE LAD. KK 1 COSTO DIRECTO GASTOS GENERALES 12% UTILIDAD 9% SUBTOTAL IGV TOTAL %AVANCE

UND. ONCRETO ARMADO

P.UNIT.

PARCIAL

TOTAL

ANTERIOR CANTIDAD IMPORTE

ACTUAL CANTIDAD IMPORTE

ACUMULADO CANTIDAD IMPORTE

SALDO CANTIDAD

15,947.92 M3. M2. KG.

M3. M2. KG. OSA ALIGERADA M3. M2. KG. UND.

M2. M2. OSTO DIRECTO ASTOS GENERALES 12% TILIDAD 9%

%AVANCE

CANT.

15.00 68.00 1,200.00

463.08 46.79 4.85

6,946.20 3,181.72 5,820.00 11,316.00

10.00 48.00 900.00

443.58 52.40 4.85

4,435.80 2,515.20 4,365.00 15,908.98

9.00 120.00 1,000.00 1,000.00

400.42 36.96 4.85 3.02

3,603.78 4,435.20 4,850.00 3,020.00

35.00 55.00

64.25 101.22

2,248.75 5,567.10

7,815.85

10.00 68.00 1,200.00 0.00 0.00 24.96 0.00 0.00 0.00 39.60 0.00 0.00 0.00 35.00 55.00

4,630.80 3,181.72 5,820.00 0.00 0.00 1,307.90 0.00 0.00 0.00 1,463.62 0.00 0.00 0.00 2,248.75 5,567.10

5.00 0.00 0.00 0.00 10.00 23.04 900.00 0.00 9.00 80.40 1000.00 1000.00 0.00 0.00 0.00

50,988.75 6,118.65 4,588.99 61,696.39 11,105.35 72,801.74 100

2,315.40 0.00 0.00 0.00 4,435.80 1,207.30 4,365.00 0.00 3,603.78 2,971.58 4,850.00 3,020.00 0.00 0.00 0.00 26,768.86 3,212.26 2,409.20 32,390.32

52.50% VR3

30,925.31

15.00 68.00 1200.00 0.00 10.00 48.00 900.00 0.00 9.00 120.00 1000.00 1000.00 0.00 35.00 55.00

6,946.20 3,181.72 5,820.00 0.00 4,435.80 2,515.20 4,365.00 0.00 3,603.78 4,435.20 4,850.00 3,020.00 0.00 2,248.75 5,567.10 50,988.75 6,118.65 4,588.99 61,696.39

100.00%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

SALDO IMPORTE

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 38,647.53 4,637.70 3,478.28 46,763.51

75.80%

% AVANCE

100% 100% 100%

100%

100%

100% 100% 50,988.75

61,696.39

100.00%

FÓRMULA POLINÓMICA OBRA: AMPLIACIÒN DE LABORATORIO UCV CONTRATISTA: TQM CONTRATISTA SAC ESPECIALIDAD: ESTRUCTURA MONOMIO DESCRIPCIÓN 1 CEMENTO PORTLAND T-I PIEDRA CHANCADA 2 MAQUINARIA HERRAMIENTA 3 MADERA TORNILLO 4 ACERO CORRUGADO 5 LADRILLO TECHO 6 MANO DE OBRA 7 GASTOS GENERALES

K=

0.15 Cr Co

+

0.057 PHr PHo

0.064 (0.2381*587.84)+(0.4444*607.14)+(0.3175*304.20) (0.2381*591.03)+(0.4444*606.47)+(0.3175*304.98)

CI

(AxIr1)+(BxIr2)+(CxIr3) (AxIo1)+(BxIo2)+(CxIo3)

Se saca del Se saca del cuadro de cuadro de INDICES INDICES UNIFICADOS por UNIFICADOS por costo según area costo según area geografica geografica

P.B: 61,695.78 SIN IGV FECHA: Jan-18 ÁREA GEOGRÁFICA: 02 SÍMBOLO C

3175*304.20) 3175*304.98)

