IADC/SPE IADC/SPE 17256 A Shallow Gas Research Program by M. Grin rod,* 0. Haaland,* and B. Ellingsen, Statoil AJS * SPE Members
Copyright 1988, IADC/SPE Drilling Conference This paper was prepared for presentation at the 1988 IADC/SPE Drilling Conference held in Dallas, Texas, February 28-March 2, 1988. This paper was selected for presentation by an IADC/SPE Program
Introduction A SHALLOW GAS RESEARCH PROGRAM Up to the present (nov. 19&7) shallow gas has been reported in 155 of the 567 Abstract
exploration and appraisal wells drilled on
Operational problems associated with the
Seven blowouts and a number of kicks caused
occurence of shallow gas in offshore
by shallow gas have been recorded.
drilling led Statoil to initiate a massive
On the night of October 6th, 1985, a gas
research program. The program consisted of
blowout occured on the semi-submersible
the Norwegian Continental Shelf.
the following subprojects: Revised drilling
"West Vanguard", during exploration
procedures, shallow gas drainage,
drilling in block 6407/6, Haltenbanken,
multistage cementing, gas tight cement,
Norwegian sector.
diverter systems, rig ventilation systems
The well blew out from a shallow gas sand
and emergency anchor release.
while drilling ·the 311mm (12 1/4") pilot
Emphasis in this paper is placed on the
hole at 523m RKB, with the marine riser
experience from the West Vanguard blowout,
installed.
and results from the subprojects on
failed as a result of the extremely large
The diverter system and riser
diverter systems, drilling procedures,
flow of gas and solids.
quick anchor release and ventilation
The eroded flow diverter system and slip
systems.
joint packing leak allowed gas to flow into
Other papers (reference 1, 2) give
the drilling platform where the gas
information on development of gas tight
subsequently ignited.
cement, stage cementing and additional
The resulting explosion and fire caused
background on shallow gas drainage.
considerable damage. The platform was quickly evacuated. One person was lost. Damage to the rig amounted to several hundred million Norwegian kroner.
629
S~£17256
A SiiALI!M GAS RESEARCH PROGRAM
2
The investigation after the West Vanguard blowout disclosed that significant
Erosive wear test of Diverter System
improvements were needed in diverter
Compo]1ents
systems. It was further evident that riser-less drilling would be the best
The West Vanguard blowout clearly
option under certain conditions. Air
demonstrated the weakness of diverter
ventilation systems had an influence on gas
systems. Holes were worn in the diverter
distribution, and the fire and explosion
bends in a period of less than 20 minutes.
pattern. The drilling procedures needed to
The largest hole was located in the first
be updated, and rig crews educated on the
bend where the diverter line was tied to
dangers of shallow gas.
the flowline. At this point the sand had cut its way through other piping and into the shale shaker room.
Shallow Gas
The second bend in the
diverter line was also eroded. Gas sands at shallow depths have frequently
Based on these facts an experimental
been penetrated.
investigation has been performed to
These sands have been
encountered as shallow as lOOm below the
determine the most suitable geometry for
seabed.
diverter components, and the relative
Predicting the exact presence of
shallow gas sands from seismic or sparker
erosion and abrasion resistance
investigations is still unreliable, and
characteristics of selected materials.
their existence is often exclusively
The test philosophy was based on comparing
disclosed by MWD and/or wire line logs.
the various coatings as well as piping
Shallow gas is primarily localized in sand
geometry.
lenses surrounded by shale in the upper
different coating were placed in a test
tertiary sediments.
loop to obtain comparable test conditions.
Identical components with
Common mild steel was used as a reference
The gas pressure in these pockets is
material.
normally at or slightly above the normal
In the appendix the mathematical
water gradient. Since the thickness of the
theory behind these tests is discussed.
sand pockets are normally limited to a
In summary the test results were:
maximum·of lOrn, the actual over-pressure in Particle velocity is the most
excess of a hydrostatic water gradient, is
significant factor on erosive wear.
small.
Particle size has very little influence
Because of the low pressure regime, spontaneous kicks with the riser installed
on the value of specific erosion.
seldom occur.
Increase of bending diameter reduces
The risks of losing primary
control lies mainly in swabbing or when
the value of specific erosion.
lost circulation occurs.
