TRACTOR MONTADO SOBRE ORUGAS Tramo 1 Longitud a cortar = 250 m Costo total tramo 1=588556893.90 Bs. Longitud tramo = 42.763 km = 42763 m. Costo tramo a cortar: 588556893.90 =2354227.575 Bs . 250 Costo neto (CN)= 2354227.575 Bs . Vida útil (n)= 13 años uso por año = 260 dias gastos generales = 6 % utilidad (U) = 8 % Efieciencia = 80 % Porcentaje de esponjamiento (sw) = 8.45% Tiempo del ciclo=3.019 min. ISI=13% Reparacion y mantenimiento=5% R=16.939 Volumen de excavacion = 269176.36 m3 Calculo de la capacidad de tractor: capacidad tractor Q= 1+ Sw

(

capacidad tractor =Q∗( 1+ Sw )=1.065∗ 1+

8.45 =1.155 m3 100

)

Tiempo de excavacion: Vexc . 269176.36 T exc = = =15890.924 Hr . R 16.939 Costo total de operación: Costo de entrega CIF: CIF=? Valor residual VR=10 ∗CIF=0.10∗CIF Costo neto CN =CIF−VR=CIF−0.10∗CIF=0.90 CN 2354227.575 CIF= = =2615808.416 Bs . 0.90 0.90 DEPRECIACION: CN 2354227.575 D= = =181094.428 Bs . n 13 VALOR PROMEDIO: CIF∗( 1+n ) 2615808.416∗( 1+13 ) VP= = =402432.064 Bs . 2∗n 2∗13 INTERESES SEGUROS E IMPUESTOS:

ISI=0.13∗402432.064=52316.168 Bs

REPARACION Y MANTENIMIENTO: RM =0.05∗81094.428 Bs=4054.721 Bs COSTO FIJO: Cf =181094.428+52316.168+4054.721=190385.317

Bs Bs =91.531 . Año Hr

COSTO VARIABLE CV =0 COSTO OPERACIÓN: CHO=91.531+ 0=91.531

Bs Hr

GASTOS GENERALES: Bs ¿=0.06∗91.531=5.491 Hr UTILIDAD: U=0.08∗91.531=7.322

Bs Hr

COSTO TOTAL DE OPERACIÓN: CTO=91.531+5.491+7.322=104.345

Bs Hr

COSTO DE EXCAVACION: Cost de excav .=104.345∗15890.924=1658130.201 Bs .

Related Documents

Tractor
November 2019 20
Tractor
April 2020 10
Costo
November 2019 50
Costo
August 2019 44

More Documents from ""

Doc1.docx
November 2019 23
November 2019 16
Maqui 6.pdf
November 2019 18