PMH M F T J GGU

+

I.U 21 5 48 37 43 3 17 47 39

0.065 Mr Mo

C.I 0.15 0.057 0.065 0.16 0.090 0.304 0.174 1.000

+

=

% 100 15.79 64.91 19.30 100 100 100 100 100

0.163 Fr Fo 0.064

ENERO Io 410.96 629.95 363.04 304.98 900.56 475.87 878.12 582.52 442.87

+

ABRIL Ir 410.96 628.08 365.01 304.2 904.3 501.98 868.72 582.52 445.52

0.09 Tr To

K 0.150 0.057 0.065 0.152 0.091 0.304 0.173 1.009 0.996 +

MAYO Ir 410.96 617.54 368.95 304.54 899.03 513.58 865.43 582.52 445.61

0.304 Jr Jo

K 0.150 0.057 0.065 0.173 0.089 0.304 0.175 1.012

+

JUNIO Ir 410.96 618.89 368.82 303.74 896.42 508.81 864.03 582.52 447.1

0.174 GGUr GGUo

k 0.150 0.057 0.065 0.171 0.089 0.304 0.176 1.011



FECHA 1 MAYO 2 JUNIO 3 JULIO

Vprg. 14,257.47

Vreal 14,257.47

K-1 0.009

Rprog. 128.32



Rreal 128.32

FECHA 1 MAYO 2 JUNIO 3 JULIO

Rrecon. 128.32

Vprg. 14,257.47 13,723.09 30,925.31 58,905.87



Vreal 14,257.47 13,723.09 30,925.31

FECHA 1 MAYO 2 JUNIO 3 JULIO

K-1 Rprog. 0.012 171.09 0.011 150.875871 0.011 340.17837

Vprg. 14,257.47 13,723.09

Vreal 14,257.47 13,723.09

Rreal 171.09 150.88 340.18

Rrecon. 171.09 150.88 340.18 662.14 340.50 321.65

K-1 0.012 0.012

Rprog. 171.09 169.41

Rreal 171.09 169.41

Rrecon. 171.09 169.41 340.50 128.32 212.18

128.32

=

212.18

UN SUPUESTO Nª 1 2

N SUPUESTO FECHA MAYO JUNIO

Vprg. VreaL K-1 14,257.47 14,257.47 13,723.09 13,723.09

Rprog. Rreal Rrecon. -0.004 -57.03 -57.03 -57.03 -0.004 -54.89 -54.89 -54.89 -111.92 128.32 -240.24

CUADRO RESUMEN DEVALORIZACION N° 01 DEL 01 AL 30 ....… DE……………. OBRA: SUP ER VISOR : C ON T R A T IST A : P R ESUP UEST O B A SE:

61,696.39

P R ESUP UEST O C ON T R A T A D O:

58,905.86

DESCRIPCIÓN

VALORIZACIÓN (V)

SIN IGV SIN IGV MONTO CONTRATAD O SIN IGV (S/.)

ANTERIOR (S/.)

58,905.86

0.00

14,257.47

14,257.47

0.00

128.32

128.32

VALORIZACION ACTUAL (S/.)

ACUMULADO (S/.)

TOTAL CONTRACTUAL Avances en porcentaje REAJUSTES (R) DEDUCCIONES (D) POR ADELANTO EN EFECTIVO POR ADELANTO PARA MATERIALES TOTAL DEDUCCION ES VALORIZACIÓN BRUTA (VB = V + R - D)

14,385.78

AMORTIZACIONES (A) AMORTIZACION DEL ADELANTO EN EFECTIVO AMORTIZACION DEL ADELANTO PARA MATERIALES TOTAL AMORTIZACIONES (A) VALORIZACIÓN NETA (VN = VB - A)

RETENCIONES ( C ) FONDOS DEGARANTIA (5% X VB) GASTOS DELICITACION MULTA POR ATRASO DEOBRA TOTAL

14,385.78

MONTO A PAGAR AL CONTRATISTA EN EFECTIVO (VN-C) MONTO POR I.G.V. (VN x 0,18) MONTO TOTAL CON I.G.V. TOTAL COMPROMISO DEPAGO>>>>>>>>>>>>>>>>

14,385.78 2,589.44 16,975.22 S/16,975.22

SALDO POR % DEAVANCE VALORIZAR ACUMULADO (S/.)

