Software Project Management By Numbers

  • April 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Software Project Management By Numbers as PDF for free.

More details

  • Words: 6,344
  • Pages: 63
1

This presentation deals with 6 topics: 1. We start with a description of today„s software industry, using a metaphor. 2. We then summarize valuable empirical information that is hardly known and seldomly used. I hope you are one of the users. 3. After this, a best practice set of 16 Key Performance Indicators is introduced that we use to analyse and benchmark software capability. 4. We then show the results of 2 out of many case studies, showing the powerfullness of this set, at least that is the experience so far of our customers. 5. We end the presentation with conclusions. 6. Finally, we take the liberty to present a new non-profit organization to you, that focusses on further exploring and exploiting the KPI set.

2

When I started my career in software engineering in the early eighties (yes, I am that young), I started with designing and programming as a freelancer, working for many companies in the embedded software industry. After more than 10 years, I became more and more interested in reasons for project failures as this was a common, returning factor in all assignments: too late, over-budget and many pre- and postrelease defects. I switched to quality engineering, started to define and implement quality systems (using ISO 9001) and became involved in an SPI program within Philips, where they introduced the SW-CMM in the early nineties. The SW-CMM was the first eye-opener to me, and in my opinion much better than ISO standards. Whereas earlier many manager explained to colleagues how good their own performance was, now everybody smiled to each others, saying: „Yes, I am at level 1 as well!“. So, the SW-CMM became my thing, and after a few years, I founded a consulting and training company. We grew in 4 years to 25 consultants/trainers and served many organizations in- and outside The Netherlands. However, in those years, we had little real successes and became frustrated seeing many software manufacturers go for level-hunting only. We observed, that they didn„t know their real capability other than being a typical Level 1 organization, adopting the SW-CMM as the reference model for improvement and defining as next year„s target Level 2. And we are afraid, this is still true today for many organizations. I think you will agree to this, although there are good examples as well. This presentation addresses how to measure real capability and to use the results as a baseline for defining improvements that make sense and are measurable.

3

In our current assignments, we still see the majority of software projects being steered at the scheduled deadline, the available budget and removing major defects prior to releasing. And to put it bluntly, this is often irrespective of CMMI levels as we shall see later. Focussing on these metrics only is very dangerous. It ignores three important dimensions: 1. What is the scope of the product being built? 2. What is the current and future quality of the product being built? 3. How efficient is the process applied for building the product? Let us illustrate this with a metaphor.

4

This slide as well as the 2 next slides are from one of our workshops. We start this workshop by asking people how fit this biker is. As you can see, the biker needs more than 2 hours to cover a distance of 32 km or 20 miles. This is actually my Sunday morning trip. The typical reaction of workshop participants is that the average speed is approximately 14 km/hour or 9 miles/hour, so that I am probably not that fit. Are they correct? Well, we need some additional information to draw a conclusion here. Analyzing distance and schedule only is a bit naive as we shall see.

5

Here you see some additional information regarding the bike tour. As you can probably see, the area where I live is not that flat. I live in a remote village, high in the Swiss Alps at the end of a valley, somewhere between Berne and Geneva. As a consequence, I am not driving a bicycle as Lance Armstrong, mine is a mountain bike and part of the tour is on an unpaved road. I have been driving this tour for years, and up till 2008, I had a very simple approach. Take two bottles of water and 2 bananas, start biking, try to go as fast as possible and never stop. If I had to make a stop, being out of breath, my Sunday was ruined. If it took me more time than average, the same ... Well, sometimes I was successful, but my performance over all those years never really changed. Worse, growing older, I more and more often had a ruined Sunday ... Let us have a further look into some additional information.