Hardfacing extends the lifetime of
The West Vanguard blowout is assumed to be a consequence of loss of hydrostatic head
bends. Efforts should be made to design
caused by gas expansion in the riser.
diverter systems as straight as possible, avoiding bends.
630
sP6
M. GRINR(£?D
17256
A.(Z). HALAND
B. ELLINGSEN
3
Components and Bend Coating
significantly longer life than the short
The test programme included some 53
bending diameter of 0.83m had almost a 50%
radius bend.
The long radius bend with a
components. This comprised of 37 bends, 10
improvement in life span compared with the
hoses and 6 valves. In addition to the
short radius bend with a bending diameter of 0.26m.
reference steel bends tested, a total of five different bend surface coatings were
Bend Angle
examined for erosive wear resistance. Test Rig
It is difficult to isolate the influence of the bend angle since the tested bends had
The erosive wear test was carried out in a closed test loop
~here
different diameters. It would appear,
high abrasive silica
however, that the 60° bend tested with a
sand was recirculated.
One mobile diesel 3 compressor capable of delivering 0.7lm /s
bend, will last about 80 % longer than the
of free air at a pressure of 10 bar was
equivalent 90° bends.
diameter similar to the short radius 90°
used to accelerate the sand to a maximum velocity of lOOm/s.
Diverter Design
Comparison of surface coatings
During the erosive wear testing it became evident that the reinforcement of diverter
One of the hardfacing materials showed
components will not provide an acceptable
significantly better restistance to erosive
level of lifetime within economical or
wear than the other materials.
This
practical limits. The hardfacing material
hardfacing material contained 60 percent by
that performed best extended the life by
weight tungsten carbide bonding in an erosive-corosive resistant alloyd matrix.
about three and a half times compared with mild steel.
The amount of tungsten carbide is of great
Consequently every effort should be made in
importance.
designing a more satisfactory diverter
Tests also were performed with
65 percent by weight tungsten carbide and these showed even better results.
system. factor.
However
Geometry being the most important
cracking was more extensive than for the
Discontinuties in the diverter line must be
other materials.
thermal strain during the hardfacing
avoided; such as bends or changes in pipe diameter.
process, and can be improved by reducing
Where bends are unavoidable, these should
the hardness in the matrix.
be hardfaced.
This is due to the
The tests have proved the
importance of material selection. The other hardfacing materials tested were not significantly better than plain steel.
In addition the straight section following a discountinuity should be hardfaced at a
Bend Diameter
length of approx. 1,5 mas this section will be exposed to heavy turbulent flow and
Since two 90° bends with different
erosive wear.
diameters were tested, the analysis
Diverter valves should be located before,
provided a direct comparison of the
or at a sufficient distance from any
influence of bend diameter. The results
discontinuty.
showed that the long radius bend had a 631
SPe
A SHALLOW GAS RESEARCH PROORAM
4
Where flanges are used, these should be
17256
The potential fire hazard from an
machined and matched to ensure that the
underwater release of shallow gas was
inside surface is perfectly smooth and free
investigated.
from steps and ridges. The testing proved that the most important
At the West Vanguard blowout the fire on
parameter effecting erosive wear is the
the ocean surface had a diameter of
particle velocity, and this parameter can
approximately 60 meters. The waterdepth was
be controlled by mounting a choke at the
220 meters giving a central gas zone of
ends of the diverter lines. On jackups and
some 35% of the water depth.
fixed platforms where the diverter system
Based on the experience from the actual
in most cases is the only protection if gas
blowout, theoretical simulations were
flow occurs, it is of great importance to
performed to investigate gas concentrations
reduce the flow rate.
on the ocean surface and above. Figure 1 is a projection of the gas cloud
Development of drilling procedures
resulting from the gas flow from the 762mm (30") wellhead after the marine riser was
The top hole drilling procedures for floaters were reviewed.
disconnected on the West Vanguard accident.
This changes can
This projection indicates the height of the
be summarised as follows:
flame up to 1 meter above sea level, which seems to be a fair assumption of what was
setting depth of the 762mm casing (30")
actually seen at the location.
based on
Figures 2
and 3 show two different projections with
expected leak off
wind velocity reduced to 3m/s.
