TECHNICAL PROPOSAL

GUTTER CLEANING

CLIENT:

PREPARED BY:

Industrial Cleaning Services Public Company Limited

99/9 Moo 5 T. Mapkha A. Nikhompattana Rayong 21180 Thailand Mobile 0915455063 Tel +66-38-601029 Fax +66-38-601030

Ref. No. :

TECHNICAL PROPOSAL

Issued Date: 10/04/2014 Rev.

Industrial Cleaning Services Public Company Limited

00

1. OVERVIEW This procedure is to clearly define the scope of work, the sequence of activities, and safety considerations associated with the cleaning activities. We propose to use the process specially designed for the petroleum and petrochemical industry. This cleaning service will utilize a technology and special machine that guarantee for the most efficient, effective, and environment friendly method of cleaning.

2. WORKING PROCEDURE 2.1. Preparation 2.1.1 Prepare work permit before working 2.1.2 Make sure all the worker and operator have already underwent safety training following client’s policy. 2.1.3 Mobilization of equipment to working area. 2.1.4 Prepare vacuum truck stand by at the sump pit 2.2.1 Prepare PPE set, worker should wear appropriate protection suit, face shield, and safety boot

2.2. Cleaning Procedure 2.2.2 Place the suction hose to the sucking point. The worker (wearing chemical protection suit) control the suction of vacuum hose 2.2.3 Suck the waste in the sump pit by vacuum truck 2.2.4 If vacuum truck full, drain the waste to designated area 2.2.5 Repeat the step for each line until job finish

FP-09-02 Rev.00 Eff. Date 01/08/2013

Page: 1

Ref. No. :

TECHNICAL PROPOSAL

Rev.

Industrial Cleaning Services Public Company Limited

3.

ITEM

Item 1 2 5 6 7

00

EQUIPMENT LOADING DECRIPTION

MAIN EQUIPMENT Vacuum truck 9 m3 Suction hose set SUPPORTING EQUIPMENT Fire extinguisher CONSUMABLES: Chemical protection suit (microguard 3000)

4.

Issued Date: 10/04/2014

Q'TY

UNIT

1 1

Unit Set

2

Ea

4

ea

REMARK

MANPOWER LOADING Description Foreman Safety Officer Vacuum truck operator helper Document control TOTAL

UNDERGROUND PIPE CEANING 1 1 1 4 1 12

FP-09-02 Rev.00 Eff. Date 01/08/2013

Page: 2

Related Documents

Gutter
October 2019 20
Technical Proposal
June 2020 7
Technical Proposal-v8
November 2019 9
Orleans Gutter
June 2020 7

More Documents from "WeDpro, Inc."