6

Early 2008, I bought a nice GPS, including a cadence and heart rate sensor, in addition to me speedometer. I started to record more data, and here we see 3 additional sources of information: 1. The elevation ranges from apprixomately 1„000 meters to 1„650 meters, with a total elevation of 1„100 meters or 3„300 feet. At certain slopes, elevation is between 14% and 16%. 2. Heart frequency ranges from 70 BPM to 160 BPM, going up when climbing. During the last climb, heart fequency is still in control. 3. Cadence, being the number of wheel rotations per minute, is relatively constant, from the beginning till the end of the tour. The figures presented here are of summer 2009, and very different from when I started recording data. In 2008, heart frequency often was up to 180 BPM, in which case I had to pause. Cadence towards the end of the tour slowed down, being extremely tired. The only positive thing was that I burned a lot of calories ... So, having adopted this multi-perspective view has brought me a lot. When I am driving now, I monitor my heart frequency to stay below 160 BPM and that makes the big difference. I normally end the tour without stopping and in addition: I can better predict the schedule, I go faster, I burn less calories and I arrive relatively fresh. So, let us revisit the original question: am I fit? Yes, I am very fit, although this cold winter has prevented me for undertaking tours since December ... We„ll see in April, when the snow is gone ...

7

Unfortunately, many managers today feel naked when it comes to decisionmaking as they lack useful information . Examples of typical questions faced: 1. Is this project plan realistic? Answser: well, this new project manager seems very experienced ... 2. Are we still on track? Answer: well, we entered the coding phase according to schedule, so probably yes ... 3. When can we stop testing? Answer: well, let us remove the most critical defects found and hope for the best ... 4. How much effort should be reserved for maintenance support? Answer: well, let us take last year„s budget, multiplied by 2 ... And we base our hopes on adopting standards and models, that everyone else seems to be adopting as well. The biking metaphor clearly demonstrates that improving performance needs measurement. I hope you agree to this.

8

So, maturing the software discipline to an engineering discipline is not about satisfying models and/or standards. Improving without baselining your current performance and setting realistic and measurable targets makes very limited sense. You want to become more predictable regarding your performance, faster by working more efficiently, more effective by reducing the scope of your effort to what is needed and deliver better output regarding current and future quality. Well, you might say, interesting, but as a level 1 organisation I first have to define and implement processes before I can collect and analyze any useful data. In our experience, this is not true. First, the software industry has collected and analyzed already a lot of empirical data for you. In the second place, it is our experience that in every organisation, irrespective of maturity levels, many sources with useful data can be found.

9

Those software manufacturers organizations that are successul, have some characteristics in common: 1. They know what their capability is, not only in terms of compliance to standfards like ISO and/or models like CMMI. 2. Estimates are not underpinned and any changes to assumptions made will be analyzed, including the impact on the estimates. 3. Projects are actively tracked, hereby understanding that estimates are not predictions. Not only schedule and effort are monitored, but also the distribution of effort across activities, the scope of the project assignment and the intermediate product quality. 4. New initiatives are not automatically adopted. Instead, their expected effects on known capability is assessed first and carefully piloted. And in all this areas, quantitative data is transformed to information, enabling organizations to make informed decisions. Let us now discuss some examples of empirical insigths and data.

10

I would like to share with you some empiricial models, that we often use in our assignments, some empirical laws that everyone should know and some benchmarking data, hereby referring to the work of Capers Jones. It is our experience that what we shall summarize here, is hardly known and seldomly used. This is not to criticize, it is a unfortunately fact.

11

The two, most widely adopted empirical models are probably COCOMO II from Barry Boehm (University of Southern California) and the Putnam Slim Model from Larry Putnam (QSM). For both models, supporting tooling is available on the market. These models allow organizations to make estimates for schedule and effort and take estimated feature size and factors that influence capability or productivity as inputs. Using such models requires experience and calibration. Experience is gained over time, by using such models, which can sometimes be accelerated by hiring external consultants. Calibration is best performed by using the models the other way around. From past projects, schedule, effort and size can be collected, that allows for determination of capability/productivity factors. Other models are available as well, and yes, using models in parallel will not always bring converging estimates. On the other hand, experience and calibration makes these models very powerful, and we recommend our customers to learn about them and use at least one to underpin project estimates.