20 inch setting depth
Here it
clearly shows how the shape, height and
site survey results
concentration of gas is highly dependent
increased mudweight in pilot hole to
upon the effect of wind, and that in this
min. 1.10 SG when drilling with marine
instance the concentration is within the
riser
limits of flameability up to a height of
MWD tool run on slick bottom hole
25 meters.
assembly
the fact that upgrading in design and
max. 30 m/hour rate of penetration
layout of the ventilation system is
However these figures support
important, since in certain instances Later the authorities' requirements led to
dangerous concentrations of gas can be
an amendment in the maritime certificates
present at 15-25 meters above sea level.
of all Norwegian flagged drilling vessels.
Reducing the amount of gas by 50% and
Stating that surface diverter systems
waterdepth to BOrn, dangerous concentrations
should only be used in the short period,
of gas up to 20m above sea level can arise,
until the riser is disconnected.
(ref. fig. 4).
This in
addition to the fact that several problems were experienced in the disconnection of the marine riser led to a philosophy where riserless drilling is accepted by Statoil as a safe and co9t effective top hole drilling procedure under certain conditions.
632
B. ELLINGSEN
M. GRINRQ)D
5
Special arrangements and modifications· in the use of a shallow gas stack:
The fact that dangerous concentrations of gas on a rig are not solved by drilling riserless, led to extra precautions when drilling through seismic anomalies without the marine riser installed. These can be summarised; by displacing the hole to sufficient mud weight, and combining the design of the hole size and bottom hole assembly so that dynamic kill is possible.
It will be necessary to be able to drift an existing specific profile on a 4 76rnrn · (18 3 I 4 ") wellhead housing through the 7621nrn (30") ID of the SGS. Flushing arrangement in the 762rnrn (30") wellhead connector will keep the wellhead area clear during cementing of the 508mrn (20") casing.
When shallow gas is encountered the pilot hole will be plugged back and 20" c~sing set immediately above. The conventional 476rnrn (18 3/4") BOP stack is then installed allowing the gas zone to be drilled with BOP control. In this case setting of a 406mrn (16") liner may be necessary. To avoid this time consuming operation Statoil is now in the process of incorporating a subsea shallow gas stack (SGS), which will allow setting of the 508rnrn (20") through shallow gas zones with BOP control.
Original minimum disconnecting requirements on 762mrn (30") connector in the upper section were: a)
69 bar pressure trapped under 6 shear ram equal to 3.1 x 10 N tension.
b)
2.7 x 10 5N tension caused by riser tensioners.
The SGS consists of an upper section and a lower section (fig. 5). The lower section has a 762mrn (30") wellhead connector with flushing ports, a spool with kill valve and a "dump" valve, 30" annular BOP, accumrnulator bottles, adaptor and framework. The lower section has a minimum inner diameter of 762mrn (30"). The upper section consists of a 762nun (30") connector capable of disconnection under extreme conditions, a shear ram, flex joint, choke/kill line, riser adaptor and framework. Minimum inner diameter of the upper section is 476mrn (18 3/4").
c)
3.4 x 10 5Nm bending caused by the flexible joint.
d)
0-10° angle on flexible joint.
The selected connector is capable of disconnecting under combined loads. The shear ram is designed to cut 127mrn (5") DP if emergency disconnection of the upper section is necessary. A control system and a flexible kill line are connected to the lower section of the SGS. This arrangement makes it possible to operate the lower section while the upper section and riser are
If gas cannot be controlled, or if formation breaks down, the upper section of the SGS will be released by means of the specially selected connector/disconnector system.
pulled.
633
sJ?e 112s6
A SHALLOW GAS RESEAHCH PROGRAM
6
Anchor emergency guick release:
Rig Ventilation system
During the shallow gas blowout/explosion on
The air ventilation system on West Vanguard
board the "West Vanguard", the emergency
was divided into several separate systems
quick release on four anchor lines was
with air intake fans and air outlet fans.
activated.
Air ventilation had manual shut-down in
on·e of the winches failed to
case of a gas alarm.
release.
The air intake fans
were stopped manually when the well started to flow; however air outlet fans remained
Considering off-shore blowouts it has been
running.
obvious that:
This is considered to have contributed to Technical damages and weak points in
gas explosions in some rig areas.
the anchor system on several occasions
The explosion potential, when gas enters
have rendered. an emergency quick
the ventilation system, was proven during
release impossible.
the blowout, i.e the generator room
Emergency quick release has not been
exploded.
activated due to risk of ignition of
this risk were investigated.