24.20%

44,648.39

CUADRO RESUMEN DEVALORIZACION N° 01 DEL 01 AL 30 ....… DE……………. OBRA: SUP ER VISOR : C ON T R A T IST A : P R ESUP UEST O B A SE:

61,696.39

P R ESUP UEST O C ON T R A T A D O:

58,905.86

DESCRIPCIÓN

VALORIZACIÓN (V)

SIN IGV SIN IGV MONTO CONTRATAD O SIN IGV (S/.)

ANTERIOR (S/.)

ACTUAL (S/.)

58,905.86

14,257.47

13,723.09

27,980.56

128.32

212.18

340.50

VALORIZACION ACUMULADO (S/.)

TOTAL CONTRACTUAL Avances en porcentaje REAJUSTES (R) DEDUCCIONES (D) POR ADELANTO EN EFECTIVO POR ADELANTO PARA MATERIALES TOTAL DEDUCCION ES VALORIZACIÓN BRUTA (VB = V + R - D)

13,935.27

AMORTIZACIONES (A) AMORTIZACION DEL ADELANTO EN EFECTIVO AMORTIZACION DEL ADELANTO PARA MATERIALES TOTAL AMORTIZACIONES (A) VALORIZACIÓN NETA (VN = VB - A)

RETENCIONES ( C ) FONDOS DEGARANTIA (5% X VB) GASTOS DELICITACION MULTA POR ATRASO DEOBRA TOTAL

13,935.27

MONTO A PAGAR AL CONTRATISTA EN EFECTIVO (VN-C) MONTO POR I.G.V. (VN x 0,18) MONTO TOTAL CON I.G.V. TOTAL COMPROMISO DEPAGO>>>>>>>>>>>>>>>>

13,935.27 2,508.35 16,443.62 S/16,443.62

SALDO POR % DEAVANCE VALORIZAR ACUMULADO (S/.)

47.50%

30,925.30

CUADRO RESUMEN DEVALORIZACION N° 01 DEL 01 AL 30 ....… DE……………. OBRA: SUP ER VISOR : C ON T R A T IST A : P R ESUP UEST O B A SE:

61,696.39

P R ESUP UEST O C ON T R A T A D O:

58,905.86

DESCRIPCIÓN

VALORIZACIÓN (V)

SIN IGV SIN IGV MONTO CONTRATAD O SIN IGV (S/.)

ANTERIOR (S/.)

ACTUAL (S/.)

58,905.86

27,980.56

30,925.31

340.50

321.65

VALORIZACION

TOTAL CONTRACTUAL Avances en porcentaje REAJUSTES (R) DEDUCCIONES (D) POR ADELANTO EN EFECTIVO POR ADELANTO PARA MATERIALES TOTAL DEDUCCION ES VALORIZACIÓN BRUTA (VB = V + R - D)

31,246.96

AMORTIZACIONES (A) AMORTIZACION DEL ADELANTO EN EFECTIVO AMORTIZACION DEL ADELANTO PARA MATERIALES TOTAL AMORTIZACIONES (A) VALORIZACIÓN NETA (VN = VB - A)

RETENCIONES ( C ) FONDOS DEGARANTIA (5% X VB) GASTOS DELICITACION MULTA POR ATRASO DEOBRA TOTAL

31,246.96

MONTO A PAGAR AL CONTRATISTA EN EFECTIVO (VN-C) MONTO POR I.G.V. (VN x 0,18) MONTO TOTAL CON I.G.V. TOTAL COMPROMISO DEPAGO>>>>>>>>>>>>>>>>

31,246.96 5,624.45 36,871.41 S/36,871.41

CION N° 01

ALORIZACION

SALDO POR % DEAVANCE ACUMULADO ACUMULADO VALORIZAR (S/.) (S/.)

0.00

662.14

100.00%

0.00

/36,871.41

N° 1 2 3 4

1 MAYO 14,257.47 14,257.47 11405.9727

2 3 JUNIO JULIO 27,980.56 58,905.86 27,980.56 58,905.86 22384.448 47124.6879

70000 60000 50000 40000 30000 20000

14,2 114

10000 0

3.00 4 1 N°

MAYO 1

70000 60000

58,905.86

50000

47124.6879147

40000 30000

27,980.56 22384.4480083346

20000

14,257.47 11405.97267008

10000 0

3.00 4 1 N°

MAYO 1

JUNIO 2

JULIO 3

Row 4 Row 5 Row 6

Related Documents


More Documents from "jackon"