12

Nearly all available models have in common that they allow for a trade-off between schedule and effort. In software engineering, there is non-linear relationship between those two, and accelerating schedule has a high penalty on effort as we see here. One of the main reasons is that schedule acceleration will require more people working in parallel, which requires more communication and leads to more miscommunication. Vice versa, reducing effort will have a penalty on schedule. Further, most models distinguish an impossible region and an impractical region. The impossible region is the region where everybody should stay away from. It is the region where schedule is accelerated approximately 25% or more compared to the nominal schedule, based on current capability, and history has neraly never revealed projects being capable in doing that. The impractical region is the region in which the limited project crew will normally not be capable of dealing with all issues. The relationships depicted here between fastest schedule, nominal schedule/effort and lowest effort are general approximations and will differ in individual organizations. Main message is that there is trade-off and especially an impossible region where one should stay away from.

13

The second eye-opener in my career was when I read the book “Measures for Excellence” from Putnam and Myers. This book or related books should be on the shelf of every software manager and introduces two equations: 1. Putnam used some empirical observations about productivity levels to derive the so-called software equation from a Rayleigh distribution. The software equation includes a fourth power and therefore has strong implications for resource allocation on large projects. Relatively small extensions in delivery date can result in substantial reductions in effort. We see this equation depicted here, its distance to the origin determined by size and productivity. 2. To allow effort estimation, Putnam introduced the so-called manpower-buildup equation and is also depicted. Simplified, this equation tells us how fast people can be effectively allocated to a project team. We call this the staffing rate and use it later. Regard it as a measure for the slope in an earned value chart

Using nominal values for a project and its environmental characteristics, the nominal development time is where the two equations intersect. It now becomes obvious that accelerating schedule requires developing less size and/or becoming more productive and/or increase staffing rate, as illustrated in this graph. Lowering size and increasing productivity only, will allow for effort reduction and schedule acceleration. Very powerful instruments to reason with software managers about capability and trade-offs.

14

Another well-respected person in the software industry is without doubt Capers Jones. He is a leading author and speaker on software productivity and measurement. Although retired, he is still very active, at the same supportive in helping other people. Many of his books can be recommended, one of the latest ones being “Applied Software Measurement”. In this book, benchmarking data can be found for different metrics, dependent on industry segment and product size expressed in function points. A summary is presented here. We see for instance in the upper left corner that the average schedule for a Management Information System (MIS) of small size (100 function points) is 6 months, whereas the best-in-class reported schedule is 4.5 months. Other metrics are effort, productivity, removal efficiency and defect density. Such benchmarking data are considered very powerful as it helps to baseline an organization‟s capability with external industry data. Unfortunately, most managers have no clue how they perform in relation to industry. Even worse, the question “How much does one function point for new applications cost you?” remains unanswered.

15

Available benchmarking data can also be used for something else as we shall see later. First, let us examine a Cost-of-Quality model as displayed here. Distinction is made between four categories: 1. Core. Costs in this category are essential and bring direct value to a customer by changing the product in some way: requirements, architecture, coding. 2. Support. Costs in this category are essential but do not bring direct value to a customer: project management, configuration management, administrative support. 3. Prevention. These are costs incurred to prevent (keep failure and appraisal cost to a minimum) poor quality: quality planning, process improvement teams, reviews, inspections. 4. Appraisal, rework. These are costs incurred to determine the degree of conformance to quality requirements: mainly testing and defect detection/removal. Using these definitions, it will be obvious that improving efficiency will normally mean reducing the overall costs by avoiding or reducing appraisal and rework costs generated at the right. This can for instance be done by increasing prevention costs.

16

We use these categories to derive another reference for benchmarking. By mapping available effort ratios for different project activities to these four categories, we find the distribution over these four categories as displayed here. In this example, using average project data from Capers Jones („Applied Software Measurement“), we see for instance that the average Prevention ratio when developing Management Information Systems equals 2.0%. Interestingly, the ratios per industry segment are not very different from each other. We are still investigating the explanation for this. In our own study environments, we complement the ratios here with our own data.