Consequently measures to reduce
the blowout gases. The anchor system is vulnerable to
Following are the results which have been
explosions at deck level.
implemented:
Most existing anchor systems lack Gas detectors installed in all air
sufficient redundancy.
intakes. Automatic stop of all ventilation fans
Information concerning the following was
when gas alarms are activated.
collected and analyzed:
Remote control ~f valves on critical air intakes.
Anchor systems and emergency quick release systems on existing platforms
Shallow gas drainage
Procedures related to operations of these systems Accidents related to blowouts
Drainage of shallow gas could be an option
Alternative release systems
in the following circumstances:
Based on the results the following items
Before commencement of development
have been implemented on Statoil operated
drilling where the fixed installations
platforms during 1986/87: 1.
Manual release of the anchor winches.
2.
Quick release panel installed on the
cannot be located outside the shallow gas area. In exploration drilling where gas layers have a large areal extent and
bridge. 3.
several wells are to penetrate the gas
Improvement of electric/electronic
layers.
components. 4.
Increased sprinkler capacity.
634
rofJts
a. GRINR0D
17256
7
During exploration drilling in block 34/10
Increasing the lifetime of surface
- i.e. Gullfaks field, in ca. 60% of the
diverters can be achieved by reducing
wells shallow gas has been penetrated. In
velocity of particles.
1983 it was decided to drill the first
velocity can be obtained by end mounted
shallow gas investigation well near the
chokes.
Reduction of
Gullfaks "A" platform location. This well was drilled to 550m MSL and shallow gas was
-Increase of bend diameter and
revealed. A number of similar wells have
hardfacing of diverterpiping, and an
been drilled since to improve the mapping
increase in pipe diameter will increase
of shallow gas in general.
lifetime of diverter systems.
Well 34/10-30 was drilled and completed with the intent to attempt depletion of the
A theoretical model for gas
gas sand before the Gullfaks "A" platform
concentrations above sea level has been
was placed on its location.
developed taking into account rate,
The sand, 312-314,5m MSL, produced during
waterdepth and wind velocity.
35 days. The production rate was approximately 60.000
SCM/day~
the maximum
Riserless top hole drilling when
rate was 115.000 SCM/day (short period).
checking out anomalies should in all cases be done with hole size and
The reservoir pressure, in the shallow
mudweight designed to allow dynamic
sand, was 33.5 bar, i.e. 1 bar in
kill.
excess of normal hydrostatic pressure. This indicates a gas column height of
Shallow gas stacks will promote control
6m.
of top hole drilling and protect
The gas was 99% methane.
against gas flow to the rig.
Sand was produced into the well. A gravel pack was done.
Rig ventilation system should be
Permeability of the reservoir: between
designed for full automatic shut down
200 and 350mD.
in case of a gas alarm.
Due to circumstances and platform placement the test was abandoned and the well
References:
plugged. In total 2.800.000 SCM had been produced.
(Ref. 1.) The desired pressure
1.
and gas depletion was not obtained.
Grinr¢d. M, Tomren. P.H, Justad. T: "Development of the Gullfaks field" Paper IADC/SPE 17220, presented at IADC/SPE Drilling Conference, March
Conclusion
1988.
Changing drilling procedures seem to be
2.
Dings¢yr. E, Vass¢y. B and Grinr¢d. M:
the most important contribution to an
"Development and Use of a Gas Tight
increased level of safety for floating
Cement" Paper IADC/SPE 17258, presented
drilling. Drilling programs and
at IADC/SPE Drilling Conference, March
procedures for top hole drilling should
1988.
be designed to enhance safety at each location based on existing information.
635
8
3.
A SHALI.CM GAS RESEARCH PR:X;RAM
D. Mills and J.S. Mason: "Conveying Velocity Effects in Bend Erosion. Proc. Int Symp. on Freight Pipeline. Washington D.C. 1976". Subsequently published in the Jnl. of Pipelines, Vo. 1, No. 1, pp 69-81, 1981.
4.
D. Mills and J.S. Mason: "Particle Concentration Effects in bend Erosion Powder Techno!. Vol. 17, No. 1, pp 37-53, 1977".
5.
D. Mills and J.S. Mason: Evaluating the Conveying Capacity and Service Life of Pipe Bends in Pneumatic Conveying Systems. Proc. Powder Europa '78. PAC Conf. Wiesbaden. Jan.
