Project:Kashmir Railway Project
Date:05-05-2009
SECURITY DEPOSIT RELEASE FORM 1. Name of Work: Execution of water booth at Island platform at Anantnag Station on Qazigund Baramulla new BG Rail Line Project. 2. Name of Agency:
M/S Itoo Construction, Mandole, Anantnag.
3. LOA No: IRCON/J&K-SGR/1008/ Water Booth Ananatnag/ A-1/19517 ; dt:13.05.2008 4. Date of completion as per LOA: 28-06-2008 5. Actual date of completion:
31-12-2008
6. Date of Final Measurement:
31-12-2009
7. Date Defect Liability Period:
14-02-2009
8. Value of Work as Per LOA:
Rs. 3,71,216.72
9. Contractor’s request Letter No: 10. Value of Work after Variation:
Rs. 2,80,915.43
11. Security Deposit Deducted:
MB No:
Page No
CC:
Amount:
11
1
Rs. 16,693.00
20
2
Rs. 10,865.00 . Rs. 27,558.00
1327
Cont………………. Page 2
12. Certificate: Certified that the work has been completed satisfactorily and certified by ShriSurajit Ghosh, DM/ Civil of Ircon. 100% S.D amount i.e. Rs. 27,558.00 may be released. 13. Certified that the defect liability period is completed and there is no defect observed during the defect liability period.
(Surajit Ghosh) DM/ Civil
DGM/Civil
AGM/Civil
JGM/Finance
GM/Srinagar
Project:Kashmir Railway Project
Date:05-05-2009
SECURITY DEPOSIT RELEASE FORM 1. Name of Work: Construction of Temporary ramp for Feeding Ballast at Chainage 21/100 in phase-II on Qazigund Baramulla new BG Rail Line Project. 2. Name of Agency: M/s Hamid Bin Rashid, R/o Sursona, Batingoo, Anantnag, Kashmir. 3. LOA No:
IRCON/J&K-SGR/1008/ Temporary Ramp/20954 Dt:22.08.2008 4. Date of completion as per LOA: 21-09-2008 5. Actual date of completion:
21-09-2008
6. Date of Final Measurement:
29-09-2008
7. Date Defect Liability Period:
06-11-2008
8. Value of Work as Per LOA:
Rs. 4,64,058.13
9. Contractor’s request Letter No: 10. Value of Work after Variation:
Rs. 4,97,467.00
11. Security Deposit Deducted:
MB No:
Page No 11 .
CC: 1
1391
Amount: Rs. 49,747.00 Rs. 49,747.00
Cont………………. Page 2
12. Certificate: Certified that the work has been completed satisfactorily and certified by ShriSurajit Ghosh, DM/ Civil of Ircon. 100% S.D amount i.e. Rs. 49,747.00 may be released. 13. Certified that the defect liability period is completed and there is no defect observed during the defect liability period.
(Surajit Ghosh) DM/ Civil
DGM/Civil
AGM/Civil
JGM/Finance
GM/Srinagar