17

This Cost-of-Quality approach is very simple, however not many organisations are aware of its existence, although it has been published fro sofwtare engineering in similar forms since many decades. It is very easy to implement and to use. Take a project plan, map the effort of all scheduled activities to the four categories and you have your ratios. Again, it is a very powerful instrument that enables you for instance to validate the feasibility of a project plan. If the projected ratio for the Appraisal/Rework ratio is 10% or lower, there should be a good explanation for this! In addition, by analysing project from the past, it is relatively easy to find out your own ratios as an internal reference. When we present this model during our work, managers normally become very enthusiastic and many of them start using it. Templates for project plans and reporting are adjusted accordingly and control is substantially increased, if the project managers have the discipline in updating their plans regularly and accurately.

18

So far for available empirical information, we shall now continue with definining a set of best practice Key Performance Indicators that help organiaztions to measure the immeasurable: their own capabiity. Worth mentioning here is that measuring is of course not new to software engineering. Many metrics have been proposed and many experimented with. However, these metrics are often at engineering level and can often not be transferred to meaningful management information: it is simply the wrong data, and either too much or too little. When someone proposes a metric, always ask the question „Why this metric, for what purpose?“ and „Suppose its value is X, Would this be good or bad? And compared to what?“

19

For the remainder of this presentation we shall make a distinction between Key Performance Indicators (KPIs) related to meaningful management information on one hand and metrics related to process/product attribute data at a lower detail level on the other hand. A set of KPIs will normally be derived from business objectives, metrics will on their turn be derived from those KPIs. The Goal-Question-Metric approach (from Victor Basili) might be used here, or the refined Goal-Question-Indicator-Metric approach from the Software Engineering Institute. In summary, KPIs are to inform management, related metrics reside at a lower detail level.

20

We shall direct in this presentation to a set of what we consider best practice KPIs, e.g., KPIs that can often be found in software manufacturer organizations. However, the set presented is not just the collection of what is being used, the KPIs have been carefully selected. Different selection criteria were applied as shown here. Ideally, each KPI should be of value to project management, software management, business unit management and corporate management. In other words, they should support short-term development and maintenance efforts as well as mid-term and long-term trends. Is this possible? Let us first see what is needed on project level.

21

Typical questions to answer during product development and maintenance are shown here. Distinction is made between four categories: 1. Project performance: What is the prediction of the performance of the project? Classical questions in this category are: will the project meet its schedule and budget? 2. Process efficiency: How efficient is the development process? Remember the earlier discussed Cost-of-Quality model: how are project activities divided among categories? 3. Product scope: How large and stable is the scope of the planned effort in terms of features and implementation size? Increased feature size may indicate scope creep, where increase of implementation size might have hardware penalties. 4. Product quality: What is the expected quality of the resulting product? Although many quality attributes can be important, dominating common ones are reliability as an indicator for current product quality and maintainability as an indicator for future product quality.

22

Here we see a further decomposition of these categories, for each of them 4 KPIs are listed. 1. Project performance: besides schedule and budget (or cost), we also define staffing rate (remember the manpower-buildup equation of Putnam) and productivity. Note that we prefer to express productivity in function points per time unit, not in LOC per time unit. 2. Process efficiency: How efficient is the development process? Yes, we use the four categories as KPIs here as defined in our earlier discussed Cost-ofQuality model. 3. Product scope: How large and stable is the scope of the planned effort in terms of features and implementation size? In addition to feature size, we also define deferral rate (ratio of features delayed to future releases) and re-use as KPIs. Deferral rate is an important indicator to see how well we can meet the agreed scope, whereas re-use tells us how much available code can be used in the new product. 4. Product quality: What is the expected quality of the resulting product? Here, we define four KPIs that are related to reliability and maintainability. High complexity at architectural level and/or code level is bad for maintainability. It also negatively influences the other 3 KPIs (test coverage, removal efficiency and defect density), that are related to reliability.

23

In summary, we now have four KPI categories with each four KPIs. Normally, everybody agrees that these KPIs make sense at project management level as well as management level. They support project management in analysing, planning and monitoring projects. At the same time, they inform management where a project stands and in what direction it is heading. But do they also support business units in measuring their capability improvement over time and organisations in comparing/benchmarking business units? Let us see.