1978"~
Jnl. of Powder and Bulk Solids Tech. Vol. 3, No. 2, pp 13-20 1979. 6.
D. Mills and J.S. Mason: "Analysis of Factors Influencing the Premature Failure of Pipe Bends in Pneumatic Conveying Systems. Proc. 2nd Conf. on Pneumatic Conveying, pp 93-103. ISBN 963 8091 64 7. HUngarian Sci. Soc. Mech. Engrs. Pees. Hungary, March 1978".
7.
D. Mills and J.S. Mason: "The Effect of Particle Size on the Erosion of Pipe Bends in Pneumatic Conveying Systems. Proc. POWTECH '70. pp H 50-96. !ChernE Conf. Birmingham. March 1979".
636
S'PE. 17256
SPE 17256 A P P E N D I X
BEND LIFE CALCULATIONS
Specific Erosion
Msf
Mbf
(ref. D. Mills and J.S. Mason)
mass eroded from component mass conveyed through component
g/tonne
tonne
E
where Msf
and
and
Mbf
E
Conveyed mass of sand before component fails
(g)
Eroded mass from component before failure
g
Specific erosion
The Time to Failure For a Component Tbf = Msf x 60 min ms Where Tbf and ms
time before failure flowrate of sand
tonne/h
In the test the sand was conveyed at a phase density (0) of 1.0 and the mass flow rate of the sand was the same as that of the air.
The Influence of Conveying Air Velocity Specific erosion increases with the increase in velocity according to E~ C 2.65
for sand conveyed through 90 degr. bends. Where C = Conveying air velocity m/s
The Influence of Phase Density Specific erosion decreases with increase in phase density according to EOc:' 0 -0.16
for sand conveyed through 90 degr. bends.
The Influence of Particle Size Particle size has little influence on the value of specific erosion, however, the influence o£ turbulence increases significantly with a decrease in the mean particle size. The influence of turbulence is additionally effected by phase density (0) and so for a 70 ~m sand, for example, the time quoted at 0=1 will vary by a factor of about +/- 2 compared with a 230 ~m sand.
637
SPE 1725b %BY VOLUME GAS IN AIR
% BY VOLUME GAS IN AIR
- · - · - · - · - 30.0 - - - - - - - - 15.0
===~
5.0 2.0 1.3
i
i
)(
)(
120 Z(M)
Z(M)
Y(M): O.OOOE + 00
Y(M): O.OOOE + 00
RATE : 120 KG/S UF WIND: 15M/S ' L: 15%, LFL: 5% WATER ' T-AIR: 10C DEPTH•• 2 20M, DIAMETER GAS ZONE· 60
RATE : 120 KG/S U WIND: 3M/S ' FL: 15%, LFL: 5% ' T-AIR• 10C ATER DEPTH• • ' T-GAS: 10C W • 220M, DIAMETER GAS Fig. 2-Weat V ZONE: &OM anguard gaa cloud with reduced wind velocity.
Fig. 1-Gaa oloud alter Weal Van guard accident. • M
% BY VOLUME GAS IN AIR
%BY VOLUME GAS IN AIR 40
---· ................
- · - · - · - · - 30 0 - - - - - - - - 15:0
5.0 2.0 1.3
.•... :::::::::
5.0 2.0 1.3
·····································
i
)(
10
40
70
Y(M)
z (M):
Z(M) Y(M): O.OOOE + 00
1.000E + 02
RATE : 60 KG/S WIND: 3M/S T ' UFL: 15%, LFL: 5% WATER DEPT'H· -AIR: 10C, T-GAS: 10C • 80M, DIAMETER GAS ZONE: 19M
RATE : 120 KG/S WIND: 3M/S T' UFL: 15%, LFL: 5% • -AIR· 10C WATER DEPTH: 220M. ' T-GAS: 10C . ' DIAMETER GAS ZONE· Fig. 3-Weat V • &OM anguard gaa cloud with reduced wind velocity.
Fig. 4-Gaa cloud with water depth and ' rate reduced.
638
SP£ 17256
SHALLOW GAS BOP
RISER ADAPTOR
FLEXIBLE KILL LINE CHOKE LINE
ANNULAR BOP DUMP
0
VALVE
FLUSHING LINE
W.H. CONNECTOR
Fig. 5-Shallow gas valve stack.
639