24

Here, the typical effects on all sixteen KPIs are shown as maturity or capability increases. 1. Project performance. Schedule and budget (cost, effort) will be reduced, whereas staffing rate and productivity will increase. 2. Process efficiency. By investing in prevention, appraisal/rework will decrease dramatically, have a positive effect on the ratios for core and support activities. 3. Product scope. Feature size will be brough back to what is really needed, less features will be deferred to next releases. As a consequence, implementation size will drop. Normally, the re-use level will go up. 4. Product quality. By reducing complexity at architectural and/or code level, significant gains will be obtained as through higher test coverage, the removal efficiency will increase and therefore defect density will decrease.

25

So what do we have so far? 1. We have demonstrated that assessing real capability requires a multidimensional view. Remember the biking metaphor! Only by measuring more than just a few things, you get a basis for real and focussed improvements. 2. There is nothing wrong with standards and models, they will help as well. However, compliance to them is no guarantee for capability improvements. 3. The sixteen KPIs not only help project managers and their direct superiors, but also allow for measuring trends over time. After this long introduction, I am sorry for this, we can now have a look at some results from case studies we performed.

26

We shall present here the case study results of two different organizations, obtained through the application of the discussed best practice KPI set.

Both organizations develop embedded systems and deliver them to other businesses. Although the systems are not consumer products, volumes are not low and vary from hundreds to many thousands. One system is considered safety critical, the other system is complicated due to regulations in the area of security of information, that may not be manipulated in any way. In early discussions with both organisations, it was revealed that process improvement is institutionalized since many years and that CMMI L3 compliance is within reach.

27

In both cases, we knew we had to deal with some common issues: 1. So far, we have not identified strong benchmarking data for deferral rates and re-use levels. We are building our own database for this, feeding it with our own study data. 2. The same holds for benchmarking data regarding test coverage and complexity. Although we had a good idea ourselves what should be strived for, solid reference data has not been identified so far. 3. Finally, a common issue in embedded systems is the way feature size is calculated. Although we prefer function points, the only data available was lines of code. We used the backfiring technique to convert lines of code to function points. In both cases the programming language used was C, the resulting number of function points was close to 1„000 in both cases. Having said this, we can now have a look at a summary of the results.

28

Here we see how both case studies compare to benchmarking data regarding schedule in calendar months. A bit higher than industry average, which might be a consequence of safety requirements for case study A and security requirements for case study B. From the graph, we conclude that there are no big surprises here.

29

Here we see how both case studies compare to benchmarking data regarding effort in staff months. We see that both cases reveal much higher effort than industry average, which might again be a consequence of safety requirements for case study A and security requirements for case study B. From this graph, we conclude that there are still no real big surprises here, although we already know that this will also result in lower productivity levels.

30

Here we see how both case studies compare to benchmarking data regarding staffing rate. Again, staffing rate is a measure for how fast people can effectively be allocated to a project team. Regard it as a measure for the slope of your earned value or S-curve. We will avoid here explaining the formulae used. From the graph, we conclude that staffing rate is only a bit higher than industry average, so the staffing profiles reveal nothing special.

31

Here we see how both case studies compare to benchmarking data regarding productivity in function points per staff month. We see that both cases reveal a much lower productivity level than industry average, which we concluded already earlier when discussing effort levels.

32

Now, things are getting more interesting. Here we see how both case studies compare to average effort distribution, using the Cost-of-Quality model. We see in both cases a ratio for Appraisal/rework of approximately 50%, which is very high. One might argue that this again is a consequence of safety requirements for case study A and security requirements for case study B. However, in that case we would have expected much higher ratios for Prevention. Presenting these results to both organizations was received with a shock. Remember how easy these ratios can be calculated, also remember that these organizations have a rich history in process improvement. It was in both cases a major eye-opener to them with consequences.

33

Finally, we present some benchmarking results regarding defect density and removal efficiency. To explain how they are calculated, look at the example presented here. The removal efficiency can only be calculated post-release time, based on the defects discovered during development and a certain time after havign the sofwtare released. It is the percentage of defects found before the software is released to its intended users. Defect density is calculated as the number of defects found post-release related to the feature size (preferably in function points). As said, in embedded system environments feature size is often backfired from the implementation size in lines of code, which is not the best approach.

34

Now, things are getting even more interesting. Here we see how both case studies compare to benchmarking data regarding defect density in defects per 1„000 line of code. For software with safety requirements and security requirements one might expect have have better figures than industry average, the contrary is the case here. The answer of management in both cases was that after releasing the software, many additional tests took place and delivery was to a limited number of users only. In other words, the defect density that finally reached the end-user was less high. On the other hand, they acknowledged that postrelease maintenance and support costs were extremely high and should be reduced.

35

And, as we would have expected, the high defect density find its origin in the low removal efficiency: too many defects remain uncovered during development and are detected post-release time.

36

What we have not discussed so far, is the quality of the software itself. During our studies, we normally perform in in-depth analysis of the source code itself to assess the quality of the architecture and the source code. The important KPI we focus on is complexity. This is an indicator how well a project team can perform its development and maintenance tasks. As such, it also influences the quality of the software product as experienced by the end-user. Higher complexity will normally lead to lower test coverage, higher defect densities and thus, higher running costs. But how can complexity be measured? Is it the famous cyclomatic complexity measure of McCabe or is it more? Let us see …

37

In our definition of complexity, we take a much broader view than cyclomatic complexity at source code level. We use an aggregated measure the combines complexity seen from three different perspectives: 1. Understandability. Here we look at dependencies at different levels and compute the fan-out and cyclomatic complexity as an indicator. 2. Modifiability. Here we look at the number of places that require attention upon modification and compute both change propagation and code duplication as an indicator. 3. Verifiability. Here we look the number of required tests and requires test time and compute with automated tooling the fan-out and cyclomatic complexity as an indicator. Let us look at some examples.

38

Here, we see the results of an automated analysis at source code level. The source code is divided into rectangles, each presenting part of the source code. The size of each rectangle corresponds to the number of files. Each rectangle is sorted from the upper left corner to the right corner below, based on change frequency. A black area indicates no changes, a blue area indicates changes over the time frame selected. Within each blue sub area, on the lower right corner, the files are listed with high change frequency and high cyclomatic complexity. This helps teams to quickly identify not only which parts of their code is complex, but also in those areas that are frequently changed. These areas are bad for understandability and verifiability. Refer to www.solidsourceit.com for the tools used here.

39

Here, we see growth of a software application over time, each file represeneted by a horizontal line. In addition, it has been derived when changes are made to the files (red spots). We see here that in several situations, when new functionality was implemented (growth), many changes propagated over many files. This indicates a low level of functional cohesion, which is bad for modifiability. Refer to www.solidsourceit.com for the tools used here.

40

Finally, we show an example of code duplication, which is also bad for modifiability. At the right top corner, you see duplication between modules or packages. When there would be duplication, the inner circle would be empty. In this case, there is approximately 17% code duplication, which we often found in our studies. This is actually very bad, as it undermines quality and productivity. Note that the tooling used here, allows to select an area of code duplication and in the right top and see the duplication itself at the lft bottom window at code level in the two related files. Refer to www.solidsourceit.com for the tools used here. All analysis shown here, are included in our studies and results are included in the debriefing sessions.

41

Okay, back to our case studies. In both cases, is was very clear to all stakeholders that there are two main weak areas: 1. The effort distribution revealed a very insufficient process, with a high ratio for Appriasal/rework. If post-release efforts for fixing defects would be included, the ratio would even become higher! 2. The code quality in both cases was low: many areas with high cyclimatic complexity were found, a high level of code duplication and a high level of change propagation. As a result, problems arise regarding understandability, modifiability and verifiability.

These two areas were considered the primary causes for low overall capability and were used as the basis to define improvements as we shall present now.

42

No surprise of course ... Appraisal and rework efforts can potentially be dramatically reduced by smartly investing into prevention. In this case, it was recommended to introduce architecture evaluations as well as active design reviews. Secondly, it was decided to re-inforce inspections for critical modules. The expected effects are clear. Less defects before coding and testing will positively influence removal efficiency and defect density, lead to lower appraisal and rework costs and finally lead to a faster schedule, lower effort and higher productivity.

43

No surprise here as well of course ... Problems in the area of understandability, modifiability and verifiability are a direct result of low code quality. In this case, tooling was connected to the configuration management system to support engineers and managers to monitor the code quality and implement improvements for identified critical code parts. The expected effects are clear. By reducing, eliminating and even avoiding such problems, test coverage will for instance increase. Further, we see the same pattern. Higher test coverage will positively influence removal efficiency and defect density, lead to lower apprasial and rework costs and finally lead to a faster schedule, lower effort and higher productivity. The good things is that after such a study, everybody agree on what is weak and in which areas improvements should be sought. In addition, the availability of quantitative data allows for developing a solid business case. That is different than stating „We want to be at level X by the end of next year“!

44

The conclusion that investing in process improvement is a waste of money would be wrong. Process improvement makes sense, as it standardizes development processes. This creates transparency with respect to roles, responsibilities, activities and deliverables. However, standardization is no guarantee for real performance improvements. That is why aiming at higher CMMI levels only is a wrong approach. The recommendation is to focus on a multi-dimensional assessment of the performance of an organization and derive improvements that make sense. A first step will be baselining the current performance using the best practice KPI set. In case measurements are not place, the first improvement actions are identified. As a second step, realistic target values must be determined for a given period of time. The gap between target and actual values is the basis for deriving improvement steps. It is hereby essential that the expected direction of each indicator is known. If changes in the right directions can be achieved, then a performance improvement is guaranteed. In addition, the positive effects are likely to show up in each category. This reduces or even eliminates the chances of sub optimization.

45

Process improvement and standardization should not be a goal in itself. Real performance improvement is achieved by taking a quantitative view on processes and products, and setting realistic and quantified improvement targets. This brings us to an important overall conclusion. The interesting fact is that improvements can only be achieved by changing the way of working. And of course, a validated improved way of working should be shared: considering standardization across projects becomes a natural process. Therefore, improving capability along a quantitative axis can perfectly combined with other improvement initiatives like CMMI. Educating an organization in collecting, analyzing and using data will automatically set requirements for processes to be used. The difference is: now we know why and what we hope to get as a result.

46

Time for another maturity model ...? No ... This model only shows what we should expect in the area of measurement when maturing through the commonly known CMMI stages. From a situation where measurements do not exist or only on an ad hoc basis, we should strive for a level where performance or capability is further optimized using KPIs. Whether these KPIs match the best practice KPI set as presented here is not improtant. You may start with this set and find out along the way that you need other as well. Feel free!

47

Finally, I would take the liberty to shortly introduce to you a new non-profit organization that was founded last year. The benchmarking studies as described here, related workshops and supporting tooling of which you have seen some examples were brought under one umbrella in the Software Benchmarking Organization. The resulting portfolio is brought to the market through a netwework of accredited partners. You can read more about this organization on the website to which the link is showed here.

48

Founding partners of SBO are SE-CURE AG, the company currently presenting to you, and SolidSource BV, from which you have seen some product examples.

49

There is probably no need to discuss in detail what the objectives of SBO are. In summary, we want to repeat many studies as we presented to you today. And yes, we consider ourselves a non-profit organization. Any profits remaining from our activities will be re-invested in maturing and extending the portfolio. There is still a lot of work to do!

50

You could help us, not only by contacting us to conduct a benchmarking study or to organize a workshop. If you are offering services yourself, we could discuss the possibility to involve you as a partner. It won‟t make you rich, but the work is exciting and very useful (at least, we think …). Finally, I would to share with you the comments of two of our clients. Both clients were not involved in the case studies presented here.

51

Let this slide speak for itself. Note: this reference was not one of the case studies discussed here.

52

Let this slide speak for itself. Note: this reference was not one of the case studies discussed here.

53

As said, the Software Benchmarking Organization has been founded to support the industry, not for us trying to become easily rich. We are available talking to you, exploring how we can help the software industry to the next level, a bit closer to a real engineering discipline. Please feel free contacting us. This brings me to the end of this presentation. Let me thank you for your time and patience! Dr. Hans Sassenburg

54

55

56

57

58

59

60

61

62

63